|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1998-11-02
[Table view] Category:UTILITY
MONTHYEARIR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items 1989-05-11
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000508/19982011998-11-0202 November 1998 Insp Rept 50-508/98-201 on 981027-28.No Violations Noted. Major Areas Inspected:Selected Construction Permit Conditions Re Termination of Construction Permit for Washington Nuclear Project Unit 3 IR 05000508/19890011989-05-11011 May 1989 Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted.Major Areas Inspected:Qa Activities Associated W/ Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19880021988-08-22022 August 1988 Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02 on 860915-880603.Major Areas Inspected:Results of Program Review of Completed Concrete Work,Including Planning/Mobilization & Problem History Review IR 05000508/19880011988-03-11011 March 1988 Insp Rept 50-508/88-01 on 880222-26.No Violations or Deviations Noted.Major Areas Inspected:Qa Activities Re Implementation of Plant Preservation Program During Extended Const Delay IR 05000508/19870041987-08-20020 August 1987 Insp Rept 50-508/87-04 on 870609-19 & 30.No Violations or Noted.Major Areas Inspected:Implementation of Readiness Review Program/Const Assurance Program for Const Work Completed Prior to Extended Const Delay IR 05000508/19870051987-06-22022 June 1987 Meeting Rept 50-508/87-05 on 870529.Major Areas Discussed: Util Supply Sys Const Assurance Program & Overview of Final Rept for Module C3-02,concrete IR 05000508/19870031987-06-0202 June 1987 Insp Rept 50-508/87-03 on 870512-15.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings Re Util Readiness Review Program Implementation ML20212N1231987-02-26026 February 1987 Notice of Violation from Insp on 861208-19 IR 05000508/19860131987-02-26026 February 1987 Insp Rept 50-508/86-13 on 861208-19,870108 & 12-13. Violations Noted:Const Spec for Concrete Installed for Reactor Bldg Did Not Incorporate Appropriate Reinforcing Steel Clearance Criteria & Concrete Grout Nonconforming IR 05000508/19860121987-02-0606 February 1987 Insp Rept 50-508/86-12 on 860915-1215.No Violations Noted. Major Areas Inspected:Readiness Review Program Module C3-01, Earthwork & Followup on Insp Repts 50-508/86-10 & 50-508/86-11 IR 05000508/19870011987-01-30030 January 1987 Meeting Rept 50-508/87-01 on 870107.Topic Covered:Util Const Assurance Program.Viewgraphs Encl IR 05000508/19860111986-11-14014 November 1986 Insp Rept 50-508/86-11 on 861027-31.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Module C3-01 Re Earthwork,Inspector Followup Item & Site Tour.Inspector Questions Will Be Addressed in Module E3-02 IR 05000508/19860101986-10-0101 October 1986 Insp Rept 50-508/86-10 on 860915-19.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860091986-08-0808 August 1986 Meeting Rept 50-508/86-09 on 860801.Topic Addressed:Const Assurance Program.Viewgraphs Encl IR 05000508/19860081986-07-31031 July 1986 Insp Rept 50-508/86-08 on 860715-18.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860061986-06-0202 June 1986 Insp Rept 50-508/86-06 on 860519-23.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Program,Const Assurance Program & Site Tour IR 05000508/19860051986-05-12012 May 1986 Insp Rept 50-508/86-05 on 860428-0502.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Allegations Re Pipe Welding IR 05000508/19860041986-04-10010 April 1986 Insp Rept 50-508/86-04 on 860324-28.No Violation or Deviation Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860031986-03-28028 March 1986 Insp Rept 50-508/86-03 on 860317-18.No Violation or Deviation Noted.Major Areas Inspected:Selected Open Issues from Previous Insp IR 05000508/19860021986-03-0303 March 1986 Insp Rept 50-508/86-02 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Readiness Review Const Assurance Program,Licensee Action on Previous Enforcement Matters & Site Tour IR 05000508/19860011986-02-21021 February 1986 Insp Rept 50-508/86-01 on 851029 & 1118-21.Const Assurance Program (CAP) Should Provide Satisfactory Assessment of Completed Const & Const Process.Implementation of CAP Will Be Inspected.Cap Module Repts Will Be Reviewed Upon Receipt IR 05000508/19850111985-12-30030 December 1985 Meeting Rept 50-508/85-11 on 851218.Major Areas Discussed: Proposed Const Assurance Program IR 05000508/19850101985-12-0505 December 1985 Insp Rept 50-508/85-10 on 851118-21.No Violations or Deviations Noted.Major Areas Inspected:Containment Structural Integrity Test Records,Readiness Review,Const Assurance Program & Site Tour IR 05000508/19850091985-11-18018 November 1985 Insp Rept 50-508/85-09 on 851101-03.