Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site TourML20141N932 |
Person / Time |
---|
Site: |
Satsop |
---|
Issue date: |
03/03/1986 |
---|
From: |
Ang W, Dodds R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
---|
To: |
|
---|
Shared Package |
---|
ML20141N927 |
List: |
---|
References |
---|
50-508-86-02, 50-508-86-2, IEIN-85-056, IEIN-85-56, NUDOCS 8603180290 |
Download: ML20141N932 (4) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:UTILITY
MONTHYEARIR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1989-05-11
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation ML20212N1231987-02-26026 February 1987 Notice of Violation from Insp on 861208-19 IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000509/20060211985-07-0909 July 1985 Notice of Violation from Insp on 850509-0621 IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint ML20055A0551982-06-28028 June 1982 Notice of Violation from Insp on 820607-11 IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items ML20207G8061977-11-21021 November 1977 PNO-77-207:on 771117,WPPSS Issued News Release Which Stated That All Work on WNP 3-5 Site Would Be Terminated to Permit Use of Available Onsite Resources to Control Erosion. Commitment Communicated to State of Washington 1998-11-02
[Table view] |
Inspection Report - Satsop - 1986002 |
---|
|
|
Text
r- s . l
.. '.
..
t ,,
tr - -*.
f g , , ;
, <. . m
.
, ;
f , , , X '? y .* *
'
e -
'
.
7. . . , - ~,. ,' ,
I, . ,
,
'I ,
- f ' '
' 4 (pg, 't
'
-
,
,
'
-
!^ '
U. S. NUCLEAR' REGULATORY COMMISSION - ~
,
,
, .
- _ ', .,
"
'
REGIUNf.N ~ _ '"'[ s
'
, ,s s ,
, \
'
}
.. Report No. 50-508/86-0 , .
"
! Docket No. 50-508 , . . .
'.'
'
,
i
~
. .
'
'
.
ci Construction Permit No. CPPR-154 <
'
('~ Licensee: Washington Public Power Supply System (WPPSS) ;
P. O. Box 1223
'
Elma, Washington 98541 ( -
Facility Name: Washington Nuclear Project 3 [' -
,
[- Inspection at: . WNP-3 Site, Satsop, Washington
[ . .
. . . ,
a
, Inspection conducted: -February 10-14, 1986 .
>
Inspector: f0 ~ 2. IC E *
l W. P. . Ang, Project Inspector Date Signed >
l Approved' By: h)
R. T. Dodds,' Chief h J!M D&t( Signed
!
Reactor Projects Section 1 l
Suassary:
,
i
. Inspection on February 10-14, 1986 (Report No. 50-508/86-02) e Areas Inspected: Routine unannounced inspection by a regionally based
'
, inspector of the-readiness review construction assurance program, licensee action'on previous enforcement matters and site tour. This' inspection
, . involved.31 hours3.587963e-4 days <br />0.00861 hours <br />5.125661e-5 weeks <br />1.17955e-5 months <br /> onsite by one inspector. Inspection procedures 63050, t 35060 and 92702 were used for guidance.
[ Results: 0f the areas inspected no violations.or~ deviations were identified.
L
!
p-I.
>
i .
i
.
l
'
l i-
'
- c j 86031802W) 860;.104 -
' y>
PDR ADOCA 0500050s -
O PDR e .
-
,
'
.% ; , ., 'x '
.
'
- ,Et . . %, *
.
- .;
'
= , 4 ,( , ..,. ,
s .i -
~< ' '
L_ _ m
.
. -pc .-- - - - - --~ - -- - + -
,
r. c .,:
p.,
~ .' ;
.
,
.
-t
.. f .
'
< ,. n -
,
1 %
+ k f'
i 3- i DETAILS j , y .( ,
-
. ;
'% * ,
'y fl.- Persons Contacted-
'
k- a.[ ' Washington Public Power Supply System
.
, P.~D. Olson, Program Director
- C. E. Love, Deputy Program Director
.
- M. M. Monopoli, Plant Manager
.
< :*D. R.; Coody Project QA Manager *E.' A. . Stauffer,: Plant QA Manager
~
k
- ' 4o *R. L. ' Knawa,' Construction Assurance Program Manager
.
i; 3
[6 4s ' b .: .Ebasco Services In A. ( 4 '
14.:
N,': O y . *J. Crnich,2 Project General Manager V ' *R. M.' TayJor, : Site Construction Manager
-*P. L. Pitman, Acting Quality Program Site Manager' '
-
,
Drinkard,' Project .QA Engineer
.
