IR 05000454/2024003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000454/2024003 and 05000455/2024003
ML24312A378
Person / Time
Site: Byron  
Issue date: 11/12/2024
From: Richard Skokowski
NRC/RGN-III/DORS/RPB3
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2024003
Download: ML24312A378 (1)


Text

SUBJECT:

BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2024003 AND 05000455/2024003

Dear David Rhoades:

On September 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On October 10, 2024, the NRC inspectors discussed the results of this inspection with H. Welt, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Byron Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Byron Station.

November 12, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Richard A. Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000454 and 05000455

License Numbers:

NPF-37 and NPF-66

Report Numbers:

05000454/2024003 and 05000455/2024003

Enterprise Identifier:

I-2024-003-0055

Licensee:

Constellation Energy Generation, LLC

Facility:

Byron Station

Location:

Byron, IL

Inspection Dates:

July 01, 2024 to September 30, 2024

Inspectors:

N. Bolling, Resident Inspector

J. Cassidy, Senior Health Physicist

A. Demeter, Senior Resident Inspector

R. Elliott, Senior Project Engineer

R. Farmer, Health Physicist

J. Heimke, Project Engineer

T. Hooker, Health Physicist

R. Knutson, Illinois Emergency Management Agency (IEMA)

J. Park, Reactor Inspector

J. Robb, Operations Engineer

L. Torres, IEMA ASME Inspector

Approved By:

Richard A. Skokowski, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Satisfy ASME Code Case N-722-1 Examination Requirements for Reactor Coolant System (RCS) Pressure Boundary Welds Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000454/2024003-01 Open/Closed

[H.7] -

Documentation 71111.08P The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation (NCV) of 10 CFR Part 50, Section 50.55a(g)(6)(ii)(E), Augmented ISI requirements: Reactor coolant pressure boundary visual inspections, for the licensees failure to assure the ASME Code Case N-722-1 examination requirements for the Class I RCS instrument connection pressure boundary welds were satisfied. Specifically, during remote visual examination of the Reactor Pressure Vessel (RPV) bottom head, the licensee failed to complete examination of all nozzle-to-thimble guide tube welds as required by N-722-1.

Failure to establish a time-based preventative maintenance schedule for Diesel Generator Ventilation Fans Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454,05000455/2024003-02 Open/Closed None (NPP)71111.12 A self-revealed finding of very low safety significance (Green) and associated non-cited violation of Technical Specification 5.4.1.a was identified for the licensees failure to establish an appropriate preventative maintenance (PM) schedule for the emergency diesel generator (EDG) ventilation fans. Specifically, time-based inspections including torque checks and other inspections to prevent excess movement of fan assembly components were not conducted on the ventilation fans despite being classified as a component needing this type of PM schedule.

The failure to establish an appropriate PM schedule resulted in the loosening of fan blade nuts going unnoticed nor corrected, increased stresses to the fan blades, and ultimately catastrophic failure of the 2A EDG ventilation fan.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000455/2022-001-01 LER 2022-001-01 for Byron Station, Unit 2, Volumetric Examinations of Reactor Pressure Vessel Head Core Exit Thermocouple 71153 Closed

Penetration P-75 Identified an Indication Attributed to Primary Water Stress Corrosion Cracking

PLANT STATUS

Unit 1 began the inspection period operating at full power. The unit entered power coast down on August 23, 2024. On September 9, 2024, Unit 1 was taken offline for a planned refueling outage. The unit remained offline and in the refueling outage for the remainder of the inspection period.

Unit 2 began the inspection period operating at full power and remained at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 safety injection system on July 9, 2024
(2) Unit 1 residual heat removal system on July 17, 2024
(3) Fuel pool cooling and cleanup system on July 31, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) Unit 2 auxiliary feedwater system ending September 27, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 11.4-0, Auxiliary Building 383-0 Elevation General Areas - North, South, and West on July 2, 2024
(2) Fire Zone 11.4A-0, Auxiliary Building 383-0 Elevation Control Room Refrigeration Equipment Room during 0A Control Room Chiller emergent maintenance on July 12, 2024
(3) Fire Zone 3.2A-1 through 3.2D-1, 439'-0" Elevation Lower Cable Spreading Room on August 6, 2024
(4) Fire Zone 5.5-1, 5.5-2, Units 1 & 2 Auxiliary Electrical Room and Fire Zone 5.2-2 Auxiliary Building Division 21 ESF Switchgear Room on August 28, 2024
(5) Review and assessment of the licensee's failure to meet Plant Barrier Impairment (PBI) requirements, as documented in Issue Report (AR) 4796221 on August 30, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in Unit 1 Area 5 during an essential service water (SX) pipe replacement on September 30, 2024

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities in Unit 1 during refueling outage B1R26 from September 9th, 2024 to September 24th, 2024.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) Ultrasonic Examination
  • Safety Injection System Pipe Welds, 1SI08FA-3 J29 and J30, Cat. R-A, Item R1.11-5 Surface Examination
  • Magnetic Particle Exam of RPV Head-to-Flange Weld, 1RC01R RVHC-01, Cat. B-A, Item B1.40 Visual Examination
  • RPV Bottom Head Visual Exam of Bottom Mounted Instrument (BMI)

Penetrations and Bare Metal Surface, Code Case N-722 Exam, Item B15.80 Welding Activities

Replacement of U1 SX Piping 1SX27DB-10 from Carbon Steel to Stainless Steel, Work Order (WO) 05029727-01, Weld No. 10 PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection

Activities (IP Section 03.02) (1 Sample)

The inspectors verified that the licensee conducted the following vessel upper head penetration inspections and addressed any identified defects appropriately:

(1) Vessel Upper Head Penetration Examinations and Defect Repair/Removal
  • PT Examination of CRDM Nozzle Overlay on RPV Head Penetration 31, Post-Repair PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1) Boric Acid Evaluations and Corrective Actions
  • Boric Acid Leakage on 1CV02A, ARs 04686053, 04552969, and 04167929

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated on-watch licensed operator performance during various activities in the main control room through September 3, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the performance of a complex casualty graded scenario by a crew of licensed plant operators in the facility's simulator on July 23, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Maintenance effectiveness review of the 0A essential service water makeup pump on August 19, 2024
(2) Maintenance effectiveness review of the Units 1 and 2 diesel generator room ventilation (VC) system following a catastrophic failure of a ventilation fan on August 27, 2024 Quality Control (IP Section 03.02) (1 Partial)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)

