MONTHYEARIR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 IR 05000003/20230012023-05-22022 May 2023 Unions 1, 2 and 3 - NRC Inspection Report Nos. 05000003/2023001, 05000247/2023001, 05000286/2023001, and 07200051/2023001 IR 05000003/20234012023-05-10010 May 2023 NRC Security Decommissioning Inspection Report Nos. 05000003/2023401, 05000247/2023401, and 05000286/2023401 IR 05000003/20220042023-03-13013 March 2023 NRC Inspection Report Nos. 05000003/2022004, 05000247/2022004, 05000286/2022004, and 07200051/2022002 IR 05000003/20220022022-11-17017 November 2022 NRC Inspection Report Nos. 05000003/2022002, 05000003/2022003, 05000247/2022002, 05000247/2022003, 05000286/2022002, 05000286/2022003, and 07200051/2022001 IR 05000003/20224022022-10-28028 October 2022 Reissued NRC Security Decommissioning Inspection Report Nos. 05000003/2022402, 05000247/2022402, and 05000286/2022402 (Letter Only) IR 05000003/20224012022-05-25025 May 2022 NRC Security Decommissioning Inspection Report Nos. 05000003/2022401, 05000247/2022401, and 05000286/2022401 IR 05000003/20220012022-05-25025 May 2022 NRC Inspection Report Nos. 05000003/2022001, 05000247/2022001, and 05000286/2022001 IR 05000003/20210042022-03-0404 March 2022 NRC Inspection Report Nos. 05000003/2021004, 05000247/2021004, 05000286/2021004, and 07200051/2021001 IR 05000003/20210032021-11-0909 November 2021 NRC Inspection Report Nos. 05000003/2021003, 05000247/2021003, and 05000286/2021003 IR 05000003/20210022021-08-0404 August 2021 NRC Inspection Report Nos. 05000003/2021002, 05000247/2021002, and 05000286/2021002 IR 05000286/20210022021-06-0707 June 2021 Integrated Inspection Report 05000286/2021002 IR 05000286/20214022021-05-0505 May 2021 Security Baseline Inspection Report 05000286/2021402 IR 05000003/20210012021-04-21021 April 2021 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Units 1 and 2 - NRC Inspection Report No. 05000003/2021001 and 05000247/2020001 IR 05000286/20210012021-04-15015 April 2021 Integrated Inspection Report 05000286/2021001 IR 05000286/20200062021-03-0303 March 2021 Annual Assessment Letter for Indian Point Energy Center, Unit 3 (Report 05000286/2020006) IR 05000247/20200142021-02-0101 February 2021 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Unit 2 NRC Inspection Report No. 05000247/2020014 IR 05000286/20200042021-01-28028 January 2021 Integrated Inspection Report 05000286/2020004 IR 05000003/20200012020-12-0808 December 2020 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Units 1 and 2, NRC Inspection Report No. 05000003/2020001 and 05000247/2020013 IR 05000286/20200032020-10-28028 October 2020 Integrated Inspection Report 05000286/2020003 IR 05000286/20200102020-09-16016 September 2020 Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000286/2020010 IR 05000286/20200052020-08-31031 August 2020 Updated Inspection Plan for Indian Point Energy Center, Unit 3 (Inspection Report 05000286/2020005) IR 05000247/20200022020-08-10010 August 2020 Integrated Inspection Report 05000247/2020002 and 05000286/2020002 IR 05000286/20200122020-07-27027 July 2020 Design Basis Assurance Inspection (Programs) Inspection Report 05000286/2020012 IR 05000247/20020102020-05-12012 May 2020 Final ASP Analysis - Indian Point 2 (IR 050002472002010) IR 05000247/20200012020-04-29029 April 2020 Integrated Inspection Report 05000247/2020001 and 05000286/2020001 IR 05000247/20190062020-03-0303 March 2020 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Report 05000247/2019006 and 05000286/2019006) IR 05000247/20190042020-02-10010 February 2020 Integrated Inspection Report 05000247/2019004 and 05000286/2019004 IR 05000003/20190012020-01-16016 January 2020 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Unit 1 - NRC Inspection Report No. 05000003/2019001 IR 05000247/20190122020-01-0909 January 2020 Temporary