IE Insp Rept 50-395/78-29 on 781128-30.No Noncompliance Noted.Major Areas Inspected:Plant Operations,New Fuel Receipt & Fuel Handling
ML19263B626
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 12/12/1978
From: Robert Lewis, Skolds J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19263B625 List:
References
50-395-78-29, NUDOCS 7901220258
Download: ML19263B626 (5)


Text

.

UNITED STATES

/jk* "80 9(o, NUCLE AR REGULATORY COMMISSION

[

REGloN il

,

n

,,

g 101 M ARIETT A sTRE ET. N.W.

  • .,

f ATL ANTA. GEORGI A 30303 s....+

Report No. 50-395/78-29 Docket No.: 50-395 License Nos.: CPPR-94 Licensee:

South Carolina Electric and Gas Company Post Office Box 764 Columbia, South Carolina 29218

.

Facility Name: Virgil C. Summer Inspection at: Virgil C. Summer Site Jenkinsville, South Carolina Inspection conducted: November 28-30, 1978 Inspectors:

J. L. Skolds k

/ Y/t/7f Approved by: [.C.

u R. C. Lewis, Chief Date Reactor Projects Section No. 2 Reactor Operations and Nuclear Support Branch Inspection Summary Inspection on November 28-30, 1978; (Report Nos. 50-395/78-29)

Areas Inspected:

Routine, unannounced inspection of plant operations, new fuel receipt and fuel handling. The inspection involved 18 inspector-hours on site by one NRC inspector.

Results:

Of the two areas inspected, no items of noncompliance were identified.

790122025%

.

.

RII Rpt. No. 50-395/78-29 I-1 DETAILS I Prepared by:

E C.

/2/fr/7f J. L. Skolds, Reactor Inspector Date Reactor Projects Section No. 2 Reactor Operations and Nuclear Support Branch Dates of Inspection: November 28-30, 1978 Reviewed by:

[. C-

-

/ Z//z/77 R. C. Lesis, Chief Date Reactor Projects Section No. 2 Reactor Operations and Nuclear Support Branch 1.

Persons Contacted South Carolina Electric and Gas (SCE&G)

  • H. T. Babb, General Manager, Nuclear Operations
  • L. D. Shealy, Plant Manager e
  • 0. S. Bradham, Maintenance Supervisor
  • A. B. Harrison, Operations Supervisor
  • H.

I. Donnely, Jr., Site QA Coordinator

  • J. G. Connelly, Startup Supervisor
  • K.

E. Beale, Health Piiysics Supervisor R. M. Campbell, QC Engineer K. Woodward, Shift Supervisor D. Maples, Test Supervisor

'tmmer, H. P. Specialist M.

'

  • Indicates those present at the exit inte rvi ew.

Westinghouse M. J. Miller, Westinghouse Fuel Representative 2.

Licensee Action on Previous Inspection Findings There are no previous inspection findings requiring licensee action.

3.

New Unresolved Items None identified during the inspection.

4.

Exit Interview The inspector met with Mr. Babb and other licensee representatives listed in paragraph 1 at the conclusion of the inspection on

s

.

RII Rpt. No. 50-395/78-29 I-2 November 30, 1978. The inspector summarized the scope and findings of the inspection. The licensee informed the inspector that Mr. Ollie S.

Bradham would assume the duties of Plant Manager effective December 1, 1978.

5.

Fuel Receipt and Storage The inspector observed fuel handling operations in the Fuel Handling Building during the handling of the following fue,1 assemblies:

Tvel Container Assembly Number B-34 102 B-33 102 B-24

A-26

A-31

A-30

A-35

g A-34

The inspector observed the containers being unloaded from the truck and the assemblies being unloaded from the containers and placed in the New Fuel Storage Racks.

Fuel handling oeprations were observed to ensure complisnce with the Special Nuclear Material license issued under 10 CFR Part 70.

Specifically, the following areas were observed:

-

Special Nuclear Material specific storage requirements Integrity of security controls

-

Control of the environment in the fuel storage area

-

Documentation of fuel assembly receipt

-

Radiological controls during receipt inspection

-

Inspection of fuel assemblies and shipping containers

-

The inspector reviewed the following documentation: