IR 05000277-06-014 and 05000278-06-014; Peach Bottom Atomic Power Station (Pbaps); Ti 2515/168. Cover Letter
ML062650075
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 09/01/2006
From: James Trapp
Reactor Projects Region 1 Branch 4
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-06-014
Download: ML062650075 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ber 1, 2006

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - NRC INSPECTION REPORT 05000277/2006014 and 05000278/2006014

Dear Mr. Crane:

On August 11, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Peach Bottom Atomic Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results, which were discussed on August 11, 2006, with Mr. J. Armstrong and Mr. C. Wiedersum of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 and the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Safeguards information determination made WARNING: Violation of Section 147, by:

Safeguards Information, of the Name/Title Barry C.Westreich, Chief Atomic Agency Act is subject to civil Organization NSIR/DNS/SOS and criminal penalties. Basis 2/25/02 NRC Order Signature /RA/

Date 5/12/06 C. In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Sincerely,

/RA/

James M. Trapp, Chief Projects Branch 4 Division of Reactor Projects Docket No. 50-277, 50-278 License No. DPR-44. DPR-56 Enclosure: NRC Inspection Report 05000277/2006014 and 05000278/2006014 ( )

cc w/o encl:

R. Braun, Vice President Nuclear Oversight J. Grimes, Plant Manager J. Armstrong, Regulatory Assurance Manager cc w/encl; w/SGI: