IR 05000382/2020004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000382/2020004
ML21034A420
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/03/2021
From: John Dixon
NRC/RGN-IV/DRP
To: Ferrick J
Entergy Operations
References
IR 2020004
Download: ML21034A420 (22)


Text

February 3, 2021

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - INTEGRATED INSPECTION REPORT 05000382/2020004

Dear Mr. Ferrick:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station, Unit 3. On January 14, 2021, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Reactor Projects

Docket No. 05000382 License No. NPF-38

Enclosure:

As stated

Inspection Report

Docket Number:

05000382

License Number:

NPF-38

Report Number:

05000382/2020004

Enterprise Identifier: I-2020-004-0002

Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station, Unit 3

Location:

Killona, LA 70057

Inspection Dates:

October 1, 2020 to December 31, 2020

Inspectors:

R. Alexander, Senior Emergency Preparedness Inspector

D. Antonangeli, Health Physicist

D. Childs, Resident Inspector

J. Drake, Senior Reactor Inspector

L. Flores, Reactor Inspector

N. Greene, Senior Health Physicist

R. Kopriva, Senior Reactor Inspector

A. Patz, Senior Resident Inspector

F. Ramirez Munoz, Senior Reactor Inspector

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Waterford, Unit 3, began the inspection period in a refueling outage. On October 31, 2020, Unit 3 was restarted and inadvertently tripped on November 2, 2020, due to an issue with the control element drive mechanism control system. Unit 3 was restarted on November 4, 2020, and achieved full power on November 15, 2020. On November 27, 2020, the licensee performed an emergent downpower to approximately 90 percent power to address governor valve oscillations and returned to full power on December 1, 2020. On December 11, 2020, the licensee initiated a rapid downpower into hot standby due to a steam leak near the turbine governor valves. On December 14, 2020, Unit 3 was restarted and remained at full power until the end of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Emergency diesel generator A with emergency diesel generator B out of service for maintenance, on October 19, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the shutdown cooling system, on October 20, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Area RCB-001, reactor containment building general area, on October 15, 2020
(2) Fire Area RAB 13-001, battery rooms, on October 30, 2020
(3) Fire Area ROOF E-001, main steam isolation valve B, on November 3, 2020
(4) Fire Area ROOF W-001, main steam isolation valve A, on November 3, 2020

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from October 8, to November 20, 2020:

03.01.a - Nondestructive Examination and Welding Activities.

  • Eddy Current Examination, RCP 1A Motor Flywheel (Entire Flywheel), Report Number: ISI-ET-20-001
  • Dye Penetrant Examination, RAB-Safeguards Pump Room B Containment Spray Anchor Attachment Weld, Report Number: ISI-PT-20-001
  • Magnetic Particle Examination, Wet MSIV Area Main Steam Welded Support to 40-inch Pipe, Report Number: ISI-MT-20-004
  • Visual Examination VT-3, RCB+46 West D-Ring Safety Injection Bolted Connection SG MSG001, Report Number: ISI-VT-20-048
  • Visual Examination VT-3, Cooling Tower Area A Component Cooling Water Rigid Restraint, Report Number: ISI-VT-20-113
  • Visual Examination VT-1, Cooling Tower Area A Component Cooling Water Rigid Restraint, Report Number: ISI-VT-30-114
  • Visual Examination VT-3, West MSIC Area Main Steam Rigid Restraint, Report Number: ISI-VT-20-096
  • Ultrasonic Examination, RCB-Loop 2 D-Ring S/G #2 Main Steam Tube sheet to Lower Shell Weld, Report Number: ISI-UT-20-005
  • Ultrasonic Examination, RAB-East Wing Area Safety Injection Elbow to 8-inch Pipe Weld, Report Number: ISI-UT-20-004
  • Ultrasonic Examination, Loop 1A Safety Injection 12-inch Pipe to 45 Degree Elbow Weld, Report Number: ISI-UT-20-006
  • Ultrasonic Examination, Loop 1A Safety Injection 45 Degree Elbow to 12-inch Pipe Weld, Report Number: ISI-UT-20-007
  • Ultrasonic Examination, Loop 1A Safety Injection 12-inch Pipe to 45 Degree Elbow Weld, Report Number: ISI-UT-20-008
  • Ultrasonic Examination, RCP 1A Motor Flywheel (Entire Flywheel), Report Number: ISI-UT-20-013
  • Welding: Work Order 520048-005, Weld Map No. 520048-05-01, Reference Drawing No. E3029LW3RC25, Flange to Pipe Weld SW 12 (Fillet Weld)
  • Welding: Work Order 520048-97, Weld Map No. 520048-07-01, Reference Drawing No. E3029LW3RC25 -- A193-134, Support - Field Welds FW1 and FW2 03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.
  • Waterford 3 started Refueling Outage RF23 in October 2020. Waterford 3 installed a new reactor head with A690 welds during Refueling Outage RF 18, spring of 2013. 10CFR50.55a requires implementation of Code Case N-729-6. Inspection of replacement head is: Bare Metal Visual for Item No. B4.30 every 3rd Refuel or 5 years. The next scheduled reactor head inspection utilizing Code Case N-729-6 is during Refueling Outage RF24.

