IR 05000395/1978018
| ML20062E263 | |
| Person / Time | |
|---|---|
| Site: | Summer |
| Issue date: | 10/16/1978 |
| From: | Ang W, Bryant J, Modenos L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20062E252 | List: |
| References | |
| 50-395-78-18, NUDOCS 7812060035 | |
| Download: ML20062E263 (6) | |
Text
o
->
a'
,,,
,
.
,
- ,'
r
,
>
'
- --
'
.
.
....
.
7.
-
e
%, __.g..;. l
- 3
,
- .u l&,
.
_
,
..
,,,,'_. f_.__ _,' M.;:,,... y =,. c M...
,.m g,a gg
. f :??-
,,. -
.h
, ',
u %:
,,.
av...,
, ~
y
,,
,-
.ei,:
- 3 '
!.^
,
u X.:., l
.... > ;' :,.-
- ~
.
,
,
,,
..
_,
I,
@ K8Sp UNITED STATES q
,
,#
jo NUCLEAR REGULATORY COMMISSION
~
~
g
.
REGION 11
$
o
-
'
- l-f
[g 101 M ARIETT A STREET. N.W.
,
ATLANTA. GEORGI A 30303
%,...../
.
..
q
$
- y
' ' '
Report No.: 50-395/78-18 Docket No.: 50-395
'
';.4
." ^
License No.: CPPR-94
. %
4-
~ ^pF Category: A3/B1
.
.
.
"
Licensee:
South Carolina Electric and Gas Company
'
P. O. Box 764 Columbia, South Carolina 29202 Facility Name: Virgil C. Summer Nuclear Station, Unit No. 1
'
Inspection at: Fairfield County, South Carolina Inspection conducted: September 5-8, 1978 Inspectors:
W. P. Ang L. Modenos
,
to /~$f'33 Reviewed by
.
%
m c
'Date j
J. C. Bryant, (hief Q
Engineering Support Section No. 1
'
Reactor Construction and Engineering Support Branch
,
,
Inspection Summary
~l Inspection on September 5-8, 1978 (Report No. 50-395/78-18)
t Areas Inspected: Work activities associated with the installation of the Q,
reactor vessel; work activities and records associated with safety-related components; work activities associated with ultrasonic testing of safety-i related piping. The inspection involved 48 inspector-hours on site by two i
~l NRC inspectors.
Results:
Of the four areas inspected, no items of noncospliance or deviations were found in three areas; one apparent item of noncompliance was found in one area (Infraction - failure to follow procedures in the area of housekeeping for the reactor vessel internal surfaces, Details I, paragraph 5 (78-18-01)).
ei e
- j 781206oo35
,
z
-
e.
--
w--,
-
,-.,--.w
- - - - -, - - -. - - - - -,,..,
,,,,-,__.,,,mn-
,,,..n.
-.. -, ~. - - -, - -,., -
,,m-,--..--,
,---,--,-.-,-----..,,,--n.n...-.-
.
-,
.,!
_.
.
2._c.x. a. s. a.-.;.u
h.a.a.c..L
-
.k,..
s',
'
-
.
.
.
i
--;
.
,
,
RII Rpt. No. 50-395/78-18 I-1 A-k DETAILS I Prepared by:_
c3
'
W. P. Ang, Mechanical Ehgineer 29 ffr
-
Engineering Support Section No. 1 Date
.
Reactor Construction and Engineering Suppor Branc
, ',
.
f J
L. Modenos, Reactor InspefEor
[
9b y
++
'
(>
Engineering Support Section No.
Da't'e ~
Reactor Construction and Engineering
Support Branch Dates of Inspection: September 5-8, 1978 i
!
()
Reviewed by
.
A
J. C. Bryant, ChtEf
'~
b s!7A
-
. 1 Engineering Support Section Ro. '~
' Dave l
r
Reactor Construction and Engineering
[
Support Branch
[;,
1.
Persons Contacted I
South Carolina Electric and Gas Company (SCE&G)
a.
,
{
!
- D. A. Nauman, QA Manager
.
- H. I. Donnelly,. Site QA Coordinator i
M. W. Clonts, Mechanical QC Supervisor
,
"
J. Bocock, Mechanical QA Supervisor
.
b.
