MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 IR 05000335/20234202023-03-21021 March 2023 Security Baseline Inspection Report 05000335/2023420 and 05000389/2023420 IR 05000335/20220062023-03-0101 March 2023 Annual Assessment Letter for St. Lucie Units 1 & 2 (Report 05000335/2022006 and 05000389/2022006) IR 05000335/20220042023-02-10010 February 2023 Integrated Inspection Report 05000335/2022004 and 05000389/2022004 IR 05000335/20220112022-12-27027 December 2022 Triennial Fire Protection Inspection Report 05000335/2022011 and 05000389/2022011 IR 05000335/20220032022-11-0404 November 2022 Integrated Inspection Report 05000335/2022003 and 05000389/2022003 ML22208A1762022-08-0404 August 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report IR 05000335/20220022022-08-0101 August 2022 Integrated Inspection Report 05000335/2022002 and 05000389/2022002 ML22210A0782022-07-22022 July 2022 Stl 2022003 Document Request IR 05000335/20220122022-06-29029 June 2022 Biennial Problem Identification and Resolution Inspection Report 05000335 2022012 and 05000389 2022012 IR 05000335/20224012022-05-20020 May 2022 Security Baseline Inspection Report 05000335/2022401 and 05000389/2022401 IR 05000335/20220012022-05-12012 May 2022 Integrated Inspection Report 05000335/2022001 and 05000389/2022001 IR 05000335/20220102022-04-27027 April 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000335/2022010 and 05000389/2022010 IR 05000335/20214022022-04-0404 April 2022 Material Control and Accounting Program Inspection Report 05000335/2021402 and 05000389/2021402 - Public IR 05000335/20210062022-03-0202 March 2022 Annual Assessment Letter for St. Lucie, Units 1 & 2 (Report No. 05000335/2021006 and 05000389/2021006) IR 05000335/20210042022-02-14014 February 2022 Integrated Inspection Report 05000335/2021004 and 05000389/2021004 IR 05000335/20214032021-12-14014 December 2021 Security Baseline Inspection Report 05000335/2021403 and 05000389/2021403 IR 05000335/20210102021-12-0707 December 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000335/2021010 and 05000389/2021010 IR 05000335/20210032021-11-0303 November 2021 Integrated Inspection Report 05000335/2021003 and 05000389/2021003 IR 05000335/20210052021-08-25025 August 2021 Updated Inspection Plan for St. Lucie Plant Units 1 & 2 (Report 05000335/2021005 and 05000389/2021005) IR 05000335/20210022021-08-10010 August 2021 Integrated Inspection Report 05000335/2021002 and 05000389/2021002 IR 05000335/20214012021-06-23023 June 2021 Security Baseline Inspection Report 05000335/2021401 and 05000389/2021401 IR 05000335/20213012021-06-21021 June 2021 NRC Examination Report 05000335/2021301 and 05000389/2021301 IR 05000335/20210012021-05-12012 May 2021 Integrated Inspection Report 05000335/2021001 and 05000389/2021001 IR 05000335/20200062021-03-0303 March 2021 Annual Assessment Letter for St. Lucie Nuclear Plant, Unit 1 and Unit 2 Report 05000335/2020006 and 05000389/2020006 IR 05000335/20203012021-02-16016 February 2021 NRC Operator License Examination Report 05000335/2020301 and 05000389/2020301 IR 05000335/20200042021-02-0808 February 2021 Integrated Inspection Report 05000335/2020004 and 05000389/2020004 and Independent Spent Fuel Storage Installation (ISFSI) Inspection 07200061/2020002 IR 05000335/20204012021-01-0505 January 2021 Security Baseline Inspection Report 05000335/2020401 and 05000389/2020401 IR 05000335/20200112020-12-16016 December 2020 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000335/2020011 and 05000389/2020011 IR 05000335/20200032020-10-30030 October 2020 Integrated Inspection Report 05000335/2020003 and 05000389/2020003 ML20296A3732020-10-22022 October 2020 Security Inspection Report IR 05000335/20200052020-08-24024 August 2020 Updated Inspection Plan for St. Lucie Plant, Unit 1 and 2 (Report 05000335/2020005 and 05000389/2020005) IR 05000335/20200022020-07-29029 July 2020 St.Lucie Units 1 & 2 Integrated Inspection Report 05000335/2020002, 05000389/2020002, and Independent Spent Fuel Storage Installation Inspection (Lsfsi) 07200061/2020001 IR 05000335/20200102020-07-16016 July 2020 Biennial Problem Identification and Resolution Inspection Report 05000335/2020010 and 05000389/2020010 IR 05000335/20200012020-05-0505 May 2020 Integrated Inspection Report 05000335/2020001 and 05000389/2020001 and Exercise of Enforcement Discretion IR 05000335/20190062020-03-0303 March 2020 Annual Assessment Letter for St. Lucie Nuclear Plant, Units 1 and 2 NRC Report 05000335/2019006 and 05000389/2019006 IR 05000335/20190032019-11-14014 November 2019 Integrated Inspection Report 05000335/2019003 and 05000389/2019003 IR 05000335/20193022019-10-18018 October 2019 NRC Examination Report 05000335/2019302 and 05000389/2019302 IR 05000335/20194112019-10-0707 October 2019 NRC Security Inspection Report 05000335/2019411 and 05000389/2019411 IR 05000335/20194012019-09-0909 September 2019 Cyber Security Inspection Report 05000335/2019401 and 05000389/2019401 (Public) IR 05000335/20190052019-08-27027 August 2019 Updated Inspection Plan for St. Lucie Plant, Unit 1 and Unit 2 - (Report 05000335/2019005 and 05000389/2019005) IR 05000335/20190112019-08-20020 August 2019 Triennial Fire Protection Inspection Report 05000335/2019011 and 05000389/2019011 2024-01-26