Instruction 2515/194 Inspection Report 05000247/2019012 and 05000286/2019012 IR 05000247/20194112020-01-0909 January 2020 Material Control and Accounting Program Inspection Report 05000247/2019411 and 05000286/2019411 (Cover Letter Only) IR 05000247/20194032019-11-0505 November 2019 Cyber Security Inspection Report 05000247/2019403 and 05000286/2019403 (Cover Letter Only) IR 05000247/20190032019-11-0404 November 2019 Integrated Inspection Report 05000247/2019003 and 05000286/2019003 IR 05000247/20194102019-10-0202 October 2019 Security Inspection Report 05000247/2019410 and 05000286/2019410 (Cover Letter Only) IR 05000247/20190102019-09-26026 September 2019 Biennial Problem Identification and Resolution Inspection Report 05000247/2019010 and 05000286/2019010 IR 05000247/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000247/2019005 and 05000286/2019005) IR 05000247/20190022019-08-13013 August 2019 Integrated Inspection Report 05000247/2019002 and 05000286/2019002 IR 05000247/20190112019-07-0909 July 2019 Design Basis Assurance Inspection (Programs) Inspection Report 05000247/2019011 and 05000286/2019011 IR 05000247/20190012019-05-13013 May 2019 Integrated Inspection Report 05000247/2019001 and 05000286/2019001 ML19130A0422019-05-0808 May 2019 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000247/2019403 and 05000286/2019403 IR 05000247/20193012019-04-18018 April 2019 Initial Operator Licensing Examination Report 05000247/2019301 IR 05000247/20180062019-03-0404 March 2019 Annual Assessment Letter for Indian Point Energy Center, Units 2 and 3 (Reports 05000247/2018006 and 05000286/2018006) IR 05000247/20180042019-02-0707 February 2019 Integrated Inspection Report 05000247/2018004 and 05000286/2018004 IR 05000247/20180102019-01-15015 January 2019 Design Bases Assurance Inspection (Teams) Report 05000247/2018010 and 05000286/2018010 IR 05000247/20180022019-01-0909 January 2019 Errata for Indian Point Nuclear Generating - Integrated Inspection Report 05000247/2018002 and 05000286/2018002 IR 05000247/20184102018-12-0606 December 2018 Security Inspection Report 05000247/2018410 and 05000286/2018410 (Cover Letter Only) IR 05000247/20182012018-11-27027 November 2018 NRC Inspection Report 05000247/2018201 and 05000286/2018201 IR 05000247/20180032018-11-0808 November 2018 Integrated Inspection Report 05000247/2018003 and 05000286/2018003 IR 05000003/20180012018-10-25025 October 2018 Entergy Nuclear Operations, Inc., Indian Point Nuclear Generating Station Unit 1 - NRC Inspection Report No. 05000003/2018001 Dated October 25, 2018 2023-08-22
[Table view] Category:Letter
MONTHYEARML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks ML23235A0602023-07-17017 July 2023 LTR-23-0194 Dwaine Perry, Chief, Ramapo Munsee Nation, Ltr Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23194A0442023-07-11011 July 2023 Clarification for Indian Point Energy Center License Amendment Request, Independent Spent Fuel Storage Installation Physical Security Plan ML23192A1002023-07-11011 July 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme ML23171B0432023-06-23023 June 2023 Letter - Indian Point Energy Center - Request for Additional Information for Independent Spent Fuel Storage Installation Facility-Only Emergency Plan License Amendment ML23118A0972023-06-0606 June 2023 06-06-23 Letter to the Honorable Michael V. Lawler, Et Al., from Chair Hanson Regarding Holtec'S Announcement to Expedite Plans to Release Over 500,000 Gallons of Radioactive Wastewater from Indian Point Energy Center Into the Hudson River ML23144A3512023-05-25025 May 2023 Clementina Bartolotta of Pearl River, New York Email Against Treated Water Release from Indian Point Site ML23144A3522023-05-25025 May 2023 Loredana Bidmead of New York E-Mail Against Treated Water Release from Indian Point Site ML23144A3412023-05-25025 