-
-
,
, * Attended; exit intervie ,
, Unresolved Items- .
I
~
'
Unreso1ved items were.not. identified during this inspection.- _ - Independent Inspection Effor '
M.,
~
..
-
-The inspector conducted a genera 1' inspection,of the reactor building ~and
. portions.of the auxiliary building'to observe construction progress and"
.
o;; housekeeping and' storage., g ,,
'
No violations'or deviations were identifie ,
~,
.
,
.
'
sw .
<
.
,4.,,. Licensee Action on Previous Enforcement Matters ,, .. ) ',}
+ :,te '
~. ! ,., 3' ;c%r , (Closed) Violation'83-02-01,'P-K Failure tot 0bserve Valve Position
, Hold Point: ;i,t g, , ,
n., . f. . . < , . . . . ,
,
, , ,
,, .
.
,. , 1 s e, . ,
.
..
'"
. _
, Supply System' letter of response dated [ March,30,.1983 was reviewed !
.and discussed with the Project QA' Manager and;EBASCO QA Program Site i Manager. The inspector reviewed, n' nconfers.snce" o report i nos.' . 5803, !
,-
5866 and 5877 and their c'orresponding corrective; action. 'In 1
-
addition'the inspector", selected"theffollowing valves.. randomly and reviewed the in line weld.jointerecord;to.idatermine if other
~
-
contractors performing similar' activities.cootrolled"the valve
position verification in a.'similar manner.,< . ,
- + .s
,
.
,
'
l
', 2 SI-VQ 008 ; i! '
~ j 2.SI-VQ 020= -.
. '2 SI-VQ 017
.
I
,
. .
"
, , y s t I
1 ,
l
. .
. j' !
.Q -%
W ,3 ,
y, ,
,
. 1 s, , <
l
,u,r, ,j p , ' ' , ,
s !
)
+ , . ~ .
4;- 3 , 3 ,m ,
,
<q ,, . .
<
.
'
2 CH-VP 011"
~ '
, .
,
1.CH-VP 006~
ry
, ,y _
- The inspector . determined that' valve position hold
- points were being
'
. Lobserved by~MK/ESI/ LORD.for:the sample selected. 'The inspector
,
, m- concluded that thefSupply System.had determined the full extent of
,
,'the subjectnoncompliancep performed the necessary survey and g > _
-
m follow-up, actions for the subject noncompliance. The violation was
.
,. .
- 2- -
closed.^
K 4 r
g, .
H j .- 3 ;b. j(Closed) UnresfI Ed' Item 85-07-01, Containment Construction Hatch
,
'
, Weld Area Configuration-
.'
[ [*. f, 'l 'The unresolved item identified a potential problem regarding the l ', ,
'
, ,s
".
fabrication and installation ^of.th'e containment construction hatch ,
in the weld' area of.the' barrel to head wel Inspection report C - 508/85-10 reviewed' licensee, AE and CBI action in response'to this
~ ~
- S item;but left the' item open pending further evaluation and
..
- / letermination of any further corrective action regarding the barrel ,n 3'
'
fabrication and source: inspection. 'During-this inspection, CBI y,
, o *
letter'213EB-85-WBC-20 dated' November-27,'1985'was. reviewed and g
'
- ' ' discussed with the licensee. The ' letter addressed the remaining
' ~
l'
'
conc'ern fod the unresolved item. The licensee was satisfied with .
'
s, the CBI~ action and. considered the item to bi an isolated case. In
. .
addition the licensee stated that'no further CBI work is anticipated cfor WNP-3.. The, licensee also stated _that'the Supply System is now w
'
.doing'all sou'rce' inspection. ~The unresolved item was close ; ;a~t >
5 .' - (open)1IE'Notici.85-56 - Ina'deq ate. Environment' Control for Components
"and Systems ' in, Extended Storage or, Lay-U '
- '
,
-
2: [1 I(7- ; .
I\i '
, . The'IE Notiee' informed,licenseesiof problems which can occur if equipment
'is 'improperlUstored or 1didiup'/ddring construction or extended plant 4ou,tage,' The" notice JwasPo'f'specia1~. significance for WNP-3 due to the
~
'
current' extended construdsion' delay'oflthe plant. - The inspector reviewed i.he WNP-3 preservat.iun7of JAss'ets-preventative Maintenance Program, revision,12;(with*the' licensee 3 During this review,.the inspector noted
. , that;no31nternaljvisual ' nspectiori i was required. for pumps, tanks or. heat
,
-exchangers;: The,in' . s pector ' selected two motor driven auxiliary feedwater
'
pumpsj fourz DG "Jacliet' cooling water.' heat exchangers and two refueling
'
water,stofage .tinnks for inspection." Receiving inspection records for the
- pumps and;the Diesel Generator >Asse'ablies were reviewed and found to
'
, y include source' inspection'for, cleanliness and' receiving inspection for adequacy of seals;and caps. The' tanks and the heat exchangers=were T
'
- internally visually ' inspected by the NRC ' inspector and found to be
.
