L-MT-17-031, Interim Report of a Deviation or Failure to Comply Regarding New Relay Coil GE Part Number 6306774G1
ML17110A244 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 04/20/2017 |
From: | Gardner P Northern States Power Company, Minnesota, Xcel Energy |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
L-MT-17-031 | |
Download: ML17110A244 (1) | |
Similar Documents at Monticello | |
---|---|
Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARL-MT-21-035, Initial and Final Written 10 CFR 21 Notification for GE Hitachi Numac Prnm System2021-05-0707 May 2021
[Table view]Initial and Final Written 10 CFR 21 Notification for GE Hitachi Numac Prnm System ML19091A0502019-03-21021 March 2019 Engine Systems, Inc. 10 CFR 21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0124, Rev. 0, Excitation Transformers for Vickers Voltage Regulator System ML19087A2522019-03-21021 March 2019 Engine Systems, Inc. - 10 CFR 21 Reportable Notification on Excitation Transformers for Vickers Voltage Regulator System ML19042A0802019-01-25025 January 2019 Part 21 Report No. 10CFR21-0124-INT; Rev. 0 - Saturable Reactor (Magnetic Amplifier) for Vickers Voltage Regulator System, P/N 8408218-ESI L-MT-18-012, Interim Report of a Deviation or Failure to Comply2018-02-12012 February 2018 Interim Report of a Deviation or Failure to Comply L-MT-18-008, Initial and Final Part 21.21(d)(4) Report Notification of Failure to Comply or Existence of a Defect Regarding Westinghouse Breaker Cubicle2018-02-0101 February 2018 Initial and Final Part 21.21(d)(4) Report Notification of Failure to Comply or Existence of a Defect Regarding Westinghouse Breaker Cubicle ML17212A6282017-07-24024 July 2017 Lake Engineering Co. - Potentially Degraded Snubber SF1154 Hydraulic Fluid Second - Interim Notification Per 10 CFR Part 21 ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17179A3782017-06-0707 June 2017 TE Connectivity - Part 21 Transfer of Information TE-023 L-MT-17-031, Interim Report of a Deviation or Failure to Comply Regarding New Relay Coil GE Part Number 6306774G12017-04-20020 April 2017 Interim Report of a Deviation or Failure to Comply Regarding New Relay Coil GE Part Number 6306774G1 ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling L-MT-17-005, Interim Report of a Deviation or Failure to Comply2017-01-17017 January 2017 Interim Report of a Deviation or Failure to Comply ML16321A4512016-10-21021 October 2016 Part 21 Reporting of Defects and Noncompliance ML16321A4502016-08-31031 August 2016 Part 21 Notification - Flowserve Swing Check Valves ML16243A4722016-08-25025 August 2016 Part 21 Reporting of Defects and Noncompliance ML16139A8342016-05-10010 May 2016 Electroswitch - Transmittal of 10CFR Part 21 Reporting of Defects and Noncompliance Regarding Vendor Inspection of Electroswitch Corporation Docket No. 99900833 ML15265A4182015-09-21021 September 2015 Sor, Inc. - Part 21 Notification of Deviation - ML15251A212 Irradiation Certification with Insufficient Margin ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14204A7082014-07-23023 July 2014 Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML14212A4012014-07-18018 July 2014 Final Report - 10 CFR Part 21 Evaluation Regarding Cracking in KCR-13 Standby Battery Jars ML14134A1222014-05-0909 May 2014 Notification of Potential Part 21 Report - Cracking in KCR-13 Standby Battery Jars ML14139A0172014-04-28028 April 2014 Updated Interim Report - Inability to Complete 10CFR Part 21 Evaluation Regarding Cracking in KCR-13 Standby Battery Jars ML14042A2022014-02-0505 February 2014 Part 21 Report Regarding Unqualified Material Used in Electrical Penetration Assemblies ML14042A2012014-01-29029 January 2014 Part 21 Report Regarding Non-Destructive Testing Did Not Meet Procedural Requirements ML13358A3062013-12-20020 December 2013 Interim Report - Inability to Complete 10CFR Part 21 Evaluation Regarding Cracking in KCR-13 Standby Battery Jars ML14006A0042013-12-13013 December 2013 Trivis, Inc., Part 21 Interim Report - Nonconforming Dry Shielded Calster Welds - Potential Substantial Safety Hazard ML13358A0462013-12-13013 December 2013 Report of Potential Substantial Safety Hazard in Accordance with Title 10 Code of Federal Regulation, Part 21 ML13340A3822013-12-0505 December 2013 Part 21 Reportable Condition Notification: Failure of Relay Logic Card Modules in 2 Out of 4 Voters ML13277A0102013-09-23023 September 2013 Interim Report Update for Component ASME Material Supplied by Mirion Technologies (Conax Nuclear), Inc. (Mtcn), as Part of Containment