60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers
ML12352A123
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Three Mile Island, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Quad Cities, Fort Calhoun, FitzPatrick, McGuire, LaSalle
Issue date: 12/13/2012
From: Porter D
GE-Hitachi Nuclear Energy Americas
To:
Office of Nuclear Reactor Regulation
References
48585
Download: ML12352A123 (13)


Text

12/13/2012 U.S. NuclearRegulatory Commission OperationsCenter Event Report easel Part 21 (PAR) Event# 48585 Rep Org: GE HITACHI NUCLEAR ENERGY Notification Date / Time: 12/13/2012 08:41 (EST)

Supplier: GE HITACHI NUCLEAR ENERGY Event Date / Time: 12/13/2012 (EST)

Last Modification: 12/13/2012 Region: 1 Docket #:

City: WILMINGTON Agreement State: Yes County: License #:

State: NC NRC Notified by: DALE E. PORTER Notifications: DANIEL HOLODY RIDO HQ Ops Officer: STEVE SANDIN ALAN BLAMEY R2DO Emergency Class: NON EMERGENCY JAMNES CAMERON R3DO 10 CFR Section: MARK HAIRE R4DO 21.21(a)(2) INTERIM EVAL OF DEVIATION NRR PART 21 EMAIL 60-DAY INTERIM REPORT INVOLVING AN EVALUATION OF A DESIGN CHANGE TO MAGNE-BLAST CIRCUIT BREAKERS The following information was received via fax:

"Summary "GE Hitachi Nuclear Energy (GEH) is investigating the adequacy of a Design Change in AM 4.16-350-2C and AM 4.16-350-2H Magne-Blast Circuit Breakers as a result of a breaker failure at a BWR Licensee.

"GEH has not completed the evaluation of this condition to determine reportability under 10 CFR Part 21 and is therefore issuing this 60-day Interim Notification. GEH will close or issue an update on this matter on or before June 14, 2013. Given the early status of the evaluation, GEH has no recommended actions at this time. This 60-day Interim Notification is issued in accordance with 10 CFR Part 21.21(a)(2), and will be sent to all GE BWR/2-6 plants and all PWRs.

"Recommendation "GEH advises licensees to take no action at this time. However, if licensees wish to determine if the extent of this issue is present at their respective plants, they may identify breaker models AM 4.16-350-2H/2C with a date of manufacture prior to October 6, 1971. Other AM breaker styles do not use the booster cylinder as designed in breaker model AM 4.16-350-2H/2C and are not included in this concern. Therefore the extent is limited to the AM 4.16-350-2H/2C models manufactured prior to October 6, 1971.

"US Plants Potentially Affected

1211312012 U.S. Nuclear Regulatory Commission OperationsCenter Event Report Paze 2 Part 21 (PAR) Event# 48585 "Nine Mile Point 1-2, Fermi 2, Columbia, Grand Gulf, River Bend, FitzPatrick, Pilgrim, Vermont Yankee, Clinton, Dresden 2-3, LaSalle 1-2, Limerick 1-2, Oyster Creek, Peach Bottom 2-3, Quad Cities 1-2, Perry 1, Duane Arnold, Cooper, Susquehanna 1-2, Brunswick 1-2, Hope Creek, Hatch 1 - 2, Browns Ferry 1-3, Monticello, Callaway, Palo Verde 1-3 , Calvert Cliffs 1-2, Ginna, Arkansas Nuclear One 1-2, Indian Point 2-3, Millstone 2, Millstone 3, North Anna 1-2, Palisades, Surry 1-2, Waterford 3, Catawba 1-2, Oconee 1-3, McGuire 1-2, Braidwood 1-2, Exelon Byron 1-2 , Three Mi le Island 1, Beaver Valley 1-2, Davis-Besse, Seabrook, St. Lucie 1-2, Turkey Point 3-4, Point Beach 1-2, DC Cook 1-2, Prairie Island 1-2, Fort Calhoun, Diablo Canyon 1-2, Crystal River 3, Robinson, Shearon Harris, Salem 1, Salem 2, Summer, South Texas Project 1-2, San Onofre 2-3, Farley 1-2, Vogtle 1-2, Sequoyah 1-2, Watts Bar 1, Comanche Peak 1-2, and Wolf Creek.

"Ifyou have an questions, please call me at (910) 819-4491.

