IR 05000395/1978017

From kanterella
Jump to navigation Jump to search
IE Inspec Rept 50-395/78-17 on 780829-31 During Which No Items of Noncompliance Were Noted.Major Ares Inspected Included:Elec Components,Quality Records & Instrumentation QA Implementing Procedures
ML20062C577
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 10/04/1978
From: Bryant J, Gibbons T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20062C573 List:
References
50-395-78-17, NUDOCS 7811090238
Download: ML20062C577 (5)


Text

,'

u~.:...:.

~.~-

- A.Du = G i 6"'Y 2.'.'. i :

...~.'.:

I' 4 %.-

'

e J.e u;' >.a a G '

h. ;..,. ~ '

.

'

.

  • a

.

.

UNITED STATES p Ho

us t

o NUCLEAR REGULATORY COMMISSION g

R EGION il

{

f, g

.

g 101 M ARIETT A STREET. N.W.

[

ATL ANTA. GEORGI A 30303

,

o

%,...../

.

,

-

'. 1

.

.

Report No.: 50-395/78-17

.

'

, j)

Docket No.: 50-395

.

-

,

/}

License No.:

CPPR-94

> ;. _."

Category:

A3

'

Licensee:

South Carolina Electric and Gas Company

,,

P. O. Box 764 Columbia, South Carolina 29202

~

f Facility Name:

V. C. Summer l

Inspection at:

Fairfield County, South Carolina Inspection conducted: August 29-31, 1978

. 4 Inspector:

T. D. Gibbons c

,

l Reviewed by:

,od {,,

e.

/t e7F

'

J. E. Bryant, ~ Chi'ef Date Engineering Support Section No. 1 Reactor Construction and Engineering Support Branch Inspection Summary j

Inspection on August 29-31, 1978 (Report No. 395/78-17)

Areas Inspected:

Electrical components and systems observation of work, j

(}

quality records; instrumentation QA implementing p ro cedu re.s.

The

'

inspection involved 20 inspector-hours on site by one NRC inspector.

Results: There were no itms of noncompliance or deviations identi t ied.

-N

{811090238

,

,

L N * 9** gee.we W m mem m%.%em.,..

,,,g

,.

,

,_

.,p

,q

,

,,

,,,

,

"^

'

-

f,

_ _

.

. ;;m e

ww. -

.

,

.-

-

a,z.+

.

,

.

,

-

,

.

,

,

.

.

]

RII Rpt. No. 50-395/78-17 I-l a

,

..

,

""?

DETAILS I Prepared by:

w1

/ f 7p,

'

T. D. Gibbons, Electrical Engineer Date

" 2 -.

Engineering Support Section No. 1 Reactor Construction and Engineering

-

. l.

Support Branch

'

I Dates of Inspection:

August 29-31, 1978

-

.

.e.,

m; q

l f

-

10 il79-

-

Reviewed by: K 1.

.Lr),t u. _ _

c,1 J. C. Bryant, Chief

.f

~

'Dite

,

Engineering Support Sectidn No. 1 Reactor Construct. ion and Engineering Support Branch

.

1.

Persons Contacted

  • H. I. Donnelly, Jr., Site QA Coordinator

'

  • E. Evans, QA Engineer
  • K. W. Nettles, QC Manager

.

-l

  • J. Woods, QC Manager
  • D. A. Nauman, QA Manager
  • Denotes those attending the exit interview.

2.

Licensee Action on Previous Inspection Findings The licensee actions on previous inspection findings were not reviewed during this inspection.

3.

Unresolved Items (

h There were no new unresolved items identified during this inspection.

4.

Independent Inspection Effort At the request of the Atomic Safety and Licensing Board the inspector examined the containment building for reported splices in electrical cables to containment penet ra t ions.

Splices were found at the 4.y specified locations; however, each spiiced cable was identified to be temporny construction wiring. There are no sa f ety-related elect rical

penetrations installed at this time.

The inspector examined Specification SP-559-044461-000 for electrical penetrations.

The speci ficat iori requi res use of splicing sleeves on some miset1laneous

,

power circuits, The bill of material has been revised to cancel this usage. The Electrical Construction Guidelines for Cable Installation.

.l

,

.I

.l...

_

---.._,..._e

....,.

_,.,..,....,_ m.,,., _.,.

m r._,,,.

..

...

.

.

,.

J!

..a u:

.. w

,l :1i.Cr E l.s.$ a i a.aa. m E.z uG L.l M

'

.n

.

.

.

.

.

.f

Ril Rpt. No. 50-395/78-17 I-2 Number 04-4461-5-200-912, dated 7/1/77 has detailed splicing

-

[ i,,

instructions.

The cable installation procedures FQCP 7.1.1. states

"No splices permitted unless specifically called for on drawings or

_

y approval of engineer" by Field Change notice.

,

The report of splicing has been verified but there are no safety-

,

related cables involved. The licensee does have provision for splicing

'-

,*

but only under the control of design engineering.

Within the areas examined there were no items of noncompliance

.

identified.

5.

Instrumentation (Cable and Terminations) Review of Quality Assurance

.