Between Refueling outage RF20 and RF21, the licensee experienced a component cooling water leak on the reactor head cooling water system, which ended up depositing molybdates on the reactor head. The reactor head was cleaned, but some residual material remained. During Refueling Outage RF22 more cleaning of the reactor head was performed. In August of 2020, the licensee experienced a leak in two incore instrumentation tubes, which sprayed boric acid over a large area, above the reactor head, in the insulation package. The licensee cleaned up most of the boric acid residue but did not perform any cleaning on the boric acid that had run across the insulation package and down the control rod drive mechanism housings and onto the reactor head. During the current Refueling Outage RF23, the licensee identified all the areas on the reactor head that had boric acid residue. The licensee took samples and ran chemical analyses on them to confirm that the radionuclides found in the samples were from the August time frame and not recent leakage of boric acid. The licensee also used the inspection crawler (utilized during required Code Case N-729-6 visual examination) to inspect all the reactor head penetrations.

Upon completion of the reactor head examination, and when the licensee confirmed that there were no active leaks from any reactor head penetration, the reactor head was cleaned using dry ice particles.

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities

  • No Steam Generator inspections were required or scheduled during Refueling Outage RF23.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during drain down activities to lower reactor coolant system inventory for reinstallation of the reactor vessel head on October 21, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator scenario during a licensed operator examination on November 16, 2020.

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Essential chilled water system, on December 18, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Emergent orange shutdown risk due to the failure of startup channel 2, on October 6, 2020
(2) Emergent failure of high-pressure safety injection pump B during surveillance testing, on October 14, 2020
(3) Emergent work on feedwater heater 2C level control valve following its failure and impact on reactor power, on November 12, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability determination of reactor coolant loop 2 shutdown cooling upstream suction isolation valve following identification of a magnesium rotor in the motor, on November 16, 2020
(2) Operability determination of high-pressure safety injection train A due to pump low recirculation flow, on November 17, 2020
(3) Operability determination of the control room emergency filtration system following failure of two dampers for the B unit, on December 15, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Emergency diesel generator B following planned maintenance, on October 19, 2020
(2) Feedwater isolation valve A following planned maintenance, on October 22, 2020
(3) Atmospheric dump valve B following planned maintenance, on October 22, 2020
(4) Reactor coolant loop 1 shutdown cooling upstream suction isolation valve following failure to stroke, on November 4, 2020
(5) Chemical volume and control pump AB following planned maintenance, on November 25, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage 23 activities from September 25, to November 1, 2020, which completes the partial sample documented in Waterford Inspection Report 05000382/2020003, Section 71111.20.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Containment sump trisodium phosphate storage basket inspection, on November 17, 2020
(2) Turbine trip testing, on December 14, 2020
(3) Control room emergency filtration unit B testing, on December 16, 2020

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Containment atmospheric release exhaust header A inlet and upstream isolation valves, on October 19, 2020

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the maintenance and testing of the alert and notification system between September 1, 2018 and November 30, 2020.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness Organization between September 1, 2018 and November 30, 2020.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the 10 CFR 50.54(q) emergency plan change process and practices between September 1, 2018 and November 30, 2020. This involved review of licensee screening and evaluation documentation. The reviews of the change process documentation do not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program between September 1, 2018 and November 30, 2020.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Emergency preparedness training evolution in the control room simulator, on November 18,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (IP Section 02.12)===

