Public Meeting Summary Watts Bar Nuclear Plant Unit 2 Presentation (NRC Inspection Report 05000391/2013601
ML13107B505
Person / Time
Site: Watts Bar 
Issue date: 04/17/2013
From:
NRC/RGN-II/DCP/CPB3
To:
Tennessee Valley Authority
Michelle Adams
References
IR-13-601
Download: ML13107B505 (17)


Text

Watts Bar Nuclear Plant Unit 2 2012 Annual Assessment

April 16, 2013

Enclosure 2

Purpose of Meeting

  • Discuss the NRCs 2012 Annual Assessment of the Watts Bar 2 construction projec * Provide an overview of the construction inspection program for Watts Bar * Introduce resident staf * Discuss the status of Watts Bar 2 inspection * Provide status of Watts Bar 2 license review
  • Respond to questions and comments from the publi Background
  • 1985; TVA suspended construction of Watts Bar Unit * 1990-1995; TVA concentrated on construction of Unit 1 and addressed quality issues on Unit * July 2000; TVA informs NRC that Unit 2 is in a deferred status in accordance with Commission Policy Statement
  • August 3, 2007; TVA informed NRC of its plan to resume construction of Watts Bar Unit * July 7, 2008, the NRC issued an Order extending the Watts Bar Unit 2 construction permit (CP) completion date to March 31, 201 * TVA has submitted a request to extend the CP completion date to September 30, 2016 - Currently under staff revie Region II Construction Inspection Program Division of Construction Inspection Division Of Construction Projects Construction Inspection Branches Construction Projects Branch 3 Senior Project Inspector Project Inspectors Senior Resident Inspector Resident Inspectors Specialist Inspectors Construction Inspection Organization

Watts Bar Unit 2 Resident Inspectors Tomy Nazario - Senior Resident Inspector

Russ Lewis - Resident Inspector

Eric Patterson - Resident Inspector

Assessment Process Assessments (Quarterly, Mid Cycle,

End Of Cycle)

Inspection Program Results Annual Public Meeting Increased Inspections Cause Evaluation Special Inspections Significant Issues Cross-cutting aspects reviewed during Mid Cycle & End of Cycle

Scope of Inspections in 2012

  • Inspections Completed in 2012:

- Six-week inspection periods that cover resident activities and weekly regional initiatives

- Quality Assurance (QA) team inspection

- Hanger Update (HAUUP) Corrective Action Program (CAP) team inspection

- Problem Identification and Resolution team inspection

  • In addition to three resident inspectors, 32 regional inspectors conducted inspections in 201 Scope of Inspections in 2012
  • NRC expended 12,488 hours0.00565 days <br />0.136 hours <br />8.068783e-4 weeks <br />1.85684e-4 months <br /> of inspection and related activities for Watts Bar 2 in 2012; decrease from 16,350 hours0.00405 days <br />0.0972 hours <br />5.787037e-4 weeks <br />1.33175e-4 months <br /> in 201 * Key areas of 2012 inspections:

- Quality assurance program;

- Corrective action program;

- Engineering activities;

- Training and qualification of key personnel;

- Procurement (included Commercial Grade Dedication);

- Actual construction activities; and

- Refurbishment activitie Inspection Program Results

  • Overall assessment results:

- TVAs program and procedures were adequate to support ongoing construction activities

- TVA was constructing the facility at an acceptable level of quality

  • Eleven (11) severity level IV violations identified by NRC inspections. No escalated enforcement or civil penaltie No substantive cross-cutting issue Inspection Program Results
  • Adjusted Region II and Resident Inspector resources to match TVAs revised schedule for fuel load (June 2015)
  • Incorporated follow-up inspection efforts for Alternate Dispute Resolution (ADR) results (2010 falsification)
  • Except as noted, no changes to Inspection Program due to 2012 inspection results
  • Continue with planned inspections for Watts Bar 2

Construction Inspection Program

  • IMC 2517, Watts Bar Unit 2 Construction Inspection Program, supplements traditional inspection program

Construction Phase IMC 2512 Startup Testing IMC 2514 NRC Construction Inspection Program

Preop Testing

& Operational Prep IMC 2513

Inspection Program Elements Inspection Program Generic Communications Previously Completed inspections New or re-work CAPs/SPs Licensing issues Allegations Historical Open items (VIO,NCV,IFI..)

Status of Inspection Program

  • Over 500 construction inspection items in the Inspection Planning and Scheduling (IP&S)

database

  • Completed inspections for 270 IP&S items
  • Many other IP&S items inspected, but additional effort required to close the item
  • Many of the 500 IP&S items are historical that TVA previously addressed; Close-out inspection involves verifying proper resolution

Upcoming Inspection Activities

  • Continue to inspect activities specified in IMC 2512 and Refurbishment activities
  • Inspect Other Areas

- CAPs and SPs

- Generic Communication items

- Open Items

  • Inspect pre-operational testing of systems

Status of License Review Commission Meeting OL SSER Safety Review Environmental Review Inspection

Status of License Review (contd)

  • Safety Reviews - 96% complete

- Results documented in SSERs 21 through 25

- SSER 26 scheduled for May 2013

  • Fire Protection and closure of open items
  • Environmental Review

- Draft published for comment in November 2011

- Staff currently addressing comments

- Final scheduled to be published in May 2013

QUESTIONS?