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Integrity Test IR 05000508/19850081985-11-0505 November 1985 Meeting Rept 50-508/85-08 on 851029.Major Areas Discussed: Util Proposed Readiness Review Programs for Const Assurance. Viewgraphs Encl IR 05000508/19850071985-10-21021 October 1985 Insp Rept 50-508/85-07 on 851007-11.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding Procedures,Work Activities & Records & Site Tour IR 05000508/19850051985-09-10010 September 1985 Readiness Review Insp Rept 50-508/85-05 on 850528-0904.No Violation Noted.Major Areas Inspected:Preservation of Assets & Preventive Maint Program IR 05000508/19850021985-07-26026 July 1985 Insp Rept 50-508/85-02 on 850715-19.No Violations or Deviations Noted.Major Areas Inspected:Activities Associated W/Welding of Containment Vessel Penetrations IR 05000508/19850031985-07-26026 July 1985 Insp Rept 50-508/85-03 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Qa Program for Extended Const Delay & Preservation Program,Including Organization,Audits,Quality Records & Site Tour IR 05000508/19850041985-07-22022 July 1985 Mgt Meeting Rept 50-508/85-04 on 850702.Major Areas Discussed:Engineering Assurance & Preservation of Assets Preventative Maint Programs.Viewgraphs Encl IR 05000509/20060211985-07-0909 July 1985 Notice of Violation from Insp on 850509-0621 IR 05000460/19850011985-06-0606 June 1985 Meeting Repts 50-460/85-01 & 50-508/85-01 on 850522.Item Discussed:Proposed Readiness Review Program,Including Preservation Program for Unit 3 IR 05000508/19820141982-07-30030 July 1982 IE Insp Rept 50-508/82-14 on 820712-16.No Noncompliance Noted.Major Areas Inspected:Nondestructive Testing Aspects of safety-related Piping Installation,Installation of safety-related Electrical Components & 10CFR50.55(e) Items IR 05000508/19820131982-07-22022 July 1982 IE Insp Repts 50-508/82-13 & 50-509/82-06 on 820601-30.No Noncompliance Noted.Major Areas Inspected:Welding for safety-related Piping,Electrical Equipment Installation, Records for Primary Loop Piping & Equipment Maint ML20055A0551982-06-28028 June 1982 Notice of Violation from Insp on 820607-11 IR 05000508/19820121982-06-25025 June 1982 IE Insp Rept 50-508/82-12 on 820607-11.Noncompliance Noted: Failure to Perform Surface Exam of Containment Electrical Penetration Welds IR 05000508/19820111982-06-16016 June 1982 IE Insp Repts 50-508/82-11 & 50-509/82-05 on 820501-31.No Noncompliance Noted.Major Areas Inspected:Open Items from Previous Insp,Weld Matl Controls,Primary Loop & Structural Welding IR 05000508/19820101982-06-0404 June 1982 IE Insp Rept 50-508/82-10 on 820503-07 & 17-21.No Noncompliance Noted.Major Areas Inspected:Licensee Action on Previous Enforcement & on 10CFR50.55(e) items,post-weld Heat Treatment,Electrical Penetrations & QA Procedures IR 05000508/19780071978-11-27027 November 1978 IE Inspec Repts 50-508/78-07 & 50-509/78-07 on 781024-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspected Incl:Structural Concrete Placement,Concrete Testing Lab & Containment Structural Steel Welding IR 05000508/19780061978-09-22022 September 1978 Insp Repts 50-508/78-06 & 50-509/78-06 on 780905-08.No Noncompliance Noted.Major Areas Inspected:Site Const, Preparation,Followup of IE Bulletins & Previously Identified Open Items ML20207G8061977-11-21021 November 1977 PNO-77-207:on 771117,WPPSS Issued News Release Which Stated That All Work on WNP 3-5 Site Would Be Terminated to Permit Use of Available Onsite Resources to Control Erosion. Commitment Communicated to State of Washington 1998-11-02
[Table view] |
Inspection Report - Satsop - 1987005 |
---|
|
|
Text
.