May 2023 Dianne Schirripa of Rockland County, New York Email Against Treated Water Release from Indian Point Site ML23144A3472023-05-25025 May 2023 David Mart of Blauvelt, New York Email Against Treated Water Release from Indian Point Site ML23144A3402023-05-25025 May 2023 Melvin Israel of New York Email Against Treated Water Release from Indian Point Site ML23144A3542023-05-25025 May 2023 Terri Thal of New City, New York Email Against Treated Water Release from Indian Point Site ML23144A3532023-05-25025 May 2023 John Shaw of New York Email Against Treated Water Release from Indian Point Site 2024-01-09
[Table view] |
Text
UNITED STATES r;--w NUCLEAR REGULATORY COIIIIiIISSION REGION I 21OO RENAISSANCE BOULEVARD, SUITE 1OO KING OF PRUSSIA, PENNSYLVANIA 1940&2713 November L6, ?812 Mr. John Ventosa, Site Vice President Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan. NY 1051 1-0249 SUBJECT: INDIAN POINT NUCLEAR GENERATING UNITS 2 AND 3 - NRC EVALUATED EMERGENCY PREPAREDNESS EXERCISE - INSPECTION REPORT NOS.
05000247 t2012503 AN D 050002861201 2503
Dear Mr. Ventosa:
On October 5,2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the October 2,2012, evaluated emergency preparedness exercise at your Indian Point Energy Center. The enclosed inspection report documents the inspection results, which were discussed on October 5,2012, with Mr. Slobodien, Entergy Director of Emergency Programs, and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-247, 50-286 License Nos. DPR-26. DPR 64
ML12324A016 g Non-sensitive g Publicly Available V suNslReview tr Sensitive n Non-PubliclyAvailable OFFICE RI/DRS RI/DRP RI/DRS NAME SBarr/DE for MGray ADimitriadis DATE 11t15t12 11115112 11116112
Enclosure:
NRC lnspection Report No. 0500024712012503 and 0500028612012503
REGION I Docket Nos.: 50-247,50-286 License Nos.: DPR-26, DPR-64 Report No.: 0500024712012503,05000286/2012503 Licensee: Entergy Nuclear Northeast (Entergy)
Facility: Indian Point Nuclear Generating Units 2 and 3 Location: 450 BroadwaY, GSB Buchanan, NY 1051 1-0249 Dates: October 1-5,2012 lnspectors: S. Barr, Sr. Emergency Preparedness Inspector, DRS, Region l (Lead)
C. Crisden, Emergency Preparedness Inspector, DRS, Region I S. McCarver, Project Engineer, DRP, Region I B. Scrabeck, Project Engineer, DRP, Region I Approved By: Anthony Dimitriadis, Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY OF FINDINGS
lR 0500024712012503, 05000286l2U25A3; rcl112012 - 101512012; lndian Point Units 2 and 3;
Exercise Evaluation ; Emergency Prepared ness Performance nd icators.
I This was an announced inspection conducted by four region-based inspectors. No findings were identified. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.
Gornerstone: Emergency Preparedness A. NRC-ldentified and Se[-Revealinq Findinqs No findings were identified.
B, Licensee-ldentified Findinos None.
REPORT DETAILS
1. REACTOR SAFEW
1EP1 Exercise Evaluation (71114.01 - 1 Sample)
a. Inspection Scope
Prior to the October 2,2012, emergency preparedness exercise, the NRC inspectors conducted an in-office review of the exercise objectives and scenario, which Entergy had submitted to the U.S. Nuclear Regulatory Commission (NRC), to determine if the exercise would test major elements of the Indian Point Energy Center Emergency Plan as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.47(bX14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The exercise evaluation consisted of the following review and assessment:
.
The adequacy of Entergy's performance in the biennial full-participation exercise regarding the implementation of the risk-significant planning standards (RSPS)described in 10 CFR 50.47(bX4), (5), (9), and (10), which are: emergency classification; offsite notiflcation; radiological assessment; and protective action recom mendations, resPectivelY.
