IR 05000382/2020003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000382/2020003
ML20303A312
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/29/2020
From: John Dixon
NRC/RGN-IV/DRP/RPB-D
To: Ferrick J
Entergy Operations
References
IR 2020003
Download: ML20303A312 (20)


Text

October 29, 2020

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - INTEGRATED INSPECTION REPORT 05000382/2020003

Dear Mr. Ferrick:

On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station, Unit 3. On October 8, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Waterford Steam Electric Station, Unit 3.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Waterford Steam Electric Station, Unit 3. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, John L. Digitally signed by John L. Dixon Dixon Date: 2020.10.29 15:50:10 -05'00'

John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Reactor Projects Docket No. 05000382 License No. NPF-38

Enclosure:

As stated

Inspection Report

Docket Number: 05000382 License Number: NPF-38 Report Number: 05000382/2020003 Enterprise Identifier: I-2020-003-0002 Licensee: Entergy Operations, Inc.

Facility: Waterford Steam Electric Station, Unit 3 Location: Killona, LA 70057 Inspection Dates: July 1, 2020 to September 30, 2020 Inspectors: J. Braisted, Reactor Inspector N. Brown, Project Engineer D. Childs, Resident Inspector L. Flores, Reactor Inspector T.J. Farina, Senior Operations Engineer S. Graves, Senior Reactor Inspector S. Makor, Reactor Inspector J. Mateychick, Senior Reactor Inspector F. Ramirez Munoz, Senior Resident Inspector D. Reinert, Reactor Inspector R. Smith, Nuclear Systems Engineer C. Speer, Reactor Systems Engineer Approved By: John L. Dixon, Jr., Chief Reactor Projects Branch D Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish Documented Work Instructions Appropriate to the Circumstance for the Safety-Related Wet Cooling Tower Fan Motors Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [P.2] - 71111.12 Systems NCV 05000382/2020003-01 Evaluation Open/Closed The inspectors reviewed a self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 6.8.1.a for the licensees failure to establish documented work instructions appropriate to the circumstance for the periodic inspection and cleaning of wet cooling tower fan motor support bulkhead drains. Specifically, the work instructions only allowed for observation of standing water in the bulkhead, but did not provide steps for verifying the drains were clear or cleaning the drains if necessary. As a result, standing water in the wet cooling tower 5A fan motor support bulkhead led to water intrusion of the motor casing, motor bearing failure, and inoperability of the fan and ultimate heat sink on May 13, 2020.

Additional Tracking Items

None.

PLANT STATUS

The Waterford Steam Electric Station, Unit 3, began the inspection period at 100 percent power.

The licensee initiated a plant shutdown on September 25, 2020, to begin Refueling Outage 23.

The unit remained shutdown for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather due to hurricanes Marco and Laura on August 22, 2020, and hurricane Sally on September 13, 2020.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Shield building ventilation train B with train A out of service for planned maintenance on July 15, 2020
(2) High pressure safety injection train A following planned maintenance on August 6, 2020
(3) Safety related 480V electrical distribution train B following planned maintenance on August 21, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire area RAB 8A-001, switchgear room A on July 8, 2020
(2) Fire area RAB 7-001, relay room on July 17, 2020
(3) Fire area RAB 39-001, elevation -35 reactor auxiliary building on September 1, 2020
(4) Fire area RAB 34-001, safeguards valve gallery A and B on September 17, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Emergency feedwater pump rooms A and B on September 2, 2020

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Condenser for refrigeration units on essential chiller system on August 25, 2020