(1) October 1, 2019, through September 30, 2020

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) October 1, 2019, through September 30, 2020

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) October 1, 2019, through September 30, 2020

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) October 1, 2019, through September 30, 2020

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) October 1, 2019, through September 30, 2020

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) January 1, 2019, through September 30, 2020

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) January 1, 2019, through September 30, 2020

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in the fire protection program that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) High pressure safety injection pump B breaker issues, on October 27, 2020

71153 - Follow-up of Events and Notices of Enforcement Discretion Personnel Performance (IP Section 03.03)

(1) The inspectors evaluated the licensees response to an automatic reactor trip due to control element drive mechanism control system timer failure on November 2,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On December 11, 2020, the inspectors presented the emergency preparedness program inspection results to Mr. J. Ferrick, Site Vice President, and other members of the licensee staff.
  • On January 7, 2021, the inspectors presented the inservice inspection results to Mr. M. Lewis, General Manager of Plant Operations, and other members of the licensee staff.
  • On January 14, 2021, the inspectors presented the integrated inspection results to Mr. J. Ferrick, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

71111.04

Procedures

OP-009-002

Emergency Diesel Generator

354

OP-009-005

Shutdown Cooling

044

71111.05

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

20-06250

Miscellaneous

RAB 13-001

Waterford S.E.S Prefire Strategy Battery Room AB

007

RCB-001

Waterford S.E.S Prefire Strategy RCB General Area

011

ROOF E-001

Waterford S.E.S Prefire Strategy Elevation +46 Roof E

MSIV B

005

ROOF W-001

Waterford S.E.S Prefire Strategy Elevation +46 ROOF W

MSIV A

2

71111.08P Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2019-0617, 2019-0762, 2020-1078, 2019-4461,

2019-4223, 2019-1758, 2019-5652, 2019-8604,

20-0180, 2020-0375, 2019-3685, 2020-2987,

2019-0931, 2019-6456, 2020-3718, 2019-0416,

20-3327, 2019-00719, 2019-03679, 2019-03685,

2019-04683, 2019-04694, 2020-04843, 2020-04845,

CR-HQN-2019, CR-HQN-2019-1125,

CR-HQN-2019-2482, CR-HQN-2019-0957,

CR-HQN-2019-2716, CR-HQN-2019-1060

Drawings

5817-10936

ICI Adapter Assembly

5817-11178

Type "B" HJTC Cable Assembly (RDP to RAS)

5817-11772

ICI & HJTC Quickloc Assembly, Sheet 1

E-9270-164-005

Nozzle Requirements Closure Head

LDRAC No.

5817-13747,

Sheet 1

Closure Head Assembly

Engineering

Changes

EC# 0000081552

Disposition of Active Leak Found on Reactor

Engineering

Evaluations

Evaluation #: 19-

WF3-0025

Boric Acid Walkdown, Reactor Head, ICI #5

08/02/2019

Evaluation #: 19-

WF3-0026

Boric Acid Walkdown, Reactor Head, ICI #8

08/03/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

Miscellaneous

17-WF3-0128

Boric Acid Leakage Identification. Component ID#:

PSLMVAAA204, Location: RAB

2/28/2017

EPID L-2018-

LLR-0125

Waterford Steam Electric Station, Unit 3-Authorization of

Proposed Alternative to ASME Code Case N-770-2 (EPID

L-2018-LLR-0125)

06/12/2019

EPID L-2019-

LLR-0003

Waterford Steam Electric Station, Unit 3 - Authorization of

Proposed Alternative to ASME Code,Section XI, IWA-

4000, "Repair/Replacement Activities."

