IR 05000261/1992008

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/92-08 on 920406-10.No Violations Noted. Major Areas Inspected:Containment Integrated Leak Rate Testing Including Review of Associated Documents,Observation of Test Activities & Verification of Test Results
ML14178A217
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/05/1992
From: Jape F, Whitener H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A216 List:
References
50-261-92-08, 50-261-92-8, NUDOCS 9205270053
Download: ML14178A217 (10)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, ATLANTA, GEORGIA 30323 Report No.: 50-261/92-08 Licensee: Carolina Power and Light Company P. 0. Box 1551 Raleigh, NC 27602 Docket No.: 50-261 License No.: DPR-23 Facility Name: H. B. Robinson Inspection Conducted: April 6-10, 1992 Inspector:

6J/I

~.

- ?2 H. L. Whitener Date Signed Approved by:

'

F. Jape, Chief

/Date Signed Test Programs Section Engineering Branch Division of Reactor Safety SUMMARY Scope:

This routine, unannounced inspection was conducted in the areas of containment integrated leak rate testing including review of associated documents, observation of test activities, and verification of test result Results:

In the areas inspected, violations or deviations were not identifie The licensee performed an "as found" integrated leak rate test (ILRT) in conjunction with a containment building structural integrity test (SIT). Preliminary analysis show that test results for both the ILRT and SIT were within the specified acceptance limits. Personnel involved in these tests were knowledgeable of the test requirements. Detailed test procedures were followed and the tests were well

.

controlle PDR ADOCK 05000261 G

PDR

REPORT DETAILS Persons Contacted Licensee Employees J. Barry, SRO, Operations

  • D. Baur, Regulatory Compliance J. Bournes, Engineer, Technical Support R. Chambers, Plant General Manager G. Comer, Engineer, Technical Support
  • C. Dietz, Vice President, Robinson Nuclear Project Department D. Dyksterhouse, Engineer, NED
  • W. Farmer, Manager, Engineering Programs
  • W. Gainey, Manager, Plant Supports
  • M. Page, Manager, Technical Support
  • D. Stadler, Licensing Engineer, Nuclear Licensing
  • W. Worthington, Engineer, NED Other licensee employees contacted during this inspection included engineers, operators, technicians, and administrative personne Other Organizations General Physics Corporation Containment Leak Rate Consultants:

R. Carey

  • R. Shirk NRC Resident Inspector(s)
  • L. Garner, Senior Resident Inspector
  • C. Ogle, Resident Inspector

The inspector reviewed and witnessed test activities to determine that the primary containment integrated leak rate test was performed in accordance with the requirements of 10 CFR 50 Appendix J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors; ANSI-N45.4-1972, American National Standard Leakage - Rate Testing of

Containment Structures for Nuclear Reactors; BN-TOP-1, Revision 1 - 1972, Testing Criteria for Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants; and, test procedure EST-085, Containment Integrated Leak Rate Tes Selected sampling of the licensee's activities which were inspected included:

(1) review of the test procedures to verify that the procedures were properly approved and conformed with the regulatory requirements; (2) observation of test performance to determine that test prerequisites were completed, special equipment was installed, instrumentation was calibrated and appropriate data were recorded; and (3) preliminary evaluation of leakage rate test results to verify that leak rate limits were me Pertinent aspects are discussed in the following paragraph General Observations The inspector witnessed and reviewed portions of the test preparation, temperature stabilization and data processing during the period April 6-10, 1992. The inspector's observations included the following:

(1)

The test was conducted in accordance with an approved procedure. Procedure changes and test discrepancies were properly documented in the procedur (2)

Test prerequisites selected for review were found to be complete (3)

Selected plant systems required to maintain test control were found to be operationa (4)

Special test instrumentation was reviewed and found to be complete (5)

Controls for preventing pressurized air sources inside containment or externally pressurized penetrations were established in the test procedur (6)

Instructions and documentation for venting, draining, and isolation of systems were established in the test procedur (7)

Problems encountered during the test were described in the test event lo (8)

A containment temperature survey was previously performed to determine representative locations of instrument (9)

An in-situ check of CILRT instruments was performed prior to the tes (10)

