|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:UTILITY
MONTHYEARIR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1989-05-11
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation ML20212N1231987-02-26026 February 1987 Notice of Violation from Insp on 861208-19 IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000509/20060211985-07-0909 July 1985 Notice of Violation from Insp on 850509-0621 IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint ML20055A0551982-06-28028 June 1982 Notice of Violation from Insp on 820607-11 IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items ML20207G8061977-11-21021 November 1977 PNO-77-207:on 771117,WPPSS Issued News Release Which Stated That All Work on WNP 3-5 Site Would Be Terminated to Permit Use of Available Onsite Resources to Control Erosion. Commitment Communicated to State of Washington 1998-11-02
[Table view] |
Inspection Report - Satsop - 1985007 |
---|
|
|
Text
___ _ _ _ = - - _ _ _ . _ .
.
.
[:
t;
- ,
,
-
' ,
F
,.
U. S. NUCLEAR REGULATORY COMMISSION r
REGION'V
. -
,
-
!
. Report No. 50-508/85-07
.
- Docket No. 50-508 Construction Permit No. CPPR-154
.
- Licensee: Washington Public Power Supply System. (WPPSS).
P.'O. Box 1223
. Elma, Washington 98541
- Facility Name: Washington Nuclear Project 3 Inspection at: WNP-3 Site, Satsop,l Washington-Inspection Conducted: October. 7-11, 198 Inspectors: N lo-It -ff
- W. P. Ang, Reattor Inspector Date Signed
'
Approved ~By: Yd 2/ J'
R. T. D6dds, Chief, Reactor Projects Section 1 D4te fiigne ~ ~
Summary:
,
Inspection on October 7-11, 1985 (Report No. 50-508/85-07)
- Areas Inspected
- Routine unannounced inspection.by a-regionally based inspector of containment structural. steel welding procedures, work activities and records and site tour. This. inspection involved 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> onsite by one inspecto Inspection procedures 55151, 55153, 55155 were used for guidanc . .
Results: Of the are s inspected'no violations or deviations were identifie >
'*
<
i ,
,
,
o M V
7 I"
)
,
+
q 4 i G,
,
--Q %
)
p" - t %- , ,, yr -
, 3 -
s_-
t
>
4 s =
. ;
'
.
<+ ;
~
.
-
.k - ' 'S -
__
,
'
_
>
-
,
_
'
~
'
s , '3 _t ~
a ,5- -
,
,.
& ,,-
= DETAILS ,.
.
. .
,
,
\
- ?
. - .- . 7 q; .. + q j_,
'
+
- Persons Contacte ,
- . 's ,
4 m _ , , ,
,
~ Washington Public" Power Supply System;'
g
-
x
- R . ' N .7 Williams,; Deputy > Program Director 1.w , . .. ?
- C. E. ' Love,, Construction Manager
'
63 ._ i
- D. R.gCoody', Project QA' 4 Manager ;
' ~
A. G..Carlyle, QA Engineer '
, .
- y m Ebasco-Services In ,
~ -
'
"
- RL M.' Taylor,-Cons'truction Site Manager-.
- P. L.. Pitman,l Acting; Quality Program' Site Manager -
,
- R.: H. Wang,* Engineering Supervisor, 'New York ! ,
"F. G.'Teague, Resident Enginee .
i G. J. Imus,; Resident Engineer .
'
'
D. G; McKinney, Resident Engineer _ ^
'
V. ,P. Gupta, Ebasco Site Services Engineer (ESSE)
s'
,
H.-Toturgul, ESSE _ ,
- "
-
,..
'
Chicago Bridge and Iron Company(CBI)
~ ~ ,
^
1W. F. Walsh, District Welding;and QA"Hanager B. G. Grimsley,. Area Welding and QA' Manager)
-
- a : E. M. Grant,: Project Superintendent :
.
' -
- J. W. Cain, Project Welding /QA Superintendent
,
- Attended exit interview.* '
~
.