[Table view] Category:Letter
MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23332A1772023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 ML23270B8882023-10-23023 October 2023 Regulatory Audit Summary Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structure, Systems, and Components for Nuclear Power Reactors EPID L-2022-LLA-0182 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A1102023-10-0202 October 2023 License Amendment Request Revision 2 for the Technical Specifications Conversion to NUREG-1432, Revision 5 L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 ML23219A0042023-09-0101 September 2023 Transmittal Letter - Safety Evaluation Related to the SLRA of St. Lucie Plant, Units 1and 2, Revision 1 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23212B2652023-07-27027 July 2023 Operator Licensing Written Examination Approval 05000335/2023301 and 05000389/2023301 L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches ML23200A1232023-07-21021 July 2023 Transmittal Letter for the St. Lucie SLRA Review L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) ML23184A0352023-06-30030 June 2023 Notification of St. Lucie Units 1 & 2 Focused Engineering Inspection (FEI) 05000335/2023010 and 05000389/2023010 and Initial Information Request L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report 2024-01-08
[Table view] |
Text
September 8, 1976 L-76-328 Norman C. Moseley, Director Office of Inspection and Enforcement, Region II U. S. Nuclear Regulatory Commission 230 Peachtree Street, N. W., Suite 818 Atlanta, Georgia 30303
Dear Mr. Moseley:
Re: IE:II:DHD 50-389/76-1 Florida Power 6 Light Company has examined the above-referenced inspection report and has determined that contains mo proprietary information.
it
~
Very truly yours,
Robert E. Uhrig Vice President REU/MV/hlc cc: Jack R. Newman, Esq.
PCOPLC... SEIRVINo VFOI'Lfi
~o q IIE00 UNITED STATES
4p 4V NUCLEAR REGULATORY COMMISSION n
REGION I I ge 230 PEACHTREE STREET, N. W. SUITE $ 18 ATLANTA,GEORGIA 30303 4+*+4 AUG 2 6 1976 In Reply Refer To:
IE II:DHD 50-389/76-1 Florida Power and Light Company ATTN: Dr. R. E. Uhrig, Vice President of Nuclear and General Engineering P. 0. Box 013100 9250 West Flagler Street Miami, Florida 33101 Gentlemen:
This refers to the inspetion conducted by Mr. D. H. Danielson of this office on July 28-30, 1976, of activities associated with your applica-tion for an NRC Construction Permit for St. Lucie Plant, Unit 2 and to the discussion of our findings held with Mr. B. J. Escue at the con-clusion of the inspection.
Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examination of procedures and representative records, interviews with personnel, and observations by the inspector.
Within the scope of this inspection we identified no significant devia-tions from the requirements of 10 CFR 50, Appendix B, "Quality Assurance Criteria for Nuclear Power Plants," of the NRC regulations.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the .
enclosed inspection report will be placed in the NRC's Public Document Room. I'f this report contains any information that you believe to be proprietary, it is necessary that you submit a written application to this office requesting that such information be withheld from public disclosure. If no proprietary information is identified, a written statement to that effect. should be submitted. If an application is submitted, it must fully identify the bases for which information is claimed to be proprietary. The application should be prepared so that information sought to be withheld is incorporated in a separate paper and referenced in the application since the application will be placed in the Public Document Room. Your application, or written statement, should be submitted to us within 20 days. If we are not contacted as specified, the enclosed report and this letter may then be placed in the Public Document Room.
I Florida Power and Light Company Should you have any questions concerning this letter, we wi11'be glad to discuss them with you.
Very truly yours, Reactor Construction and Engineering Support Branch Enclosure:
XE Inspection Report No.
