IR 05000508/1986002
| ML20141N932 | |
| Person / Time | |
|---|---|
| Site: | Satsop |
| Issue date: | 03/03/1986 |
| From: | Ang W, Dodds R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML20141N927 | List: |
| References | |
| 50-508-86-02, 50-508-86-2, IEIN-85-056, IEIN-85-56, NUDOCS 8603180290 | |
| Download: ML20141N932 (4) | |
Text
l r-
..
t s.
- -*.
.. '.
,,
tr
,
f.
. m
.
f
. *
'
g
<.
,
,,
X
'?
y f
- , (5
,,
,
'
,
.
7..., -
~,.,'
-
e
,
I,
.
' 4 (pg,
't
-
,
'I
- f
' '
,
,
,
'
-
,
!^
U. S. NUCLEAR' REGULATORY COMMISSION -
'
'
REGIUNf.N ~ _
',
~
,
,
.
- _
.,
,
'"'[
s
"
'
'
,s s
,
,
\\
,
'
}
.. Report No. 50-508/86-02.
,
.
-
!
Docket No. 50-508
...
'.
"
'
~
,
,
'
'
i
..
.
ci
'
Construction Permit No. CPPR-154
'
<
('~
Washington Public Power Supply System (WPPSS)
Licensee:
P. O. Box 1223
'
Elma, Washington 98541 (
Facility Name: Washington Nuclear Project 3
[' -
-
,
[-
Inspection at:. WNP-3 Site, Satsop, Washington
[
.
.
.
-February 10-14, 1986 a
, Inspection conducted:
.
.
,
.
>
Inspector:
f0
~ 2. IC E
l W. P.. Ang, Project Inspector Date Signed
>
Approved' By:
h)
h J!M l
R. T. Dodds,' Chief D&t( Signed
!
Reactor Projects Section 1 l
Suassary:
,
. Inspection on February 10-14, 1986 (Report No. 50-508/86-02)
e i
Areas Inspected: Routine unannounced inspection by a regionally based inspector of the-readiness review construction assurance program, licensee
,
'
action'on previous enforcement matters and site tour. This' inspection
. involved.31 hours3.587963e-4 days <br />0.00861 hours <br />5.125661e-5 weeks <br />1.17955e-5 months <br /> onsite by one inspector.
Inspection procedures 63050,
,
t 35060 and 92702 were used for guidance.
[
Results: 0f the areas inspected no violations.or~ deviations were identified.
L
!
p-I.
>
i
.
i
.
l
'
l i-
'
c j
86031802W) 860;.104 PDR ADOCA 0500050s
' y>
-
O PDR e
.
-
.
-
'x
'
'
.% ;,
.,
,
'
- ,Et..
%,
.
=, 4,(,
..,.
-.;
'
,
~<
' '
L_
_
m s.i
-
.
. -pc
.-- -
-
-
-
--~
-
-- - +
-
,
p.,
~
.'
r. c
.,:
.
- t
,
.
.. f
.
<
,.T.
'
n
-
,
%
+
ki DETAILS f'
3-i j y.(
,
,
.
-
'%
,
'y fl.-
Persons Contacted-
'
k-a.[ ' Washington Public Power Supply System
.
P.~D. Olson, Program Director
,
- C. E. Love, Deputy Program Director
.
- M. M. Monopoli, Plant Manager
.
- D. R.; Coody Project QA Manager
<
- E.' A.. Stauffer,: Plant QA Manager k
s.
~
4o
- R. L. ' Knawa,' Construction Assurance Program Manager
- '
.
[6 i;
34s
' b.:.Ebasco Services Inc..
A. (
14.:
4 '
N,': O y
. *J. Crnich,2 Project General Manager V '
- R. M.' TayJor, : Site Construction Manager
-*P. L. Pitman, Acting Quality Program Site Manager'
'
-
- W...K.' Drinkard,' Project.QA Engineer
,
.
-
- Attended; exit interview.
-
,
,
2.
-Unresolved Items-
,
,
.
I
~
Unreso1ved items were.not. identified during this inspection.-
'
s.
_
-3.
Independent Inspection Effort.
'
M.,
-
~
..
-The inspector conducted a genera 1' inspection,of the reactor building ~and
. portions.of the auxiliary building'to observe construction progress and"
.
o;;
housekeeping and' storage.,
g,,
'
No violations'or deviations were identified.
,
~,
.
<
'
.
,
.
sw w.
.