(Partial)

Safety-related diesel engine fuel injectors on September 30, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Review and evaluation of the risk associated with a one-time surveillance interval extension for 1B emergency diesel generator monthly testing on July 22, 2024
(2) Review and evaluation of the risk associated with new fuel receipt and inspection in preparation for Refueling Outage B1R26, as documented in WO 5491204 through August 8, 2024
(3) Review and evaluation of the risk associated with restoring 125VDC engineered safety feature battery 212 cell above administrative limit after discovery of the cell approaching operability limit on August 21, 2024
(4) Review and evaluation of the risk management actions associated with a planned Risk Informed Completion Time (RICT) implementation during replacement of Battery 212 on September 6, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of several chemical volume control system valves following discovery of the installation of incorrectly rated gaskets, as documented in AR 4783268 on July 5, 2024
(2) Evaluation of the operability of the 2B component cooling pump following discovery of elevated seal leakage, as documented in AR 4790521 on August 1, 2024
(3) Evaluation of the operability of the moderator temperature coefficient (MTC) as noted in the core operating limits report (COLR) following incorrect calculation, as documented in AR 4721679 on August 16, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Review of permanent plant modification per engineering change (EC) 634799, CDO - 1SX27DA-10" SX Pipe Replacements with Stainless Steel and Install Line Stop Fitting on 1SX07HB-20".
(2) Review of temporary plant modification per EC 642106: TCC Temporarily Jumper Out Cell 24 of ESF Battery 212 to Allow 125VDC ESF Batter 212 Operation with 57 Cells

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated Refuel Outage B1R26 activities from September 8, 2024 to September 30, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1) Functional and operational testing of power range detector N-42 following troubleshooting and maintenance due to degraded indications, as documented in WO 5555325 on July 12, 2024
(2) Functional and operational testing of the 0A control room HVAC chiller following unscheduled maintenance, as documented in WO 5426260 on July 30, 2024
(3) Functional and operational testing of the 2B auxiliary feedwater pump following extent of condition torque checks, as documented in WO 5567419 on August 14, 2024
(4) Functional and operational testing of the 1B auxiliary feedwater pump following extent of condition torque checks, as documented in WO 5567440 on August 19, 2024
(5) Functional and operational testing of the 125VDC battery (DC Bus 212) following cell replacement, as documented in WO 5568409 on September 6, 2024
(6) Functional and operational testing of the 2B emergency diesel generator following maintenance performed during Refueling Outage B1R26, as documented in various WOs on September 30, 2024
(7) Functional and operational testing of the Unit 1 reactor core through low power physics testing following Refueling Outage B1R26, as documented in WO 5350240 on September 30, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1)2BOSR 8.1.2-1, Unit Two 2A emergency diesel generator operability surveillance on July 12, 2024 (2)2BOSR 5.5.8.SX-4, component cooling heat exchanger essential service water outlet valve stroke surveillance on August 27, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) Local leak rate testing of primary containment isolation valves 1RF026, 1RF027, 1RF055, and 1SI8968, as documented in various WOs on September 26, 2024

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Observation of the technical support center (TSC) focus area drill that covered the escalation of emergency action levels (EAL) from alert to general emergency due to the loss of fission product barriers on July 10, 2024.

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Observation of an emergency preparedness medical drill assessing offsite medical response capabilities on August 8,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Workers exiting the primary radiologically controlled area
(2) Licensee surveys of potentially contaminated material leaving the containment access facility

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Buffing and blending of identified defects on penetration #31 of Unit 1 reactor head
(2) Local leak rate testing under the transfer canal
(3) Inspections on the Unit 1 control rod drive mechanisms High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1) Unit 1 in-core detector thimble tube penetrations
(2) Unit 1 reactor head stand Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Portable HEPA Unit #428 in use at Unit 1 Reactor Head

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

71124.04 - Occupational Dose Assessment

Special Dosimetric Situations (IP Section 03.04) (1 Sample)

The inspectors evaluated the following special dosimetric situations:

(1) The use of EDEX for Emergent Repairs of Unit 1 Reactor Head

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (July 1, 2023 through June 30, 2024)
(2) Unit 2 (July 1, 2023 through June 30, 2024)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2023 through June 30, 2024)
(2) Unit 2 (July 1, 2023 through June 30, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (July 1, 2023 through June 30, 2024)
(2) Unit 2 (July 1, 2023 through June 30, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors reviewed the corrective actions associated with AR 4721470, Fuel dilution in 2AF01PB-K diesel engine is in ALERT range.
(2) The inspectors reviewed the corrective actions associated with AR 4697929, 0FX02PC High Head Flex Pump has Stuck Open or Bad Piston.

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors reviewed, evaluated, and closed the following licensee event reports (LERs):

(1) Unit 2 LER 05000455/2022-001-01, Volumetric Examinations of Reactor Pressure Vessel Head Core Exit Thermocouple Penetration P-75 Identified an Indication Attributed to Primary Water Stress Corrosion Cracking (ADAMS Accession No.

ML23243A934). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foreseen and corrected and therefore was not reasonably preventable. During the Unit 2 refueling outage in the spring of 2022, volumetric examinations of the reactor vessel head identified a recordable indication in core exit thermocouple penetration number 75 (P-75) that did not meet the applicable acceptance criteria. By letter dated September 29, 2023 (ADAMS Accession No. ML23272A242), Constellation submitted a request for alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle (RPVHPN) P-75. NRC staff authorized the use of the proposed alternative until the next scheduled inspection in spring 2025. This position was documented under Byron Station, Unit No. 2 - Authorization and Safety Evaluation for Alternative Request No. I4R-24 (ADAMS Accession No.

ML24131A007). No performance deficiency nor violation of NRC requirements was identified. This LER is Closed.

INSPECTION RESULTS

Failure to Satisfy ASME Code Case N-722-1 Examination Requirements for Reactor Coolant System (RCS) Pressure Boundary Welds Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000454/2024003-01 Open/Closed

[H.7] -

Documentation 71111.08P The inspectors identified a finding of very low safety significance (Green) and an associated Non-Cited Violation (NCV) of 10 CFR Part 50, Section 50.55a(g)(6)(ii)(E), Augmented ISI requirements: Reactor coolant pressure boundary visual inspections, for the licensees failure to assure the ASME Code Case N-722-1 examination requirements for the Class I RCS instrument connection pressure boundary welds were satisfied. Specifically, during remote visual examination of the Reactor Pressure Vessel (RPV) bottom head, the licensee failed to complete examination of all nozzle-to-thimble guide tube welds as required by N-722-1.

