IR 05000263/2019003

From kanterella
(Redirected from IR 07200058/2019001)
Jump to navigation Jump to search
Integrated Inspection Report 05000263/2019003 and 07200058/2019001
ML19319A809
Person / Time
Site: Monticello  Xcel Energy icon.png
Issue date: 11/14/2019
From: Julio Lara
NRC/RGN-III
To: Church C
Northern States Power Co
References
EA-14-193 IR 2019001, IR 2019003
Preceding documents:
Download: ML19319A809 (26)


Text

November 14, 2019

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000263/2019003 AND 07200058/2019001

Dear Mr. Church:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On October 22, 2019, the NRC inspectors discussed the results of this inspection with Mr. C. Church, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

Additionally, this inspection focused on assessing one open Condition (V.9) related to Confirmatory Order EA-14-193, issued December 21, 2015 (ML15344A459). Previously Confirmatory Order Conditions V.1, V.2, V.3, V.4, V.5, V.6, V.7, and V.8 were closed in NRC Inspection Report (IR) Nos. 05000263/2017008, 07200058/2017001, 05000263/2018004 and 07200058/2018002. The inspector review of Condition V.9 was satisfactory and the Condition is closed.

The NRC has determined that the results of this inspection, in conjunction with previously completed inspection activities related to interim milestones, provide adequate assurance that the required terms as directed by the December 21, 2015, Confirmatory Order have been satisfied by Northern States Power Company, Minnesota. Confirmatory Order EA-14-193 is closed. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA Mohammed Shuaibi Acting for/

Julio F. Lara, Director Division of Reactor Projects

Docket No. 05000263 and 07200058 License No. DPR-22

Enclosure:

As stated

Inspection Report

Docket Number:

05000263 and 07200058

License Number:

DPR-22

Report Number:

05000263/2019003 and 07200058/2019001

Enterprise Identifier: I-2019-003-0062 and I-2019-001-0151

Licensee:

Northern States Power Company, Minnesota

Facility:

Monticello Nuclear Generating Plant

Location:

Monticello, MN

Inspection Dates:

July 01, 2019 to September 30, 2019

Inspectors:

N. Egan, Sr Physical Security Inspector

T. Go, Health Physicist

L. Haeg, Senior Resident Inspector

D. Krause, Resident Inspector

V. Myers, Senior Health Physicist

P. Negrete, Security Specialist

V. Petrella, Reactor Inspector

K. Pusateri, Resident Inspector

J. Robbins, Reactor Inspector

N. Shah, Project Engineer

M. Ziolkowski, Sr Physical Security Inspector

P. Zurawski, Senior Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Monticello Nuclear Generating Plant in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000263/2019-002-00 LER 2019-002-00 for Monticello Nuclear Generating Plant, Two Manual Primary Containment Isolation Valves Found Open Resulting in a Condition Prohibited by Technical Specification 71153 Closed OR EA-14-193 Confirmatory Order for NDE on Dry Cask Condition V.9 92702 Closed

PLANT STATUS

Monticello began the inspection period operating at approximately 100 percent power and, with the following exceptions, remained at that level throughout the inspection period. Environmental temperature and canal discharge temperatures resulted in power reductions to the following approximate power levels: July 15, 2019 (90 percent); July 18, 2019 (90 percent); and July 19, 2019 (80 percent). On September 14, 2019, the unit was down-powered to 73 percent for quarterly turbine valve testing. The unit was returned to 100 percent after each power reduction.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated readiness for impending adverse weather conditions for extreme hot weather affecting Canal Discharge Temperatures on July 16, 2019

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

(1)12 Standby Liquid Control (SBLC) System protected while 11 SBLC in maintenance on August 5, 2019

(2) Reactor Core Isolation Cooling (RCIC) System while protected on September 17, 2019 (3)
  1. 13, 250 VDC System while protected on September 18, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the "A" Reactor Protection System (RPS) train that was protected while troubleshooting "B" RPS train on July 23, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (5 Samples)

(1) Fire Zone (FZ) 03-A - Recirculation Motor Generator area on July 26, 2019
(2) FZ 13-C - Turbine Building 911 level motor control center on July 30, 2019
(3) FZ 31-A - Emergency Filtration Train, 1st Floor - Division I on August 6, 2019
(4) FZ 13-B - Rx Feed Water Pump and Lube Oil Reservoir on September 7, 2019
(5) FZ 05-C - Fuel Pool Skimmer Tank Room on September 27, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Underground Cables (IP Section 02.02c.) (1 Sample)

(1) Vaults 2MH01, 2MH02, 2MH03, 2MH04, CP100, NMH301, NMH302 on August 2, 2019

71111.07A - Heat Sink Performance

Annual Review (IP Section 02.01) (1 Sample)

(1)11 Emergency Diesel Generator (EDG) Emergency Service Water (ESW) Heat Exchanger on July 15, 2019

===71111.07T - Heat Sink Performance

Triennial Review (IP Section 02.02)===

(1) Residual Heat Removal Division 2 Heat Exchanger, E-200B (2)13 Residual Heat Removal Pump Motor Cooler, P-202C
(3) Ultimate Heat Sink, Section 02.02d, specifically Sections 02.02d.6 and 02.02d.7 were completed