Electric Penetration Assemblies (EPA) ML13246A0842013-08-23023 August 2013 Notification of Potential Defect & Interim Report Regarding a Potential Defect of Materials Supplied to Operating Us Nuclear Power Plants by Mirion Technologies (Conax Nuclear) Inc. (Mtcn) with Containment Electric Penetration Assemblies ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML13042A0962013-02-0808 February 2013 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12347A3082012-12-12012 December 2012 Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology ML12319A0122012-09-27027 September 2012 Error in Main Steam Line High Flow Calculational Methodology ML12177A0562012-06-21021 June 2012 Part 21 - Reliability Degradation of Resistors in Trip Units and Readout Assemblies ML12163A1302012-06-0606 June 2012 Part 21 Report - Failure of CRD Collet Retainer Tube/Outer Tube Weld ML12158A4472012-06-0606 June 2012 Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld ML12058A1412012-02-23023 February 2012 Part 21 Report - Rosemount Nuclear Instruments, Inc., Pressure Transmitter with Nonzero Based Calibrations ML12040A2832012-02-0707 February 2012 Notification of Potential Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance ML12038A0282012-02-0202 February 2012 Failure of CRD Collet Retainer Tube/Outer Tube Weld ML12032A2402012-02-0101 February 2012 Notification of Potential Part 21 - 60-Day Interim Report Notification: Failure of CRD Collet Retainer Tube/Outer Tube Weld ML11341A0602011-12-0505 December 2011 Notification of Potential Part 21 Involving Defective Spring Clips Used as Seismic Restraints on Two Scientific Modules ML11340A1002011-12-0505 December 2011 Letter 10 CFR Part 21 Notification Report, CON2000 and RTD2100 Spring Clips 2021-05-07 Category:Letter type:L MONTHYEARL-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024
[Table view]Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 L-MT-23-030, Subsequent License Renewal Application Supplement 32023-07-0404 July 2023 Subsequent License Renewal Application Supplement 3 L-MT-23-025, Subsequent License Renewal Application Supplement 22023-06-26026 June 2023 Subsequent License Renewal Application Supplement 2 L-MT-23-019, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report L-MT-23-020, Submittal of 2022 Annual Radioactive Effluent Release Report2023-05-10010 May 2023 Submittal of 2022 Annual Radioactive Effluent Release Report L-MT-23-021, Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 322023-05-0202 May 2023 Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 32 L-MT-23-017, 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2023-04-18018 April 2023 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) L-MT-23-010, Subsequent License Renewal Application Supplement 12023-04-0303 April 2023 Subsequent License Renewal Application Supplement 1 L-MT-23-013, Core Operating Limits Report (COLR) for Cycle 31, Revision 32023-03-28028 March 2023 Core Operating Limits Report (COLR) for Cycle 31, Revision 3 L-MT-23-012, Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 22023-03-17017 March 2023 Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 2 L-MT-23-008, 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003)2023-02-0707 February 2023 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003) L-MT-23-004, CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program2023-01-23023 January 2023 CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program L-MT-23-005, Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088)2023-01-0606 January 2023 Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088) L-MT-22-049, Industry Groundwater Protection Initiative Special Report2022-12-15015 December 2022 Industry Groundwater Protection Initiative Special Report L-MT-22-052, L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative2022-12-15015 December 2022 L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative L-MT-22-046, 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462022-12-13013 December 2022 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-22-048, Update to the Monticello Technical Specification Bases2022-11-28028 November 2022 Update to the Monticello Technical Specification Bases L-MT-22-047, Withdrawal of Request for Relief from ASME OM Code for the Sixth Inservice Testing Interval2022-11-10010 November 2022 Withdrawal of Request for Relief from ASME OM Code for the Sixth Inservice Testing Interval L-MT-22-045, Letter Submitting Post-Exam Package2022-11-0404 November 2022 Letter Submitting Post-Exam