.
!
U. S. NUCLEAR REGULATORY COMMISSION REGION V !
Report N /87-05 Docket N Construction Permit No. CPPR-154 Licensee: Washington Public Power Supply System P. O. Box 1223 Elma, Washington 98541 r
Facility Name: Washington Nuclear Project 3 Meeting at: Region V, Walnut Creek, California I Date: May 29, 1987 Prepared by: - 8- Y [-22- P 7 A. D. Toth, Project spector j Date Signed Approved by: Ms # [Ir /- J 2 -l' 7 S' A. Rich' arff s,' Chief, Engiyrsririg Section Date Signed Summary:
Meeting on May 29, 1987, to discuss the Supply System Construction Assurance Program for WNP-3, overview of final report for module C3-02, concret i
<
8707110033 870623 PDR ADOCK 05000508 ,
G PDR
!
!
!
'
_ _ _ _ _ _ _ _ _ _ _ _
.
.
DETAILS 1. Personnel Attending Meeting l RV-NRC l
D. F. Kirsch, Director, Division of Reactor Safety and Projects R. J. Pate, Chief, Reactor Safety Branch A. D. Toth, Project Inspector, WNP-3 NRR-NRC G. Bagchi,. Chief, Structural und Geosciences Branch D. C. Jeng, Section Chief, Structural and Geosciences Branch NRC-(Gibson Hill, Consultant)
0. Mallon, Consultant j
WPPSS R. B. Glasscock, Director, Litensing and Assurance L. J. Garvin, Program Manager, Readiness Review R. L. Knawa, Manager, Construction Assurance Program T. A. McCormick, Review Team Leader (Bechtel)
l 2. General The meeting was convened at the request of the Supply System, to permit a presentation of an overview of the fire: report of Module C3-02 l (concrete) of the Construction Assurance Program. The WPPSS attendees discussed program overview, methodology, logic used, results and organization of the final report; also discussed was the content of the transmittal lette View graphs presented by the Supply System attendees are included as Attachment to this repor . General Discussion In addition to the topics noted in Attachment 1 of this report, the Supply System attendees discussed the following points: Although a review of contractor procedures was not a specific part of the mission of the C3-02 review, selected procedures were reviewed in depth (including past revisions) in some cases where a root cause analysis was conducted for identified problems. An example involved review of concrete curing practices and associated ambiguities in procedure Grout and concrete block masonry wall construction were reviewed under module C3-02, but NRC acceptance is not requested in the final report due to a need for additional studies which would be conducted upon project restar Also, review of some concrete embeds will
--
_ _ _ _ _ _ --
,
'
,
similarly be deferre These items are identified in the WPPSS Construction Assurance Program open item list to assure attention upon project restart, A need for some FSAR amendments has been identified during the C3-02 review; such amendments have not been submitted to NRC, but have been identified on the WPPSS Construction Assurance Program open item list to assure attention at project restar The administrative method of handling discrepancies identified during the C3-02 review was changed during the review process. This was due to constraints on resources, such as access to computer time i and clerical staff reduction The practice of entering each I discrepancy into the CAP Open Item List was discontinued, and a lower level screening process adopted. This is described in the final repor The key supervisors involved in the C3-02 review will be available at the site through June 26, 1987 to respond to an NRC site inspection. The two quality control inspectors who actually performed detailed records reviews, have already been released and would be unavailable on-sit The principal objective of the C3-02 review was to provide additional assurance of construction adequacy (beyond that provided by the original quality assurance program) via sampling of completed products of construction and construction control . Conclusions The Supply System will submit the final report to NRC, including the public document room, on June 1, 198 The NRC representatives stated that NRC review of the final report would probably be complete by the end of September 198 . . . .
.. .. . . . . . . . . - .. .. .. .. ..,
(
,
~
[
0
-
8
/
1 0
T -
N0 E5 M
-
Ht C r Ao Tp Te :_
AR
_
_
5 8 6 8 9 5 8 9 1 8 9 1 9 M1
, l l 1 A
,
8 A R ,
M 2 1 R ,
G 5 _
A 1 G 5 O2
_
R R U 2 R G Y E R P Y O L B P R R R U M E E A .
P J l E E B C U _
l T C O N R _
W C A P N T A B E R R E A C R E I N G S R O U F V O U S E Y R C S C S C R B P R S R AR N A N N S
.