08/27/2019

PQR-024

Procedure Qualification Record, Manual Gas tungsten &

Shielded Metal Arc Welding (GTAW & SMAW), Base

Metal: P-No.1, SA-106 Gr. B

PQR-107

Procedure Qualification Record, Manual Gas Tungsten &

Shielded Metal Arc Welding (GTAW & SMAW), Base

Metal: P-No.8, SA-312 Type 304

PQR-170

Manual Gas Tungsten & Shielded Metal Arc Welding

(GTAW & SMAW), Base Metal: P-No.8, SA-240 Type 304

PQR-330

Manual Gas Tungsten & Shielded Metal Arc Welding

(GTAW & SMAW), Base Metal: P-No.1, Group 1 to 2,

SA-516 Gr. 60 to SA-516 Gr. 60 to SA-516 Gr. 70

PQR-331

Manual Gas Tungsten & Shielded Metal Arc Welding

(GTAW & SMAW), Base Metal: P-N0.1, Group 1 to 2,

SA-516 Gr. 60 to SA-516 Gr. 70

W3F1-2008-0060

Request for Alternative W3-iSI-006, Proposed Alternative

to Extend the Second 10-Year Inservice, Inspection

Interval for Reactor Vessel Internal Weld Examinations,

Waterford Steam Electric Station, Unit 3, Docket No.

50-382, License No. NPF-38

09/18/2008

W3F1-2009-0006

RAI Response to Request for Alternative W3-ISI-006 To

Extend the Second, 10 Year AMSE Code ISI and License

Amendment Request, NPF-38-280 To Support Request

for Alternative W3-ISI-006, Waterford Steam Electric

Station, Unit 3 (Waterford 3), Docket No. 50-382, License

No. NPF-38

03/19/2009

W3F1-2013-0044

Waterford 3 Request for Alternative W3-ISI-023, ASME

09/26/2013

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

Code Case N-770-1, Successive Examinations, Waterford

Steam Electric Station, Unit 3, Docket No. 50-382,

License No. NPF-38

W3F1-2013-0044

Waterford 3 Request for Alternative W3-ISI-023, ASME

Code Case N-770-1, Successive Examinations, Waterford

Steam Electric Station, Unit 3, Docket No. 50-382

License No. NPF-38

09/26/2013

W3F1-2018-0008

Request for NRC Alternative to ASME IWA-5211

Regarding Charging Pipe, Visual Inspection, Relief

Request W3-ISI-030, Waterford Steam Electric Station,

Unit 3 (Waterford 3)

Docket No. 50-382, License No. NPF-38

2/20/2018

W3F1-2018-0067

Response to NRC Request for Additional Information

Regarding Request for, Alternative to ASME Code Case

N-770-2, Successive Examinations, Relief, Request

W3-ISI-031

11/19/2018

W3F1-2019-0009

Proposed Inservice Inspection Program Alternative

WF3-RR-19-1 for Application of Dissimilar Metal Weld Full

Structural Weld Overlay - Reactor Coolant System Cold

Leg Drain Nozzles

01/28/2019

W3F1-2019-0017

Closure of Commitment Associated with Inservice

Inspection Program, Alternative WF3-RR-19-1 for

Application of Dissimilar Metal Weld Full, Structural Weld

Overlay - Reactor Coolant System Cold Leg Drain

Nozzles

2/14/2019

W3F1-2019-0049

Commitment Change Notification and Closure of

Commitment Associated with Inservice Inspection

Program Alternative WF3-RR-19-1 for Application of

Dissimilar Metal Weld Full Structural Weld Overlay -

Reactor Coolant System Cold Leg Drain Nozzles

07/16/2019

W3F1-2020-0055

CFR Part 21 Report: Defect of Masoneilan 8012N-3C

Electropneumatic Positioner. Waterford Steam Electric

Station, Unit 3 (Waterford 3), NRC Docket No. 50-382

Renewed Facility Operating License No. NPF-38

09/01/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

WPS-CS-1/1-C

Shielded Metal Arc Welding (SMAW) of P-No,1 carbon

steels, in all positions, for all joint types, fillets and repairs

using A-No.1 carbon steel filler metal, with or without

Postweld Heat Treatment (PWHT).

WPS-SS-8/8-B

Manual Gas Tungsten Arc Welding (GTAW) of P-No.8

stainless steels, in all positions, for all joint types, fillets

and repairs using A-N0.8 stainless steel filler metal,

without Postweld Heat Treatment (PWHT).

NDE Reports

BOP-VE-19-002

RCS Loop 1A Lower Cold Leg, Nozzle to Safe End

Circumferential Weld, Component ID: 07-009-WOL

2/06/2019

BOP-VT-19-005

Reactor Cavity, RVCH CEDM Nozzles.