Package L-MT-22-030, Sixth Interval Inservice Testing (1ST) Plan2022-09-0606 September 2022 Sixth Interval Inservice Testing (1ST) Plan L-MT-22-037, Supplement to 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval, Alternative VR-10, Excess Flow Check Valve Testing Frequency2022-08-29029 August 2022 Supplement to 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval, Alternative VR-10, Excess Flow Check Valve Testing Frequency L-MT-22-007, Response to Request for Additional Information for the Monticello Nuclear Generating Plant Alternative Request VR-08 (EPID: L-MT-22-007)2022-07-22022 July 2022 Response to Request for Additional Information for the Monticello Nuclear Generating Plant Alternative Request VR-08 (EPID: L-MT-22-007) L-MT-22-026, Changes to the Emergency Plan2022-07-19019 July 2022 Changes to the Emergency Plan L-MT-22-024, Response to a Request for Additional Information for the Monticello Nuclear Generating Plant Related to the Amendment to Adopt Advanced Framatome Methodologies2022-06-0606 June 2022 Response to a Request for Additional Information for the Monticello Nuclear Generating Plant Related to the Amendment to Adopt Advanced Framatome Methodologies L-MT-22-022, Response to a Request for Additional Information: Monticello Alternative VR-10, Excess Flow Check Valve Testing Frequency2022-05-25025 May 2022 Response to a Request for Additional Information: Monticello Alternative VR-10, Excess Flow Check Valve Testing Frequency L-MT-22-017, 2021 Annual Radiological Environmental Operating Report2022-05-11011 May 2022 2021 Annual Radiological Environmental Operating Report L-MT-22-018, 2021 Annual Radioactive Effluent Release Report2022-05-11011 May 2022 2021 Annual Radioactive Effluent Release Report L-MT-22-016, 2021 Annual Report of Individual Monitoring2022-04-28028 April 2022 2021 Annual Report of Individual Monitoring L-MT-22-019, Withdrawal of Requests for Relief from ASME OM Code for the Sixth Inservice Testing Interval2022-04-18018 April 2022 Withdrawal of Requests for Relief from ASME OM Code for the Sixth Inservice Testing Interval L-MT-22-010, License Amendment Request to Revise Technical Specification 3.6.1.8 Residual Heat Removal (RHR) Drywell Spray Header and Nozzle Surveillance Frequency2022-03-18018 March 2022 License Amendment Request to Revise Technical Specification 3.6.1.8 Residual Heat Removal (RHR) Drywell Spray Header and Nozzle Surveillance Frequency L-MT-22-012, Special Report for the Bypass of the Offgas Treatment Storage System2022-03-15015 March 2022 Special Report for the Bypass of the Offgas Treatment Storage System L-MT-22-008, 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval Alternative Related to Excess Flow Check Valve Testing Frequency (L-MT-22-008)2022-03-0707 March 2022 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval Alternative Related to Excess Flow Check Valve Testing Frequency (L-MT-22-008) L-MT-22-006, 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval OMN-26 (L-MT-22-006)2022-02-18018 February 2022 10 CFR 50.55a Request Associated with the Monticello Sixth Inservice Testing Ten-Year Interval OMN-26 (L-MT-22-006) 2024-01-11 |
Text
2807 West County Road 75 Monticello, MN 55362 (}, Xcel Energy*
RESPONSIBLE BY NATURE*
800.895.4999 xcelenergy.com April 20, 2017 L-MT-17-031 10 CFR 21.21 (a)(2)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License No. DPR-22 Interim Report of a Deviation or Failure to Comply Pursuant to 10 CFR 21.21 (a)(2), Northern States Power Company, a Minnesota Corporation, (NSPM), doing business as Xcel Energy, hereby submits this interim report.
As part of a rebuild of a station relay, a new relay coil GE part number 6306774G1, failed to meet voltage pickup criteria during bench testing per GEl-38945. The relay coil was out of the acceptance band of 65-70 VDC. This relay coil had never been installed, but was purchased under a vendor's 10 CFR Appendix B program and had been receipt inspected prior to the failed bench test. The failed relay coil has been sent to GE for evaluation; however, the expected return of the evaluation has yet to be determined by the vendor.
If there is any question or if additional information is needed, please contact Stephen Sollom, at (763) 295-1611.
Summary of Commitments There are no new commitments and no revisions to existing commitments in this letter.
~
Peter A. Gardner Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company - Minnesota cc: Administrator, Region Ill, USNRC Resident Inspector, MNGP, USNRC Project Manager, MNGP, USNRC