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during minimum shift staffing activities arising from labor actions on September 5, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated Licensed Operator Requalification; MT-LOR-19D-001V, Crew 2 on August 12, 2019
(2) The inspectors observed and evaluated Licensed Operator Requalification; Monticello Emergency Preparedness Evaluated Exercise on September 10, 2019

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

(1) Structural Monitoring of Condensate Storage Tanks on August 28, 2019
(2) 11 and 12 Emergency Diesel Generators on August 29, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

(1) CV-3134: "D" Moisture Separator Drain Tank Drain Valve failure on July 15, 2019
(2) G-6: Security Diesel Engine Cycling issues on July 15, 2019
(3) DPIS-2-129B, Recirculation Loops DP-LPCI Select interlock; Troubleshoot and Repair, on September 15, 2019
(4) VD-9051B, "A" Control Room Ventilation Fresh Air Damper Excessive Oil Leak on September 25, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (4 Samples)

(1) Control Rod Drives (CRD) Refurbished without ASME X1 RR Plan on August 1, 2019
(2) Emergency Core Cooling System (ECCS) Instrumentation Recirculation Riser Differential Pressure Instrumentation Switch (DPIS) failed on August 15, 2019 (3)12 ESW Pump Discharge Check valve missed IST Surveillance on August 22, 2019
(4) Drywell Spray Valve thrust exceeding design basis on September 9, 2019

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

(1) Use of low-side switches for DPIS-2-129B, high side failed on August 16, 2019
(2) Removed bad temperature signal point from TR-2-2-31; 11 Recirculation Pump, on September 30, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

(1) OPS-G-3A, 11 EDG #2 Air start Post Maintenance Test (PMT) on July 16, 2019
(2) RM-7858A, A Stack WRGM PMT on July 18, 2019 (3)12 EDG PMT on July 23, 2019
(4) OPS-PCIV-2092; RCIC Cooling Water to Barometric Condenser PMT/TRS on September 8, 2019
(5) MO-1751; 11 Core Spray Injection Outboard Isolation Valve PMT on September 11, 2019

71111.22 - Surveillance Testing

Surveillance Tests (other) (IP Section 03.01) (1 Sample)

(1) "A" Standby Gas Treatment System Filtration Test on July 20, 2019

Inservice Testing (IP Section 03.01) (1 Sample)

(1) 0255-09-IA-1; Recirculation System Valve Operability Test on September 10, 2019

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1)0255-01-IIC-2; Reactor Heat Removal (RHR) System Loop "B" Biennial Leakage Inspection on August 21, 2019

FLEX Testing (IP Section 03.02) (1 Sample)

(1) #12 Flex 480V Portable Diesel Generator G-507 on July 16, 2019

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Monticello Full-Scale Emergency Preparedness Drill on August 6, 2019

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

(1) Licensed Operator Requalification; (DEP) MT-LOR-19D-001V, Crew 1 on August 19,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors evaluated radiation monitoring instrumentation during plant walkdowns.

(1) The inspectors reviewed the following:

Portable Survey Instruments

  • RO-20 Ion Chamber SN RO79; Calibration Due Date 03/14/2020
  • Ludlum Model 9-3; SN 93-1; Calibration Due Date 10/04/2019
  • RO-2 SN RO46; Calibration Due Date 03/03/2020
  • Portable ARM DRM-2 MGP SN 534030; Calibration Due Date 06/10/2020
  • Alpha/Beta Counter iSolo Canberra No. 2; Calibration Due Date 11/28/2019

Source Check Demonstration

  • Telepole TP-5; Calibration Due Date 09/11/2020
  • Small Article Monitor (SAM); Source Checked on 09/12/2019
  • ARGOS 2-B at 931' Elevation Turbine Building; Calibrated on 09/12/2019

Area Radiation Monitors and Continuous Air Monitors

  • A-1 Refuel Floor Low Range
  • A-2 Refuel Floor High Range
  • A-6 1001' Decon Area
  • A-7 985' Sample Hood
  • A-8 Reactor Clean Up Demineralizer Area
  • A-19 Chemistry Lab
  • F-1 Off-Gas Stg Bldg Foyer
  • F-2 Off Gas Stg Foyer High Range
  • RM-79932 DryWell CAM Rad Monitor at 935' Elevation Reactor Building

Personnel Contamination Monitors, Portal Monitors and Small Article Monitors

  • ARGOS 2-B at 931' Turbine Building; Calibrated on 09/12/2019
  • Small Article Monitor (SAM)

Calibration and Testing Program (IP Section 02.02) (1 Sample)

The inspectors evaluated the calibration and testing program implementation.

