IR 05000391/2013002

From kanterella
Jump to navigation Jump to search
Construction Deficiency Report 50-391/2013-02 - Instrument Sense Line Slope Issue - Final Report
ML13182A460
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 06/27/2013
From: Hruby R
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IR-13-002
Download: ML13182A460 (5)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 June 27, 2013 CDR-50-391/2013-02 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 10 CFR 50.55(e)Subject: Reference:

Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 -CONSTRUCTION DEFICIENCY REPORT 50-391/2013-02-INSTRUMENT SENSE LINE SLOPE ISSUE -FINAL REPORT TVA letter to NRC dated April 29, 2013, "Watts Bar Nuclear Plant (WBN) Unit 2 -Construction Deficiency report 50-391/2013-02-Instrument Sense Line Slope Issue -Interim Report" The purpose of this letter is to provide a final report for Construction Deficiency Report (CDR) 391/2013-02 regarding a condition that TVA has identified as a significant (programmatic)

breakdown in the instrument sense line installation program and, thus, a significant breakdown in a portion of TVA's quality assurance program. Walkdowns have been completed and have not identified examples where instrument line slopes as installed would have prevented the associated instruments from performing their intended safety function(s).

Therefore, no substantial safety hazards have been identifie Initial notification was made on April 1, 2013, via Event Notification 48871.The apparent cause of this condition involved a misinterpretation of construction procedure 25402-000-GPP-0000-N3401, "Instrument and Instrument Line Installation," which lacked proper detail to define the boundary of the sense line from the panel isolation valve to process connection including the root valve. Further details of this condition can be found in the CDR 391/2013-02 provided in the enclosure.

There are no new commitments contained in this lette U.S. Nuclear Regulatory Commission Page 2 June 27, 2013 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 7 th day of June, 2013.If you have any questions, please contact me at (423) 365-1260 or Gordon Arent at (423) 365-2004.Respectfully, Raymond A. Hruby, Jr.General Manager, Technical Services Watts Bar Unit 2 Enclosure:

Construction Deficiency Report (CDR) 391/2013-02, Instrument Sense Line Slope Issue -Final Report cc (Enclosure):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 U.S. Nuclear Regulatory Commission Page 3 June 27, 2013 bcc (Enclosure):

Jessie Quichocho U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 ENCLOSURE WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 REGARDING INSTRUMENT SENSE LINE SLOPE CONDITION 10 CFR 50.55(e) CONSTRUCTION DEFICIENCY REPORT (CDR) 50-391/2013-02 FINAL REPORT DESCRIPTION OF DEFICIENCY TVA has identified a condition that was a significant (programmatic)

breakdown in the instrument sense line installation program and, thus, a significant breakdown in a portion of TVA's quality assurance program. Specifically, TVA determined that a condition existed where certain portions of the instrument line installations in multiple systems have not been completely inspected to ensure that proper slope requirements (1/4 inch per foot) were met. Inadequate sense line slope could result in the degradation of the associated safety-related instrument due to the effects of air entrapment which could adversely affect the accuracy or time response of the instrument or cause noise.Walkdowns have been completed for those systems that contained the identified issue.Inspection results did not identify examples where instrument line slopes as installed would have prevented the associated instruments from performing their intended safety function(s).

Therefore, no substantial safety hazards have been identifie Since this condition had the potential to be a significant (programmatic)

breakdown in the instrument sense line installation program and, thus, a potential breakdown in TVA's quality assurance program, this condition was conservatively reported previously in accordance with 10 CFR 50.55(e).

Initial notification was made on April 1, 2013, via Event Notification 48871.The issues documented in CDR 50-391/2013-02 were captured in TVA's corrective action program as Problem Evaluation Report (PER) 680826.CAUSE OF THE DEFICIENCY The apparent cause for PER 680826 involved a misinterpretation of construction procedure 25402-000-GPP-0000-N3401, "Instrument and Instrument Line Installation." The construction procedure lacked proper detail to define the boundary of the sense line from the panel isolation valve to the process connection including the root valve.The standard Engineering Document Construction Release (EDCR) work scope statement for defining the sense line boundary is "Sense line connection from the process connection (e.g. root valve) to the panel isolation valve." However, the manner in which construction procedure 25402-000-GPP-0000-N3401 was written could be interpreted to mean that the required slope inspection did not include the root valve.TVA believes the misinterpretation was a more recent condition rather than a historical one. Early in the project, work was performed by Knowledge, Skill and Rule-based personne The Knowledge was developed through design review meetings that were conducted for the EDCRs prior to issuanc These meetings provided the expectations and level of detail needed to resolve the issues related to the Instrument Line corrective action plan through extensive walkdowns involving construction and design personnel.

As the project progressed, the Skill and Rule base traits have remaine However, the Knowledge base has been diminished given the length of time that elapses between the issuance of design packages and the work that takes place to complete their implementation.

E-1 9.ENCLOSURE WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 REGARDING INSTRUMENT SENSE LINE SLOPE CONDITION 10 CFR 50.55(e) CONSTRUCTION DEFICIENCY REPORT (CDR) 50-391/2013-02 FINAL REPORT SAFETY IMPLICATIONS Walkdowns have been completed for those systems which contained the issue.Inspection results did not identify examples where instrument line slopes as installed would have prevented the associated instruments from performing their intended safety function(s).

Therefore, no substantial safety hazards have been identified.

CORRECTIVE ACTIONS 1. Procedure 25402-000-GPP-0000-N3401, "Instrument and Instrument Line Installation," has been revised to identify the sense line boundary from the process connection through the root valve to the panel isolation valve.2. Training to the above revised procedure has been provided to applicable Field Engineers, Planners, and Design personnel to eliminate any Knowledge gap.3. The standard statement in the EDCRs discussed above has been removed from each EDCR through approved procedures for revising EDCRs.4. TVA has revalidated instrument line slopes for the affected systems and has subsequently prepared and processed Field Change Requests to document changes requiring correction found during these walkdown None of these changes would have resulted in a substantial safety hazard had they remained uncorrecte For the remaining systems yet to be completed, TVA has corrected the program as described above to complete those systems as intended from this time forward.E-2