Temperature, pressure, humidity, and flow data were recorded at 15-minute intervals. Data were assembled and retained for final evaluation and analysis by the licensee. A final leak rate test report will be submitted to the Office of Nuclear Reactor Regulation pursuant to Paragraph V of Appendix J to 10 CFR 5 Procedure Review (70307) Unit 2 Portions of EST-085, Containment Integrated Leak Rate Test, Revision 3, dated March 27, 1992, were reviewed to verify that test conditions, test controls, valve alignments, and acceptance criteria are specified. The inspector concluded that test conditions and controls were specified in detail in the text; valve alignments and valve restoration were specified in detail in attachments 9.2 and 9.8; system venting and draining were specified in detail in attachment 9.11; and, provisions were made for recording leakage of penetrations not in the required alignment and leakage correction due to repair or adjustment of leakage barriers in attachment 9.7. The procedure specifies the determination of the "as found" leak rate. However, in this case, the test was performed in the "as found" condition and correction of the measured leakage was not required. Detailed instrumentation information is provided in an associated procedure EST-09 Several temporary changes to the test procedure were reviewed to confirm that minor procedure changes to accommodate system conditions did not affect test leakage boundarie Penetration valve alignment for a limited selection of systems were reviewed against plant drawings to verify that correct alignments were specified. The penetrations reviewed included:

Penetration N Description

Pressurizer RLF Tank H2 Supply

Pressurizer RLF Tank Makeup-Primary Water

Penetration N Description (cont'd)

Primary SYS Vent HDR

Reactor Coolant Drain Tank Gas Analyzer

Drain HDR - Reactor Coolant Tank

Reactor Coolant SYS Sample Line (Pressurizer STM Sample)

Reactor Coolant SYS Sample Line (Pressurizer Liquid Sample)

Reactor Coolant SYS Sample Line (Loops 2 and 3)

Instr Air HDR

Accumulator Sample Line

Hydrogen Supply No problems were identified in the review of the above penetration valve alignment The inspector concluded that the integrated leak rate test procedure contains the required information and level of detail to adequately address regulatory requirement Containment Integrated Leak Rate Test (CILRT) Performance - Unit 2 (70313)

(1)

Method The integrated leak rate test was performed at the calculated accident pressure (Pa) by the absolute test metho Acceptance criteria were included in the test procedure for Mass Point, Total Time and Short Duration testing in accordance with the specifications of ANSI/ANS-56.8-1981,

"Containment System Leakage Testing Requirements"; ANSI N45.4-1972, "Leakage-Rate testing of Containment Structures for Nuclear Reactor"; and, BN-TOP-1, Revision 1-1972,

"Testing Criteria for Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants", respectivel The computer program for analysis of test data was provided by General Physics Corporation. The program included capability for analysis of test data according to the Mass Point, Total Time or Short Duration test methodologies. The test analysis was performed using the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Mass Point metho (2)

Description The licensee performed a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> test at 42 psig with hold points at 14, 21, 35 and 42 psig for collection of structural Integrity Test (SIT) dat Values bounding the test conditions were as follows:

Containment Volume 1950000 cubic feet Accident Pressure (Pa)

42 psig Maximum Allowable Leakage (La)

0.1 wt. percent per day System conditions for performance of the integrated leak rate test were as follows:

Reactor Vessel

-

Vented to containment atmosphere: water filled RHR System

-

One loop operating in the shutdown cooling mode Containment Ventilation

-

Fans tripped: No forced System air flow. Cooling water flow at 860 gp Containment Isolation

-

Vented, drained, and System aligned per procedure EST-08 The following Table gives a brief description of test sequence and events extracted from the test logboo Date -

Time Event 04/06/92 5:00 pm Final walkdown of containment followed by containment closeout and initial pressurizatio /07/92 9:00 am Start stabilization for SIT data collection at 14 psig platea :00 am Inboard purge exhaust valve leaking:

pressure between isolation valves is the same as containment: outboard purge valve not leakin :46 pm Secured pressurization at 21.5 psig plateau for collection of SIT data:

two minor leaks identified at WD1896 and FP 314: no repair mad /8/92 6:45 am Secured pressurization at 35 psig for SIT data collectio :30 am Start pressurization to 42 psig plateau (test pressure).