Dale E. Porter Safety Evaluation Program Manager GE-Hitachi Nuclear Energy Americas LLC" Hitachi Reference Number: MFN-128 RO

09:57:05 a.m. 12-13-2012 1/11 910 602 4829 ATC 1st FLOOR GE Hitachi Nuclear Energy 0 HITACHI To: NRC Operations Center Fax: 301-816-5151 From: Dale E. Porter, GE Hitachi Nuclear Energy Fax: 910-819-4829 Date/Time: December 13, 2012 8:45 am Number of pages, including this one: 11 Comments:

910 602 4829 ATC 1st FLOOR 09:57:11 a.m. 12-13-2012 2111 HITACHI GE Hitachi Nuclear Energy Dale E. Porter GE-Hitacti Nuclear Energy Americas LLC Safety Evaluation Program Manager December 13, 2012 MFN 12-128 RO 3901 Castle Hayne Rd.

Wilmington, NC 28401 USA U.S. Nuclear Regulatory Commission T910 819-4491 Attn: Document Control Desk Dale.Porter@GE.Com Washington, DC 20555-0001

Subject:

Part 21 60-Day Interim Report Notification:

Adequacy of Design Change In AM Magne-Blast Circuit Breakers This letter provides information concerning an evaluation being performed by GE Hitachi Nuclear Energy (GEH) regarding the adequacy of a Design Change in AM 4.16-350-2C and AM 4.16-350-2H Magne-Blast Circuit Breakers. As stated herein, GEH has not concluded that there is a reportable condition in accordance with the requirements of 10CFR 21.21(d).

Testing and continued evaluation is required to determine whether this condition is a reportable condition and what impact and extent of this condition may exist.

The information required for a 60-Day Interim Report Notification per §21.21(a)(2) is provided in Attachment 3. The commitment for follow-on actions is provided in Attachment 3, item (vii).

If you have any questions, please call me at (910) 819-4491.

Sincerely, Dale E. Porter Safety Evaluation Program Manager GE-Hitachi Nuclear Energy Americas LLC Attachments:

1. Description of Evaluation
2. US Plants Potentially Affected
3. 60-Day Interim Report Notification Informition per §21.21(a)(2)

910 602 4829 ATC 1st FLOOR 09:57:22 a.m, 12-13-2012 3/11 MFN 12-128 RO Page 2 of 2 cc: S. S. Philpott, USNRC S. J. Pannier, USNRC

0. Tabatabai-Yazdi, USNRC D. C. Crawford, GEH J. F. Harrison, GEH J. G. Head, GEH G. A. Watford, GEH P. L. Campbell, GEH Washington PRC File DRF Section No. 0000-0155-6212

ATC 1st FLOOR 09:57:30 a,m, 12-13-2012 4/11 9106024829 MFN 12-128 RO Attachment I - Description of Evaluation Page 1 of 3 Summary GE Hitachi Nuclear Energy (GEH) is investigating the adequacy of a Design Change in AM 4.16-350-2C and AM 4.16-350-2H Magne-Blast Circuit Breakers as a result of a breaker failure at a BWR Licensee.

GEH has not completed the evaluation of this condition to determine reportability under 10 CFR Part 21 and is therefore issuing this 60-day Interim Notification. GEH will close or issue an update on this matter on or before June 14, 2013. Given the early status of the evaluation, GEH has no recommended actions at this time. This 60-day Interim Notification is issued in accordance with 10CFR Part 21.21(a)(2), and will be sent to all GE BWRI2-6 plants and all PWRs.

Discussion On October 30, 2012 GEH determined that a part of a Safety Related Breaker (Model AM 4.16-350-2H/2C 1200A, 2000A, 3000A) may be installed in such a manner that could cause the breaker to fail.

A customer reported a breaker failure which involved the booster piston impacting the bottom of the booster cylinder. GEH performed a causal evaluation for the licensee and the root cause was indeterminate. It was noted that there were multiple contributing maintenance factors associated with the breaker failure. The report concluded that no single issue could have caused the impact and subsequent failure.

GEH developed the design of this model breaker in the late 1960's and were sold to Licensee's as Safety Related, prior to the development of IEEE-323. However, that did not relinquish GEH from developing test reports according to existing industry standards. One industry standard established at that time was ANSI C37.06, which required successful demonstration of 10,000 cycles under no load. This standard is used today as part of the IEEE-323 Qualification.

GEH constructed, tested and supplied a specialized breaker for a licensee in 1971 to improve response time. Heavier springs were installed on a base model AM 4.16-350-2H.