Description:

Byron Unit 1 RPV bottom head has

(58) Bottom Mounted Instrument (BMI) nozzle penetrations, which require visual examination every other outage. These penetrations are identified as Item Number B15.80 under N-722-1. The penetration nozzles are connected to thimble guide tubes by welds, and these instrument connection welds require visual examination once every interval. These welds are identified as Item Number 15.100 under N-722-1.

On September 9, 2024, during the last outage (B1R26) of the current fourth interval, the licensee performed remote visual examination of the RPV BMI nozzle penetrations, Item Number B15.80, along with the bare metal surface. During the review of the examination records, the inspector selected a few sample areas of the bottom head region for review.

Each of the selected areas represented different geometrical configuration due to the shape of the bottom head. Of particular interest was the instrument connections located near the center of the head. The inspector noted that due to the configuration of the existing lower insulation package below the bottom head, the visibility of the centermost instrument connection welds was either fully or partially obstructed by the existing insulation materials. Consequently, not all welds were within the visual line of sight during the visual examination activity.

Further review of the licensees ISI Program Plan for the current Fourth Ten-Year Inspection Interval, ER-BY-330-1001, Rev. 3, revealed that the instrument connections identified as Item Number 15.100 were listed under Section 2.2.8 of the program plan as not applicable. It was also revealed that these connections had not been listed in the program plan as applicable since the implementation of N-722-1 during the second period of the third interval.

Consequently, the program plan had not required examination of these connection welds.

However, upon detailed review, it was determined these welds should have been identified as applicable under this category.

The licensee was not able to produce evidence that the insulation package under the bottom head was removed to access these welds for the prior N-722-1 related examinations.

Therefore, the licensee concluded that a total of eight centermost instrument connection welds that were visually obstructed by the insulation materials had not been examined since the third interval when the N-722-1 requirements were implemented.

Corrective Actions: The licensee entered the issues into their corrective action program. The licensee verified that the other

(50) instrument connection welds that were within the visual line of sight had been examined during the N-722-1 activity. The examination verified there were no indications of leakage through these welds. Additionally, the licensee performed evaluation of the
(8) centermost instrument connection welds that had not been examined.

The evaluation concluded there was reasonable assurance that adequate pressure boundary and structural integrity were maintained. The inspectors reviewed the evaluation. The licensee documented within their corrective action program planned corrective actions to evaluate this issue on Unit 2, the alternate unit, for applicability.

Corrective Action References: AR 04802795

Performance Assessment:

Performance Deficiency: The licensees failure to satisfy the examination requirements of ASME Code Case N-722-1 for the RCS pressure boundary welds was contrary to 10 CFR 50.55a(g)(6)(ii)(E) and was a performance deficiency. Specifically, the licensee did not complete the visual examination of all nozzle-to-thimble guide tube pressure boundary welds during the RPV bottom head visual examination activity.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the RCS Equipment and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensees failure to complete examination of all Class I nozzle-to-thimble guide tube connection welds to satisfy the requirements of N-722-1 did not provide assurance the RCS pressure boundary was maintained.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors answered No to question, Does the finding involve potential non-compliance with regulatory requirements for protection of the reactor pressure vessel against fracture (e.g., pressure-temperature limits or pressurized thermal shock issues)? under Section B of Exhibit 3 - Barrier Integrity Screening Questions. Therefore, the finding was screened as having very low safety significance (Green).

Cross-Cutting Aspect: H.7 - Documentation: The organization creates and maintains complete, accurate and up-to-date documentation. Through documentation reviews and interviews with licensee staff, the inspectors determined the licensee failed to satisfy the examination requirements of N-722-1 because the examination activities were governed by the licensees ISI program that did not require the examination of the RPV bottom head instrument connection welds.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations, Part 50, Section 50.55a(g)(6)(ii)(E),

Augmented ISI requirements: Reactor coolant pressure boundary visual inspections, stated,

(1) All licensees of pressurized water reactors must augment their inservice inspection program by implementing ASME Code Case N-722-1, subject to the conditions specified in paragraphs (g)(6)(ii)(E)(2) through
(4) of this section. The inspection requirements of ASME Code Case N-722-1 do not apply to components with pressure retaining welds fabricated with Alloy 600/82/182 materials that have been mitigated by weld overlay or stress improvement.

The licensees RPV bottom head nozzle-to-thimble guide tube welds were fabricated with Alloy 82 material that have not been mitigated by weld overlay or stress improvement.

ASME Code Case N-722-1 required, in part, that the additional examinations of Table 1 shall be performed for pressurized water reactor plants having partial or full penetration welds in Class 1 components fabricated with Alloy 600/82/182 material.

Table 1 of Code Case N-722-1 required, in part, that the instrument connections identified as Item No. B15.100 be visually examined once per interval.

Contrary to the above, as of September 9, 2024, the licensees inservice inspection program failed to comply with the requirements of ASME Code Case N-722-1. Specifically, the licensee failed to complete visual examination of all Class 1 nozzle-to-thimble guide tube welds to satisfy the requirements of N-722-1. The conditions specified in paragraphs (g)(6)(ii)(E)(2) through

(4) of Section 50.55a did not apply.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to establish a time-based preventative maintenance schedule for Diesel Generator Ventilation Fans Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454,05000455/2024003-02 Open/Closed None (NPP)71111.12 A self-revealed finding of very low safety significance (Green) and associated non-cited violation of Technical Specification 5.4.1.a was identified for the licensees failure to establish an appropriate preventative maintenance (PM) schedule for the emergency diesel generator (EDG) ventilation fans. Specifically, time-based inspections including torque checks and other inspections to prevent excess movement of fan assembly components were not conducted on the ventilation fans despite being classified as a component needing this type of PM schedule. The failure to establish an appropriate PM schedule resulted in the loosening of fan blade nuts going unnoticed nor corrected, increased stresses to the fan blades, and ultimately catastrophic failure of the 2A EDG ventilation fan.