,4.,,. Licensee Action on Previous Enforcement Matters
.. )
',}
,,
+ :,te
- c%
'
u.
~. !
3'
r
,.,
,
a.
(Closed) Violation'83-02-01,'P-K Failure tot 0bserve Valve Position Hold Point:
- i,t g,
,
,
,
n.,.
e,
.
,
.
,
f.
.. <,....,
,
,
,
,,
.
s
.
,.
,
..
, Supply System' letter of response dated [ March,30,.1983 was reviewed
!
. _
'"
.and discussed with the Project QA' Manager and;EBASCO QA Program Site i
The inspector reviewed, n' nconfers.snce" report i nos.'. 5803,
!
Manager.
o 5866 and 5877 and their c'orresponding corrective; action. 'In
,-
-
addition'the inspector", selected"theffollowing valves.. randomly and reviewed the in line weld.jointerecord;to.idatermine if other contractors performing similar' activities.cootrolled"the valve
~
-
position verification in a.'similar manner.,<.
,
,
- +
.s
.
,
',
'
2 SI-VQ 008
~
j
- i! '
2.SI-VQ 020=
-.
'2 SI-VQ 017
.
.
,
.
v.
.
,,
y
"
t s
I
,
. s.
.
. j'
.Q
-%
!
W,3 y,
. 1
,
,
,
s,
,
<
,,j p, ' '
2.
s
,
,
-
,r,
)
u
+
,.
~
.
,
4;- 3
,m
,
,
<q
,,.
.
<
.
2 CH-VP 011"
'
~
a.
'
1.CH-VP 006~
,
,
.
ry
- The inspector. determined that' valve position hold
- points were being
,y
_
Lobserved by~MK/ESI/ LORD.for:the sample selected. 'The inspector
,
.
'
concluded that thefSupply System.had determined the full extent of m-
,
,
,'the subjectnoncompliancep performed the necessary survey and
,
m follow-up, actions for the subject noncompliance. The violation was g
_
-
>
.
closed.
2-
-
-
,..
^
K
.
j(Closed) UnresfI Ed' Item 85-07-01, Containment Construction Hatch
r g,
H j
3 ;b.
.-
,
Weld Area Configuration-
'
,
.'
[
[*.
f,
'l 'The unresolved item identified a potential problem regarding the
'
".
fabrication and installation ^of.th'e containment construction hatch l ',,
,
,
,s in the weld' area of.the' barrel to head weld.
Inspection report C
~
- 508/85-10 reviewed' licensee, AE and CBI action in response'to this
~
-
S item;but left the' item open pending further evaluation and
- /
letermination of any further corrective action regarding the barrel
,n
..
3'
'
- fabrication and source: inspection. 'During-this inspection, CBI y,
letter'213EB-85-WBC-20 dated' November-27,'1985'was. reviewed and g
,
o
' ' discussed with the licensee. The ' letter addressed the remaining l'
'
-
'
' conc'ern fod the unresolved item. The licensee was satisfied with
.
~
s, the CBI~ action and. considered the item to bi an isolated case.
In
'
..
addition the licensee stated that'no further CBI work is anticipated
cfor WNP-3.. The, licensee also stated _that'the Supply System is now w
.doing'all sou'rce' inspection. ~The unresolved item was closed.
'
t
n.
- a~
>
5.' -
(open)1IE'Notici.85-56 - Ina'deq ate. Environment' Control for Components
"and Systems ' in, Extended Storage or, Lay-Up.
'
- '
,
2: [1 I(7- ;
.
I\\i '
-
. The'IE Notiee' informed,licenseesiof problems which can occur if equipment
,
'is 'improperlUstored or 1didiup'/ dring construction or extended plant d
4ou,tage,' The" notice wasPo'f'specia1~. significance for WNP-3 due to the J
current' extended construdsion' delay'oflthe plant. - The inspector reviewed i.he WNP-3 preservat.iun7of JAss'ets-preventative Maintenance Program,
~
'
revision,12;(with*the' licensee 3 During this review,.the inspector noted that;no31nternaljvisual ' nspectiori was required. for pumps, tanks or. heat i
.
,
The,in' pector ' selected two motor driven auxiliary feedwater-exchangers;:
. s
,
pumpsj four DG "Jacliet' cooling water.' heat exchangers and two refueling
'
z water,stofage.tinnks for inspection." Receiving inspection records for the
'
- pumps and;the Diesel Generator >Asse'ablies were reviewed and found to
'
y include source' inspection'for, cleanliness and' receiving inspection for
,
adequacy of seals;and caps. The' tanks and the heat exchangers=were T
- internally visually ' inspected by the NRC ' inspector and found to be l
'
-acceptably cleanig A slight film of' rust-was observed in the heat
.