(1) The inspectors reviewed the following:

Alarm Setpoint and Calibration Method Check of Personnel Contamination Monitors, Portal Monitors and Small Article Monitors

  • Small Article Monitor (SAM); Source Checked on 09/12/2019
  • ARGOS 2-B at 931' Turbine Building; Calibrated on 09/12/2019

Failure to Meet Calibration or Source Check Acceptance Criteria

  • ARGOS 2-B at 931' Turbine Building; Calibrated on 09/12/2019

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors walked down the following gaseous and liquid radioactive effluent monitoring and filtered ventilation systems to assess the material condition and verify proper alignment according to plant design:

(1)

  • Reactor Building Wide Range Gaseous Monitors
  • Plant Stack Wide Range Gaseous Monitors
  • Discharge Canal Liquid Monitor
  • Turbine Building Normal Waste Sump Liquid Monitor
  • Standby Gas Treatment Filtration System Calibration and Testing Program (Process & Effluent Monitors) (IP Section 02.02) (1 Sample)

The inspectors reviewed the following gaseous and liquid effluent monitor instrument calibrations and tests:

(1)

  • Plant Stack Wide Range Gaseous Effluent Monitor Train "A"
  • Turbine Building Normal Waste Sump Liquid Monitor

Sampling and Analysis (IP Section 02.03) (1 Sample)

The inspectors reviewed the following:

(1) Radioactive Effluent Sampling and Analysis Activities
  • Plant Stack Continuous Discharge Sampling
  • Reactor Building Continuous Discharge Sampling
  • Turbine Building Normal Waste Sump Discharge Sampling

Instrumentation and Equipment (IP Section 02.04) (1 Sample)

The inspectors reviewed the following radioactive effluent discharge system surveillance test results:

(1) Standby Gas Treatment System

Dose Calculations (IP Section 02.05) (1 Sample)

The inspectors reviewed the following to asses public dose:

(1) Liquid and Gaseous Discharge Permits
  • Drywell Purging via Stack, MTGB2018-101
  • Plant Stack Continuous, MTGC2019-026
  • Reactor Building Vent Continuous, MTCG2019-032

Annual Radiological Effluent Release Reports

Abnormal Gaseous or Liquid Tank Discharges

  • Abnormal Liquid Discharge, MTLB2007-002

71124.07 - Radiological Environmental Monitoring Program

Site Inspection (IP Section 02.01) (1 Sample)

The inspectors evaluated the radiological environmental monitoring program implementation.

(1) The inspectors reviewed the following:

Walkdowns, Calibrations, and Maintenance Record Review

  • Air Station M-1 Location within 11 miles at Sector NW (Control)
  • Air Station M-2 Location within 0.8 miles at Sector SE
  • Air Station M-3 Location within 0.6 miles at Sector ESE
  • Air Station M-4 Location within 0.8 miles at Sector SSE
  • Air Station M-5 Location within 2.6 miles at Sector SE
  • TLD M09A County Road 75, 0.38 miles at Sector SSW
  • TLD M10A County Road 75, 0.38 miles at Sector SW
  • TLD M07A Parking Lot H, 0.47 miles at Sector SSE
  • TLD M04S Pinewood School, 2.3 miles at Sector SE
  • TLD M06S Monticello Public Works. 2.6 miles at Sector SE
  • No. 5829; REMP Air Samplers Calibration; dated 02/13/2018
  • Dose Assessment for Operation of MNGP During 2018 Calendar Year Calculation
  • 154-Rascal Data Validation MET/Rad Data Sources; dated 07/23/2019

Environmental Sample Collections and Preparation Observation

  • River Water M-8(c) Upstream of the Plant within 1000 ft Upstream of the Plant Intake
  • River Water M-9 Downstream of the Plant within 1000 ft Downstream of the Plant Discharge
  • Vegetation M-41 Training Center within 0.8 miles at Sector SSE
  • Vegetation M-42 Biology Station Road within 0.6 miles at Sector SE

Licensee Actions in Response to Missed Sample, Inoperable Sampler, Lost TLD or Anomalous Measurement

  • River Water Sampling Upstream M-8; water frozen entire month, no composite for 2018
  • Air Station M-2; station lost power from the service drop, sampler was restarted on 06/08/2018 with temporary power
  • Fish Samples M-8 and M-9; invertebrate samples were collected late due to unsafe river conditions; Spring 2018
  • M-8 on the 4th Quarter 2018 quarterly composites were not collected; due to frozen water; dated 11/07/2018

Sampling Program for the Potential of Licensed Material Entering Groundwater

  • Monitoring Well MW-9A has indicated elevated tritium level; tritium plume originated from process water that migrated through turbine building; it was discovered in 2009 and corrected in 2011 after analysis and remediation
  • Monitoring Well MW-10; tritium is regularly identified on this well part of the groundwater monitoring of below grade piping under the Turbine Building

Groundwater Protection Initiative (GPI) Implementation (IP Section 02.02) (1 Sample)

(1) The inspector reviewed licensee's actions as a result of a leak through MW-9A surveillance originated from process water that migrated through turbine building that was discovered in 2009 and it was corrected in 2011. Ongoing surveillance per Groundwater Protection Initiative at the time of the inspection.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification MS06: Emergency AC Power Systems (IP Section 02.05)

(1) Unit 1 (07/01/2018 - 06/30/2019)

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) Unit 1 (07/01/2018 - 06/30/2019)

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) Unit 1 (07/01/2018 - 06/30/2019)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 1 01/01/2018 - 12/31/2018

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Unit 1 01/01/2018 - 12/31/2018

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) Unit 1 01/01/2018 - 12/31/2018

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action and adverse condition monitoring programs for potential adverse trends involving safety system leakage that might be indicative of a safety issue during the weeks of September 16 & 23, 2019.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Repeat issues with RCIC Primary Containment Isolation Valve (PCIV) instrumentation on September 30, 2019
(2) Repetitive leaking vent/siphon quick connect fitting prior to completing sealing operations on Dry Shielded Canisters dated February 6 through September 30, 2019