Description:

On November 1, 2023, the 2A EDG and associated diesel ventilation fan, 2VD01CA, were started per 2BOSR 8.1.14-1, Unit Two 2A Diesel Generator 24 Hour Endurance Run and Hot Restart Test, for the annual 24-hour endurance run. At approximately 0930 on November 2, 2023, a loud bang was heard in the 2A EDG room and the main control room received the DG ROOM 2A VENT FAN DP - LOW alarm. The 2A EDG was shut down and placed into maintenance outage mode and the vent fan switch placed in the pull-to-lock position. On November 2, 2023, at 0941, the 2A EDG was declared inoperable and unavailable. Repairs to 2VD01CA were completed on November 8, 2023, and at 1615, the 2A EDG was returned to service.

Upon removal, 16 fan blades were broken at or near their bases on the fan hub. Blade fragments were ejected from the fan housing and strewn down the supply ductwork. The hub, with all broken blade roots in place, was transported to the mechanical maintenance shop.

Inspections performed by the licensee determined that three of the 16 blade root connector nuts, which are used to prevent relative motion between the blade root and opening of the fan hub, had excessive looseness. These nuts are intended to be torqued to a minimum of 220 foot-pounds, but the three loose nuts were found to be torqued to less than 50 foot-pounds.

Additional inspection found other signs of improper relative motion between the blade root and hub. This looseness and relative motion during operation resulted in increased bending stresses and premature failure. A corrective action program evaluation (CAPE) determined that the cause of the catastrophic failure of 2VD01CA was high cycle, low stress fatigue of a fan blade, subject to excessive bending induced by a loose fan blade root nut.

A review of operating experience identified catastrophic failures of a fan in the circulating water pump house (CWPH) ventilation caused by high cycle, low stress fatigue from Byron (2013) and Braidwood (2014). Additionally, in 2019, while the auxiliary building ventilation system was in operation, two exhaust fan blades fractured due to high cycle, low stress fatigue. As a result of the failures of the CWPH fans, a time-based PM task was created and implemented to address the cause of the failure, which was not implemented for similar fans, including 2VD01CA.

Per ER-AA-200-1001, Equipment Classification, the fan was classified as a Non-Critical, Mild Environment, Low Cycle component and should have had time-based inspections. The CAPE determined the lack of regular inspection and torque verification was a casual factor of the failure. Inadequate preventative maintenance led to a loose blade going unnoticed or corrected that ultimately failed due to increased bending stress and high cyclic fatigue.

Corrective Actions: In response to the failure, the licensee performed extent of condition inspections on the three remaining EDGs prior to each of their next scheduled run and didn't not find additional loose bolts. Additionally, a CAPE was performed to review and document the failure mechanism of the fan and provide a more in depth understanding of the issue and necessary corrective actions to mitigate and/or eliminate reoccurrence. The licensee has reclassified the diesel ventilation fans as critical components and are creating and implementing new PMs to perform additional inspections, including torque checks.

Corrective Action References: 4714774; Low dP Alarm on 2A DG Vent Fan; 11/02/2023 4716165; 1A EDG EOC work required for DG Vent Fan Failure; 11/08/2023 4716167; 1B EDG EOC work required for DG Vent Fan Failure; 11/08/2023 4716168; 2B EDG EOC work required for DG Vent Fan Failure; 11/08/2023

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to create and implement a preventative maintenance schedule for the EDG ventilation fans was contrary to Technical Specification 5.4.1.a and was a performance deficiency. Specifically, the failure to perform torque checks and other inspections to prevent excess movement of fan assembly components led to allowing a loose blade to go unnoticed nor corrected, that ultimately failed due to increased bending stress and high cyclic fatigue.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensees preventative maintenance and testing program did not identify required tests and inspections and was not implemented in such a manner to prevent failure. The inadequate PM frequency and scope for the EDG ventilation fans resulted in catastrophic failure of 2VD01CA which rendered the 2A EDG inoperable and unavailable.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors compared the finding with the examples listed in Inspection Manual Chapter (IMC)0612, Power Reactor Inspection Reports, Appendix E, Example of Minor Issues and found example 4.l to be similar. Specifically, time-based preventative maintenance was not conducted on the EDG ventilation fans despite being classified as a component needing this type of PM schedule. The failure to establish an appropriate PM schedule resulted in the loosening of fan blade nuts going uncorrected which increased stresses to the fan blades, and ultimately catastrophic failure of the 2A EDG ventilation fan. This resulted in the inoperability and unavailability of the 2A EDG.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Byron Unit 2 Technical Specifications 5.4.1.a, requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

NRC Regulatory Guide 1.33, Revision 2, Appendix A, Section 9 addresses Procedures for Performing Maintenance and Section 9.b states, in part, that preventative maintenance schedules should be developed for inspections of equipment.

Contrary to the above, prior to the catastrophic failure of the diesel ventilation fan on November 2, 2023, the licensee failed to develop a preventative maintenance schedule for inspections of susceptible portions of the EDG ventilation fans. Specifically, the licensee failed to establish or implement a time-based PM schedule as necessitated by their classification as non-critical, mild environment, low cycle components.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Diesel driven auxiliary feedwater pump fuel oil dilution 71152A The inspectors performed a detailed review of AR 4721470, Fuel dilution in 2AF01PB-K diesel engine is in ALERT range. On December 4, 2023, Byron received sample results back from the 2B diesel driven auxiliary feedwater pump (AFP) that showed crank case fuel dilution levels high out of range per MA-AA-716-230-1001, Oil Interpretation Guidelines.

Confirmatory sample results received on December 7, 2023, confirmed an unfavorable trend in fuel dilution and viscosity.

Braidwood had experienced similar fuel dilution issues in the months preceding the issues at Byron. Byron took proactive measures during an ongoing AFP work window in October 2023 that coincided with the discovery of the issues at Braidwood. Following the issues in December, Byron entered an emergent work window to replace the crank case oil and perform additional inspections and maintenance. Following completion of the emergent work, the AFP passed all post maintenance testing and was returned to service.

Both stations identified areas for improvements in their maintenance strategy during their investigations. These included enhancing pressure testing practices, incorporating vendor recommended torque values for fuel injector bolts, and not reusing end fittings for the fuel pipes.

The inspectors concluded that the licensees actions were in accordance with their corrective action program and reasonable given the overall safety significance of the issue. Byron incorporated lessons learned in real-time based on the discovery at Braidwood, such as bearing inspections that were missed by Braidwood and improvements in maintenance practices for the abovementioned gaps. Additionally, tests performed by the licensee demonstrated that, even with increased fuel dilution, the AFP would be capable of performing its safety-related function for the required mission time.

No findings or violations of NRC requirements of more than minor safety significance were identified by the inspectors in the course of this review.