D N N
_
S E O Y G Y O Y E T I B N B I B N P T I T I E A D R D C D D C V E E E U E A C R T E T R T E A E P N P T P R S E I E S E T E C G C N C P R C N C O C E P A E A C A C
N _
O _
C o o o
-
.
_
_
.
.. 1
-
8
/
_, 2
' 2
/
-
_
litIIl l)lll ll l]
o i !
.
' -
8
/
1 l
i U
5 T 6 0
6
/ t 8 9 l /
H 1 C S 5 R A 8 S
1 W / 5 l i
5 1 8 0 8 O , 1 / I
/ T A 2 T 8 !
l l
l 1 S 7
_
_ D l E E 6 8
_ Y V E E T V U 8 / 7
_
_ R T S Q / 2 8 O 1 1 T T Y l l
8 /
T O 1 A S 0 O C 4 S I i I' I T O R I G B C Y G T l O
H
.
l E U
.
R G
.
_ L E E T
_ R S 1
P R S 8 6 Y
_
P P l l / 8 B 6
_
_ A T l i
l l U T 0 2 / 8
_
_
_
C A 0 l S A P S D /
_ 1 i S C E 8
_
.
.
_
Y G T W O C E R W T
.
_ L R P T R R 1 i E P W
_
_ R l l I 0 l l' I E E
_
_ A R l1 S l l Y V C I
_ E l i C i 1 1 H E B E C V
_ T S T 0 T T R A E 1 E E 1 I S E R W U E T W Y C K K H S S I R R E G 1 t E 0 I
A O O T
_
.
_
I J
A C U l
Y T W W E
_ I R I Q I L P l i H R T G L T P E T T C E O B C E P C R R N E R U R E U C A A O l
i P P I I
l i S A E E C o o o o 0 o o o 0 o
_
_
7
- _
/
.
/
, I
l
! li i
-
-
G
/
D _
E T
A I
T -
1 f
I E _
_
T E
R C
f
_
0 _
G C .
8 G 7
/ F 8 8 7 7 O / / 6 0 1 / _
Y D W 1 5 _
_
R R E V O A I G 7 0 T 0 V 1 l
1 8 1 S 8 E I 0 / Il 7
-
I l R T 1 4 T 8 i
G
_
l l E E /
O ,
E E W E 5 P D f l
R E 1 A l l E l
C _
C A T E T V E R E E E A E E N T T L T R T N P T C T O E W i l I R T I T _
C E 0 M l l
R M _
E I C M O 1 T
_
R V O l i P i
0 R E i r C T E C O R A I R P E
L T W T E P l i E H R T G 0 T G E W I l
E I T R E S I R S I C I R T C R M N V E E 1 1 E B O E V E 0 V U
_
C R O M C O S
_
_
o o o o o o o
_
.
7
- -
/
- 2
.
/
.
_
.
_
_
_
_
_
.
_
_
_
_
.
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
.
.
_
_
_
.
_
_ M
_
.
_
A
_
_
R
_ G
_
.
O
_ R
_
_ P N S
_
_ O l l
_
_
E I A
_ C T L
_
_ N P P
_ A I S
_ R R W T
_ U C
_ E R
_
S S I O
_
_ S E S V P
_
_ A D E E E R
_
.
_
1 i R R
_
_
.
f f U
_
0 A D E E I R E
.
L L
.
_
_
_
T G C U U
_ C O O D D U
_
_
R R 0 O
_
_ R P P 1 1 M T
.
_
S
.
_
_
_
_
N O
_
C o o 0 o
_
_
_
.
_
.
_
_
_
.
.
.
.
.
_
.
_
.
_
_
.
_
.
_
_
_
_
.
.
.
_
_
.
_
.
_
.
_
.
.
.
.