'
-acceptably cleanig Al slight film of' rust-was observed in the heat 0 exchanger internals. The pumps could not be internally visually
'"-
inspected without; disassembly of the pump. The.above noted conditions
~
..were discussed with the licensee. The licensee: indicate Fthat the ~
auxiliary feedwater pumps already:had maintenance work; requests issue
>- e and'would be' disassembled and cleaned befsre startup. . Pumps in gen'eral s- ' would 'not be periodically. internally visually inspected..due to the yo'rk
.i effort required for disassembly. However, the licensee further-indicated thatthepumpswouldbemonitoredduringthetestprogramupgresumptior.'
3 - ,
P
'
r 4; ,
v .7
. .
> < ,
g
'
. . ). -
, , ,
L
g ,
y .
. g - - - - -
p
[.[ s i- ['
gy
'
'
'
!
M ,
'
.
v. ,
'
N, 'of plant completion. The licensee agreed-to:further review the l
, preservation. program to determine the need for internal visual inspection l of items.that.could be inspected without extensive disassembly. Pending g
g a[q ,
-further licensee review,.the IE' Notice was left open.
~p .. . . .m
No violations or deviations were. identified..
y
"
'
.
,
. . Readiness' Review - Construction Assurance Program (CAP)
'
J . 1 . . . .
Supply System' letter.G03-85-563~ dated September 25, 1985 submitted its Q[bpi CAP for NRC review. NRC provided its comments to the WNP-3 CAP by a RV p '
. .. letter 1. dated Noves:ber 20',;1985.. ' Supply System letter G03-86-026 dated
' l. .
.
'
January 39, 1986 provided the licensee's response to the NRC comment w The CAP'and the response to NRC comments were discussed with the j' ; licensee. (The111censee. intends to. submit a' revised CAP module. review
.-
- y., schedule to reflect a rearrangement'of the. sequence of modules reviewe .
- Thxe" intended sequence 'would allow civil engineering' modules to overlap
~
.
l , ", michanical. engineering modules resulting in maximum usage of-team F
s
,' p . '
member '
i c. F . 7 7- . . .
'
. . - The: inspector also reviewed with the CAP manager a'nd QA manager a. listing
,
,, @ 'of open inspector follow up it'ns, e unresolved items, violations, 10 CFR y $* -50l$5(e)' reports, Part 21 reports, Generic Letters', Bulletins and
>
.. Notices. 'It was noted that licensee action .for approximately half of the r
- items,had been reported to be complete and could be reviewed during L ' readiness review.
- The' licensee was requested to determine the impact of Q g the incomplete"open items on readiness review.
,. y ). -
I' ?"' No violations or deviations were identified.
<
'
r '8.~ Exit Interview !
!
. / ...
The inspection scope and findings were' summarized on November 21, 1985,
- with those persons indicated. in pararraph 1. The inspector described the are.g . inspected'and discussed in detail the inspection findings. No
, dissenting comments we e received:from the licensee. The licensee did ,
f not identify as proprietary any of,the material provided to or reviewed by the inspector during this inspectio ,
,
v .. I, ) g *
'
h, '
- ,
,
,
g;
_s4
< "; ,<s, +
g ,
2 , [k . -,, .(;
[k , C *
'% J, 4.., a
.i' ,! ' % , .
5 J ; .4 , 's
, ,
" '
.
3 f..* < , f '. p 1'
,
p vg -
,
,
l j : : J;g
. .
.e'
.
'
.
([ 5 N) '"*Af' ,,
e ;
e * :,: ,, 5 i **'n,
' .
,
V y ' f .
k s ,
b wf '
f %, $ ., J j l
', 5} . y ; 1 ,e 3 -
.
xy
"
h *
af . ] , , Y#
y _ ; ; y:' ~[
- < a[f c <
L -o o ,;,3
, .
. .y !( - ,
n
- vy, <
L,
'
,.T/ "
'
i
'( . ' -
.
, a
. . ,.
&. ki' . .
,
, . .