'
exchanger internals. The pumps could not be internally visually inspected without; disassembly of the pump. The.above noted conditions
' " -
..were discussed with the licensee. The licensee: indicate Fthat the
~
~
auxiliary feedwater pumps already:had maintenance work; requests issue and'would be' disassembled and cleaned befsre startup.. Pumps in gen'eral
> -
e
' would 'not be periodically. internally visually inspected..due to the yo'rk s-
.i effort required for disassembly. However, the licensee further-indicated thatthepumpswouldbemonitoredduringthetestprogramupgresumptior.'
P
-
,
4;
,
'
r v.7 0.
s t
,5>
>
<
.
.
,
g
'
/
I S
)
L
... -
,,,
g
,
y
.
.
g
-
-
- - -
p
[.[
i-
['
- -~, '
s p.
4.
gy
'
'
'
,O ' g y.
.
M
'
'
.
v.,
'
,
N,
'of plant completion. The licensee agreed-to:further review the l
preservation. program to determine the need for internal visual inspection
,
l of items.that.could be inspected without extensive disassembly. Pending g a[q-further licensee review,.the IE' Notice was left open.
g
,
~p
...
.
.m
- -
No violations or deviations were. identified..
,
y
.
.
6.
. Readiness' Review - Construction Assurance Program (CAP)
'
"
'
J
.
.
.
.
.
Supply System' letter.G03-85-563~ dated September 25, 1985 submitted its Q[bpi CAP for NRC review. NRC provided its comments to the WNP-3 CAP by a RV p
... letter 1. dated Noves:ber 20',;1985.. ' Supply System letter G03-86-026 dated
'
' l..
January 39, 1986 provided the licensee's response to the NRC comments.
'
.
w The CAP'and the response to NRC comments were discussed with the
; licensee. (The111censee. intends to. submit a' revised CAP module. review j'
.-
- y., schedule to reflect a rearrangement'of the. sequence of modules reviewed.
- Thxe" intended sequence 'would allow civil engineering' modules to overlap
.
l
",
michanical. engineering modules resulting in maximum usage of-team
~
.
,
,' p.
members.
F
'
'
i s
c. F. 7
'
7-
..
.
.. -
The: inspector also reviewed with the CAP manager a'nd QA manager a. listing
,, @ 'of open inspector follow up it'ns, unresolved items, violations, 10 CFR e
,
$*
-50l$5(e)' reports, Part 21 reports, Generic Letters', Bulletins and y
Notices. 'It was noted that licensee action.for approximately half of the
>
..
r
items,had been reported to be complete and could be reviewed during L
' readiness review. :The' licensee was requested to determine the impact of Qt.
the incomplete"open items on readiness review.
g
,. y
).
-
I'
?"'
No violations or deviations were identified.
<
'
'8.~
Exit Interview
!
r
!
. /
...
The inspection scope and findings were' summarized on November 21, 1985,
- with those persons indicated. in pararraph 1.
The inspector described the are.g. inspected'and discussed in detail the inspection findings. No
,
dissenting comments we e received:from the licensee. The licensee did
,
f not identify as proprietary any of,the material provided to or reviewed by the inspector during this inspection.
,
,
v..
s.
I, ) g *
h,
'
'
,
,
_s4
,<s,
,
g;
< ";
g
,
+
2, [k.
[k, C
-,,
.(;
'% J, 4..,
a
. i ',! ' %,
.
5 J ;.4,
's
" '
f..*
<,
,
f '. p 1'
- -
,
.
,
p vg l j g.
- : J;g
.e'
,
-
,
'
..
.
.
([ 5 N)f.
'"*Af'
,,
e
- :,:,, 5
- 'n, e
'
V y ' f.
k b wf
.
i
'
,
s
,
.
%, $
J l
', 5}. y ; 1
f
.,
j
,e 3 -
xy
"
h af
. ]
Y#
,,
a[f y _ ; ; y:'
~ [
c
<
L
- <
- o
,.
o,;,3
..y
!( -
n
,
<
vy,
-
L,
.
,.T/
"
'(
. '
'
'
-
i
,
a
&. ki'l
.
.
,
,
.
.
,.
.
.
.