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspector reviewed and evaluated the results of the licensed operator annual requalification operating exam administered from June 15 to July 15, 2020.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during plant protection system testing on August 1, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the simulator during a training evolution on August 12, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Controlled ventilation area system on July 29, 2020
(2) Shutdown cooling system on September 8, 2020
(3) Wet cooling tower fan motor bearing failures due to water intrusion on September 22, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Emergent yellow risk for troubleshooting emergency diesel generator B due to an incomplete start sequence on July 22, 2020
(2) Planned yellow risk for relay maintenance associated with high pressure safety injection train A on August 3, 2020
(3) Emergent maintenance on the core operating limit supervisory system due to failed power supply in channel D incore nuclear instrumentation on September 2, 2020
(4) Planned plant configuration changes during modifications of motor control center 315A on September 9, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Emergency feedwater pump A following test failure on August 16, 2020
(2) Control element assembly ejection analysis incorrect input on August 17, 2020
(3) Reactor coolant loop 1 hot leg injection flow control valve when an associated relay was found at an inappropriate setting on August 17, 2020
(4) Airborne radiation monitors error in calculation of particulate concentrations on August 24, 2020
(5) Emergency diesel generators due to non-conservative Technical Specification surveillance frequency and voltage values on September 24, 2017

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Permanent modification for reactor coolant loop 1 hot leg injection check valve replacement on August 13, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Spent fuel pool heat exchanger component cooling water outlet temperature control valve on July 7, 2020
(2) Shield building ventilation train B following maintenance on the emergency filtration unit on July 21, 2020
(3) Nitrogen gas regulator valve for accumulator number 5 following valve internals replacement on August 28, 2020
(4) Shutdown cooling flow control valve train A following planned maintenance on September 2, 2020
(5) Core operating limit supervisory system following emergency maintenance on a power supply in channel D incore nuclear instrumentation on September 28, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1) (Partial)

The inspectors evaluated Refueling Outage 23 activities in accordance with Sections 03.01.a, 03.01.b, 03.01.c(5), and 03.01.c(8), between September 25 and September 30, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Emergency feedwater pump A operability test on July 14, 2020
(2) Reactor trip circuit breakers 1, 2, 5, and 6 on August 18, 2020
(3) Emergency diesel generator A integrated test on September 29, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Auxiliary component cooling water pump A inservice test on July 9, 2020

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Simulator-based training scenario on July 14,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07) ===

(1) July 1, 2019 through June 30, 2020

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) July 1, 2019 through June 30, 2020

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) July 1, 2019 through June 30,

INSPECTION RESULTS

Failure to Establish Documented Work Instructions Appropriate to the Circumstance for the Safety-Related Wet Cooling Tower Fan Motors Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [P.2] - 71111.12 Systems NCV 05000382/2020003-01 Evaluation Open/Closed The inspectors reviewed a self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 6.8.1.a for the licensees failure to establish documented work instructions appropriate to the circumstance for the periodic inspection and cleaning of wet cooling tower fan motor support bulkhead drains. Specifically, the work instructions only allowed for observation of standing water in the bulkhead, but did not provide steps for verifying the drains were clear or cleaning the drains if necessary. As a result, standing water in the wet cooling tower 5A fan motor support bulkhead led to water intrusion of the motor casing, motor bearing failure, and inoperability of the fan and ultimate heat sink on May 13, 2020.

Description:

The ultimate heat sink consists of two 100 percent capacity loops, each consisting of a dry and wet cooling tower and water stored in the wet cooling tower basins.

Each wet cooling tower consists of two cells, and each cell is serviced by four induced draft fans, for a total of eight fans per wet cooling tower. With a wet cooling tower fan inoperable, the entire wet cooling tower must be declared inoperable, unless the inoperable fan has an approved cover installed. One wet cooling tower fan may be covered, and the ultimate heat sink remains operable per Technical Specification 3.7.4. A vibration switch mounted outside on the wet cooling tower fan motor duct causes an alarm in the control room on high fan motor vibration. During normal plant operations, the wet cooling towers operate to maintain the component cooling water system temperature. During accident conditions, the wet cooling towers operate until the dry cooling towers can dissipate the heat load from the component cooling water system.