Implementing Procedures

The inspector reviewed Work Procedures (WP) and Field QC Procedures (FQCP) listed'below, a.

WP-X11-01 Cable Pulling b.

WP-X111-01 Cable Terminations

'

c.

FQCP 7.1.1 Cable Pulling d.

FQCP 7.1.2 Cable Terminations e.

FQCP 2.1.4 Nonconformance Control and Procedure f.

FQCP 7.1.7 Installation of Cable Trays, Supports, Electrical Noise and Fire Barriers

.

g.

FQCP 3.1.0 Receiving Inspection h.

FQCP 3.2.0 Storage, Handling and issue i.

FQCP 2.2.3 Field and Engineering Change Procedure

j.

Bisco Quality Assurance Procedures (Fire Barrier)

1.

DM1-1 Damming Inst ruction (]'

2.

207-IP Silicone foam Installation The above procedures were reviewed to assure that the requirements of f

the FSAR were included.

The areas reviewed included receiving

,

j inspection, special handling and s t o ra ge,

storage inspection >,

qualification testing and documentation and the handling of

'

nonconforming material.

The installation procedures assure proper installation, implementation of special instructions for terminations,

.;

j qualification of workers and inspectors and the periodic verification of tooling.

Procedures require inspections of the installation and termination of instrument cables.

The results of :aspections are reviewed by QA personnel and management. QC procedures assure that the cable is traceable to the specification requirements and material certifications from receipt to installation.

Wireway separation.

!

protection, cable separatson and redundancy are required inspect mn

.

!

!

...-____._...c.

_

.

_.

.

.,. -.

. _ _., -

,

.

,.. -.,.,,.

.

.

.......

.

.

.

au --.a.a2.h 1.2:,:20:. S.ida.w..'..e.

~L. L ca,.d: k.%. x

... - ~. -

.,

.w -

-

.

..

.

.

.

'

o

,.

,,,,. i s

.

'

RII Rpt. No. 50-395/78-17 I-3 m

e l

'

  • .o (,

items. All changes are required to be documented and approved prior to

... n execution.

<-

.

.C@

~

Within the areas examined there were no items of noncompliance

'

identified.

u

,.

' ' "

6.

Electrical (Components and Systems I) Observation of Work

,

'"

and Work Activities

~

t.,

B

+o assure

' hat the FSAR requirements were

.

accomplished in the areas of receiving inspection, storage,

,

identification location, protection separation and qualification of the inspection personnel.

'

O The inspector inspected the installation of the 7200 volt switchgear XSW-IDB-ES which is fed from EDG B.

The inspection included review of

-

receiving inspection, identification, installation procedures, protection, cleanliness, location, separation and redundancy, and procedure revision control.

The inspector selected the 480V Load Center XSW-IDB2-ES and motor control centers XMC-IDB2X-ES and XMC-IDB2Y-ES which are fed f rom 7200V switchgear XSW-IDB-ES.

These items were inspected to verify that receiving inspection, storage, handling, identification, installation, anchoring, location and inspection were in conformance with the FSAR and site procedures.

Nonconformance reports involving the equipment were reviewed to verify their accuracy and disposition.

Several inspectors were interviewed to verify their qualifications.

i (]

Within the areas examined there were no items of noncompliance v

identified.

7.

Electrical (Components and Systems 1) Review of Quality Recordy

?

The inspector reviewed the quality records of the equipment inspected in paragraph 6.

The records confirm that receiving inspection and source inspection h, I been conducted.

The source inspection contractor conducted source inspection and issued shipping

-

releases af ter all inspect ion and testing at the vendors t'acility had

-

been corrp l e t ed.

Records confirm that the required installation inspections were conducted.

The inspector selected eight nonconformance notices and three

~l def iciency not it es for re.tew.

In each case the current status was

-

i t

._

.._.._

_. -

..,.

....

_ _ _,.

,

,. _.

..,.

..

I' ' : 20

^J L d'

.

-.a

-

-,. a x :. M ;. W ::2

..e

.

O. w../

., a:.:

-

a

..

~

q

,-

.

1 W

.c

. 1 RII Rpt. No. 50-395/78-17 I-4-o ni,

4,j identified.

The notices were complete, reviewed as required and the 4/.

resolution status was identified.

~

A review of the qualification records of three QC inspectors and three QA auditors was conducted. The records included training, experience

-

-

,

and testing reports which identified them as qualified.

,

.n',~

l f Four QA audits were reviewed to verify that the required audits were i

conducted and that the deficiencies identified were corrected.

~

..f Corrective actions included steps to prevent repetition of the

'

deficiency.

Within the areas examined there were no items of noncompliance identified.

8.

Exit Interview The inspector met with licensee representatives, (denoted in

-

l paragraph 1) at the conclusion of the site inspection. The inspector summarized the scope of the inspection as follows:

a.

Electrical (Components and Systems)

(1) Observation of work and work activities (2) Review of quality records b.

Instrumentation (Cable and Terminations) Review of Quality

,{

Assurance implementing Procedures l

There were no items of noncompliance or deviations identified.

!

!

,