Observation: 0C high head FLEX pump unavailable greater than 90 days 71152A The inspectors performed a detailed review of several issue reports (ARs) related to the 0C high head FLEX pump (0FX02PC). These included, but were not limited to:

  • AR 4697929, 0FX02PC High Head Flex Pump has Stuck Open or Bad Piston
  • AR 4781773, Vendor Did Not Fully Implement Supplemental Oil Cooler MOD
  • AR 4782124, Delays in restoration of the 0C High Head Flex pump
  • AR 4780856, 0FX01PC and 0FX02PC Original Supply Receipt Inspection On March 12, 2012, the NRC directed licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in response to a beyond-design-basis external event. This was later codified under 10 CFR 50.155. On December 7, 2016, the licensee confirmed development and implementation of these strategies using low, medium, and high head pumps, referred to as the FLEX pumps. The licensee used the guidance in NEI 12-06 and obtained three of each type of pump (based on "N+1" philosophy). NEI 12-06 guidance was also used when formulating the licensee's mitigation plan which allowed for one of these pumps to be out of service for up to 90 days.

On August 22, 2023, the licensee with vendor support conducted full flow testing on 0FX02PC where it did not meet the acceptance criteria as stated in the test procedure when it failed to develop proper discharge pressure. 0FX02PC was secured per vendor instruction and declared not functional.

On February 28, 2024, the licensee attempted a flow test following vendor repairs on 0FX02PC and was unsuccessful. When the hose was disconnected, ice was identified being pumped out. The vendor recommended removing the pump from the site to perform further investigation and repair.

On June 19, 2024, during return receipt inspection of 0FX02PC from the vendor, the licensee identified that the planned modification to support an additional oil cooler was not complete.

The modification was missing a new relief valve and manifold that would allow maximum output of the auxiliary charge pump and allow adequate backpressure on the auxiliary oil pump.

As of September 30, 2024, 0FX02PC has been out of service for a total of 405 days, or 315 days beyond the 90 days permitted by the licensees mitigation plan.

The inspectors examined the licensees recent corrective action to determine whether other outstanding issues and questions had been addressed, but the inspectors acknowledge that not all investigative and maintenance activities have been completed. Several observations by the inspectors include, but were not limited to:

  • Due to the inability to meet acceptance criteria, the vendor recommended the installation of a second hydraulic oil cooler on all three high head flex pumps, including 0FX02PC. The need to equip a second hydraulic oil cooler to meet acceptance criteria is indicative of potential shortcomings in the original design of the pumps as purchased.
  • AR 4780856 identified medium head flex pump 0FX01PC and 0FX02PC did not have a supply receipt inspection conducted as required, and therefore, there is no documentation that a quality control inspection was performed.
  • The inability to return 0FX02PC to service within the 90 days allowed by their mitigation plan/strategy constituted a performance deficiency that was within their ability to foresee, and which should have been prevented. However, since the licensee maintained the ability to implement their mitigation strategy even with 0FX02PC out of service for the extended period, the issue was minor.

No findings or violations of NRC requirements of more than minor safety significance were identified by the inspectors in the course of this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 10, 2024, the inspectors presented the integrated inspection results to H. Welt, Site Vice President, and other members of the licensee staff.
  • On September 20, 2024, the inspectors presented the radiation protection inspection results to S. Harvey, Plant Manager, and other members of the licensee staff.
  • On September 24, 2024, the inspectors presented the inservice inspection results to H. Welt, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

