Provides Response to NRC Comments on Plant Proposed Defueled Physical Security Plan.Response Withheld
ML20247B978
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 04/30/1998
From: Mellor R
CONNECTICUT YANKEE ATOMIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CY-98-074, CY-98-74, NUDOCS 9805110178
Download: ML20247B978 (2)


Text

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ -

i

\

SAFEGUARDS INFORMATION CONNECTICUT YANKEE ATOMIC POWER COMPANY l

HADDAM NECK PLANT 362 INJUN HOLLOW ROAD e EAST HAMPTON, CT 06424-3099 April 30,1998 Docket No. 50-213 CY-98-074 Re: 10CFR73.5 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Haddam Neck Plant Proposed Defueled Physical Security Plan Response To NRC Comments The purpose of this letter is for the Connecticut Yankee Atomic Power Company (CYAPCO) to provide the response to NRC comments on the Haddam Neck Plant (HNP) proposed Defueled Physical Security Plan.

CYAPCO submitted, to the NRC, the proposed Defueled Physical Security Plan on June 19,1997.W in a letter dated March 19,1998,(2) the NRC provided comments on CYAPCO's submittal. In discussions between the NRC Staff and CYAPCO personnel on April 16,1998 and April 21,1998, CYAPCO presented it's approach to resolve these comments and proposed additional changes that differed from the original submittal.

The enclosed information, documents the results of those discussions and the resolution of NRC comments.

9805110170 900430 PDR ADOCK 05000213 F PDR (1) CYAPCO Letter CY-97-071 from T. C. Feigenbaum to the U. S. Nuclear Regulatory Commission, " Physical Security Plan And Security Suitability, Training And Qualification Plan," dated June 19,1997.

(2) NRC Letter from A. E. Chaffee to R. A. Mellor, " Comments To The Haddam Neck Plant Defueled Physical Security Plan Submittal," dated March 19,1998.

' U G .n *

,. Enclosures to this coverletter contsln_ Safeguards Information.

Upon removal of enclosures, this coverIctteris decontroIIed.

IS$3 j/j/

1 I

I SAFEGUARDS INFORMATION U. S. Nuclear Regulatory Commission CY-98-074/Page 2 Enclosed with this letter are the following attachments:

Attachment 1 Response To NRC Comments, Attachment 2 Summary Of Changes To The Proposed Defueled Physical Security Plan, Attachment 3 Revised Proposed Defueled Physical Security Plan, and Attachment 4 Additional NRC Requested information.

I The enclosures to this cover letter contain Safeguards Information of a type specified in 10CFR73.21 and should be witheid from public disclosure. In accordance with ]

j 10CFR2.790, a copy of this cover letter, less enclosures, may be placed in the NRC 1 1

Public Document Room.

If the NRC Staff should have any questions regarding this submittal, please contact Mr. G. P. van Noordennen at (860) 267-3938.

Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY r \

&~ i J

R. A. Mellor Vice President - Operations and Decommissioning Attachments cc: H. J. Miller, NRC Region I Administrator T. L. Fredrichs, NRC Project Manager. Haddam Neck Plant W. J. Raymond, NRC Senior Resident inspector, Haddam Neck Plant Enclosures to this coverletter contain Safeauards Information, Upon removal of enclosures u this coverletteris decontmiled.