~** Contacted byjtelephone. , '
-
$. *
Unresolved Items * -
, m '.
,
., , . , s . . .-
Unresolved: items are matters about,which"more\information_is required lto .
-
2 determine whether they 'are' acceptable.or may involve violations or; deviations. One'new unresolved' item identified during thisiinspection is
~ ~
a discussed.infparagraph5.b.", _
i
' )IndependentInspectionEffoNt= .
, -
,
, f TLThe inspector conducted a general! inspection of .the reactor building an portions'of the auxiliary, building ~to? observe ' construction progress and
.f, ' construction activities.such as welding,Gmaterial.handlingcand control; A '
l housekeeping and storage.. 'In addition the inspector' discussed the '
~
'
licensee's:and_itsl constructor's!Preparationstfor the planned: containment' '
"
structural integrity:testJ to a'ssess :the ' adequacy' of the:11'censee's- 3 - ~
activities in thatJarea? 9
. . .- l
'
.Within.'th,e areas examined 'no violati.o' ns. oridev.'istions'..were.' identifie .
"
,
- ' '
w , t
'
, , ,
J .'+
y 4 ,'
'
[i) -
4 ,
.n .
< e
,, . g+ ,
- * 1 '
t'
_
_., ,
, ,
,
- - -
-
- m n - - -
,
-
<
,
. ,
- ,
.
.
e y
% ~K J g_
ji
?"'
_ _
. )_e p-
,
'
,
'
_
x-
/
,
'
%,
l'
,
- ' 4 . m
'
-
-
-
,g "
-
- m , -
.
14. # Licensee' Identified' Items
~
^
,<
{ ,, ,_ .
_ _
(Closed) Item 508/82-09-B "0 mission'of' Compressible Material Around .
<
~
Containment Penetrations" (10xCFR 50.55(e)).
'
,
/The licensee's" final report was sEbmitted on February 11, 1985. The
- -licensee had determined that hadethe deficiencies remained uncorrected,; -
( they would not'. havefadversely'sffected the, safety of the plant at anytime-
~
'
[:'
'
throughout_the expected-lifetime of the plant and:therefore was not ~
'
reportable in accordance'with~the 10 CFR 50.55(e)! criteria. . An analysis
_
!
<
had'been performed by;Ebasco andlCBI'that' supported this: conclusion.: -
_
'
,Although the actual. analysis was,not:available on site, san Ebasco report
~
on'the analysis was available,Trevieked_by:the inspector and discussed:
, q e with both the~ licensee'and Ebasco.; Nonconformance report (NCR)114161 y
documente'd the~ discrepancy;and the A/E's evaluation and disposi. tion. The" g :L
_
NCR required clarificationitofmore" clearly, document the items,being y
, u -
ac.cepted as-is and lthe remainder of? work' require T,he' licensee ~
, -clarified the NCR during the' inspection.;. Based'on,the' inspector's review -
E ,"
' of the rlicensee's and A/E's: evaluation- and ~' disposition-_of the reported -
-
_
discrepancy, the 10-CFR 50.'55(e) item was close s
': _
l' : '5.,_ContainmentSteelStructures'-Weldina'andNondestr$ctiveExamination:-~
'
,
eChicago Bridae and Iron (CBI) , t T 4 y :
4 . . .
.
'CBT structural steel welding activitiesMinside' containment had been-
.
.
l '~
'previously inspected and 'the inspection documented on RV: inspection report 50-508/82-08. Although WNP_-3 is currently in an extended
,
, construction delay phase, the licensee has? decide'd to.completeithe=
u containment structural steel work to the extent-that would allow * *
performance of._ a containmentroverpressure/ structural: integrity. test. J An -
S inspection was performed to; verify licensee compliance with:FSAR r_ ..
-
'
,. commitments and NRC requirements'regarding containment structural stsel- /
^
i
'
. welding. ..The licensee commitments lare contained'in WNP-3 FSARisectione '
' .
- .
.
. > >
. . .