.
The overall adequacy of Entergy's Indian Point emergency response facilities with regard to NUREG-0696, "Functional Criteria for Emergency Response Facilities,"
and Emergency Plan commitments. The facilities assessed were the Control Room Simulator, Technical Support Center (TSC), and Emergency Operations Facility (EoF).
o A review of other performance areas, such as: the licensee emergency response organization's (ERO's) recognition of abnormal plant conditions; command and control; intra- and inter-facility communications; prioritization of mitigating activities; utilization of repair and field monitoring teams; interface with offsite agencies; staffing and procedure adequacy; and the overall implementation of the emergency plan and its implementing procedures.
o A review of past performance issues from the last NRC Indian Point exercise inspection report and Entergy's EP drill reports, to determine the effectiveness of licensee corrective actions as demonstrated during the October 2,2Q12, exercise and to ensure compliance with 10 CFR 50.47(bX14).
o The licensee's post-exercise critiques, to evaluate Entergy's self-assessment of its ERO performance during the October 2,2012, exercise and to ensure compliance with 10 CFR Part 50, Appendix E, Section lV'F.2.9.
The inspectors reviewed the documents listed in the attachment to this report.
b. Findinqs No findings were identified,
4. OTHER ACTIVIflES (OA)
4OA1 Performance Indicator (Pl) Verification (71151- 3 Samples)
a. Inspection Scope
The inspectors reviewed data for the lndian Point EP Pls, which are:
- (1) Drill and Exercise Performance (DEP);
- (2) ERO Drill Participation; and, (3)Alert and Notification System (ANS) Reliability. The last NRC EP inspection at Indian Point was conducted in tl're third calendar quarter of 2011, so the inspectors reviewed supporting documentation from EP drills, training records, and equipment tests from the third calendar quarter of 2011 through the third quarter oI2Q12, to verify the accuracy of the reported Pl data.
The review of these Pls was conducted in accordance with NRC Inspection Procedure 71151, using the acceptance criteria documented in NEI 99-02, "Regulatory Assessment Performance Indicator Guidelines," Revision 6' This inspection activity represented the completion of three samples.
b. Findinqs No findings were identified.
4OAO Meetinqs, includinq Exit On October 5,2012, the inspectors presented the results of this inspection to Mr. M. Slobodien, Entergy Director of Emergency Programs, and other members of the Entergy staff. No proprietary information was provided to the inspectors during this inspection.
ATTACHMENT SUPPLEM ENTAL I NFORMATION KEY POINTS OF CONTACT Licensee Personnel M, Slobodien, Entergy Director of Emergency Programs M. Miele, Manager, Emergency Preparedness LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED None.
LIST OF
DOCUMENTS REVIEWED
Section 1EP1: Exercise Evaluation
Indian Point Energy Center Emergency Plan (Revision 11)
Indian Point Energy Center Emergency lmplementing Procedures
Indian Point Energy Center Emergency Plan Administrative Procedures
lndian Point October 2,2012, Emergency Exercise Scenario Package
lndian Point Emergency Preparedness Drill Reports, January 2011 - September 2012
lndian Point Energy Center Emergency Preparedness Unit 2 FEMA/NRC Exercise October 2,2012,
Performance Report (Drill Number 2012-5)
Section 4OA1 : Performance lndicator Verification
EN-EP-2O1, Performance Indicators (Revision 12)
ERO Drill Participation Pl Data, July 2011 - September 2012
Public Notification System Pl Data, July 2011 - September 2012
DEP Pl Data, July 2011 - September 2012
LIST OF ACRONYMS
ADAMS Agencywide Documents Access and Management System
ANS Alert Notification System
CR Condition Report
DEP Drill and Exercise Performance
EAL Emergency Action Level
EOF Emergency Operations Facility
EP Emergency Preparedness
ERO Emergency Response Organization
NEI Nuclear Energy Institute
NRC Nuclear Regulatory Commission
PAR Protective Action Recommendation
Pl Performance Indicator
RSPS Risk Significant Planning Standard
TSC Technical Support Center
Attachment