Modification testing revealed that the heavier springs provided extra momentum to the mechanism, causing the puffer piston and booster cylinder bottom to contact. Two additional design changes were performed to eliminate the contact. First, the opening and closing spring rates were decreased. Second, another design change lowered the booster cylinder in relation to the booster piston, providing additional impact margin (gap). Follow-up testing revealed no impact; however, the contribution of either design change is unknown. The heavier springs were utilized for the special breaker and the product line

910 602 4829 ATC 1st FLOOR 09: 57:4 7 a.m. 12-13-2012 5/11 MFN 12-128 RO Attachment 1 - Description of Evaluation Page 2 of 3 returned to the standard springs for subsequent breaker manufacture. The modification to lower the booster cylinder was incorporated into the base product design on October 6, 1971 (with standard springs) and has carried forth until the present. This modification increased the clearance between the piston end stroke and booster cylinder bottom.

GEH has attempted to locate documentation of the No Load Cycle Test required per ANSI C37.06 for both the pre-modification and post modification designs relating to the booster cylinder change. GEH has documentation that demonstrates the post modification models successfully passed the ANSI C37.06/C37.09 testing in 1977, as part of the IEEE-323 Qualification. GEH has been unable to locate ANSI C37.06 No Load Cycle Testing for the design prior to the 1971 modification (with standard springs). Additionally, GEH is not aware of any further design changes which would invalidate the Qualification of the breakers prior to the IEEE-323 Qualification in 1977.

The GEH position, regarding the pre-1971 modified breakers, is that the breakers will perform all safety related functions involving the booster cylinder and piston. This is based on:

" The GEH Service center has performed maintenance on this style breaker for over 40 years. There have been no documented piston impacts on the booster cylinder bottom, except for the single licensee failure noted above.

" GEH has also performed an EPIX search for all functional failures regarding this product line. The only instance where this occurred was the above mentioned licensee failure.

GEH has taken a conservative approach to this issue and has committed to testing an AM 4.16-350 breaker per ANSI C37.06, for purposes of validating the pre-modification design.

GEH advises Licensees to take no action at this point. However, if licensees wish to determine the extent, they may identify breaker models AM 4.16-350-2H/2C with a date of manufacture prior to October 6, 1971. Other AM breaker styles do not use the booster cylinder as designed in breaker model AM 4.16-350-2H/2C.

Extent of Condition GEH has documentation that the licensee who reported the failure, was shipped additional breakers that fall within the date of manufacture prior to October 6, 1971. GEH is unable at this time to identify other licensees who may have been shipped this series of breakers.

This is not of concern because the current GEH position is that no defect exists. If testing identifies any anomaly with the pre-October 6, 1971 design, GEH will immediately begin determining the extcnt of condition, and initiate notification to the industry and regulatory authority.

9106024829 ATC 1st FLOOR 09:58:05 a.m. 12-13-2012 6/11 MFN 12-128 R0 Attachment.1 - Description of Evaluation Page 3 of 3 ABWR and ESBWR Design Certification Documentation Applicability The issue described above has been reviewed for applicability to documentation associated with 10 CFR 52, and determined to have no effect on the technical information contained in either the ABWR certified design or the ESBWR design in certification. This is true because the Technical Specifications submitted with the Design Certification Documentation do not include specific details associated with these components.

Recommendation GEH advises licensees to take no action at this time. However, if licensees wish to determine if the extent of this issue is present at their respective plants, they may identify breaker models AM 4.16-350-2H/2C with a date of manufacture prior to October 6, 1971.

Other AM breaker styles do not use the booster cylinder as designed in breaker model AM 4.16-350-2H/2C and are not included in this concern. Therefore the extent is limited to the AM 4.16-350-2H/2C models manufactured prior to October 6, 1971.

CorrectivelPreventive Actions GEH will complete the testing and post-test evaluation and issue either a closure of this 10CFR Part 21 concern or issue an update, based on the results of these tests, by June 14, 2013.

Refer to Attachment 3, Item (vii) for corrective actions.

9106024829 ATC 1st FLOOR 09:58; 15 a.m. 12-13-2012 7/11 MFN 12-128 RO Page 1 of 3 Attachment 2 US Plants Potentially Affected US B WR Plants and Associated Facilities Plant x Constellation Energy Nine Mile Point 1-2 x Detroit Edison Co. Fermi 2 x Energy Northwest Columbia x Entergy Grand Gulf x Entergy River Bend x Entergy FitiPatrick x Entergy Pilgrim x Entergy Vermont Yankee x Exelon Clinton x Exelon l)resden 2-3 x Exelon LaSalle 1-2 x Exelon Limerick 1-2 x Exelon Oyster Creek x Exelon Peach Bottom 2-3 x Exelon Quad Cities 1-2 x FirstEnergy Nuclear Operating Co. Perry I x Florida Power & Light Duane Arnold x Nebraska Public Power District (:Coper x PPL. Susquehanna LLC Susquehanna 1-2 x Progress Energy Brunswick 1-2 x PSEG Nuclear, LLC -Hope Creek x Southern Nuclear Operating Co. Hatch I - 2 x Tennessee Valley Authority Browns Ferry 1-3 x Xcel Energy Monticello

