IR 05000346/1982012

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-346/82-12 on 820405-07.No Noncompliance Noted.Major Areas Inspected:Inservice Insp,Data,Matl & Equipment Certifications & Work Activities
ML20052B591
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/13/1982
From: Danielson D, Ward K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20052B586 List:
References
50-346-82-12, TAC-48349, NUDOCS 8205030338
Download: ML20052B591 (4)


Text

'

U.S. NUCLEAR REGULATORY COMMISSION Region III Report No. 50-346/82-12(DETP)

Docket No. 50-346 License No. NPF-3 Licensee: Toledo Edison Company Edison Plaza 300 Madison Avenue Toledo, OH 43652 Facility Name: Davis-Besse Nuclear Power Station, Unit 1 Inspection At: Davis-Besse Site, Port Clinton, OH Inspection Conducted: April 5 and 7, 1982 g/Irt4um-

""

,K 3!#L Inspector: g. D. Ward l

dWLN}A-Approved By:

D. H. Danielson, Chief

/ 3/P 2-Materials and Processes Section Insepction Summary Inspection on April 5 and 7, 1982 (Report No. 50-346/82-12(DETP))

Areas Inspected:

Review of inservice inspection (ISI) data; material and equipment certifications; nondestructive examination (NDE) personnel certi-fications and observed work activities. The inspection involved a total of six onsite inspector-hours by one NRC inspector.

Results: No items of noncompliance or deviations were identified.

,

,

t 820503 0 33B i

~

.

.

s

,

x

'

(

' DETAILS Persons Contacted The Toledo Edison Company (TECol

'

  • C. Daft, QA Director E. Doerr, Code Inspection Supervisor

.

J. Singer, Associate QC Specialist

"

Babcock and Wilcox Company (B&W)

C.'

n, Group Leader ISI The Hartford Steam Inspection and Insurance Company T. Sanford, Authorized Nuclear Service Inspector (ANII)

The inspector also contactnd and interviewed other licensee and contractor

. employees.

  • Denotes those present at the exit interview.

Functional or Program Areas Inspected 1.

General

-

Ref: NRC Report No. 50-346/82-11(DETP) (Inservice Inspection)

The Eddy Current Examination (ET) consisted of a 3% random sample

[

plus a 100% lane tube examinaticn in each steam generator (SG). The 3% random sample examination in each generator included a limited number of "special interest" tubes such as concentrations of " dings" at a particular elevation on cross sectional area or the abnormal ding findings. The "special interest" tubes were counted as part of

.the 3% random sample examination in accordance with guidelines set forth in the Davis-Besse 1 Technical Specification.

In addition, a special examination of approximately 48 tubes in front of the eight internal auxiliary feedwater header brackets / dowel pin locations in each SG were also selected for ET.

Visual examination (VT) of the tube to tube support plate interfaces and accessible internal auxiliary feedwater headcr bracket / dowel pin locations-were performed in the "A" and "B" SG's through the XI-axis, Upper Secondary Manway.

In SG "A", one tube was found to have a 69% thin wall by ET.

Because of the results an-additional 6% ET was performed of SG "A".

Tube lists for the ' additional 6% ET 'were developed as part of the pre-outage planning effort and were supplied to B&W along ~with the 3% tube list for use as required.

f

!

,

u Z

'

u-

,.

.-

,',_

k

_

..

.

-

-

.

.

..

. - _. -

.

- -

. -

. _- -- - -

~

.

2.

Procedure Review

,

The inspector reviewed the following procedures:

B&W, Personnel Qualification - Eddy Current Examination, ISI-24,

.

Revision 4.

/

B&W, Ultrasonic Examination of Piping and Vessel Velds Joining

.

Similar and Dissimilar Materials, ISI-120, Revision 12.

B&W, Insertion, Calibration, Operation and Removal of Eddy a

.

Current OTSG Tube Examination Equipment in the Upper Head, ISI-406, Revision 4.

B&W, Multifrequency Eddy Current Examination of OTSG Tubing in

.

177 Steam Generators, ISI-416, Revision 3.

No items of noncompliance or deviations were identified.

'

3.

Equipment Certification and NDE Personnel Certifications The inspector reviewed eddy current equipment certifications and several B&W NDE personnel certifications, Level I, II and III, in accordance with SNT-TC'1A, 1975 Edition.

t No items of noncompliance or deviations were identified.

4.

Observation of Work Activities and Data Review

,

The inspector observed ET on several A and B SG tubes.

,.

i

!

Multi-frequency ET equipment was used for examining both SG's.

Therefore, debris data was taken simultaneously on all tubes probed for defect data.

Data was also reviewed on the following systems:

<

Service Water System

.

,

Reactor Coolant Drain System

.

Containment Spray System

.

.

Low Pressure Injection System

.

!

Emergency Core Cooling System

.

Decay Heat Removal System

.

,

Steam Generator Secondary System

.

'

Reactor Coolant System - Loop A

<

.

.

,

.

.u-rr

.-.

m.

.

. -

.

. ___.-.. =

- -....- _

_.. _. -

__

_-

_ - -..

...

_

.

,.

~

I Reactor Coolant Pump

.

Radwaste Coolant

.

Makeup and Purification System

.

,

No items of noncompliance or deviations were identified.

Exit-Interview The inspector met with C. Daft at the conclusion of the inspection. The

inspector summarized the scope and findings of the inspection noted in this report.