IR 05000390/2025010

From kanterella
Jump to navigation Jump to search
Fire Protection Team Inspection Report 05000390/2025010 and 05000391/2025010
ML25077A071
Person / Time
Site: Watts Bar  
Issue date: 03/18/2025
From: Daniel Bacon
NRC/RGN-II/DORS/EB2
To: Erb D
Tennessee Valley Authority
References
IR 2025010
Download: ML25077A071 (1)


Text

SUBJECT:

WATTS BAR NUCLEAR PLANT - FIRE PROTECTION TEAM INSPECTION REPORT 05000390/2025010 AND 05000391/2025010

Dear Delson C. Erb:

On February 27, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Watts Bar Nuclear Plant. On February 27, 2025, the NRC inspectors discussed the results of this inspection with William C. Reneau and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Daniel M. Bacon, Branch Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000390 and 05000391 License Nos. NPF-90 and NPF-96

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000390 and 05000391

License Numbers:

NPF-90 and NPF-96

Report Numbers:

05000390/2025010 and 05000391/2025010

Enterprise Identifier:

I-2025-010-0042

Licensee:

Tennessee Valley Authority

Facility:

Watts Bar Nuclear Plant

Location:

Spring City, TN

Inspection Dates:

February 10, 2025 to February 27, 2025

Inspectors:

P. Braaten, Senior Reactor Inspector

M. Hagen, Reactor Inspector

W. Monk, Senior Reactor Inspector

Approved By:

Daniel M. Bacon, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection team inspection at Watts Bar Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1)a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA)analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies.

Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR)pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

1. Auxiliary Feedwater System

2. Emergency Raw Cooling Water

3. CO2 System in Computer Rooms

4. CO2 System in Diesel Generator Building

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1)

1. Transient Combustible Controls and Hot Work

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1)

1. WB-23-034

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On February 27, 2025, the inspectors presented the fire protection team inspection results to William C. Reneau and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EPMTHJ102192

CO2 Fire Protection System Required Quantity

10/17/2009

NDQ0009992024

Fire Protection Equipment Surveillance Optimization

Evaluations

Rev. 0

Calculations

SDD-N3-39-4002

CO2 STORAGE, FIRE PROTECTION, AND PURGING

Rev. 13

CR 1523621

I was placed into a hazardous environment without my

knowledge

07/10/2019

CR 1799637

Broken Thermal Detector Base at DGB - 0-TS-13-122B

09/19/2022

Corrective Action

Documents

CR 1929672

Fleet initiative to Implement Fire Protection Equipment

Surveillance Optimization

09/02/2024

CR 1991914

25 FPTI - O-FOR-39-2 Frequency Extension

2/13/2025

Corrective Action

Documents

Resulting from

Inspection

CR 1995309

NRC FPTI Minor Violation on 0-FOR-39-2

2/27/2025

Drawings

WBN-0-47W240-

6-CC

Fire Protection Compartmentation - Fire Cells Plan EL

2 & 708

2/03/2015

Engineering

Changes

WBN-23-034

Disconnect feeder cables in fire zones which support

Diesel Auxiliary Boards 2A1-A and 2A2-A

Rev. 0

WBN Fire

Protection Report

PART II

FIRE PROTECTION PLAN

Rev. 64

Miscellaneous

WBN Fire

Protection Report

PART VI

FIRE HAZARD ANALYSIS

Rev. 64

0-AOI-30.1

Plant Fires

Rev. 12

0-AOI-30.2

Fire Safe Shutdown

Rev. 06

0-AOI-30.2 C.21

Fire Safe Shutdown Room 757-A3

Rev. 0

0-AOI-30.2 C.22

Fire Safe Shutdown Room 757-A4

Rev. 0

0-AOI-30.2 C.49

Fire Safe Shutdown Room 713-A6 or 713-A8

Rev. 03

0-AOI-30.2 C.5

Fire Safe Shutdown Room 772-A3

Rev. 0

0-AOI-30.2 C.53

Fire Safe Shutdown Room 692-A1A (West)

Rev. 00

0-AOI-30.2 C.6

Fire Safe Shutdown Room 772-A4

Rev. 01

71111.21N.05

Procedures

0-AOI-30.2 C.69

Fire Safe Shutdown Room Control Building

Rev. 13

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-FOR-39-2

Month CO2 Fire Protection Inspection and Test for

Powerhouse Areas

Rev. 31

0-FOR-39-2

Month CO2 Fire Protection Inspection and Test for

Powerhouse Areas

Rev. 33

0-FOR-39-3-A

Month CO2 Fire Protection Inspection and Test for

DGB - Train A Areas

Rev. 18

0-FOR-39-3-A

Month CO2 Fire Protection Inspection and Test for

DGB - Train A Areas

Rev. 19

0-FOR-39-3-B

Month CO2 Fire Protection Inspection and Test for

DGB - Train B Areas

Rev. 17

0-FOR-39-3-B

Month CO2 Fire Protection Inspection and Test for

DGB - Train B Areas

Rev. 18

0-FOR-39-4

Quarterly CO2 Flow Path Verifications

Rev. 7

0-FOR-39-4

Month CO2 Flow Path Verifications

Rev. 8

0-SOI-24.01

Raw Cooling Water System

Rev. 32

0-SOI-39.01

POWERHOUSE CO2

Rev. 3

0-SOI-39.02

DG CO2 System

Rev. 0

NPG-SPP-18.4.7

Control of Transient Combustibles

Rev. 20

NPG-SPP-18.4.8

Control of Ignition Sources (Hot Work)

Rev. 15

WO 121162077

0-FOR-39-3-B 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR DGB - TRAIN B AREAS

10/15/2021

WO 122249422

0-FOR-39-2 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR POWERHOUSE AREAS

09/29/2022

WO 122403588

0-FOR-39-3-B 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR DGB - TRAIN B AREAS

08/03/2023

WO 122403634

0-FOR-39-3-A 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR DGB - TRAIN A AREAS

07/06/2023

WO 123371928

0-FOR-39-3-A 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR DGB - TRAIN A AREAS

2/23/2022

WO 123419100

0-FOR-39-2 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR POWERHOUSE AREAS

07/30/2024

Work Orders

WO 123988522

0-FOR-39-3-B 18 MONTH CO2 FIRE PROTECTION

INSPECTION AND TEST FOR DGB - TRAIN B AREAS

09/12/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 124090655

0-FOR-39-4 QUARTERLY CO2 FLOW PATH

VERIFICATIONS

06/10/2024

WO 124090657

0-FOR-39-4 QUARTERLY CO2 FLOW PATH

VERIFICATIONS

09/08/2024