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

(1) LER 2019-002, Two Manual Primary Containment Isolation Valves found open resulting in a condition prohibited by Technical Specifications (ADAMS accession:

ML19221B735.) Inspector review of the circumstances of this LER was conducted as part of Inspection Report 05000263/2019002. A Green Non-Cited Violation of Technical Specification 5.4.1.a had been identified in Section 71153 of that report.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===92702 - Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders

Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders (1 Sample)

(1) The inspectors reviewed documents to determine if adequate corrective actions had been implemented associated with Confirmatory Order (CO) EA-14-193, and NRC IR Nos. 05000263/2015008 and 07200058/2014001. Specifically, the inspectors evaluated the corrective actions associated with CO Condition V.9: Completion Letter.

92709 - Licensee Strike Contingency Plans

Licensee Strike Contingency Plans===

(1) On August 31, 2019, at midnight, the contract between the United Security Professionals (USP) Local 2, who represent security supervisors, and G4S expired.

In preparation for the strike/lockout, the NRC inspectors evaluated the adequacy of the licensees contingency plan. The inspectors assessed the adequacy of the strike/lockout staffing levels, staff training and qualifications, safety conscious working environment, and site access in meeting operational and security requirements.

92711 - Continued Implementation of Strike Plans During An Extended Strike Continued Implementation of Strike Plans During An Extended Strike

(1) On August 31, 2019, at midnight, the contract between the United Security Professionals (USP) Local 2, which represents MNGPs security supervisors, and G4S expired. During the strike/lockout, the NRC inspectors evaluated the adequacy of the licensees implementation of its contingency plan. The inspectors assessed:

1. The augmented security supervisor force transition of duty

2. The continuity of security force operation

3. The impact of plant operations, minimum staffing requirements, safety

conscious working environment, and site access

92712 - Resumption of Normal Operations After A Strike Resumption of Normal Operations After A Strike

(1) On September 6, 2019, a tentative contract between the United Security Professionals (USP) Local 2, which represents MNGPs security supervisors, and G4S was reached. On September 9, 2019, MNGPs security supervisors returned to duty. The contract was ratified on September 24, 2019. During the resumption of normal operations following the strike/lockout, the NRC inspectors evaluated the adequacy of the licensees transition from a strike/lockout condition to normal plant operation.

INSPECTION RESULTS

Observation: Adverse Condition Monitoring Program - Safety System Leakage 71152 The inspectors did a semi-annual review, in aggregate, of safety system leakage issues being monitored as part of the licensee's adverse condition monitoring program. Programmatic requirements and processes were also reviewed to determine whether active safety system leakage adverse conditions were being appropriately tracked, managed, and resolved. The inspectors also reviewed whether the licensee was appropriately monitoring adverse conditions by establishing criteria or set points for which further evaluation or action was designated. The inspectors determined, overall, that the licensee was effectively managing adverse conditions and no concerns were identified as part of this review.

Observation: RCIC Primary Containment Isolation Valve Issues 71152 As part of routine corrective action program document reviews, the inspectors noted a trend in repetitive issues with reactor core isolation cooling primary containment isolation instrumentation. Specifically, inspector's noted Quality Management Issue (QIM)501000030703 identified differential pressure indicating switch (DPIS) DPIS-13-84 (RCIC High Steam Flow Isolation) had been found out of its As-Found tolerances on August 13, 2019 during its quarterly calibration. Review of the calibration history for this component determined that the DPIS had been outside of its As-Found tolerances six times in the last two years. In each case the DPIS was restored to within As-Left tolerances with no issues.

Inspectors reviewed licensee actions to the QIM and determined the licensee appropriately implemented its corrective program in regard to identification, disposition, and correction of the issue. Given the trend, the inspectors also reviewed the licensee's extent of condition and determined it included a review of calibration history for RCIC high steam flow isolation DPIS (13-83) as well as both HPCI high steam flow switches (DPIS-23-76A & DPIS23-76B).

Overall, the licensee evaluation of the As-Found switch out of tolerances were a result of drift between calibrations and remained in the conservative direction. Inspectors determined the licensee established an action to evaluate expanding the DPIS set-point bands. Overall, the inspectors did not identify any concerns as part of this review.

Observation: Dry Canister Vent/Siphon Helium Leakage 71152 As part of routine corrective action reviews, the inspectors noted two licensee-identified issues relating to dry storage canister vent/siphon helium leakage. Inspectors determined these issues to be noteworthy of further review because of an open dry cask storage Confirmatory Order. Inspectors determined the licensee appropriately documented the two issues in its corrective action system. The inspectors reviewed licensee corrective actions associated with each issue and did not have any concerns. Additionally, the inspectors determined that as part of the licensee's extent of condition review, two additional helium leakage issues had been identified by the licensee. Similar reviews were conducted by the inspectors with no concerns identified. Overall, inspectors determined the licensee adequately implemented its corrective action program no concerns were identified as part of this review.