Daniel Construction Company (DCC)
,
j (-)
- R. D. Gunderson, Project Manager
',
V
!
i
- W. L. West, Project QA Manager
!
- G. R. Curtis, QC Supervisor l
W. Wais, Supervisory Mechanical Engineer
'
c.
Westinghouse Electric Company (W)
f
.!
!
D. D. Wieland, Site Manager
, -
d.
,
Nuclear Energy Services, Conam Inspection Division E
i
,
i
i
'
J r
.
h
,
l '
- )
-~m m-.-
-
-. - - -. -...
.
..-
T-G.0, hacks '-
-
^2
=1 c
l
'
e'
M:Jur_a - ^
W
-
'
'
.
-
-
,.
k
- 1.
,
.
4 yj
-
-
si fc,.y
,
.
,
ff; j
,2 RII Rpt. No. 50-395/73-18 I-2
'
, J 4{
d
.
L ('b
..j[
C. A. Talbott, Supervisory Inspector
'
d:M;.%
- j#
- Denotes those present at the exit interview.
,,
t k-4 2.
Licensee Action on Previous Inspection Findings nR9 gg This area was not inspected.
, o s.
'E 3.
Unresolved Items
..wg
- 1 No unresolved items were identified during this inspection.
~ -
.]
-
4.
Independent Inspection Effort
"
.;
a
.
Q The inspector made a walk-through inspection of the reactor plant. The
inspector observed general work activities, cleanliness (housekeeping), storage conditions, protection, and maintenance of
"
safety-related equipment. The inspector observed ultrasonic testing for wall thickness determination being performed on a safety-related pipe. The inspector discussed the test procedure (Daniel Construction Procedure WE-I-03 Rev.
- Ultrasonic Inspection)
with the
'
nondestructive test inspector.
The nondestructive test inspector's qualification records were
-
examined.
No items of noncompliance or deviations were identified.
-
5.
Reactor Vessel Installation - Review of Quality Records
>
n Pertinent quality related work and inspection records relevant to the V
installed reactor vessel (RV), were examined.
The following records i
for housekeeping inspections, QA audits and QC inspections were examined.
QC Storage Inspection Form MS-2-1 for 3-28-78 and 5-16-78 a.
b.
QA Surveillance Report #10-3-77 PC on Transporting and Setting of the RV l
l-c.
QC Form FQCP 6.2.2 - Inspection of Installation of Equipment -
For the Reactor Vessel - 12-14-77
- 4
]
d.
QC Housekeeping Inspection Forms FQCP 6.7.1-1 for the Reactor
- i Building
,
.i
4
1
~ ~~.-- - -,.
w._.....
..
...... _ _
..y_,,,,_,_
.,,.,, _ _, _.. _ _,,,,,,,,
,,,,, _,,,,, _ _,,,, _ _
=-a-w.
w.
.c
,.9.+y-y-
- -
--.
.--.,+,.-,--e
..c
- - ---
w.
-
---.e y--
'
l
'.
-
b_aa;.s ~
hc
.r_ a c.:2_a_ x'; ~
- e
- -
-
-
o
- i
- '
-
,
.
housekeeping area. SCEG Procedure FQCP 3.5.0 prohibits the use of food
^
or tobacco in Zone IV areas.
The inspector noted several cigarette
,,r
-
butts and an empty cigarette wrapper at the inside bottom of the RV underneath the work platform. Also noted at the bottom were several
loose bolts, a rag with what appeared to be liquid penetrant dye on it
,
,
and loose pieces of plastic tubing. This noncompliance was identified to the licensee as an Infraction, No. 395/78-18-01.
6.
Safety-Related Components I - Observation of Work and Work Activities i
Components selected from within the reactor coolant pressure boundary
!
n were the charging-safety injection pumps A, B & C.
The partially (./
installed pumps were inspected for location, grouting, supports and
maintenance of inspection records. The following procedures were used to verify the installation of these pumps.
SCE&G FQC Procedure 6.2.2 DCC WP-III-06 DCC WP-VI-03
.
Alignment of pumps to motors and pipe had not yet been done. SCE&G FQC procedure 6.2.1 provides instructions for alignment. Alignment is to be accomplished at a later date.
No items of noncompliance or deviations were identified.