, t , Review of Quality Assurance Implementina Proceduresb '
i "'.
Thefinspectors'ampledandreviewed'kheCBINuclearQualitylAssurance Manual for ASME-Section.III' Products,' issue. number 10_. dated
- 1981'andWeldProcedureWS-30,WeldProc~edureSpecification]Aprilh
_
l
L E7018/74-3431LRev."S k The procedures were' reviewed for compliance'
/
'
-
~
'with ~the appropriate requirements of the FSAR,' th's AWS ' Structural'
'
Welding Code ANSI standards' and'ASME' Cod ,
' ~
,
' '
- No violations or deviations were identifie >
~ .
I.' ^ .. . .
~
bh Observation'of Work and Woik' Activities-
' '
'
-
i ,
<
+
~ r The inspector observed the work' activities on' the; 32 foot diameter
~
!4 m ,
L containment construction' hatch. S
! between the hatch barrel and headwere' lpecifically,._
observed and welding discussedactivities' with .
' ~
! ,
_
the-licensee, the A/E and'with CBIfpersonnel. 'The. inspector noted;-
-during this discussions that"a potential problem existed'regarding-
'thefexterior hatch to barrel weld.~ :It appeared:that? upon f
~
f, .,
,
' '
4 .L
'
i, e
,
M
'
h -
- #
'l s s
'
Jm . . . _
-
__ _m...o_ _ . _ _ .-__-_-_im
/ v yp , -
.
e '
4 y' <
n y+ n w w $"T? e ,$ v w m g[q~
--
' .
'
,' Tr ^A
' ^ '
fi -[
. .l' x .%; i , '%".$
- 3 am' w ,y. . lx[ ' ' ~y . - ~
,p_ . c ':
__
-;p c y *
r ;
'3; T _
- t-, 1
) %- -
- % / f
.. ,
, e
, . .,
h {".Jj$(:(
wa<r
)M' ,=
2'
, *
U,
'
r
'N
,
"
g P'#
Kx-G W Pa&. '
, +
Biu ~
.
y ~.
'
- c ? " . -
g n- A= .. +
installation of theldesigned 1.5? inch: thick weld on the barrel'to - e .. . . .
.
. .,
u
@4' f w " hatch . joint, the jointg configuration; would vary. from the originaf . # ~j gw' '
-
2+ ' design in.that an edge-would be left approximately 1/2 inch Thove "
r the weld'on the' barrel. JThe installation of more than 1.5~ inch ~ weld,
"fY#. W would require post-weld heat treatment 4which(is not currently * '
i W e ] planned. Di~scussionstwith CBI1,indicatedLthat the corrective' action 4 y[la M
,
. ,
5 would beito remove'_theledgeion;the barrel'to be.in accordance with :
E vgz the joint' configuration.f However, CBI didinotLhave a , procedure to
,q 7., m
. accomplish this' work'during th'e' inspection.-.Furthertinspecg' ion of t '
%- " ' '_ '
.CBI. contract.74-3431 drawing l64 rev.14 ; 2 32? feetLdiamet,er? ' ~
.
. ;
, construction hatch and~ drawing 66'rev.-2,; barrel'and,hnd' details,,- _ .
.
indicate that'if the barreltand head'were manufactur'edin accordance ~
- with the' drawings,'the problem.would'not exist. 1Reco~ds
'
( _
r available
, "1 , , ,
'
s on site indicate that the barrer.and head had?been inspected 7"
, . , s
'
'subsequenta to= manufacture and: had 'been' certified ;to be in'accordanc t with theidrawidas. Recoids on site'also indicate thatsthe barrel'
"
A '
and; head,hadJsatiIsfactorily s'
~
The - a inspector'alsoinoted thatino[pa' ;NCR'sthodibeen sed receipt written 1 inspection regarding ~. the 5
'
1 potential. problemX However,an October 510jf 1985, CBI entered item
'
s" J ,
t
-
-
number 264'os their'nonconformance'controlElist regarding the .
