L-MT-17-005, Interim Report of a Deviation or Failure to Comply

From kanterella
Jump to navigation Jump to search
Interim Report of a Deviation or Failure to Comply
ML17017A501
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 01/17/2017
From: Gardner P
Northern States Power Company, Minnesota, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-17-005
Download: ML17017A501 (1)


Text

2807 West County Road 75 Monticello, MN 55362 800.895.4999 xcelenergy. com January 17,2017 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License No. DPR-22 Interim Report of a Deviation or Failure to Comply (l Xcel Energy RESPONSIBLE BY NATURE*

L-MT-17-005 10 CFR 21.21 (a)(2)

Pursuant to 10 CFR 21.21 (a)(2), Northern States Power Company, a Minnesota Corporation, (NSPM), doing business as Xcel Energy, hereby submits this interim report.

The deviation to be evaluated is the failed bench test of a commercially dedicated contactor by Engine Systems Incorporated (ESI), model LC1 D115GD. The contactor was found to be mechanically binding preventing its associated contacts from closing. The failed contactor has been sent to ESI for evaluation.

If there is any question or if additional information is needed, please contact Andrew Kouba, at (763) 271-7251.

Summary of Commitments There are no new commitments and no revisions to existing commitments in this letter.

-;#-ft~

Peter A. Gardner Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company-Minnesota cc:

Administrator, Region Ill, USNRC Resident Inspector, MNGP, USNRC Project Manager, MNGP, USNRC