910 602 4829 ATC 1st FLOOR 09:58:23 am. 12-13-2012 8/11 MFN 12-128 RO Page 2 of 3 Attachment 2 US Plants Potentially Affected U.S' PWR Plants and.4ssocialedFacilities Utilit* Plant x AmerentJE Callaway x Arizona Public Service Palo Verde 1-3 x Constellation Energy Calvert Clilts 1-2 x Constellation Energy Ginna x Entergy Arkansas Nuclear One 1-2 x Entergy Indian Point 2-3 x Dominion Kewaunee x Dominion Millstone 2 x Dominion Millstone 3 x Dominion North Anna 1-2 X-x Dominion Palisades x Dominion Surry 1-2 x Dominion Waterford 3 x Duke Energy Corporation Catawba 1-2 x Duke Energy Corporation Oconce 1-3 x Duke E'nergy Corporation McGuire 1-2 x Exelon Braidwood 1-2 x Exelon Byron 1-2 x Exelon Three Mile Island I x FirstEnergy Nuclear Operations Co. Beaver Valley 1-2 x FirstEnergy Nuclear Operating Co. Davis-Besse x Florida Power & Light Seabrook x Florida Power & Light St. [Lucie 1-2 x Florida Power & Light Turkey Point 3-4 X Florida Power & Light Point Beach 1-2 x Indiana Michigan Power Corp D C Cook 1-2 x Northern States Power Prairie Island 1-2 x Omaha Public Power District Fort Calhoun x Pacific Gas & Electric Co. Diablo Canyon 1-2 X Progress Energy Crystal River 3 x Progress Energy Robinson xx Progress Energy Shcaron Harris X PSEG Nuclear LLC Salenl I x PSEG Nuclear LLC Salem 2 x South Carolina Electric & (;as Co. Su,*1ier x South Texas Project Nuclear Operating Co. South Texas Project 1-2 x Southcrn California Edison Co. San Onolrc 2-3 x Southern Nuclear Operaming Co, Fiarley 1-2 X Southern'i Nukiclea Operating Co. VogLo I-2 "l'(:IMn!'cS* V1/ley Ac\uthui'ity Setluoy;ih I-2

9106024829 ATC 1st FLOOR 09!58:39 a.m. 12-13-2012 9/11 MFN 12-128 RO Page 3 of 3 x Tennessee Valley Authority Watts Bar I x TXU Electric Generation Co. Comanche Peak 1-2 x Wolf Creek Nuclear Operating Corp. Wolf Creek

9106024829 ATC 1st FLOOR 09:58:44 a.m. 12-13-2012 10/11 MFN 12-128 RO Page 1 of 2 Attachment 3 60-Day Interim Report Notification Information per §21.21(a)(2)

(i) Name and address of the individual or individuals informing the Commission.

Dale E. Porter GE Hitachi Nuclear Energy Safety Evaluation Program Manager 3901 Castle Hayne Road, Wilmington, NC 28401 (ii) Identification of the facility, the activity, or the basic component supplied for such facility which fails to comply or contains a defect.

AM 4.16-350-2C and AM 4.16-350-2H Magne-Blast Circuit Breakers (iii) Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.

GE Hitachi Nuclear Energy (iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.

Failure of a Safety Related AM 4.16-350-2H/2C breaker to close or open. Failure to prevent arching between phases during opening.

(v) The date on which the information of such defect or failure to comply was obtained.

A Potential Reportable Condition Evaluation in accordance with 10 CFR Part 21 was initiated on October 30, 2012.

(vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.

As a conservative measure this Transfer of Information is being supplied to all BWR and PWR plants as the AM 4.16-350-2H/2C breaker is widely used.

(vii) The corrective action, which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.

GEH will complete the testing and post-test evaluation and issue either a closure of this 10CFR Part 21 concern or issue an update, based on the results of these tests, by June 14, 2013.

. 910 602 4829 ATC 1st FLOOR 09:58:59 a.m. 12-13--2012 1/11 MFN 12-128 RD Page 2 of 2 Attachment 3 60-Day Interim Report Notification Information per §21.21(a)(2)

(viii) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.

GEH advises Licensees to take no action at this time.

(ix) In the case of an early site permit, the entities to whom an early site permit was transferred.

This is not an early, site permit concern.