2/01/2019

ISI-VE-19-009

RCS Loop 1A Lower Cold Leg, Nozzle to Safe-End

Circumferential Weld. Component ID: 07-009

01/16/2019

ISI-VE-19-013

RCS Loop 2A Lower Cold Leg, Nozzle to Safe-End

Circumferential Weld. Component ID: 00-007

01/24/2019

ISI-VT-19-038

Cooling Tower Area B, Rigid Restraint. Component ID:

CCRR-0393

01/14/2019

ISI-VT-19-063

Loop 2A, Rigid Restraint, Component ID: RCRR-0094

01/19/2019

ISI-VT-19-064

Loop 2A, Rigid Restraint. Component ID: RCRR-0182

01/19/2019

ISI-VT-20-008

RAB - 4 Wing Area, Sampling - RAB, Component ID:

13.3.3

2/12/2020

ISI-VT-20-029

RAV-MSIV Area, N2 Accumulator VI Subsystem,

Component ID: 13.3.26

05/26/2020

Procedures

CEP-BAC-001

Boric Acid Corrosion Control (BACC) Program Plan,

Entergy Nuclear Engineering Programs.

CEP-ISI-100

ASME Section XI, Division 1, Fleet Administrative

Controls for Inservice Inspection Program, Entergy

Nuclear Engineering Programs

CEP-NDE-0400

Ultrasonic Examination, Entergy Nuclear Engineering

Programs

CEP-NDE-0404

Manual Ultrasonic Examination of Ferritic Piping Welds

(ASME XI), Entergy Nuclear Engineering Programs

CEP-NDE-0423

Manual Ultrasonic Examination of Austenitic Piping Welds

(ASME XI), Entergy Nuclear Engineering Programs

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

CEP-NDE-0493

Manual Ultrasonic Examination of Reactor Coolant Pump

Flywheel, Entergy Nuclear Engineering Programs

CEP-NDE-0497

Manual Ultrasonic Examination of Weids in Vessels (Non-

App. VIII), Entergy Nuclear Engineering Programs

CEP-NDE-0497

Manual Ultrasonic Examination of Welds in Vessels (Non-

App. VIII), Entergy Nuclear Engineering Programs

CEP-NDE-0730

Non-Section XI Magnetic Particle Examination (MT),

Entergy Nuclear Engineering Programs

CEP-NDE-0731

Magnetic Particle Examination (MT) for ASME Section XI,

Entergy Nuclear Engineering Programs

CEP-NDE-0901

VT-1 Examination, Entergy Nuclear Engineering

Programs

CEP-NDE-0903

VT-3 Examination, Entergy Nuclear Engineering

Programs

EIP-PT-001

ASME Section XI Pressure Test (PT) Program, Entergy

Nuclear Engineering Programs.

310

EN-DC-319

Boric Acid Corrosion Control Program (BACCP)