Confirmatory Order (Closed)

Confirmatory Order for NDE on Dry Cask Condition V.9 OR 92702

Description:

Condition V.9 stated "Upon completion of all terms of the Confirmatory Order, Xcel Energy shall submit to the NRC a letter discussing its basis for concluding that the Order has been satisfied." On March 26, 2016, Xcel Energy submitted a letter to describe the completion of actions taken to satisfy all the CO conditions. With the submission of the completion letter on March 26, 2019, CO Condition V.9 is considered complete. Previously CO Conditions V.1, V.2, V.3, V.4, V.5, V.6, V.7, and V.8 were closed in NRC Inspection Report (IR) Nos.

05000263/2017008, 07200058/2017001, 05000263/2018004 and 07200058/2018002.

EA 14-193

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On October 22, 2019, the inspectors presented the integrated inspection results to Mr. C. Church, Site Vice President and other members of the licensee staff.
  • On July 25, 2019, the inspectors presented the Radioactive Gaseous/Liquid Effluent Treatment and REMP Inspections inspection results to Mr. D. Barker, Plant Manager and other members of the licensee staff.
  • On August 23, 2019, the inspectors presented the Exit Meeting inspection results to Mr. D. Barker, Plant Manager and other members of the licensee staff.
  • On September 13, 2019, the inspectors presented the Radiation Monitoring inspection results to Mr. C. Church, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

501000029549

Down Power due to Environmental Conditions

501000029601

River Appropriation Limits Reached

71111.04Q Drawings

NE-36640-4

250V DC Distribution & Panel Schedule D31, D33

NH-36251

P&ID RCIC (Steam Side)

NH-36252

P&ID RCIC (Water Side)

NH-36253

Standby Liquid Control System

NX-7879-4

Standby Liquid Control System Process Diagram

2

Miscellaneous

B.09.09-01

250 VDC System; Function and General Description of

System

Procedures

0913-01

No. 13 250 VDC Battery Operability Check (Division 1)

71111.04S

Drawings

NE-36771-4

Reactor Protection Power System Distribution Panel Y40 &

Y50

NX-7834-63

Elementary Diagram RPS MG Set Control

075

NX-7834-67-10

Elementary Diagram Reactor Protection System

Miscellaneous

B.09.12-05

Reactor Protection Power Supplies - System Operation

71111.05Q Fire Plans

A.3-03-A

Fire Strategy for Zone 3-A - Recirculation Motor Generator

Set Room

A.3-05-C

Fire Strategy for Zone 5-C - Fuel Pool Room

A.3-13-B

Fire Strategy for Zone 13-B - Turbine Building (Feed Water

Pump Area) - Elevation 911

A.3-13-C

Fire Strategy for Zone 13-C - Turbine Building Basement -

MCC Area East

A.3-31-A

Fire Strategy for Zone 31-A - Emergency Filtration Train

Building - 1st Floor (Division 1)

71111.06

Calculations07-021

Reactor Building, Turbine Building, & Intake Structure Water

Height - Internal Flooding

1-A

07-029

Reactor Building, Turbine Building, & Intake Structure Water

Height - Internal Flooding

0-B

Drawings

NF-36763

Raceways, Grounding & Direct Buried Cable Runs - South

Turbine Generator Building

Miscellaneous

DBD-S.04

Intake Structure

71111.07A

Work Orders

700040957

EDG ESW Heat Exchanger Performance Test

08/29/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07T

Calculations07-045

RHR Pump Motor Model 5K511DT5410 Cooling Coil

Minimum Flow Evaluation

2A

97-056

Determination of RHR Heat Exchanger U-Values and K-

Values at Various Flow Conditions

Calibration

Records

LT-1852 and LT-1853 Calibration Records

Corrective Action

Documents

01517655

RHR Motor Outlet Cooling Flow Less Than Required

04/03/2016

501000007157

RHR Motor Flow < 2 gpm via FI-4955

01/11/2018

501000021445

P-109D Low Pressure During Surveillance

2/27/2018

501000026135

B FSW Leak in Elbow

04/23/2019

Corrective Action

Documents

Resulting from

Inspection

501000030960

NRC Question

08/19/2019

501000030967

2019 UHS - A.6 River Temp Question

08/20/2019

501000031066

2019 UHS - OG Comp Leak Into Cooling SYS

08/22/2019

Drawings

NH-36664

P&ID RHR Service Water & Emergency Service Water

Systems

NH-36665

P&ID Service Water System & Make-Up Intake Structure

104

Miscellaneous

CW PMP Pit Level and the 12 CW PMP Pit Level Trend

Report

1R29 SW/MIC Results Summary Table

1R28 SW/MIC Results Summary Table

IST-ESW Pump 14 Vibration Trends

IST-ESW Pump 13 Vibration Trends

IST - ESW Pump 12 Vibration Trends

IST - ESW Pump 11 Vibration Trends

IST - RHRSW Pump 14 Vibration Trends

IST - RHRSW Pump 13 Vibration Trends

IST - RHRSW Pump 12 Vibration Trends

IST - RHRSW Pump 11 Vibration Trends

NDE Reports

XCEL11-MN1-03

Final Eddy Current Inspection Report NO: XCEL#11-MN1-

of Residual Heat Removal RHR HX E-200B for

Monticello Nuclear Generating Plant RFO25 - March 2011

03/24/2011

Procedures

A.6

Acts of Nature

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EWI-11.01.14

Buried Piping and Tanks Inspection

FP-PE-FAC-01

FAC Program

FP-PE-SW-01

SW/MIC Program

FP-PE-UPT-01

Underground Piping and Tanks Integrity Program

Work Orders

00394234

PM 4058-1 ("A" RHR Room MTR Cooler Cleaning & Test)