. _ _ _ _ . _ _ _ _ _ . _ _ _
l l e i
W K
'
1 N
-
i
'
O
&
<
~
L CO
\
I Q &
W & D O U')
W W 2 C % 3 Cn <C Cn W
& I = O H 2 CL H La.J >
W F-- L Z 3 * O %
3 C W W CO W W < x H O .-.I O H W H > Z J Z
> & O Lt ) O O <C W C Z O O C O W L O W % = % * 2 a W --i 0 CO H w
& LL., W D W 2 & z W H O O O O T -
Cr s.J Z W H O q O < P-') O M F-- CL o Z O O C O <C W O O X & X > K O Q CL C z O O LU *
.o CL W Q Lu O C,0 US p
<C LLJ CL W CD H e O C Z O 3 O
= H J W CD
>- d e
W Z W H W J o
CO < > > O < w CO >< LLJ W <C Z g
<C W Q % C <C -
o o o o o o o Ln I
N
- N N
Ln
S I T I N A
L L E E P P V S S E R T E T ,
S L A N P N R T E M A A E N D L A E L , L E A E C E P P E P N L I U T C I P F i f
,
R S R G I D A A B A 1 l R T 4 E B E E E A R I M L ,
L E E T F C R C E L C A I ,
U E U C C L E J I E I J l l V ,
S A C N A Il S R U S 6 I G R R A Q M G U 6 O E
,
N ,
S T Y D ,
C E C S ,
C E R S S A A E 0 L E D E D D P 3 B D i
E S M A S I S L S N D E E R L R P R I E S L A P A I A N S E l E C E L I A l l
A Y C Y S
N Y I B I V 1 t
E 9 l 6 R 0 I 0 T 2 O 1 P 3 C C o o o o
'
_
S E
D I
U G
.
S G T E N s R E l l
M 0 .
E I S R T R I A A U C S L Q I E U E F R C 1
R I U S R 0 C D D I 1 T S E E R C T C T4 P C A A E f S O D ,
M J 1E R l l S R O l P A l U
Ti l f R 0 T I F P l l
1 R S T 1 r
i T O E I D M C T Y L E O U C R L T N C R A T U C I T R S B E M R S T U J A A l l
l i D C O X
E S o 0 l l R R F C C I I I
P o o o o o o
.
-
_
_
_ l
-
. .
.
.
_
_
_
.
.
_
_
_
_
-
_
_
.
..
-
_
W E _
I _
V _
E R
N F
R O -
A K L R P O U
W E U -
I E V ) T E C E R I L U P H O M S --
G L O N S U ( C O E -
O I R _
R S 0 T U .
O E 1
A D H
.
T A I E
-
T U R C B S M A O A I D A V R R R R P D
E P
T T
O C
G O
R O M
-
A E R F A O R S P R L T T E G
.
E l Y S G _
V l
L O _
A F I N A R -
_
E T I L I l l
-
P D R T K L 0 O N C P I D P E E M T E M D H A A S I I C S R U
.
o 0 o o o o
.. -
8
/
2
. /
_
_
_
.
.
_
_
_
_
_
-
E S h
.
T N A l E R O r lP l A 4
- -
LS O P !
T -
VC Rp . BTLRE A .
g l a M UOR t
'
D A
H F' ESF SE L N E
.
s tt SR A A M -
IN M u F s O A e C R E
-- r P
A g
.
e R R 1 v G - it r
IO 4 is 1 V o R g
.
P I P iF A
O S -
EL T L .
S E A f
1 I RW 4
- S Y
V CK .
L NC ig I A _
OO F N < .
CL A
-
B 8
. '8 Y S D W ) ; T N NS E S R _
T SOHI CO AT t
V N . O LIS ENO e T P Y OCT T E N
I RA PL RET U s R REAR K VA r VO 4 A e ACEA WC EE MEU 1 I R . T T R L INRSP RSL G ig I R7 C A UEE I H V O(A F O N N MORR I
LS P EC
F R E V P M
I F
E 1& E I R P P -
,
&T YE
f d
.
-' -
l RE ME i
4
-
t V IC .
g LA i I E M
_
.
EL F & E DP IN E T L _
M RNB RUT R EO _
ETX T AEF P T E N N Y c
.
D E O MIT i
'
'
1EA DL L .
s t
EU g lu -'
i I s MQ F R
e E
e i
v t
a g Y e
EH . N RR TT b T EG 1 ON _
RN E
-
P 4 A
' 1 CE .
NR ig I OT F CS 9 -
-
8
_
-
/
2
/
s
. -
_
-
.
_
_
. _
.
