MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] Category:License-Monthly Operating Report
MONTHYEARML0517304622005-06-15015 June 2005 May 2005 Monthly Operating Report for Arkansas Nuclear One Units 1 and 2 0CAN050505, April 2005 Monthly Operating Report for Arkansas Nuclear One Units 1 & 22005-05-16016 May 2005 April 2005 Monthly Operating Report for Arkansas Nuclear One Units 1 & 2 0CAN040504, March 2005 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 22005-04-15015 April 2005 March 2005 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 ML0508202342005-03-15015 March 2005 February 2005 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 0CAN020504, January 2005 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 22005-02-15015 February 2005 January 2005 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 2 ML0502501742005-01-14014 January 2005 December 2004 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 2 ML0435501462004-12-15015 December 2004 November 2004 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 ML0432804032004-11-15015 November 2004 October 2004 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 2 0CAN100404, September 2004 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 22004-10-15015 October 2004 September 2004 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 2 0CAN090405, August 2004 Monthly Operating Report for Arkansas Nuclear One Units 1 and 22004-09-15015 September 2004 August 2004 Monthly Operating Report for Arkansas Nuclear One Units 1 and 2 0CAN080402, July 2004 Monthly Operating Report for Arkansas Nuclear One Units 1 and 22004-08-16016 August 2004 July 2004 Monthly Operating Report for Arkansas Nuclear One Units 1 and 2 ML0421000782004-07-15015 July 2004 June 2004 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 2 0CAN050403, April 2004 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 22004-05-13013 May 2004 April 2004 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 ML0411006372004-04-15015 April 2004 2004 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 2 0CAN030403, February 2004 Monthly Operating Report for Arkansas Units 1 and 22004-03-15015 March 2004 February 2004 Monthly Operating Report for Arkansas Units 1 and 2 0CAN020404, January 2004 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 22004-02-16016 February 2004 January 2004 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 2 0CAN010402, December 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 22004-01-15015 January 2004 December 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 ML0335102182003-12-15015 December 2003 November 2003 Monthly Operating Report for Arkansas Nuclear One (Ano), Units 1 and 2 0CAN110301, October 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 22003-11-17017 November 2003 October 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 2 0CAN100301, September 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 22003-10-15015 October 2003 September 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 2 0CAN090301, August 2003 Monthly Operating Report for Arkansas Nuclear, Units 1 and 22003-09-15015 September 2003 August 2003 Monthly Operating Report for Arkansas Nuclear, Units 1 and 2 ML0323302512003-08-15015 August 2003 July 2003 Monthly Operating Report for Arkansas Nuclear One 0CAN070303, June 2003 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 22003-07-15015 July 2003 June 2003 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 2 ML0317701562003-06-16016 June 2003 May 2003 Monthly Operating Report for Arkansas Nuclear One - Units 1 & 2 0CAN050301, April 2003 Monthly Operating Report for Arkansas Nuclear One Units 1 & 22003-05-15015 May 2003 April 2003 Monthly Operating Report for Arkansas Nuclear One Units 1 & 2 ML0310702682003-04-15015 April 2003 March 2003 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 2 ML0307803122003-03-14014 March 2003 February 2003 Monthly Operating Report for Arkansas, Units 1 & 2 ML0305102682003-02-14014 February 2003 January 2003 Monthly Operating Report for Arkansas Nuclear One - Units 1 & 2 ML0302301942003-01-15015 January 2003 December 2002 Monthly Operating Report for Arkansas Nuclear One - Units 1 & 2 0CAN120203, November 2002 Monthly Operating Report for Arkansas Nuclear One Units 1 & 22002-12-16016 December 2002 November 2002 Monthly Operating Report for Arkansas Nuclear One Units 1 & 2 0CAN110203, October 2002 Monthly Operating Report for Arkansas Units 1 & 22002-11-14014 November 2002 October 2002 Monthly Operating Report for Arkansas Units 1 & 2 0CAN010020, September 2002 Monthly Operating Report for Arkansas Nuclear One Units 1 & 22002-10-15015 October 2002 September 2002 Monthly Operating Report for Arkansas Nuclear One Units 1 & 2 0CAN009020, August 2002 Monthly Operating Report for Arkansas One Units 1 & 22002-09-16016 September 2002 August 2002 Monthly Operating Report for Arkansas One Units 1 & 2 ML0223206792002-08-15015 August 2002 July 2002 Monthly Operating Report for Arkansas Nuclear One 0CAN070202, June 2002 Monthly Operating Report for Arkansas Units 1 & 22002-07-15015 July 2002 June 2002 Monthly Operating Report for Arkansas Units 1 & 2 0CAN060205, May 2002 Monthly Operating Report for Arkansas Units 1 & 22002-06-12012 June 2002 May 2002 Monthly Operating Report for Arkansas Units 1 & 2 0CAN050205, April 2002 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 22002-05-15015 May 2002 April 2002 Monthly Operating Report for Arkansas Nuclear One - Units 1 and 2 0CAN040202, March 2002 Monthly Operating Report for Arkansas Nuclear One - Units 1 & 22002-04-15015 April 2002 March 2002 Monthly Operating Report for Arkansas Nuclear One - Units 1 & 2 0CAN030201, February 2002 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 22002-03-15015 March 2002 February 2002 Monthly Operating Report for Arkansas Nuclear One, Units 1 & 2 0CAN020201, January 2002 Monthly Operating Report for Arkansas Units 1 & 22002-02-15015 February 2002 January 2002 Monthly Operating Report for Arkansas Units 1 & 2 0CAN010201, December 2001 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 22002-01-15015 January 2002 December 2001 Monthly Operating Report for Arkansas Nuclear One, Units 1 and 2 2005-06-15
[Table view] |
Text
Entergy Operations, Inc.