- subject problem. .During;thefinspectioni the' licensee, the A/E'and' V
,
. 1CBI'were unable to obtainfaccurate a:easurements of the barrel 'due, to
'
-
<
interferences'Oith h'esting element"siand the actual welding being' '
S-Y performed. ' Pen' ding accurateidefidition of the. potentisl problem,. <
D evaluationiand; corrective a'ciiion,"this has ,been tidentined _as -
P '
Unresolved Item
'
,
construction' hatch weld *
area con' fig'rationf508/85-07-01,"dontainmentlh
.
u '
' p tv
'
-
g
,
y .
.'3 >k L ., . LNo violations or devia,tions were 'iden'[tifle, ~ '%:
x
-
1, _
n4 .
'~
_- .
-
-
(< \
.
=c.- Review of Records, C _
99 -
s y
' '
,
_
.
. , . ,. fp ' ' '
' ' "
'
,The' inspector examined the l iualificatioil testirecor$ and '
p
'
, , qualification checklists:fo'r three welders who had performed" welding .,
^
'
on structdralisteel discussed in paragraph 5(b). The inspector;I .[
t -
'
, verified proper qualification for'the: positions'and preaesses used -
"
M <
in accordance with the AWS Structural! Welding Code.~ :Thesinspector' 4 -
- , also examined the contractor's method fortensuring tn t 5
.(
( '
t
.qualificatifons were being maintained.' The inspector examined ther ( ' " N, .
[ # m ". ci .;, * _ Jgualifications of the Level II '(liquid penetrant), examiner discussed
'
. ~ W~ . in paragraph ~5(b) for compliance:with the' requirements of ANST-TC-1 ,
.;
~
m ,. .
~
Y< -(1975);. - / A .,,
' '
4,
'
, & J ,.
. ,
f; ; y e- L n ,
,
i
-
. .
T ' #: s e
' *
. . -. ,
r ; .' N5-m ..n'~# = No violationsfor/ deviations'were identified.". '
,>
,
jt
. p rn -<
,-p'. ,,, ., ,-
m ,
-
j
-
cm ic e A 3%. * g-. +qm ;4
. . .v e
-
s 51 ,
,.sW'u
.
,
y_ m 16.e : Exit 1 Interview ?v ".
~
,
^
-; ~ j j
M^ "
.
.'
' -
+
/- .
M
-
>
41 : ..W . :: ,, _
a r -L;>
t 1
.j:. +.
_
. c 4,, g
. a,
. . . vr-
_
.
.
~ . ,
.
... .
L
3;~b ~2 j:" 'The? inspection scope;and findingsparagraph' with-those^personseindicatedlin
'
lwere summarized-on: The' inspector October described ..11,11985,j;ef th
%
,,
4$ , : areas inspected and;discussedLin detailtthe inspection" findings., No1 f "y
~
> '
~
Mg6 * " j [dissentingMomme'nts were?receivedifrom:the flicensee.The*1icensee ^did T ' '
l' ~ o- e9ff gnot identifyfas_proprietaryfany of.the material.provided to or; reviewed P:
,
,1 t 7 f-i- 7 g-1 iby tthe} inspector during ;this ? inspectionk f N ' % . ' ,. * ,' g. 3 'S -
9 9
-
. o g .., m
-
w ,
,
,
I ' ~
. .n \? j^ > >
- _
' ' - , .
3 ,~ :
+q-
- <
-
, , .. , ,
,
, , 3 - t YM '
'
v+,',I/(- jf s7
,-
, a
,
,
' '
- +
,
.
j- +
s s.,y; b *
": .
.
<
.
e g. g ,
)i 7 D') .. i43 - f'g , , ,3
+
' .[ ; ,
.; [_ .
-'
'f
'L f }l'. Y
, ~ '
t
} ,f f
'e s
~ ,
~;'d
'
'*
, , l -
"
. . <
'
, - . .- .
.. ;
- 'a;*- - .