Forwards Response to RAI Per 10CFR50.54(f) Re Adequacy & Availability of Design Bases Info
ML20136H103
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 03/11/1997
From: Reid D
VERMONT YANKEE NUCLEAR POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
BVY-97-34, NUDOCS 9703190052
Download: ML20136H103 (2)


Text

._ . _ . _ _ _ _ __ __ __.- . - _ - .._-__m . ---- .-

VEEMONT YANKEE NUCLEA,R POWER CORPORATION l

l .

--7 Ferry Road, Brattleboro, VT 05301-7002 ENGINE RIN OFFICE 580 MAIN STREET BOLTON MA 01740 l (508)779-6711 1

March 11,1997 BW 97-34 1

United States Nuclear Regulatory Commission ATTN: Document Control Desk l Washington, DC 20555

References:

(a) License No. DPR-28 (Docket No. 50-271) .;

(b) Letter, USNRC to VYNPC, NVY 96-158, dated October 9,1996 l I

' (c) Letter, VYNPC to USNRC, BW 97-23, dated February 14,1997 (d) Letter, USNRC to VYNPC, NW 97-23, dated February 28,1997

Subject:

Vermont Yankee Supplemental Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Adequacy and Availability of Design Bases Information In Reference (b) the NRC requested information regarding the adequacy and availability of design bases information. Among the information requested, the NRC asked Vermont Yankee to provide, if design review or reconstitution programs are being conducted, a description of the review program, including identification of Systems, Structures, and Components (SSCs) ,

and plant-level design attributes, and the review program implementation schedule. In Reference (c), Vermont Yankee provided the requested information, including a detailed description of our on-going Design Basis Document (DBD) Program. However, as noted in Reference (d), NRC has requested information on our implementation schedule. The purpose of this letter is to respond to that request.

Vermont Yankee is currently planning to develop and independently review 23 DBDs by the end of 1997. As described in Reference (c), each DBD will be issued once it has been '

approved. Validation of the DBDs will be performed after they are issued. The intent of the DBD validation is to provide reasonable assurance that design basis information is consistently kO

?

reflected in both the physical plant and in documents used to support plant operation (e.g.

operating, surveillance, test and emergency operating procedures). The validation process for all 23 DBDs is scheduled to be completed by October 1998.  %/g"t 9703190052 970311 DR ADOCK 050002 1 180124 uppappppppy

> 1

,t

  • VERMONT YANKEE NUCLEAR POWER CORPORATION United States Nuclear Regulatory Commission .

i March 11, 4997 l

Page 2 of 2 l

We trust that this submittal provides the requested information, However, should you have questions or require additional information, please contact this office.

I Sincerely, VERMONT YANKEE NUCLEAR POWER CORPORATION Donald A. Reid Vice President, Operations I

c: Director, Office of Nuclear Reactor Regulation l USNRC Region I Administrator USNRC Project Manager- VYNPS  ;%

USNRC Resident inspector- VYNPS . 4 C/qjgop .

j.

T ,

NDTARY y STATE OF VERMONT ) g pyggg g f

)ss -

WINDHAM COUNTY ). _g+f>.

Then personally appeared before me, Donald A Reid, who being duly sworn, did s hGQ)pi VicS ident, Operations, of Vermont Yankee Nuclear Power Corporation, that he is duty authorized execute omf* file the foregoing document in the name and on the behalf of Vermont Yankee Nuclear Power Corporation, and that the statements therein are true to the best of his knowledge and belief.

/M Sally A S(ndstrum, Notary Public My Commission Expires February 10,1999 l

l J

f