Entergy 1448 S.R. 333 Russellville, AR 72802 Tel 501 858 5000 OCAN120301 December 15, 2003 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Monthly Operating Report Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
Dear Sir of Madam:
Arkansas Nuclear One (ANO), Units 1 and 2 Technical Specifications 5.6.4 and 6.9.1.6, respectively, require the submittal of a Monthly Operating Report. The purpose of this letter is to complete the reporting requirement for November 2003.
There are no new commitments contained in this submittal.
Sincerely, Glenn R. Ashley Manager, Licensing GRAISLP Attachment(s)
-15&." -2,
OCAN120301 Page 2 cc: Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. John Minns Mail Stop 0-7 D1 Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission Attn: Mr. Thomas Alexion Mail Stop 0-7 D1 Washington, DC 20555-0001
-- f OPERATING DATA REPORT DOCKET NO. 50-313 UNIT NAME Arkansas Nuclear 4:)ne -Unit I DATE December 15, 2003 COMPLETED BY Steven L. Coffman TELEPHONE (479) 858-5560 REPORTING PERIOD: November 2003
- 1. Design Electrical Rating (MWe-Net): 850
- 2. Maximum Dependable Capacity (MWe-Net): 836 MONTH YR-TO-DATE CUMULATIVE
- 3. Number of Hours Reactor Was Critical 341.1 7,604.0 200,045.5
- 4. Number of Hours Generator On-Line 341.1 7,565.7 197,331.4
- 5. Unit Reserve Shutdown Hours 0.0 0.0 817.5
- 6. Net Electrical Energy Generated (MWh) 290,374 6,381,316 152,201,653 UNIT SHUTDOWNS Type Method F: Forced Duration of Cause &
No. Date S: Scheduled (Hours) Reason' Shutting Corrective Action Down2 Comments 2003-02 031115 F 378.9 A I The Unit was manually shut down due to Main I___
__Transform
_ ___ ___ ___ ___ er problem s.
SUMMARY
- The Unit began the month at full power. On 11/15/2003, the Unit was manually shutdown because of potential problems discovered in the Main Transformers. The Unit ended the month in a forced shutdown to replace 2 of the 3 Main Transformers.
I 2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual TriplScram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
OPERATING DATA REPORT DOCKET NO. 50-368 UNIT NAME Arkansas Nuclear IOne - Unit 2 DATE December 15, 2003 COMPLETED BY Steven L. Coffman TELEPHONE (479) 858-5560 REPORTING PERIOD: November 2003
- 1. Design Electrical Rating (MWe-Net): 912
- 2. Maximum Dependable Capacity (MWe-Net): 858 MONTH YR-TO-DATE CUMULATIVE
- 3. Number of Hours Reactor Was Critical 720.0 7,543.7 169,417.6
- 4. Number of Hours Generator On-Line 720.0 7,523.0 166,864.5 S. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy Generated (MWh) 730,077 7,293,542.0 143,483,803 UNIT SHUTDOWNS Type Method F: Forced Duration of Cause & Corrective No. Date S: Scheduled (Hours) Reason' Shutting Action Down2 Comments None
SUMMARY
- The Unit operated the entire month at full power.
1 2 Reason: Method:
A Equipment Failure (Explain) I Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic TriplScram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)