04/09/2011

00440540

PM 4058-1 ("A" RHR Room MTR Cooler Cleaning & Test)

04/20/2013

00491126

PM 4126 (Inspect West Service Water Bay)

04/24/2015

00491127

PM 4125 (Inspect East Service Water Bay)

05/07/2015

00504142

P-202C/MTR, Replace Motor Cooling Coil

09/01/2015

00519464

1136-02 RHR Heat Exchanger Efficiency Test - DIV II

2/23/2017

00529075

255-11-III-3 13 ESW Pump Flow Test

04/03/2016

00531773

1404-01 11 EDG ESW Heat Exchanger PRFM Test

11/22/2016

00533934

PM 4126 (Inspect West Service Water Bay)

05/14/2017

00534534

255-05-IA-1-2 "B" RHRSW QRTRLY PMP & Valve Test

06/30/2016

00534919

255-11-III-3 13 ESW Pump Flow Test

07/07/2016

00535068

255-05-IIC-1 RHRSW System Leakage Test - Loop A

04/25/2017

00535069

255-11-IIC-1 ESW System Leakage Test - Loop A

04/22/2017

00535070

255-11-IIC-3-1 EDG-ESW Loop A Leak TST-Access

Compon

07/10/2016

00535071

255-11-IIC-3-2 EDG/ESW Leak Test - Loop A Buried

Piping

11/22/2016

00540063

255-05-IA-1-2 "B" RHRSW QRTRLY Pump & Valve Test

09/30/2016

00540526

255-11-III-3 13 ESW Pump Flow Test

10/14/2016

00545290

255-05-IA-1-2 "B" RHRSW QRTRLY Pump & Valve Test

2/28/2016

00545647

255-11-III-3 13 ESW Pump Flow Test

01/06/2017

00549811

255-05-IA-1-2 "B" RHRSW QRTRLY Pump & Valve Test

03/30/2017

00550108

255-11-III-3 13 ESW Pump Flow Test

04/04/2017

00554448

255-05-IA-1-2 "B" RHRSW QRTRLY Pump & Valve Test

06/30/2017

00554799

255-11-III-3 13 ESW Pump Flow Test

07/06/2017

533935

E Service Water Bay

09/22/2016

700014461

RHR Heat Exchanger Efficiency Test

2/18/2018

700014471

"B" RHRSW Quarterly Pump and Valve Tests

2/28/2017

700017684

ESW Quarterly Pump and Valve Tests

10/05/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

700017685

ESW Quarterly Pump and Valve Tests

01/11/2018

700021812

Comprehensive 12 RHRSW Pump and Valve Tests

04/02/2018

700026492

RHR Pump 13 and Core Spray Pump 11 Motor Cooler

Chemical Cleaning

06/18/2018

700027873

"B" RHRSW Quarterly Pump and Valve Tests

05/11/2018

700028135

ESW Quarterly Pump and Valve Tests

07/05/2018

700028543

West Service Water Bay Inspection/Dredging

05/14/2019

700028562

EDG ESW Heat Exchanger Performance Test

09/05/2018

700031712

RHR Service Water System Leakage Test - Loop B

04/24/2019

700031715

Emergency Service Water System Leakage Test - Loop B

05/06/2019

700031716

EDG-ESW System Leakage Test Loop B Accessible

Pressure Boundary Components

08/09/2018

700032957

ESW Comprehensive Pump and Valve Test

04/04/2018

700033107

"B" RHRSW Quarterly Pump and Valve Tests

06/26/2018

700033331

ESW Quarterly Pump and Valve Tests

10/10/2018

700033406

East Service Water Bay Inspection/Dredging

04/27/2019

700036565

"A" RHRSW Quarterly Pump and Valve Tests

2/06/2018

700037422

"B" RHRSW Quarterly Pump and Valve Tests

09/27/2018

700037458

"B" RHRSW Quarterly Pump and Valve Tests

2/28/2018

700038490

ESW Quarterly Pump and Valve Tests

01/09/2019

700042061

Emergency Diesel Generator / 12 ESW Quarterly Pump

and Valve Tests

2/01/2019

700045733

"B" RHRSW Quarterly Pump and Valve Tests

03/29/2019

700046070

ESW Quarterly Pump and Valve Tests

04/12/2019

700050083

"B" RHRSW Quarterly Pump and Valve Tests

06/27/2019

700054695

MT:1:ESW:ESW5-4-HBD

700054695

Pipe

71111.11Q Miscellaneous

Monticello Nuclear Generating Plant Emergency Plan Full

Exercise

09/10/2019

MT-LOR-19D-

001V - RQ-SS-

113

Simulator Exercise Guide (Crew 2)