In 2004, the licensee instituted required preventive maintenance task 10403 to inspect and clean the A wet cooling tower floor drains monthly. This task also included work instructions to inspect and clean the wet cooling tower fan motor support bulkhead drain in each wet cooling tower fan shroud. The intent of preventive maintenance task 10403, with respect to the motor support bulkheads, was to ensure the drains were clear so that water could not accumulate in the bulkhead after a rainfall event. Water accumulation (or standing water) in any bulkhead could mean partial immersion of that motor. The work instructions were two steps in total: 1) INSPECT bulkhead drain and CLEAN if needed and 2) IF discrepancy present that cannot be resolved by basic cleaning, INITIATE a CR [condition report] to address issue.

In February 2019, the licensee installed new motors for 15 of the16 wet cooling tower fans.

During performances of required preventive maintenance task 10403 between February 2019 and May 2020, the licensee identified eight separate instances of standing water in various A wet cooling tower fan motor bulkheads. Of these instances, the licensee identified standing water seven times in fan motor 5A, five times in fan motor 8A, and three times in fan motor 3A. The licensee identified standing water in all the A wet cooling tower fan motor bulkheads on at least one occasion during this period. Despite the intent of preventive maintenance task 10403 to clean the drains if needed, the licensee did not make any attempts within the performances of 10403 to clean the drains when they identified standing water. In each of these cases, the licensee initiated a new condition report or documented a reference to a condition report, which had previously been initiated in the work order. In all cases, the licensee documented the implementing work order for preventive maintenance task 10403 as complete although the licensee had not performed any cleaning. To address the standing water, the licensee-initiated work requests from each of the condition reports.

However, the licensee had not implemented any of the work requests as they were still in planning as of September 2020.

On May 13, 2020, the control room received an unexpected annunciator alarm indicating high vibrations on wet cooling tower fan motor 5A, which was one of the motors replaced in February 2019. The licensee collected vibration data on the fan motor and determined it indicated motor bearing damage. Subsequently, the licensee secured wet cooling tower fan 5A and opened its breaker due to the condition. The licensee then declared both the wet cooling tower fan 5A and the A ultimate heat sink inoperable. The plant entered Technical Specification 3.7.4 and cascading technical specifications, resulting in entry into an unplanned 72-hour shutdown limiting condition of operations. The following day, the licensee installed a cover over fan motor 5A and declared the A wet cooling tower and A ultimate heat sink operable, exiting the affected limiting conditions of operation.

The licensee sent wet cooling tower fan motor 5A to the motor vendor to perform a failure analysis. In its preliminary report, the vendor documented that water intrusion of the motor casing had caused the high vibration. Specifically, standing water on the exterior of the water, due to the clogged bulkhead drain, resulted in water entering the grease drain plug and stator cavity drain plug. The motor drains were designed to allow moisture to exit the motor. Consequently, water displaced the grease lubricant in the bearing, resulting in poor lubrication characteristics and bearing failure.

In a review of required preventive maintenance task 10403, the inspectors noted that it had numerous inadequacies. For example, the inspection of the bulkhead drains was limited to looking through a 3-inch viewport and identifying any standing water, but it does not permit actual viewing of the drain to ensure it is clear nor the ability to see inside the bulkhead for debris, which might migrate toward the drain and clog it. Additionally, the inspectors noted that no cleaning, even basic cleaning, could be performed using the instructions in preventive maintenance task 10403 given that access to the bulkhead is limited to the viewport and that any cleaning would require the licensee to secure the fan motor and erect scaffolding to ensure the necessary access, among other actions. Furthermore, the inspectors noted that the work instructions do not identify any objective criteria for determining the intent of the task is complete. Finally, the inspectors noted that standing water due to a clogged drain can evaporate between performances of preventive maintenance task 10403 (or the drain might be partially clogged, but still retain water while draining slowly), resulting in a condition where the motors could be partially immersed in water unbeknownst to the licensee. This is demonstrated by the identification of standing water in only some of the performances of 10403 without the licensee having performed any cleaning of the drains.