_
. _
_
__
_
l l
0 l 1 i T T A P H E U D _
I S L D E A N I _
E C A T R I A ,
T V W l E l l I D iu C U T R l N 0 C A T E l l
A H C D A E E l f N T D P 0 l l O E E S P I I R T i l S T C C I E D A l l
E R A V 0 P ,
R O R C S 0 O R E N 4 I C B S D I I E E T ,
- R l
,
S S S P E S E T '
N D D T I R O ,
R R D C I S A O R U l l T E l l
C OA A R E F ,
M U F R ,
S R T 0 S S ' O C T DL C F U 3 C R A E N R T E O U P I T S J C Q S S E O E F T R RL ,
O D P E S E E Y 1 I G Y T C D T N N T C A E l O I E E L W l S W I P P E A R A R S -
I U E R A N l V O P D V I l
I E
R _
o 0 o 0 0 _
-
.
- _
1
-
. 7
. 8
/
_
.
/
9 t
CO
^ W CO H H Hl CO O J} H 2 l D J W i
CD .t LJ CO' O Z Z H W U O O H w1J W :. J u) H O H & ~
l C D 2 2 J W D H W <
J H O CL H J T 1 O H 1 O H M Z
!
!
O H O 2 W
=
<C
")
LJ
=
< H CO >- 0 O CO O 2 C z 2 = = 0 )
i O <C O W W N i
H
'
2 O H H CO CD i H LaJ e-l D C C *
l
<C * % CO O W CO j
> "O
. LJ H H H W j
Z r-- >- Z Z H H H W D H < H <C v O CO t--i -4 'I H > 2 CO J J O <C % CO W
'
O M <C % LJ W H O D <C D LO D O l UJ W O C 3 D u) H i O = N O CD u j
I <C O M O
'
- H uJ E N LO O O O O O -4 m .* CO A CO m + N Ln m l
O O O O O O O-e l M
! %
' e N
N N
N
.
- - - - _ _ _ _ - - - - _ _ _
I
. 1
l i
l j
i W
O l Z
H l RJ !
CL
-
W O O u)
Z L H W O Z
.3: H Rt W W uJ Z H 2 LAJ LLI CO
> C % % '. LI LJ O O H D x O uJ B V)
O O CC LAJ Q u_ RJ H H O 2 %
uJ D O O Z O W e-4 J Z O CO AJ Z J ^ H l Z % <C CO O O I O I Z 2 O RJ H O <C CO O Z LAJ r-1 H LA. 'O
. uJ WH CO O u! Z O Z~ O H
,
I O O <C RJ D I CO O H 2 i O O Z
O Z Z < ><
H Z U"> LAJ N I H >
l CO 2 2 OJ l D O ~ ~J O O <C O
J H x H D H O H O & OH O Z O H O Z Z O D O D Q. uJ O O & <C x H H i H K H J O I CO H CO < M I
= = = = x 1 O
O O o H m O i O O u. w 2 l l
o o o o o N
k w I
r CC N
.
N
.
N LD
W E
I V
E W T R E N l E
& l1 V H 0 E S G I S R S N T L E I A I M S T 1 i A E S R R T T A O O E S P F D Y E E N S E R 1 E
T
.
i Y T F T T L I S O R P H I 4 l O P H S T I P U O Y N A E S C L U T R A O N E T N M O T V H A A C N I G E S I T S R l l S A E E A R E L H P E R I O X V G F C E O o o o o o
-
.
.
N O
G I N T T I A C S G E N I J E T O C S R I E P L V D -
N E K F R I N O O T
-
R I O Y F N R A W E T A E G G I E L H O D S L P T N T E S B R O L E AE U I S W C T H F T E O E PT A U N N E - D M N K N C F E R I O A C O E O T E I A N F N T T M N N O AC A S O T I C R U E I I U O R T T O L S B T E A R L S A S E T R G A E L N L E E R C E O B R P D E O C A C O N V R D E N A O P E E G O E P T D C F Y W O E E A R E L R L 3 S N I EC W - O V V N O P D S E EO N N N A R D C K WA M o o o o o
. 4
. -
8
/
.
d
2
/
_ _ _ - _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ -
-
.
CONCRETE MODULE, C3-02, FINAL REPORT CONTENTS INTRODUCTION SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS REVIEW PROGRAM DESCRIPTION PROGRAM MANAGEMENT METHODOLOGY PROGRAM RESULTS OVERSIGHT COMMITTEE ASSESSMENT APPENDICES REVIEW PLAN OPEN ITEMS LIST (0IL) REPORT: IN-PLACE TESTING OF CONCRETE
'
s
\