IR 05000302/1980001

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-302/80-01 on 800107-10.No Noncompliance Noted.Major Areas Inspected:Review of Operations,Ie Bulletin Followup & Tour of Facility & Corporate Headquarters
ML19323C340
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/04/1980
From: Martin R, Quick D, Beverly Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19323C338 List:
References
50-302-80-01, 50-302-80-1, NUDOCS 8005150366
Download: ML19323C340 (4)


Text

.

/

tg UNITED $TATES

'

!"

i NUCLEAR REGULATORY COMMISSION 80051503 %

,

.-

,e REGION 11

~*

g

/

101 man:ETTA ST,. N.W., SUITE 3100 g

.

ATLANTA, GEORGIA 30303

.

.....f Report No. 50-302/80-01 Licensee: Florida Power Corporation 3201 34th Street, South St. Petersburg, FL 33733

.

Facility: Crystal River 3 Docket No. 50-302 License No. DPR-72 Inspection at Crystal River site near Crystal River, Florida Inspectors:

W/u

///(/!,P/J D. R. Qu*ck g~

Date S'igned 1)

R&

tSht -

YlY B. W. Smith g

Date' Sfgried Accompanied by:

R.

Martin

/

Approved by:

!

hh

/////[M R. D'.~ Martin, Section Chief, RONS Branch Date'Aigned SUMMARY Inspection on January 7-10, 1980

.

Areas Inspected

,

This routine, unannounced inspection involved 64 inspector hours on site in the areas of review of operations, IE Bulletin followup and a tour of the facility

,,'

and corporate headquarters.

t Results

,

Of the three areas inspected, no items of noncompliance or deviations were identified.

i I

i

!

l!

-

.

>

.

.. -,

.. -.. - _ -

-. -....

. -.

-.

-

--

-e-

_

_

-_._ -...-.- --.--

-

-

---

-~~-

-

o

.

DETAILS 1.

Persons Contacted Licensee Employees

.

  • D. C. Poole, Nuclear Plant Manager
  • P. F. McKee, Operations Superintendent

,

  • G. R. Westafer, Maintenance Superintendent
  • E. K. Neuschaefer, Compliance Auditor
  • J. Cooper, Jr., QA/QC Manager
  • R. W. Kennedy, QA Supervisor
  • J. L. Bufe, Compliance Auditor
  • T. C. Lutkehaus, Technical Services Superintendent J. Kraiker, Shif t Supervisor D. A. Shook, Manager, Nuclear Engineering Other licensee employees contacted included 2 technicians, 5 operators and 2 office personnel.

NRC Resident Inspector

  • B. W. Smith
  • Attended exit interview 2.

Exit Interview The inspi -tion scope and findings were summarized on January 10, 1980, with l

those perions indicated in Paragraph I above. The licensee acknowledged

'che inspector's comments.

i l

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items Unresolved items were not identified during this inspection.

5.

Plant Operations Plant Operations were reviewed by the inspector to ascertain conformance with regulatory requirements and technical specifications.

a.

Daily Activities The inspector maintained daily awareness of plant status and signifi-cant activities through discussions with members of the plant staff

.

s

- -

'~

. _ -

-

- - - - - _ - -. - -

-

--. - - - --.-- - - -

-

-2-

.

and operating personnel.

Selected portione. of the various daily log books and control room data sheets were examined on a daily basis during the report period. The inspector made several plant tours in selected areas of the turbine and auxiliary buildings. The control room was visited on a more frequent basis than other portions of the plant. Observations included instrument readings and recordings,

-

housekeeping and status of operating systems and components.

Informal discussions were held with operators and other personnel on work activities and status of equipment. Questions developed by the inspec-tor were satisfactorily answered.

Interviews with a number of plant operations personnel were held on the day and night shifts. Supervisors and control operator's actions were observed. Their actions and activities were responsive to annun-cistor alarms and appeared to be cognizant of plant status, b.

Plant Jumper Log The inspector reviewed the Plant Jumper Log Book to verify that jumpers placed on equipment were controlled and that a safety evaluation had been performed on each jumper. No discrepancies were noted at this time.

Plant Equipment Clearance and Switching Orders c.

The inspector reviewed the Plant Equipment Clearance and Switching

,

Order logs to verify that equipment or components, required for the plant mode of operation at the present time (Mode 1), were available for operation as required by Technical Specifications and that the clearance logs were properly filled out and completed as per CP-115,

"In-Plant Equipment Clearance and Switching Orders." No discrepancies were noted at this time.

d.

Short Term Instructions The inspector reviewed the Short Term Instruction book to assure that all operations personnel had read all current instructions. No discre-pancies were noted.

e.

Plant Tours As part of the plant operations review, the inspector toured accessible portions of the plant. During the tour, observations were made regarding the general plant housekeeping and cleanliness and radiation control practices. The inspector noted that improvements had been made, however, the lack of storage space, leaking valves, and the rough condition of the floor pose continuing housekeeping and decontamination problems in the auxiliary building. Another recurring problem noted was that personnel are apparently discarding their anti-contamination

.

-

_ _

.

-3-

clothing on the floor of the auxiliary building rather than in the provided containers. The licensee stated he would evaluate this situatirn.

6.

Review of IE Bulletins The inspectors met with the Manager of Nuclear Engineering at the licensee's corporate headquarters for the purpose of reviewing the status of implemen-

-

tation of the various TMI-2 related Bulletin and Order requirements.

Although some equipment procurement problems were noted, the licensee stated that the implementation requirements would be met. No other dis-crepancies were identified at this time.

7.

Resident Inspector Assignment B. W. Smith was introduced to the licensee as the newly assigned resident inspector at the Crystal River Site. The inspector conducted B. W. Smith on a site and corperate headquarters familiarization tour to acquaint him with the licensee facilities and to introduce him to key licensee personnel.

The licensee was informed that B. W. Smith would be in a training status for approximately one year.

l

.

,

.

---w

_.

_%-

~

- - - -