71111.12

Corrective Action

501000018660

Emergency Diesel Generator Failed to Load

10/15/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

501000020519

EDG Oil Temperature Trending Down

501000020848

EDG Coolant Leak

501000020998

DGN Engine Signature Analysis Results

501000021007

DGN Engine Signature Analysis Results

501000024068

Coolant Leak on 11 EDG

501000025369

EDG Procedure Step Not Within Band

501000025405

Portions of 11 EDG PM and Test Not Performed

501000027532

NRC Questions on 12 EDG

501000027722

Small Oil Leak on 11 EDG

501000028287

Monticello Nuclear Generating Plant Maintenance Rule

Condensate Storage Tank Condition Monitoring

501000029082

EDG Oil Seeps

501000029844

G-3A, 11 EDG Low Oil Level

501000030102

EDG Governor Leaking

501000030576

EDG Oil Pump Increased Oil Leak

Engineering

Evaluations

501000018660

Emergency Diesel Generator Failed to Load

2000006755

Maintenance Rule Functional, MSPI and Equipment

Reliability Clock Reset Failure Evaluation

10/23/2018

NUC2017147

Condensate Storage Tanks, Desludge, Inspection and

Repair

Miscellaneous

2019 Period 1

Plant Health Report--System Report, "Condensate and

Reactor Feedwater System"

