0CAN110203, October 2002 Monthly Operating Report for Arkansas Units 1 & 2

From kanterella
Jump to navigation Jump to search
October 2002 Monthly Operating Report for Arkansas Units 1 & 2
ML023260292
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 11/14/2002
From: Ashley G
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
0CAN110203
Download: ML023260292 (4)


Text

~ Entergy Entergy Operations, Inc.

1448 S R 333 Russellville, AR 72802 Tel 501 858 5000 OCAN110203 November 14, 2002 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Monthly Operating Report

Dear Sir or Madam:

Arkansas Nuclear One (ANO), Units 1 and 2 Technical Specifications 5.6.4 and 6.9.1.6, respectively, require the submittal of a Monthly Operating Report. The purpose of this letter is to complete the reporting requirement for October 2002.

Sincerely, Glenn R. Ashley Manager, Licensing GRA/SLP Attachment

-1ý-,94

OCAN1 10203 Page 2 cc: Mr. Ellis W. Merschoff Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. William D. Reckley Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission Attn: Mr. Thomas Alexion Washington, DC 20555-0001

OPERATING DATA REPORT DOCKET NO. 50-313 UNIT NAME Arkansas Nuclear One - Unit I DATE November 15, 2002 COMPLETED BY Steven L. Coffman TELEPHONE (479) 858-5560 REPORTING PERIOD: October 2002

1. Design Electrical Rating (MWe-Net): 850
2. Maximum Dependable Capacity (MWe-Net): 836 MONTH YR-TO-DATE CUMULATIVE
3. Number of Hours Reactor Was Critical 94.3 6,645.3 191,246.6
4. Number of Hours Generator On-Line 94.3 6,645.3 188,590.5
5. Unit Reserve Shutdown Hours 0.0 0.0 817.5
6. Net Electrical Energy Generated (MWh) 56,729 5,574,300 144,826,009 UNIT SHUTDOWNS Type Method F: Forced Duration of Cause & Corrective Action No. Date S: Scheduled (Hours) Reason' Shutting2 Comments Down 2002-01 021004 S 650.7 C 3 Automatic turbine/reactor trip due to turbine oil trip system malfunction I_ I_ I_ I I I began the 1R17 Refueling Outage

SUMMARY

The Unit began the month at -75% reactor power, with a reactor core coast down in progress.

On 10/04/2002, at 2119 hours0.0245 days <br />0.589 hours <br />0.0035 weeks <br />8.062795e-4 months <br />, a power reduction was commenced in preparation for a refueling outage. At 2215 hours0.0256 days <br />0.615 hours <br />0.00366 weeks <br />8.428075e-4 months <br /> that same day, the Unit automatically tripped off line from 42% reactor power while performing pre-outage testing of the Main turbine oil trip system. The 1RI 7 refueling outage commenced at this time.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

OPERATING DATA REPORT DOCKET NO. 50-368 UNIT NAME Arkansas Nuclear One - Unit 2 DATE November 15, 2002 COMPLETED BY Steven L. Coffman TELEPHONE (479) 858-5560 REPORTING PERIOD: October 2002

1. Design Electrical Rating (MWe-Net): 912
2. Maximum Dependable Capacity (MWe-Net): 858 MONTH YR-TO-DATE CUMULATIVE
3. Number of Hours Reactor Was Critical 745.0 6,794.4 160,427.7
4. Number of Hours Generator On-Line 745.0 6,772.4 157,908.9
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy Generated (MWh) 753,588 6,558,629 134,746,739 UNIT SHUTDOWNS Type Method F: Forced Duration of Cause & Corrective Action No. Date S: Scheduled (Hours) Reasoni Shutting 2

Comments Down None

SUMMARY

The Unit operated the entire month at full reactor power.

1 2 Reason: Method:

A Equipment Failure (Explain) I Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)