Corrective Actions: The licensee implemented an emergent work order to replace wet cooling tower fan motor 5A on May 27, 2020, and collected vibration data on the remaining wet cooling tower fan motors and determined the data was satisfactory. Additionally, the licensee lowered the alert/alarm limits for wet cooling tower fan motor vibration monitoring and initiated actions to correct the deficiencies in required preventive maintenance task 10403.

Corrective Action References: Condition Reports CR-WF3-2020-02188, CR-WF3-2020-03716, CR-WF3-2020-04493

Performance Assessment:

Performance Deficiency: The failure to establish documented instructions appropriate to the circumstance for the inspection and cleaning of the A wet cooling tower fan motor support bulkhead drains in accordance with NRC Regulatory Guide 1.33 was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, as a result of the licensee not completing the intent of required preventive maintenance task 10403 on multiple occasions, the A wet cooling tower fan motors were subjected to periods of standing water in the motor support bulkheads which led to the failure of fan motor 5A and an unplanned entry into a 72-hour technical specification limiting condition for operation.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined that the finding was of very low safety significance (Green) because

(1) the finding was not a deficiency affecting the design or qualification of a mitigating system;
(2) the degraded condition did not represent a loss of the PRA function of a single train technical specification system for greater than is technical specification allowed outage time;
(3) the degraded condition did not represent a loss of the PRA function of one train of a multi-train technical specification system for greater than its technical specification allowed outage time;
(4) the degraded condition did not represent a loss of the PRA function of two separate technical specification systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />;
(5) the degraded condition did not represent a loss of a PRA system and/or function as defined in the PRIB or licensees PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and
(6) the degraded condition did not represent a loss of the PRA function of one or more non-technical specification trains of equipment designated as risk-significant in accordance with the licensees maintenance rule program for greater than 3 days.

Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance. Specifically, while the licensee initiated corrective actions through work requests to clean the bulkhead drains when standing water was identified during multiple performances of required preventive maintenance task 10403, the licensee did not evaluate the cause of the condition which was, ultimately, inadequate work instructions. Therefore, after the first identification of standing water in the bulkheads, the licensee had the opportunity to correct the work instructions in 10403 to allow completion of the task as intended for every future implementation of the task.

Enforcement:

Violation: Technical Specification 6.8.1.a, requires, in part, that procedures shall be established, implemented, and maintained covering the applicable procedures recommended in NRC Regulatory Guide 1.33, Revision 2. Appendix A to NRC Regulatory Guide 1.33, Section 9.a, requires, in part, that maintenance that can affect the performance of safety-related equipment be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. The licensee established required preventive maintenance task 10403, in part, to inspect and clean the A wet cooling tower fan motor support bulkhead drains monthly.

Contrary to the above, between 2004 and May 2020, required preventive maintenance task 10403 was not appropriate to the circumstance because inspection and cleaning of the A wet cooling tower fan motor bulkhead drains could not be completed in accordance with the documented instructions. As a result, standing water in the wet cooling tower 5A fan motor support bulkhead between August 2019 and April 2020 led to water intrusion of the motor casing, displacement of grease lubricant, motor bearing failure, and inoperability of the fan and ultimate heat sink.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 22, 2020, the inspectors presented the annual requalification inspection results to Mr. V. Ford, Operations Training Superintendent, and other members of the licensee staff.
  • On October 8, 2020, the inspectors presented the integrated inspection results to Mr. J. Ferrick, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Procedures EN-FAP-EP-010 Severe Weather Response 8