EN-DC-328

Entergy Nuclear Welding Program

RF-001-013

Incore Instrument Flanges

315

SEP-BAC-WF3-

001

Waterford 3 Boric Acid Corrosion Control Program

(BACCP) Program Section SEP-BAC-WF3-001

SEP-CISI-104

Program Section for ASME Section XI, Division 1, WF3

Containment Inservice Inspection Program, Entergy

Nuclear Engineering Programs

SEP-ISI-104

Program Section for ASME Section XI, Division 1, WF3

Inservice Inspection program, Entergy Nuclear

Engineering Programs

SEP-ISI-104

Program Section for ASME Section XI Division 1 WF3

Inservice Inspection Program, Entergy Nuclear

Engineering Programs

Self-

Assessments

LO-WLO-2019-

00031

Pre-NRC RF23 ISI Activities Self-Assessment Report

06/29/2020

Work Orders

Work Orders

27322-01

71111.12

Corrective Action

CR-WF3-YYYY-

2019-08796, 2019-08801, 2019-08806, 2019-08826,

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

Documents

NNNN

2019-08839, 2020-03991, 2020-05725, 2020-06388

71111.13

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

20-05855

Procedures

EN-WM-104

On-Line Risk Assessment

2

OI-037-000

Operations Risk Assessment Guideline

315

71111.15

Miscellaneous

W3-DBD-038

Safety-Related HVAC - Control Room Design Basis

Document

301

71111.19

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

20-05885

71111.22

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

20-07126

2/17/2020

Miscellaneous

Process Applicability Determination Form For OP-903-

115, Revision 052

09/22/2020

FSAR Section

8.3.1

AC Power Systems

Technical

Specification

3/4.8.1

A.C. Sources

Procedures

ME-007-002

Molded Case Circuit Breakers

OP-903-027

Inspection of Containment

306

OP-903-115

Train A Integrated Emergency Diesel

Generator/Engineering Safety Features Test

OP-903-123

Control Room Envelope Pressure Test

311

STA-001-004

Surveillance Procedure Local Rate Test

318

Work Orders

157704

Perform Maintenance on Breaker Referencing

ME-007-002

09/03/2013

71114.02

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2018-05551, 2018-05591, 2018-07075, 2019-04362,

2019-06326, 2019-06327, 2019-08824, 2019-08930,

20-03581, 2020-04021, 2020-04022, 2020-04023,

20-04507, 2020-06251

Miscellaneous

Updated Alert/Notification System Design Report

(December 2014)

(Addendum 0,

Revision 1)

KLD TR-825

Waterford 3 Steam Electric Station: 2015 - Population by

Siren Contour Analysis Update

2/19/2016

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

Procedures

EPP-422

Siren and Helicopter Warning System Maintenance

013

EPP-424

Siren Testing and Siren System Administrative Controls

20

71114.03

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2018-05402, 2018-07228, 2019-04576, 2019-06270,

2019-07314, 2019-07397, 2019-07817, 2020-01181,

20-02280, 2020-02886

Miscellaneous

ERO Callout Test Analysis Results (Multiple Quarterly

and Monthly Reports)

3Q/2018 -

3Q/2020

Waterford 3 Station On-Shift Staffing Analysis Final

Report (April 4, 2017)

Procedures

EN-EP-310

Emergency Response Organization Notification System

009

EP-002-015

Emergency Responder Activation

304

EPP-462

Evaluation of ERO Callout Test

71114.04

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2019-08175, 2019-08488, 2020-00857

Miscellaneous

CFR 50.54(Q)(3) Screening & Evaluation: EP-002-010,

Rev 316

04/24/2019

CFR 50.54(Q)(3) Screening & Evaluation: EN-EP-313,

Rev. 003

10/25/2019

CFR 50.54(Q)(2) Review: Plant Entrance and Exit

Points (for COVID-19 Screening)

03/24/2020

CFR 50.54(Q)(2) Review: EN-EP-609, EOF

Operations, Rev 6

2/17/2020

CFR 50.54(Q)(2) Review: EP-001-010, Unusual Event,

Rev 307

2/04/2019

CFR 50.54(Q)(2) Review: EP-001-020, Alert, Rev 310

2/04/2019

CFR 50.54(Q)(2) Review: EP-001-030, Site Area

Emergency, Rev 309

2/08/2019

CFR 50.54(Q)(2) Review: EP-001-040, General

Emergency, Rev 310

2/08/2019

CFR 50.54(Q)(2) Review: EP-002-052, Protective

Action Guidelines, Rev 026

04/24/2019

Procedures

EN-EP-305

Emergency Planning 10CFR50.54(q) Review Program

& 8

71114.05

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2018-06295, 2018-07047, 2019-00361, 2019-00399,

2019-00401, 2019-03651, 2019-04353, 2019-06431,

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

2019-06444, 2019-07149, 2019-07467, 2019-07477,

2019-07547, 2019-07722, 2019-08611, 2019-08638,

2019-08640, 2019-08711, 2020-00228, 2020-01114,

20-01180, 2020-01319, 2020-01325, 2020-01992,

20-06193

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-2020-07046, WTWF3-2020-00381

Miscellaneous

ERO Red Team Drill (3/4/2020) Report

04/03/2020

ERP Blue Team Drill (4/3/2019) Report

04/15/2019

ERO Red Team Site Drill (4/30/2019) Report

05/30/2019

TSC Limited Scope Focused Drill 2019-07 Report

05/13/2019

ERO Orange Team NRC Dress Rehearsal Drill

(9/25/2019) Report

10/23/2019

TSC Operations Coordinator Focused Drill 2019-05

03/11/2019

ERO Blue Team Site Drill (12/6/2018) Report

01/20/2019

HP Drill Report (12/09/2019)