4:15 pm Pressurization secured: start minimum 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> stabilization at 42 psig platea :30 pm First data point for ILRT 4/9/92 2:58 pm Data collection for 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Mass Point ILRT in progress: dew cell #5 found to be erratic and eliminated:

Leak rates recalculated: additional minor leakages identified at WD 1787A, PAS-9, AND IA 3766: no repairs mad :30 pm Mass Point 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ILRT terminated:

Lam = 0.059 wt. percent per da :45 pm Supplemental test started

Date Time Event (cont'd)

4/10/92 3:45 am Supplemental test terminated:

LC = 0.156 wt. percent per da Test Analysis and Results (1)

Type A Test The Technical Specification for H.B. Robinson Unit 2 specifies the allowable containment leakage rate (La) as 0.1 wt. percent per day of the containment volume of 1,950,000 cu.f calculated for the accident pressure (Pa) of 42 psig. Therefore, the acceptance limit for the integrated leak rate (Type A) test of 0.75La is 0.075 wt. percent per da Analysis of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of data using the Mass Point methodology shows that the calculated leak rate using a linear regression technique was 0.0593 wt. percent per day with a 95 percent Upper Confidence Limit (UCL) of 0.0602 wt. percent per da No add-on leakage corrections were required. The resulting "as left" leakage rate of 0.0602 wt. percent per day for the 95 percent UCL meets the Appendix J Limit of 0.075 wt. percent per day. Total Time calculations for the calculated leak rate of 0.0564 wt. percent per day and a 95 percent UCL of 0.0644 wt. percent per day were in reasonable agreement with Mass Point Calculations. Also, the inspectors calculational checks were reasonably consistent with the licensees test result (2)

Supplemental Test Appendix J requires that a supplemental test be performed to verify the accuracy of the Type A test and the ability of the CILRT instrumentation to measure a change in leak rate. An acceptable supplemental test method is described in Appendix C of ANSI-N45.4-1972, as follows:

A know leak rate (Lo) is imposed on the containment and the measured composite leak rate (Lc) must equal, within

+ 0.25 La, the sum of the measured Type A leak rate (Lam) plus the known leak rate (Lo).

The acceptance criteria is expressed as:

Lo + Lam - 0.25 La < Lc < Lo + Lam + 0.25 La A four hour supplemental test was performed by the imposed leak rate method described in Appendix C to ANSI-N45.4-197 The following values in units of wt. percent per day were obtained using Mass Point analysi Mass Point (wt. percent per day)

Lam 0.0593 Lo 0.0996 0.25 La 0.025 Lc 0.1563 Using these values in the acceptance criteria yields the following:

0.133 < 0.1563 < 0.1839 Lc = 0.1563 satisfies the above inequality and therefore, the supplement test is acceptabl.

Status of Containment Leak Rate Testing This integrated leak rate test (ILRT) was performed as an "as found" ILRT and is also the "as left" ILRT. No repairs or adjustments were made to containment leakage barriers prior to the Type A test. The measured leak rate UCL of 0.0602 wt. percent per day satisfied both the "as found" leak rate limit of 0.1 wt. percent per day and the "as left" leak rate limit of 0.075 wt. percent per day. The inspector concluded that the licensee has demonstrated an acceptable containment leakag.

Structural Integrity Test The licensee performed a containment building structural integrity test in conjunction with the integrated leak rate test. SIT data was collected at pressure plateaus of 14, 21, 35 and 42 psig. The data collected and instrumentation used in this test was essentially the same as that used in the 1970 and 1974 tests to permit direct comparison to the earlier test results. Preliminary analysis of test results was as follows:

  • Deflection of Cylinder Acceptance criteria 1.62 inches Measured 0.8 inches Measured 1974 0.8 inches Vertical Elongation Acceptance criteria 0.175 inches Measured 0.13 inches maximum Measured 1974 0.138 inches maximum (Taunt wire device) Vertical Rise at Top of Dome Measured 0.25 inches Measured 1974 0.231 inches Crack Patterns (Same Areas as 1974)

Maximum observed 0.20 inches Maximum 1974 0.231 inches The licensee indicated that there appeared to be more cracks and cracks opened earlier but maximum gap was about the same as 197 Data collected from the IST will be analyzed in detail at the corporate offic.

Exit Interview The inspection scope and results were summarized on April 10, 1992, with those persons indicated in paragraph 1. The inspector described the areas inspected and discussed in detail the inspection result Proprietary information is not contained in this report. Dissenting comments were not received from the licensee.