71111.01 Procedures OP-901-521 Severe Weather and Flooding 334

71111.04 Miscellaneous SD-SBV System Description for Shield Building Ventilation 11

71111.04 Procedures OP-006-001 Plant Distribution (7KV, 4KV, SSD) System 337

71111.04 Procedures OP-006-005 Inverters and Distribution 343

71111.04 Procedures OP-008-008 Shield Building Ventilation 10

71111.04 Procedures OP-009-008 Safety Injection 44

71111.05 Procedures RAB 7-001 Waterford-3 S.E.S Prefire Strategy Relay Room 12

71111.05 Procedures RAB 8A-001 Waterford-3 S.E.S Prefire Strategy Switchgear Room A 12

71111.06 Calculations ECM15004 Waterford 3 FLEX Internal Flooding Calculation 000

71111.06 Calculations MNQ3-5 Flooding Analysis Outside Containment 006

71111.06 Corrective Action CR-WF3-YYYY- 2020-04162

Documents NNNN

71111.06 Drawings G153 Flow Diagram Feedwater, Condensate & Air Evacuation 49

Systems

71111.06 Drawings G875 Reactor Auxiliary Building Plan EL -34.75 Plumbing & 20

Drainage

71111.06 Drawings G880 Riser Diagrams & Details Plumbing & Drainage 23

71111.06 Miscellaneous EC 87897 Chilled Water (CHW) inlet drain piping downstream of 09/03/20

CHWMVAAA481 for the Air Handling Unit HVRMAHU0038-

B (AH-17-(3B-SB)), was found to be corroded

71111.06 Miscellaneous LOU 1564.266 Ebasco Specification - 5kV & 15 kV Power Cables 8

71111.06 Procedures EN-OP-123 Time Critical Action/Time Sensitive Action Program Standard 003

71111.07A Corrective Action CR-WF3-YYYY- 2020-02697, 2020-02703

Documents NNNN

71111.07A Engineering EC 83727 Essential Chiller A Degraded (Corroded) Piping Operability 0

Evaluations Input CR-2020-3375, CR-2020-3376, CR-2020-3377, CR-

20-3378, CR-2020-3379, CR-2020-3380, CR-2020-3437,

Inspection Type Designation Description or Title Revision or

Procedure Date

CR-2020-3515

71111.07A Engineering ER-W3-2001- CCW Monitoring Plan 0

Evaluations 1125-000

71111.07A Engineering ER-W3-2001- CCW Monitoring Plan Clarifications 0

Evaluations 1125-001

71111.07A Engineering SAP-HX-WF3- Generic Letter 89-13 Heat Exchanger Test Basis 001

Evaluations 001

71111.07A Miscellaneous Letter W3P90- WF3 Response to Generic Letter 89-13 01/29/1990

207

71111.07A Miscellaneous SD-CHW Essential Chilled Water 12

71111.07A Work Orders WO 52522251 01 RFRMCLR0002 A -Evaporator/Condenser Clean/Eddy 0

Current Tube

71111.07A Work Orders WO 52696304 01 RFRMCLR0002 B - Evaporator/Condenser Clean/Eddy 0

Current Tube

71111.07A Work Orders WO 52734218 01 RFRMCLR0002 AB - Clean Evaporator & Condenser/Eddy 0

Current

71111.11A Miscellaneous 2020 Annual Requalification Operating Exam Results 07/15/2020

71111.11Q Procedures OP-903-107 Plant Protection System Channel A, B, C, and D Functional 315

Test

71111.12 Corrective Action CR-WF3-YYYY- 2019-07661, 2020-01430, 2020-03291, 2020-00618,

Documents NNNN 2020-04190, 2019-06453, 2019-08317, 2020-00123,

20-00575, 2020-02188, 2020-02267, 2020-03267,

20-04493

71111.12 Miscellaneous WEG Motors and Drives, Installation and Maintenance

Manual for Electric Motors

71111.12 Miscellaneous SD-CC, Component Cooling Water 25

71111.12 Procedures EN-DC-313-01 Procurement Engineering - Item Equivalency Evaluation 3

71111.12 Procedures EN-LI-102 Corrective Action Program 42

71111.12 Work Orders 52915865

71111.13 Calculations EC 75985 Replacement and Relocation of Motor Control Center (MCC) 1

315A

71111.13 Corrective Action CR-WF3-YYYY- 2020-03359, 2020-03612

Documents NNNN

71111.13 Miscellaneous Protected Equipment List 1PE-1 07/22/2020

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.13 Procedures EN-WM-104 On Line Risk Assessment

71111.13 Procedures ME-003-410 Motor-Operated Valve Thermal Overload Channel 310

Calibration

71111.13 Procedures ME-003-410 Motor-Operated Valve Thermal Overload Channel 311

Calibration

71111.13 Procedures OI-037-000 Operations Risk Assessment Guideline

71111.13 Work Orders 00517391, 52554711, 00530423

71111.15 Calculations 19365 High Pressure Safety Injection System Capacity 001

71111.15 Calculations EC-M98-068 LPSI System Performance Surveillance Requirement Basis 0

71111.15 Corrective Action 2020-03271

Documents

71111.15 Corrective Action CR-WF3-YYYY- 2020-3655, 2020-3698, 2020-03629, 2017-8982, 2018-4043

Documents NNNN

71111.15 Miscellaneous 0000047119 Upgrade to Regulatory Guide 1.9 Revision 4 for Emergency 000

Diesel Generators

71111.15 Miscellaneous FSAR Section Containment Airborne Radiation Monitor

2.3.4.2.3.1

71111.15 Miscellaneous FSAR Section Containment Airborne Particulate Radioactivity Monitoring

5.2.5.1.2

71111.15 Miscellaneous Regulatory Guide Pressurized-Water Reactor Control Rod Ejection and June 2020

RG 1.236 Boiling-Water Reactor Control Rod Drop Accidents

71111.15 Miscellaneous TD G080.0095 General Electric Switchgear Magne Blast Circuit Breakers 6

71111.15 Miscellaneous Technical Reactor Coolant System Leakage Detection Instrumentation

Specification

3.4.5.1

71111.15 Miscellaneous W3F1-2019-0073 License Amendment Request to Revise Technical 10/23/2019

Specification 3.8.1.1 Surveillance Requirements

71111.15 Miscellaneous W3F1-2020-0033 Response to U. S. Nuclear Regulatory Commission Request 05/29/2020

for Additional Information Regarding License Amendment

Request to Revise Technical Specification 3/4.8.1, "A.C.

Sources Operating"

71111.15 Miscellaneous WSES-FSAR- Waterford 3 FSAR Section 15.4 Reactivity and Power 309

UNIT-3 Distribution Anomalies

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.15 Operability CR-WF3-YYYY- 2020-4019