BOP AF-E2

Unit 2 Auxiliary Feedwater Electrical Lineup

BOP AF-M2

Auxiliary Feedwater System Valve Lineup

BOP CD-M2

Condensate System Lineup

BOP DO-M2

Diesel Fuel Oil System Valve Lineup

BOP FC-E1

Unit 0 Fuel Pool Cooling System Electrical Lineup

BOP FC-M1

Fuel Pool Cooling and Cleanup System Valve Lineup

BOP RH-E1

Unit 1 Residual Heat Removal System Valve Lineup

BOP RH-M1

Unit 1 Residual Heat Removal System Electrical Lineup

BOP SI-E1

Unit 1 Safety Injection System Electrical Lineup

BOP SI-M1

Unit 1 Safety Injection System Valve Lineup

BOP SX-M2A

Unit 2 Train A Essential Service Water System Valve Lineup

71111.04

Procedures

BOP SX-M2B

Unit 2 Train B Essential Service Water System Valve Lineup

Corrective Action

Documents

04796221

APS: PBI Requirements not met

08/22/2024

Pre-Fire Plan

  1. 132

Fire Zone 11.4-0 North Auxiliary Building 383-0 Elevation

General Area - North

Pre-Fire Plan

  1. 135

Fire Zone 11.4A-0 Auxiliary Building 383-0 Elevation Control

Room Refrigeration Equipment Room

Pre-Fire Plan #19

Fire Zone 3.2A-1 Auxiliary Building 439-0 Elevation Lower

Cable Spreading Room

Pre-Fire Plan #21

Fire Zone 3.2B-1 Auxiliary Building 439-0 Elevation Lower

Cable Spreading Room

Pre-Fire Plan #23

Fire Zone 3.2C-1 Auxiliary Building 439-0 Elevation Lower

Cable Spreading Room

Pre-Fire Plan #25

Fire Zone 3.2D-1 Auxiliary Building 439-0 Elevation Lower

Cable Spreading Room

Pre-Fire Plan #44

Fire Zone 5.2-2 Auxiliary Building 426-0 Elevation Division 21

ESF Switchgear Room

Pre-Fire Plan #49

Fire Zone 5.5-1 Auxiliary Building 451-0 Elevation Unit 1

Auxiliary Electrical Room

71111.05

Fire Plans

Pre-Fire Plan #50

Fire Zone 5.5-2 Auxiliary Building 451-0 Elevation Unit 2

Auxiliary Electrical Room

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Pre-Fire

Plan #133

Fire Zone 11.4-0 South Auxiliary Building 383-0 Elevation

General Area - South

Pre-Fire

Plan #134

Fire Zone 11.4-0 West Auxiliary Building 383-0 Elevation

General Area - West

Calculations

3C8-1281-001

Auxiliary Building Flooding Calculations

Corrective Action

Documents

4802550

B1R26-1B SX Line Repl-Grout Set Needed for Pipe Support

09/17/2024

BAP 1100-3A3

Pre-Evaluated Plant Barrier Matrix

71111.06

Procedures

CC-AA-201

Plant Barrier Control Program

04167929

Inactive Bolted Connection Leak on 1CV02A

08/28/2018

04552969

1CV02A - Expired BACC Evaluation

2/06/2023

04561059

Recordable Indications - B1R25 ASME Sec. XI, IWE Exam

03/10/2023

04561270

Recordable Indications on 1RC01PD RCP Seal Housing Bolts

03/11/2023

04561294

B1R26 ISI - Relevant Condition on 1SX01PA Support

03/11/2023

04563486

1CV8119 Appears to be Leaking

03/20/2023

04686053

INPO: Incorrect Corrosion Calculation Used in BACC Evals

06/21/2023

04774048

Trend - Missing Documentation from ASME R/R Work

Packages

05/14/2024

04774906

Missing Welding Docs, WO:01431732-01

05/17/2024

04782912

ASME Replacement WO#05322470 Documentation

Incomplete

06/25/2024

04803434

WO 05347432-01 ASME R/R Closeout Review

09/20/2024

Corrective Action

Documents

04803746

B1R26LL: NOS QV ID Weld Rod Ticket Issue

09/23/2024

Corrective Action

Documents

Resulting from

Inspection

04802795

NRC ID: N-722-1 Augmented ISI Program Implementation

Issues

09/18/2024

Drawings

1193E54 Sheets

and 2

Byron/Braidwood/Marble Hill Unit 1 Bottom Mounted

Instrumentation Field Assembly

1CV02A

Evaluation of Leakage from Bolted Connection from 1CV02A

06/22/2023

Engineering

Evaluations

1CV8119

Evaluation of Leakage from Bolted Connection from 1CV8119

08/29/2023

71111.08P

Miscellaneous

Process

Specification

2127JS

Welding Reactor Vessel Bottom Mounted Instrumentation

Connections

03/07/1983

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

B1R26-MT-001

Magnetic Particle Examination Report for RPV Head-to-Flange

Weld

09/20/2024

B1R26-MT-002

Magnetic Particle Examination Report for RPV Head-to-Flange

Weld

09/20/2024

B1R26-PT-001

Liquid Penetrant Examination for RPV Head Penetration No.

09/13/2024

B1R26-PT-002

Liquid Penetrant Examination for RPV Head Penetration No.

09/14/2024

B1R26-PT-003

Liquid Penetrant Examination for RPV Head Penetration No.