50-S89/76-1
~
'ItII Ci REC0, Np UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I I i
230 PEACHTREE STREETt N W SUITE 818 ATLANTA,GEORGIA 30303
+**++
IE Inspection Report No. 50-389/76-1 Licensee: Florida Power and Light Company P. 0. Box 013100 Miami, Florida 33101 Facility Name: St. Lucie Unit 2 Docket No.: 50-389 License No.: Pending Category: Al tt Location.'utchinson Island, Florida Type of License: 800 Mwe (CE)
Type of Inspection: Routine, Unannounced, Preconstruction t
Dates of Inspection: July 28-30, 1976 Dates of Previous Inspection'. December 16-18, 1975 Principal Inspector: D. H. Danielson, Reactor Inspector Projects Section Reactor Construction and Engineering Support Branch Accompanying Inspector: R. M. Wright, Reactor Inspector Engineering Support Section No. 1 Reactor Construction and Engineering Support Branch Other Accompanying Personnel: C. E. Murphy, Chief Reactor Construction and Engineering Support Branch Principal Inspector:
D. H. Danielson, Reactor Inspector Date Projects Section Reactor Construction and Engineering'upport Branch
IE Rpt. No. 50-389/76-1 Reviewed by:
C. Brya~ Chief ate rojects Section Reactor Construction and Engineering Support Branch
IE Rpt. No. 50-389/76-1 SUMMARY OF FINDINGS I. Deviations None II. Licensee Action on Previousl Identified Deviations Hone III. New Unresolved Items None IV. Status of Previousl Re orted Unresolved Items None V. Desi n Chan es None VI. Unusual Occurrences None VII. Other Si nificant Findin s None VIII. Mana ement Interview On July 30, 1976, the inspectors met with Mr. B. J. Escue, Prospect Construction Superintendent, and members of the plant staff to review the scope and findings of the inspection. It was noted that within the scope of the inspection we identified no signi-ficant deviations from the requirements of 10 CFR 50, Appendix B.
IE Rpt. No. 30-389/76-1" DETAILS I Prepared by:
I'~
D. H. Danielson, Reacto Inspector Date Pro3ects Section Reactor Construction and Engineering Support Branch Dates of Inspection: July 28-30, 1976 Reviewed by:
C, Brya t', Chi 'f Date rojects ection Reactor Construction and Engineering Support Branch 1. Individuals Contacted Florida Power and Li ht Com an (FPSL B. J. Escue Project Construction Superintendent N. T. Weems Assistant .QA Manager, Construction A. M. Anderson Senior QA Engineer, Electrical.
D. R. Stone Project QC Supervisor 2. Sco e of Ins ection This inspection was performed to review the licensee's site audit activities and onsite contractor organizations'A/QC programs for site preparation activities. authorized under an LWA-2.
3. Site Audits The PSAR, Chapter 17, paragraph 17.1.18.5, specifies the FP6L audit commitments. The detailed instructions for conducting and scheduling audits are provided in Quality Procedure Nos. QR 18.1 and QP 18.2, respectively.
To verify compliance with the above commitments, the inspector examined reports and related records for five audits performed since February 1976. This examination covered audit planning, scope and purpose, documentation of results, management review, and followup of corrective action. FPGL reports of audits that were reviewed are as follows:
a. EBASCO Document Control, QAC-EBASCO-76-16
'b. FPSL Document Control System, QAC-FPL-QC-76-17
ZE Rpt. Ho. 50-389/76-3. I-2 c. FP&L QC Construction Material Control, QAC-FPL-CONSTR-QC-76-2 d. EBASCO Indoctrination and Training, QAC-EBASCO-76-3 e. FP&L Construction QA Indoctrination and Training, QAC-FPL-CONSTR-76-6 Within the areas examined, there were no deviations disclosed.
4. Review of Contractor A Manual The PSAR, Chapter 17, paragraph 17.1.4.3, specifies the FP&L suppliers'A program evaluation commitments. The detailed instructions for evaluation of a suppliers QA program are provided in Quality Proce-dure No. Qp 4.3.*
W ~t Raymond International, Inc. is installing sheet piling for the reactor containment building cofferdam and the intake structure cofferdam. The inspector reviewed the Raymond International QA manual to assure adequate plans and procedures had been established for their scope of work. This review included site organisation, management review, control of material and processes, control of conditions adverse to quality, document control, test control and control of test equipment, control of quality records and audits.
In addition, documented evidence of FP&L evaluation and acceptance of the Raymond International QA program and procedures was reviewed by the inspector. Within the areas examined, there were no devia-tions disclosed.