_
7.
Safety-Related Components I - Review of Quality Records h
rertinent quality related work and inspection records of partially installed component cooling system valve XVG-9605-CC, records for receipt inspection, material and fabrication certifications / test reports, storage, installation, and QA audits were examined.
The following records and procedures relevant to valve XVG-9605-CC were examined:
a.
SCEG Field QC Procedure 3.2.0 Rev. 12 - Storage, Handling and Issuing j
b.
SCEG QC Procedure VII-05 - Iaspection of Cleaning and Storage of j
Fabricated Piping Subassemblies.
!
!
i
'
i
.
. _. _ _.
_........,.,_.
.
., _ _
_.. _.... - _ _
. _ _ _ -... _ _ _... _... _. _
.
,
- ,.
....
,.,
,,.
,
L v a ',< a,a
-
$, d
'
$:Y'-
'
- SM
'?
'
s.
t
.
..
t
.
<!
-
.
,
-
s
.
.
.
,
,
j RII Rpt. No. 50-395/78-18 I-4
,
=il;.
,
'r c.
SCEG QC Form MS-2-1 for 2/24/77 to 8/30/78 - In Place Storage
.,1, Inspection.
',c i d.
SCEG QC Form MS-3-1 for 6/24/78, 3/29/78, 12/29/78, 9/28/77, 7/7/77 and 3/30/77 - Inspection of Valves in Storage.
SCEG Material Reviewing Report No. SR-4748 dated 1-24-78
.-
e.
f.
Daniel Receiving Inspection Report No. 2241
,,
,
g.
Gilbert Certificate of Inspection dated 1-6-78
..!
h.
SCEG Warehouse Receiving Inspection dated 1-17-78
.j-l Q
i.
Anchor Darling Valve Co. Certificate of Compliance for Purchase v
Order No. SN-10109 SR dated 1-4-78 j.
SCEG Surveillance Reports from 1-4-78 to 8-26-78 k.
Anchor Darling Drawing 3319-3 Rev. C-8" 150# Gate Valve 1.
SCEG QA Procedure 12.20 Rev. 4 - Surveillance of Site Activities
,
SCEG QA Group Administrative Procedure #1 dated 9/10/76 m.
i n.
Qualifications for Two SCEG Mechanical QA Auditors o.
Daniel QA Audit Report No. 31 for July,1978 p.
Daniel QA Audit Report No. 32 for August,1978 h
q.
Daniel Certificates for Two Daniel QA Auditors j
r.
Daniel Work Packet SE-CC-47 s.
Daniel Work Packet SE-CC-37 No items of noncompliance or deviations were identified.
A review of the quality related work and inspection (QC) records of a component within the reactor coolant pressure boundary was done on safety injection pump XPP-43C-CS. Inspection of FQC Form No. 6.2.2-1
" Inspection of Installation of Equipment" confirmed that specifications and installation procedures were met. SCEG Deficiency i
Notice DN-1268M on Anchor Bolts that did not have double auto were i.
~**
-..
..., - ~.
,
.
_,.,,.,.,
.
,,..
_, _,,,
.
., _,
,...,,,
- s c....
.. ~,
- s.a..
. ax;,;ai
- '- -
'5 a' ~
-
"
-
.&
*
'
a
.
.
..
f i
-
d
,
.
.
-
-j RII Rpt. No. 50-395/78-18 I-5
.
r
,,.
reviewed. SCEG Field Quality Control Procedure 6.2.2 was followed and
,.
C records were legible.
,
No items of noncompliance or deviations were identified.
.
H" 8.
Exit Interview m
The inspector met with licensee representatives at the conclusion of the inspection. The inspector summarized the scope and findings of the
,
^?
inspection of the reactor plant, safety-related components and reactor
-
vessel.
The licensee was informed that one apparent item of noncompliance was identified.
This concerned the presence of
-'
cigarette butts and a cigarette wrapper in the bottom of the reactor vessel. No dissenting comments were received from the licensee.
' i O
.
.
.
O
3
?
!
t i
l f
)
... _..,. _ _ _ _ _.... _ _.,
.... -,. _ _..... _ _. _... _ - -..
.,_.-.._._. _.-~.,,_-_.
_.. _ _
.,.
_ - _ _