Evaluations NNNN

71111.15 Procedures EN-OP-104 Operability Determination Process 16

71111.15 Procedures ME-003-327 4.16KV G.E. Magne-Blast Breaker 020

71111.15 Procedures ME-004-115 4.16/6.9 KV G.E. Magne-Blast Breaker Overhaul 6

71111.15 Procedures OP-903-115 Train A Integrated Emergency Diesel Generator/Engineering 052

Safety Features Test

71111.15 Procedures OP-903-116 Train B Integrated Emergency Diesel Generator/Engineering 053

Safety Features Test

71111.18 Engineering EC 83354 Replace SI-512A with a Swing Check Valve 0

Changes

71111.18 Miscellaneous Specification Reactor Coolant Hot Leg Injection Check Valve SI 2

SPEC-15-00002- MVAAA512 A/B Replacement

W

71111.18 Procedures OP-903-008 Reactor Coolant System Isolation Leakage Test 19

71111.18 Procedures OP-903-108 SI Flow Balance Test 18

71111.19 Corrective Action CR-WF3-YYYY- 2020-03195, 2020-03335, 2020-03338, 2020-03347,

Documents NNNN 2020-04190, 2020-04168

71111.19 Engineering EC 87874 Temporary Incore Channel D Chassis Power Supply 0

Changes

71111.19 Engineering EC87434 Target Rock Regulating Valve for use in NG-811

Changes

71111.19 Miscellaneous FSAR Section ASME allowable Stress Values, S, For Ferritic Steels For

9.39 Nitrogen Class 2 and Class MC Components

Systems

71111.19 Miscellaneous System Design Core Operating Limit Supervisory System 11

Description SD-

COL

71111.19 Procedures OP-008-008 Shield Building Ventilation 10

71111.19 Procedures OP-903-118 Primary Auxiliaries Quarterly IST Valve Tests 52

71111.19 Procedures OP-903-119 Secondary Auxiliaries Quarterly IST Valve Test 34

71111.19 Procedures OP-903-121 Safety Systems Quarterly IST Valve Tests 031

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.19 Work Orders 52706788, 52775106, 53713

71111.22 Corrective Action CR-WF3-YYYY- 2020-3207

Documents NNNN

71111.22 Miscellaneous SD-EFW System Description for Emergency Feedwater System 17

71111.22 Procedures OP-903-006 Reactor Trip Circuit Breaker Test 15

71111.22 Procedures OP-903-046 Emergency Feed Pump Operability Check 323

71111.22 Procedures OP-903-050 Component Cooling Water and Auxiliary Component Cooling 42

Water Pump and Valve Operability Test

71111.22 Work Orders 52927052

71151 Corrective Action CR-WF3-YYYY- 2019-07833, 2020-00276

Documents NNNN

71151 Miscellaneous ECH-NE-09- Waterford 3 mitigating System Performance Index Basis 7

00036 Document

71151 Miscellaneous PSA-WF3-06-05 WF3 PSA Input to MSPI Basis Document 0

71151 Miscellaneous W3F1-2019-0075 NRC Performance Indicator (PI) Data - 3rd Quarter ROP 10/17/2019

Data

71151 Miscellaneous W3F1-2020-0004 NRC Performance Indicator (PI) Data -4th Quarter 2019 01/16/2020

ROP Data

71151 Miscellaneous W3F1-2020-0008 NRC Performance Indicator (PI) Data - CR (Change Report) 01/22/2020

ROP 4th Quarter ROP 2019 - PRA Change

71151 Miscellaneous W3F1-2020-0013 NRC Performance Indicator (PI) Data - CR (Change Report) 02/24/2020

ROP 4th Quarter ROP 2019 - Software change and MSPI

correction (CR-WF3-2020-00276)

71151 Miscellaneous W3F1-2020-0022 NRC Performance Indicator (PI) Data - QR (Quarterly 04/20/2020

Report) ROP 1st Quarter 2020

71151 Miscellaneous W3F1-2020-0048 NRC Performance Indicator (PI) Data - QR (Quarterly 07/16/2020

Report) ROP 2nd Quarter 2020

71151 Miscellaneous W3F1-2020-0049 NRC Performance Indicator (PI) Data - CR (Change Report) 07/17/2020

ROP 2nd & 3rd Quarter ROP 2019 (Emergency

Preparedness DEP)

71151 Procedures EN-LI-114 Regulatory Performance Indicator Process 17

71152 Miscellaneous LOU 1564.249W Penetration Radiation Shields, Fire Stops and Air Seals For 09/13/1984

Electrical, Mechanical, and HVAC Systems - Interface

Inspection Type Designation Description or Title Revision or

Procedure Date

Material, Non-Seismic

71152 Miscellaneous W3-DBD- 10 CFR 50.48 (a) & (c)/NFPA 805/FIRE PROTECTION 3

18_0_003-1 UPPER LEVEL DESIGN BASIS DOCUMENT

71152 Miscellaneous WF3-FP-10- WF3 Code Compliance Report for NFPA 10 Portable Fire 001

00008 Extinguishers 1978 Edition

71152 Procedures ME-003-006 Fire Barrier Penetrations Seals 315

71152 Procedures ME-003-009 Fire-rated Walls, Floors, and Ceilings 309

17