DETAILS II Prepared by: Fi9 7G R. W. Wright, React r Inspecto'r Date Engineering .Support Section No. 1 Reactor Construction and Engineering Support Branch Dates of Inspection: July 28-30, 3.976 Reviewed by:
T. E. Conlozi,:Chief- Date Engineering Support Section No. 1 Reactor Construction and Engineering Support Branch l. ersons Contacted a. Florida Power and Li ht Com an (FPSL)
N. T. Weems Assistant QA Manager, Construction A. M. Anderson QA Engineer, Electrical L. T. Stone QA Engineer, Civil B. J. Escue Project Construction Superintendent D. R. Stone Project QC Supervisor R. G. Reesby - Area QC Supervisor (Civil)
b. Contractor Or anizations (1) Ebasco Services Inc. (Ebasco) ~
J. C. Murphy Sr. Resident Engineer (2) Moretrench American Cor oration MAC)
C. Williams 2. ~8co c This inspection was conducted to observe and evaluate the work in progress and to ascertain whether activities relative to site preparation are being accomplished in accordance with NRC requirements and SAR commitments, and to determine if procedures and recordkeeping requirements have been developed and are being properly implemented in the subject inspection areas.
Procedure Review The following Ebasco specifications, FP&L quality control procedures, construction site procedure, and contractor operating procedure
were examined for conformance to SAR commitments, applicable codes and standards.
Document Number Title FLO-2998.472 (R5) Dewatering FL0-2998.471 (R2) Excavation and Backfill QA lo.8 (Rl) Checking/Record Review of Dewatering Systems and Components QI 10.10 (Rl) Inspection of Excavations and Fill Compaction CSP 25 Excavation and Backfill COP-2-1 Sheet Pile and Excavation No items of procedural noncompliance were identified.
4. Observation of Work Activities a. Pro ect Status Prior to Commencement of LWA-2 Work The soils above elevation minus 60 feet were excavated and recompacted to a relative density of 85 percent AASHO over the entire plant area to provide satisfactory bearing, settlement and resistence to liquefaction characteristics. The final site grade is at elevation plus 18 feet and the ground water level is esthnated to be the normal high water level in the Indian River at elevation plus 2 ft.
b. Activities Observed Raymond International has completed the driving of sheet piling and the installation 'of the top wale for the reactor containment building cofferdam. The inspector observed the driving of sheet piling for the intake structure Cofferdam.
Moretrench has reactivated wells formerly used for Unit 1 to draw down the water level within the construction boundaries of Unit No. 2 from elevation plus 2 to minus 15. Excavations below elevation minus 15 will require individual systems set up for each particular excavation.
The IE inspector observed the contractor installing such
a system for the reactor containment building base mat excavation. The well casing utilized was 8 inch diameter PVC pipe capable of withstanding 160 psi and meeting code requirements ASTM 1785 and ASTM 2665. This internal well system should be capable of lowering the water table within the reactor containment building area to elevation minus 30.
(3) Blastin Excavation Fill Placement Since no structure has its foundation below elevation minus 60 no blasting for ease of excavation is anti-cipated. The contractor has removed the fill to ap-proximately elevation plus 5 in order to commence with the driving of the intake structure sheet piles. Ho other excavation nor backfill opeations have begun.
(4) C Ins ection and Laborator Testin Facilities The IE inspector observed the QC coverage being implemented for the above earthwork activities and conducted conversations wit% several QC inspectors during the course of their surveillances. These discussions indicated the inspectors were knowledgeable with their respective quality control procedures and they were found to be satisfactorily implementing them. An inspection was made of the FPGL soils laboratory facilities, noting particularly their testing capabilities, checking for up-to-date calibration of equipment, and the experience of its personnel.
No items of noncompliance were identified in any of the above areas of inspection.
5. Record Review The following quality records were selected for review to ascertain that the work was being accomplished and documented in accordance with applicable codes, commitments and procedural requirements:
a. Reactor Containment Building Cofferdam Report Package containing QC surveillance inspection reports for pile driving and associated nonconformance reports for the period 6/3/76 to 7/27/76 b. Main Yard Dewatering System Testing Records conducted 7/27/76
t IE Rpt. No. 50-389/76-1
~ ~ II-4 c. Certifications and personnel qualification records for various soil inspectors d. Inspector training records e. Sheet Piling Welding (1) Welding procedure qualifications (2) Welder performance qualifications (3) Welding materials control records No items of noncompliance were identified in any of the above areas of record inspection.
6. Nondirected Ins ection Activities The IE inspector made a cursory inspection of the concrete batching facilities. The inspector also observed the sampling and testing of a non-safety related pour (warehouse foundation) for slump, air content, temperature, yield, and the molding of concrete cylinders
- ~'Nor compressive testing. All testing is similar to safety related.
pours.
No items of noncompliance were identified.