2/17/2019

HP Drill Report (06/20/2019 - #2019-08)

10/01/2019

Onsite Medical Drill Report (10/30/2019)

2/03/2019

ERO Orange Team NRC Exercise (11/20/2019) Report

2/17/2019

Waterford Emergency Plan - Appendix C (Letters of

Agreement with Hahnville Volunteer Fire Department,

U.S. Coast Guard, St. Charles Parish Sheriffs Office, &

Panther Helicopter)

Various(Updated

2019-2020)

Waterford Emergency Plan - Appendix I (Emergency

Medical Assistance Program, Letters of Agreement with

St. Charles Parish Hospital and West Jefferson Medical

Center)

Various

(Updated 2019 -

20)

Waterford 3 Steam Electric Station Emergency Plan

50, 51

Emergency

Preparedness

Focused

Tabletop #2017-

Focused Drill for Site Accountability

2/28/2018 &

11/27/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

KLD TR-1017

Waterford-3 Steam Electric Station 2018 Population

Update Analysis

09/08/2018

KLD TR-1092

Waterford-3 Steam Electric Station 2019 Population

Update Analysis

09/07/2019

KLD TR-1172

Waterford-3 Steam Electric Station 2020 Population

Update Analysis

09/05/2020

KLD TR-502

Waterford-3 Steam Electric Station Development of

Evacuation Time Estimates

11/2012

QA-7-2019-W3-1

Audit Report: Emergency Preparedness (10 CFR 50.54(t)

Program Review)

05/13/2019

QA-7-2020-W3-1

Audit Report: Emergency Preparedness (10 CFR 50.54(t)

Program Review)

05/18/2020

Trimester 19-02

Nuclear Independent Oversight Functional Area

Performance Report

10/20/2019

Trimester 20-01

Nuclear Independent Oversight Functional Area

Performance Report

03/17/2020

Trimester 20-02

Nuclear Independent Oversight Functional Area

Performance Report

06/29/2020

Trimester 20-03

Nuclear Independent Oversight Functional Area

Performance Report

10/23/2020

W3D3-2019-0001 Summary Drill Report: Control Room Emergency

Breathing Air Drill (Scenario #2019-06)

05/08/2019

W3D3-2019-0002 Summary Drill Report: Control Room Emergency

Breathing Air Drill (Scenario #2019-06)

2/06/2019

W3D3-2020-01

Summary Drill Report: Control Room Emergency

Breathing Air Drill (Scenario #2020-08)

04/30/2020

W3D3-2020-02

Summary Drill Report Control Room Emergency

Breathing Air Drill (Scenario #2020-10)

08/24/2020

Procedures

EN-LI-102

Corrective Action Program

EP-001-001

Recognition and Classification of Emergency Conditions

EP-002-052

Protective Action Guidelines

26

EP-002-071

Site Protective Measures

304

EP-003-040

Emergency Equipment Inventory

310

Inspection

Procedure

Type

Designation

Description or Title

Revision or Date

EPP-428

Equipment Important to Emergency Response

307

Self-

Assessments

LO-WLO-2019-

00024

Pre-NRC Evaluated Exercise Assessment

09/09/2019

LO-WLO-2020-

00041

20 Pre-NRC Emergency Planning Program Inspection

Assessment

08/24/2020

Work Orders

WO-WF3-NNNN

00333437, 00489973, 00495967, 00511576,

0052930321, 0052930321, 0052933267

71151

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNN

20-07050

Miscellaneous

WF3 Key ERO Member Participation Reports & ERO

Rosters

4Q/2019-

3Q/2020

WF3 Drill and Exercise Performance Indicator Records

(from License Operator Exam/Requalification, Team

Drills, and other ERO Activities)

4Q/2019 -

3Q/2020

WF3 ANS (Fixed Siren) Testing Records

4Q/2019 -

3Q/2020

Procedures

EN-EP-801

Emergency Response Organization

EN-FAP-EP-005

Emergency Preparedness Performance Indicators

EN-LI-117

Regulatory Performance Indicator Process

71152

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNN

20-03400

Procedures

MM-007-010

Fire Extinguisher Inspection and Extinguisher

Replacement

25