2019 Period 1

System Report--Emergency Diesel Generator

Operability

Evaluations

501000018660

Past Operability Evaluation for 11 Emergency Diesel

Generator Failure to Load

10/24/2018

Work Orders

00446817

1385 Periodic Structural Online Inspection

11/04/2013

700006331

1385 Periodic Structural Inspection

09/06/2018

700036105

Condensate Storage Tank Aging Management Walkdown

Completion

2/15/2018

71111.13

Corrective Action

Documents

501000029418

Security Diesel Test Abort due to Speed Control Issues

501000029526

CV-3134 Not Controlling Level

501000030792

DPIS-2-129B did not Reset

501000031945

VD-9051B Excessive Oil Leak

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

700059052

Diesel Engine Emergency Security Power

07/15/2019

700063297

VD-9051B Excessive Oil

09/17/2019

71111.15

Corrective Action

Documents

501000030066

Containment Spray Valves Thrust Exceeds Calculations

501000030237

CRDs Refurbished without ASME XI RR Plan

501000031053

ESWW-1-2 IST Test not Performed in 1R29

Engineering

Changes

601000001705

Use of Low Side Contact for DPIS-2-129B

Miscellaneous

2019-29-041

ASME Section XI Repair/Replacement Plan

08/05/2019

Procedures

FP-PE-MOV-07

Motor Operated Valve Program

71111.18

Engineering

Changes

601000001574

Remove Bad Temperature from TR-2-2-31, Recirculating

Pump "A" Motor Temperature Element

05/31/2019

601000001705

Low Side Output Switch for DPIS-2-129B

08/16/2019

71111.19

Work Orders

700023229

Emergency Diesel Generator #1 Air Start PMT

07/25/2019

700039721

Core Spray injection Outboard Valve PMT

09/12/2019

700039817

4100-2, 11 Diesel Generator G-3A #2 Air Start System

07/16/2019

700051669

Stack "A" Effluent Noble Gas Monitor PMT

07/20/2019

700052015

RCIC Quarterly Pump and Valve Tests

08/16/2019

71111.22

Work Orders

700020892-0010

"A" Train Standby Gas Treatment System Filter Tests

08/16/2017

700024592-0020

"A" Train Standby Gas Treatment System Filter Tests

2/08/2018

700040870

G-507-Flex Generator Annual Preventative Maintenance

07/15/2019

700052934

Recirculation System Valve Operability Test

08/25/2019

700054406

253-01A, Standby Gas Treatment Train "A" Monthly Test

07/20/2019

700056662

Residual Heat Removal System Leakage Test - Loop B

08/20/2019

71114.06

Miscellaneous

Monticello Emergency Plan Full Scale Drill Guide/Scenario

08/06/2019

MT-LOR-19D-

001V

Licensed Operator Requalifcation; (DEP) Crew 1

08/19/2019

71124.05

Calculations

Mirion Service

Calibration of the Canberra Fastscan WBC System at the

XCel Energy Monticello Nuclear Generating Plant

2/20/2019

Calibration

Records

0908-177

UTC516834

NSPM RP Instrument Response Investigation Report

2/14/2018

309888/3098889

NSPM RP Instrument Response Investigation Report

03/21/2018

AZ-11 UTZ

No:478971

ARGOS Calibration

09/12/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Model 89-400

J.L. Shepherd & Associates Model 78-2M Calibrator

01/28/1991

NSP No. 248

Source No. 81622

Certificate of Radioactivity Calibration of Cs-137 Sealed

Source Containment High Range Radiation Monitor

11/01/1981

PM-7-1 UTC

310244

Portal Monitor Calibration PM-7

06/04/2018

TP-5 UTC 515541 MG Telepole Calibration

09/11/2019

WO 700014151-

20

Containment High Range Radiation Detectors Calibration

Procedure

04/24/2019

Corrective Action

Documents

501000009743

RP Procedure R.09.14 Outdated Info

03/20/2018

Corrective Action

Documents

Resulting from

Inspection

501000031850

NRC Observation of Containment High Range Monitor Cal

Source Strength

09/13/2019

Procedures

28-02

Containment High Range Radiation Detector Calibration

Procedure

R.09.14

Micro REM Calibration and Functional Check

R.09.62

ARGOS Contamination Monitors Function Check and

Calibration

71124.06

Calibration

Records

Radiation Safety

And Control

Services

Technical Support

Document 17-004

Primary Calibration of Turbine Building Normal Waste Sump

at Monticello Nuclear Generating Plant

Corrective Action

Documents

501000021912

"B" Stack Wide Range Gaseous Monitor Remains Non-

Functional

01/12/2019

501000022675

Traceability for Stack and Reactor Building Vent Wide

Range Gaseous Monitor Calibration

2/01/2019

501000023937

Incorrect Calibration Coefficient In RADEAS

03/07/2019

Engineering

Changes

235

Methodology for Determining Stack Noble Gas Release

Rates

Procedures

I.02.06

Airborne Continuous Release Report

I.02.08

Airborne Batch Release Report

I.02.09

Stack/Reactor Building Vent Sample Analysis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

I.05.09

Stack/Vent Tritium Sampling

I.05.26

Stack Noble Gas Sampling

Work Orders

700021755-0010

Reactor Building Vent Wide Range Gas Monitor Calibration

03/21/2018

700034829-0010

Service Water Monitor Calibration

11/07/2018

700036453-0010

Stack Wide Range Gas Monitor Calibration

2/13/2018

700051669-0010

Stack "A" Effluent Noble Gas Monitor

07/15/2019

71124.07

Corrective Action

Documents

501000013464

Missed REMP Air Sample Plant Access Road

06/20/2018

501000013755

The M0-5S & M0-5SE Environmental REMP TLDs, One

Came Up Missing, the Other Damaged

06/28/2018

603000000923

Missed 2018 REMP Sample Tracking

01/03/2018

Corrective Action

Documents

Resulting from

Inspection

501000030003

NRC Observation during REMP Walkdown; M-4 Air Sample

was Facing Away from the Plant

07/24/2019

Engineering

Evaluations

1015118 Priority

Index Worksheet

Guideline For Implementing a Groundwater Protection

Program at Nuclear Power Plants

08/23/2017

AT-0175

CFR 50.75(g) Files

09/09/2009 -

07/30/2011

No. 8010; Docket

No. 50-263

ATI Environmental Midwest Lab; Annual Radiological

Environmental Operating Report

01/01/2018 -

2/31/2018

Project #4583-01

2017 ANNUAL GROUNDWATER MONITORING REPORT

from Carlson/McCain Engineering Report

05/01/2017

Miscellaneous

ODCM-07.01

Offsite Dose Calculation Manual; Radiological

Environmental Monitoring Program

Procedures

1.05.41

Annual Land Use Census and Critical Receptor Identification 10

1308

MET Tower Inspection Procedure

Self-Assessments 2018 ARERR

2018 Annual Radioactive Effluent Release Report

05/13/2019

71151

Miscellaneous

QF0739

NRC Performance Indicator Data; Emergency Preparedness

- MSPI AC Power; 3rd quarter 2017 - 2nd quarter 2018

08/27/2019

QF0739

NRC Performance Indicator Data; Emergency Preparedness

- MSPI High Pressure Injection Systems; 3rd quarter 2017 -

2nd quarter 2018

08/27/2019

QF0739

NRC Performance Indicator Data; Emergency Preparedness

- MSPI Heat Removal Systems; 3rd quarter 2017 - 2nd

08/27/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

quarter 2018

Procedures

QF0445

NRC/INPO/WANO Collection and Submittal Forms Fuel

Performance

71152

Corrective Action

Documents

501000001614

DPIS-13-84 Out of asFfound

501000008279

DPIS-13-84 Found out of as Found

501000015236

DPIS-13-84 Out of as Found

501000019912

DPIS-13-84 Found Outside as-found

501000024127

V-EAC-14B (B CRV) Oil Pressure Low

501000027478

DPIS-13-84 Out of as-found

501000030703

DPIS-13-84 Out as-found

Procedures

501000027329

Drywell Identified Leakage

501000027677

PI-4430B Freon Leak

FP-OP-ACM-01

Adverse Condition Monitoring Plan Process

11/29/2016

71153

Miscellaneous

501000028365

Root Cause Evaluation Report: Primary Containment

Isolation Valves Found Open

2702

Corrective Action

Documents

500001400973

ISFSI DSC 15 Helium Leak When Sealing

501000018344

Unable to Complete DSC Siphon Cover Weld

501000018399

NRC Resident Questions 10-10-18

501000021865

DSC-14 Quick-Connect Leak During Closure

501000023368

DSC-12 Leaking Vent Fitting

Miscellaneous

XcelEnergy Confirmatory Order, EA-14-193, Closure Letter

03/26/2019

50100021865

Prompt Operability Determination

2709

Procedures

CD 11.5

Strike Contingency Plan

2711

Miscellaneous

QF 1727

10CFR20 Work Hour Limits Waiver (Penrod)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Jelen)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Williams)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Broich)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Peterson)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Ergen)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Morgan)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Flood)

09/05/2019

QF 1727

10CFR20 Work Hour Limits Waiver (Maciej)

09/05/2019

Procedures

FP-S-FMP-01

10CFR20 Fatigue Management Fleet Procedure

23