31, Post-Repair

09/19/2024

B1R26-UT-033

UT Calibration/Examination Report for Weld 1RC-01-R/H-34

09/20/2024

B1R26-UT-036

UT Calibration/Examination Report for Weld 1SI08FA-3/J29

09/20/2024

B1R26-UT-037

UT Calibration/Examination Report for Weld 1SI08FA-3/J30

09/20/2024

B1R26-UT-041

UT Calibration/Examination Report for Weld 1RC-01-R/H-09

09/20/2024

B1R26-VEN-002

Visual Examination NDE Report for RPV Upper Head

Penetration Surface

09/22/2024

NDE Reports

BAR26-VEN-001

Visual Examination NDE Report for RPV BMI

09/14/2024

ER-AA-335-002

Liquid Penetrant (PT) Examination

ER-AA-335-003

Magnetic Particle (MT) Examination

ER-AA-335-048

Ultrasonic Examination in Accordance with ASME Section XI,

Appendix III

ER-AP-331

Boric Acid Corrosion Control (BACC) Program

ER-AP-331-1002

Boric Acid Corrosion Control (BACC) Program Identification,

Screening, and Evaluation

ER-AP-335-001

Bare Metal Visual Examination for Nickel Alloy Materials

ER-BY-330-1001

Byron Generating Station Units 1 & 2, Inservice Inspection

(ISI) Program Plan, Fourth Ten-Year Inspection Interval

ER-BY-330-1002

Byron Generating Station Units 1 & 2, Inservice Inspection

(ISI) Classification Basis Document, Fourth Ten-Year

Inspection Interval

PDI-UT-2

Generic Procedure for the Ultrasonic Examination of Austenitic

Pipe Welds

J

Procedures

WPS 8-8-GTSM

ASME Welding Procedure Specification Record

04836037-03

NDE Visual Exam of RX Head CRDM Seismic Support Tie

Rods

03/22/2020

71111.08P

Work Orders

05029727-01

Replace 1SX27DB-10 with Stainless Steel

4701020

0A SX Makeup Pump Trip

09/07/2023

4701152

Potential Trend in 0A SX M/U Pump Trips

09/08/2023

4104858

0B SX Makeup Pump Tripped During Monthly Surveillance Ru

2/16/2018

4709470

1B AF Pump EOC Fuel Dilution Review Results

10/13/2023

4710871

2B AF Diesel Rebuilt Injectors Did Not Pass Inspection

10/19/2023

4714774

Low dP Alarm on 2A DG Vent Fan

11/02/2023

4716165

EOC Work Required for DG Vent Fan Failure

11/08/2023

4716167

EOC Work Required For DG Vent Fan Failure

11/08/2023

4716168

EOC Work Required for DG Vent Fan Failure

11/08/2023

4719499

1VD02CC Tripping on High DP

11/24/2023

4739352

MRC Rejection of CAPE

01/30/2024

4748804

Potential Trend for Ventilation Equipment

2/08/2024

4755659

Revise BOP DG-11T2 to Include VD Components

03/05/2024

4761713

0A SX M/U Pump Trip

03/28/2024

4763519

Refurbished Injector for 16V149 Aux Feed Diesel

04/04/2024

4765868

Results for 2B EDG Fuel Injector Testing

04/09/2024

4766509

LTA Closure of CAPE 4714774

04/15/2024

Corrective Action

Documents

4796271

NOS ID: CA Closed without Actions Being Implemented

08/22/2024

Maintenance Rule (a)(1) Determination for 0A SX Makeup

Pump Trip 04701020

01/31/2024

Miscellaneous

BYR-33907

Power Labs Failure Analysis of Relay and Relay Bases for the

0A Essential Service Water Makeup Pump

05/21/2024

ER-AA-320

Maintenance Rule Implementation per NEI 1810

71111.12

Procedures

ER-AA-320-1004

Maintenance Rule - (a)(1) And (a)(2) Requirements

4787078

One-Time Extension of 1B EDG Monthly Surveillance

07/15/2024

Corrective Action

Documents

4793742

2 Battery Below Admin Level

08/14/2024

Engineering

Changes

2106

TCC Temporarily Jumper Out Cell 21 of ESF Battery 212 to

Allow 125 VDC ESF Batter 212 Operation with 57 Cells

000

RICT Package for Planned DC Bus 212 Cell Replacement

09/05/2024

BY-24-001

Surveillance Test Interval Evaluation Form for One-Time

Revision to 1B DG Monthly Surveillances to 62 Days

000

71111.13

Miscellaneous

PORC Meeting

Plant Operations Review Committee for Surveillance

07/18/2024

  1. 24-015

Frequency Control Program Change for a One-Time Revision

to 1B DG Monthly Surveillances to 62 Days

PRA Analysis BY-

STI-061

Risk Evaluation of One-Time Surveillance Interval Extension

for 1B EDG Monthly Test (SRs 3.8.1.2, 3.8.1.3, 3.8.1.4,

3.8.1.5, 3.8.1.6, 3.8.3.1, 3.8.3.3)

ER-AA-425

Implementation of the Technical Specification Surveillance

Frequency Control Program

ER-AA-600-1012

Risk Management Documentation

Procedures

ER-AA-600-1051

Risk Assessment of Surveillance Test Frequency Changes

Work Orders

5491204

U-1 Receive & Inspect New Fuel

08/09/2024

4451252

2A CC Pump Inboard Seal Leak

10/06/2021

4476583

2A CC Pump Inboard Seal Leak Got Worse

2/07/2022

4694519

CID 482906 Description and Part Numbers Dont Align

08/03/2023

21679

COLR MTC (Section 2.3.1) Incorrectly Calculated - BYR/BRW

2/05/2023

22310

Incorrect MTC Elimination checks for Byron and Braidwood

2/08/2023

4783268

CID 482906 Byron Installation History

06/26/2024

Corrective Action

Documents

4790521

2B CC Pp Inboard Seal Leaking

07/30/2024

71111.15

Procedures

MA-AA-716-010-

1104

Mechanical Seal Leakage Evaluation and Reporting

Calculations

1346-0076-RPT-

001

Design Report for Byron SX Modified Piping Subassembly for

EC 634799

27883

2SX27DB-10" SX Pipe Replacements with Stainless Steel

000

631320

CDO - 1SX27DB-10" SX Pipe Replacements with Stainless

Steel and Install Line Stop Fitting on 1SX07HB-20"

000

634799

CDO - 1SX27DA-10" SX Pipe Replacements with Stainless

Steel and Install Line Stop Fitting on 1SX07HA-20"

000

Engineering

Changes

639768

MR90 Evaluation for Use of Line Stop on 1SX07HB-20" and

Pipe Disconnection on Line 1SX27DB-10" with Valve

1SX057B Removed

000

71111.18

Engineering

Evaluations

BYR99-122

Review of Design Report for ITT 2.0 Inch Class 150 lb. Ball

Valve (ITT Corporation Industrial Process, Design Report

W-521, Revision 13) for EC 634799

4785438

N-42 Lower Detector Delta I Indications/Alarms Failing

07/07/2024

4786475

0A VC Chiller Secured due to Lowering Oil Level

07/11/2024

71111.24

Corrective Action

Documents

4789581

MA-AA-716-006 Improvements Needed Based On 0A VC

Chiller Oil

07/24/2024

4793457

2B AF Pump Turbo Exhaust Disconnected

08/12/2024

4793475

Work Request Needed for 1B Aux Feed Pump

08/12/2024

4793476

Work Request Needed for 2B Aux Feed Pump

08/12/2024

4793637

2B AF Pump Extent of Condition

08/13/2024

4793642

1B AF Pump Extent of Condition

08/13/2024

4793644

AF Pump Clamp Torquing Discrepancy during EOC

08/13/2024

4801862

As Found LLRT on P-55 UNSAT

09/14/2024

1BOSR 0.5-

2.AF.3-1

Unit One Auxiliary Feedwater Valves Train A Indication Test

1BOSR 6.1.1-18

Unit One Primary Containment Type C Local Leakage Rate

Tests and IST Tests of Containment Floor Drains System

1BOSR 6.1.1-22

Unit One Primary Containment Type C Local Leakage Rate

Test and IST Tests of Safety Injection System

1BOSR 7.5.4-2

Unit 1 Diesel Driven Auxiliary Feedwater Pump Monthly

Surveillance

1BOSR 8.1.11-2

Unit One 1B Diesel Generator Sequencer Test

1BOSR 8.1.17-2

Unit One 1B Diesel Generator SI Signal Override Test

1BOSR 8.1.9-2

Unit One 1B Diesel Generator Safe Shutdown Sequencer and

Single Load Rejection Test

2BOSR 5.5.8.SX-

Component Cooling Heat Exchanger Essential Service Water

Outlet Valve Stroke Surveillance

2BOSR 7.5.4-2

Unit Two Diesel Driven Auxiliary Feedwater Pump Monthly

Surveillance

2BOSR 8.1.2-1

Unit Two 2A Diesel Generator Operability Surveillance

BOP AF-5

Motor Driven Auxiliary Feedwater Pump 1A Startup on Recirc

BOP DG-11T2

Diesel Generator Operating Log

Procedures

NF-BY-510

Low Power Physics Test Program

5301687

LR-U1 Motor Driven AF Pump - Clean and Inspector Lube Oil

Cooler

09/26/2024

5330914

(Sample/Change) Motor Driven Aux Feedwater Pump 1A

09/26/2024

5347121

Rebuild Actuator, Regulators/Replace Elastomers

09/23/2024

5347127

1RF055 IST Relief Valve Test (Pre/Post LLRT Req)

09/20/2024

5347369

1B Diesel Generator SI Signal Override Test

09/23/2024

Work Orders

5347370

1B Diesel Generator Safe S/D Sequencer and Single Load

Reject

09/26/2024

5347371

1B Diesel Generator Sequencer Test

09/26/2024

5347513

LLRT for P-55 - 1SI8880 and 1SI8968

09/23/2024

5347517

LLRT for P-47 - 1RF026, 1RF027 and 1RF055

09/20/2024

5350240

Low Power Physics Testing Program Using the ADRC

09/30/2024

26260

0A VC Chiller Adjust Oil Level as Required for - 2024

07/30/2024

5551220

(NEIL)-LR-2A Diesel Generator Operability Surveillance

07/05/2024

5555325

Perform N-42 Troubleshooting

07/12/2024

5567419

Work Request Needed for 2B Aux Feed Pump

08/14/2024

5567440

Work Request Needed for 1B Aux Feed Pump

08/14/2024

5568009

2 Battery Below Admin Limit

09/06/2024

5568409

NERC-Quarterly 125VDC Battery Surveillance - 2DC02E

09/06/2024

EP-AA-1002

Addendum 3

Constellation Emergency Action Levels for Byron Station

EP-AA-1102

ERO Fundamentals

71114.06

Procedures

EP-AA-122

Drills and Exercise Program

BY-1-24-00647

Penetration - Prep & PT (P-31/43)

