IR 05000280/1980031

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-280/80-31 on 800805-06.Noncompliance Noted: Improper Pipe Support Installation & Insp
ML18139A839
Person / Time
Site: Surry Dominion icon.png
Issue date: 09/08/1980
From: Compton R, Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18139A835 List:
References
50-280-80-31, NUDOCS 8011200390
Download: ML18139A839 (4)


Text

,*

Report No. 50-280/80-31 UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 Licensee: Virginia Electric and Power Company Richmond, VA 23261 Facility Name:

Surry Docket No. 50-280 License No. DPR-32 Inspection at Stone & Webster Engineering Corporation, Boston Mas Inspector~~~, (~CM\\,~

R. M. Compton v.tw~.d Accompanying Personnel: J. R. Costello, Inspector, Vendor Inspection Branch, RIV

,

j') '[) / J~A-~K. Herr, Investigator, RIV Approved by: (,(;f\\ /Jr;I )llj,,,


A. R. Herdt, Section Chief, RCES Branch SUMMARY Inspection on August 5-6, 1980 Areas Inspected This special, announced inspection involved 10 inspector-hours onsite in the areas of licensee actions on previous inspection finding Results One item of noncompliance was identified (Infraction - improper pipe support installation and inspection - Paragraph 3).

..... --**-* -* *****------*******.

.

.

.. '

' Persons Contacted Licensee Employees J. L. Wilson, Station Manager DETAILS

  • T. A. Peebles, Technical Services Superintendent
  • R. K. MacManus, Associate Engineer Other Organizations H. W. Durkin, Project Engineer, Stone & Webster Engineering Corp (S&W)

A. Banerjee, Assistant Project Engineer, S&W J. W. Kelly, QA Program Administrator, S&W

  • Attended exit interview Exit interview The inspection scope and findings were summarized on August 6, 1980 with those persons indicated in Paragraph 1 above and on August 12, 1980 with J. L. Wilson, Station Manage.

Licensee Action on Previous Insp_ection Findings (Closed) Unresolved Item 280/80-22-01: Timely evaluation and reporting of nonconformances identified by IEB 79-14. During an inspection of Vepco at Stone & Webster (S&W) during June 16-18, 1980 it was noted that, for stress problem 3033, over two months had elapsed between the initial identification of a potential overstress condition and the notification of Vepco that a nonconformance existe IE Bulletin 79-14 specifies that the licensee should assure that he is promptly notified when the Architect/Engineer identifies a nonconformance and that the significance of nonconformances with respect to system operability be evaluated by engineering judgement within two days of identification and by analysis within 30 day Because the handling of problem 3033 did not appear to meet the intent of the Bulletin, Vepco and S&W agreed to evaluate the situation and provide more details about the timeliness of S&W's evaluation, analysis and notification of Vepc During this inspection the Vepco and S&W programs for IEB 79-14 were dis-cussed with responsible individual The progress of stress problem 3033 was reviewed in detail, including the results, request for generation qf hardware modifications, support modification packages and the nonconformance/

overstress notification for All available personnel involved with this stress problem were interviewed as to their qualifications, responsibilities and the actions take,.

-2-The last computer run recorded in the log for this problem was dated December 1, 197 S&W indicated that additional runs could have been made in the interim between December 1, 1979 and February 19, 1980 when Vepco was informed of the overstresse However, they could provide no evidence of any action during this tim One analysis was made on February 19, 1980 at the request of Vepco, after their notificatio Stress problems 3028 and 3015 were briefly reviewed and had similar identi-fication, evaluation and notification time frames, but had apparently less significant nonconformance The licensee indicated several conditions that contributed to the delays in evaluation and notification of nonconformances. The original design records for Surry were inadequate or nonexistent so that the standard comparison procedure outlined in the bulletin was not directly applicable. Therefore, the as-built condition of all systems was documented on drawings from which a stress analysis was performed. Additional, more refined and accurate analyses were performed when possible to reduce any indicated high stresse These additional analyses took more time but many initial overstress indica-tions were eliminate Secondly, in order to expedite completion of the total IEB 79-14 work effort, all the as-builts were initially analyzed prior to any detailed evaluation of the result Thirdly, there is an overall shortage of qualified stress analysis personnel due to the impact of Bulletins 79-02 and 79-14 on industry resource Regardless of the above stated conditions, the efforts by Vepco and S&W are considered inadequat S&W procedure STF-3, through Revision 1, "Procedure for the Evaluation of Stress and Reporting of Over Allowable Stress for IE Bulletins 79-14, 79-02 and Show Cause Efforts did not specify any time -

limits for stress problem review or reanalysis nor did it address the two day initial engineering judgement or the 30 day analytical engineering evaluation specified in IEB 79-1 S&W correspondence to Vepco in February 1980 stated that the evaluation and analysis times specified in the Bulletin were not being met and that this should be identified to the NRC. Vepco's reply incorrectly indicated that the actions being taken had been adequately presented in prior correspondence with the NR The maximum stresses indicated by the December 1, 1979 analysis were very high; exceeding the material's ultimate strength. However no attempt was made to screen stress problems after their initial analysis to give priority to the potentially most significant problem Vepco, in letter serial number 972 dated November 28, 1979 to NRR, indicated that support modifications would be ".designed based on preliminary evalua-tions while analyses continued to conclusion"; stating that this parallel approach results in the most expeditious upgrading of system However.,

for problem 3033 the four very simple support modification designs were not signed by the designer until February 14, 1980, over two months after preliminary analysis showed significant overstresse.......

'...

't'

-3-The procedures for accomplishing IEB 79-14 failed to provide for the timely evaluation, analysis and licensee notification of identified nonconformance Unresolved Item 280/80-22-01 is being upgraded to an infraction and will be identified as 280/80-31-0 The NRC RIV Vendor Inspection Branch will examine the actions taken by S&W on this matter for other facilitie.

Unresolved Items Unresolved items were not identified during this inspectio