BY-1-24-00647

CRDM Inspection & Associated Activities - No Under Head

Work

BY-1-24-00649

Emergent Rx Head Repair

ALARA Plans

BY-1-24-00649

Emergent Rx Head Repair

04679377

Unanticipated Dose Rate Alarm

05/19/2023

04681694

1RE-PR-027

05/31/2023

04692990

New Serv. Bldg. High Temp Impacting Required RP WBC

Units

07/27/2023

04707535

Self-Assessment Discrepancies Identified

10/06/2023

04711416

Level 2 PCE

10/21/2023

04799820

PEI doc. Not Completed / Turned Into Records Timely

09/06/2024

Corrective Action

Documents

04801438

Poor Rad Worker Behaviors While Working Around Posted

HRA

09/13/2024

Corrective Action

Documents

Resulting from

Inspection

04803132

NRC Observations on Under Head Work

09/19/2024

NISP-RP-003

Radiological Air Sampling

71124.01

Procedures

NISP-RP-010

Radiological Job Coverage

RP-AA-302

Determination of Alpha Levels and Monitoring

RP-AA-302

Determination of Alpha Levels and Monitoring

RP-AA-460

Controls for High and Locked High Radiation Areas

RP-AA-460-001

Controls for Very High Radiation Areas

RP-AA-460-002

Additional High Radiation Exposure Control

RP-AA-503-F-01

Unconditional Release Instructions Using the Tool and

Equipment Monitor (TEM) for Personal Items Used in the

Radiologically Controlled Area (RCA) and in a Contaminated

Area

24-224617

Head Stand Scaffold B-6039 and B-0640

09/13/2024

24-224691

Under Head Survey For Pen34 Inspection

09/15/2024

Radiation Surveys

24-224988

Head Stand Scaffold B-6035

09/18/2024

BY-1-24-00649

Emergent Rx Head Repair

Radiation Work

Permits (RWPs)

BY-1-24-00649

Emergent Rx Head Repair

AR 04540870

Contamination Control Self-Assessment

10/30/2023

Self-Assessments

AR 04540871-02

Control of Radioactive Material

10/30/2023

RP-AA-825-1014

Operation and Inspection of the 3M Versaflo TR-300,

TR-300+ PAPR System

71124.03

Procedures

RP-AA-870-1004

Use of Air Movers/Portable Fans in Radiologically Controlled

Areas

Miscellaneous

RP-AA-210-1001

Emergent RX Head Repair Multiple Dosimetry EDEX

Evaluation Sheet

09/13/2024

71124.04

Procedures

RP-AA-210

Dosimetry Issue, Usage, and Control

NRC Performance Indicator Data; Mitigating

Systems - Mitigating System Performance Index for Residual

Heat Removal Systems

07/01/2023-

06/30/2024

NRC Performance Indicator Data; Mitigating

Systems - Mitigating System Performance Index for Cooling

Water Systems

07/01/2023-

06/30/2024

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating

Systems - Mitigating System Performance Index for Heat

Removal Systems

07/01/2023-

06/30/2024

4697929

0FX02PC High Head Flex Pump has Stuck Open or Bad

Piston

08/22/2023

4717747

0BOL FX1 Comp Actions

11/15/2023

71152A

Corrective Action

Documents

21470

Fuel dilution in 2AF01PB-K diesel engine is in ALERT range

2/04/2024

22187

Long Term FLEX Pump Storage Strategy

2/07/2023

22225

2B AF Diesel Crankcase Confirmatory Oil Sample Results

2/07/2024

4753970

C High Head FLEX Pump Needs Further Repair

2/28/2024

4759115

Create WR for Installation of FLEX Pump Cooler

03/19/2024

4765443

0FX02PC-0C High Head FLEX Needs Additional Work

04/11/2024

4775101

Delays in 0C Flex Pump from Vendor

05/19/2024

4780856

0FX01PC and 0FX02PC Original Supply Receipt Inspection

06/14/2024

4781773

Vendor Did Not Fully Implement Supplemental Oil Cooler

MOD

06/19/2024

4782124

Delays in restoration of the0C High Head Flex pump

06/21/2024

P21-12182023-

FN

10CFR Part 21 Final Notification of Defect with Detroit

Diesel/MTU Fuel Injectors PN R5229660 Cat ID#0001390618

Miscellaneous

P21-12182023-IN

10CFR Part 21 Initial Notification of Defect with Detroit

Diesel/MTU Fuel Injectors PN R5229660 Cat ID#0001390618

0BOSR FX-A1

Flex Pump Annual Flow Surveillance

CC-AA-118

Diverse and Flexible Coping Strategies (FLEX), Spent Fuel

Pool Instrumentation (SFPI), and Hardened Containment Vent

System (HCVS) Program Document

Procedures

MA-AA-716-230-

1001

Oil Analysis Interpretation Guidelines

Corrective Action

Documents

4786272

U2 RPVH Pen-75 Flaw Repair WO and Comp. Action Not

Needed

07/11/2024

LER 2022-001-01

Byron Station Unit 2 Volumetric Examinations of Reactor

Pressure Vessel Head Core Exit Thermocouple Penetration

P-75 Identified an Indication Attributed to Primary Water Stress

Corrosion Cracking

04/23/2024

Letter BYRON

23-0042

Licensee Event Report (LER) Supplement

No. 455-2022-001-01 Byron Station Unit 2 Volumetric

Examinations of Reactor Pressure Vessel Head Core Exit

Thermocouple Penetration P-75 Identified an Indication

Attributed to Primary Water Stress Corrosion Cracking

08/31/2023

71153

Miscellaneous

Relief Request

I4R-24

Alternative for Post-Peening Reexamination Frequency for

Reactor Pressure Vessel Head Penetration Nozzle Number 75

09/29/2023