03/27/2017 Summary of Closed Meeting with Firstenergy Nuclear Operating Company Regarding Changes to the Davis-Besse Nuclear Power Station, Unit No. 1, Security Plan
ML17087A188
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/28/2017
From: Purnell B A
Plant Licensing Branch III
To:
FirstEnergy Nuclear Operating Co
Purnell B A, NRR/DORL/LPLIII, 415-1380
References
Download: ML17087A188 (3)


Text

LICENSEE: FIRSTENERGY NUCLEAR OPERATING COMPANY FACILITY: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1

SUBJECT:

SUMMARY OF MARCH 27, 2017, CLOSED MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY REGARDING CHANGES TO THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1, SECURITY PLAN On March 27, 2017, a closed meeting was held between U.S. Nuclear Regulatory Commission (NRC) staff and representatives of FirstEnergy Nuclear Operating Company (FENOC, the licensee) via teleconference. The purpose of the meeting was to discuss changes included in Revision 19 to the Davis-Besse Nuclear Power Station, Unit No. 1, security plan submitted by letter dated September 28, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16281A489). The meeting notice is available in ADAMS at Accession No. ML 17069A137, and a list of attendees is enclosed. No decisions were made at this meeting. The NRC staff noted that the licensee provided a detailed description of its early warning system, but the staff had a few questions about certain items which were not described. The staff also noted that the use of early warning systems at nuclear power plants had been discussed at a closed meeting with industry on August 31, 2016, and a related summary of questions and answers was developed (ADAMS Package Accession No. ML 16293A229). In addition, the staff also had questions regarding changes to the security force numbers. FENOC addressed the NRC staff's questions, but was unable to provide a detailed response over an unsecure telephone connection. Please direct any inquiries to me at 301-415-1380, or Blake.Purnell@nrc.gov. Docket No. 50-346

Enclosure:

List of Attendees cc w/encl: Listserv Sincerely, il;C Blake Purnell, Project Manager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Name B. Purnell D. Gordon J. Frost S. Sullivan J. Petrucelli D. Mills L. Willis E. Burnworth B. Jackway J. Hite B. Slvker G. Wolf LIST OF ATTENDEES MARCH 27, 2017, MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY Affiliation NRC/NRR NRC/NSIR NRC/NSIR NRC/NSIR NRC/NSIR NRC/Rlll FE NOC FE NOC FE NOC FE NOC FE NOC FE NOC Enclosure

SUBJECT:

SUMMARY OF MARCH 27, 2017, CLOSED MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY REGARDING CHANGES TO THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1, SECURITY PLAN DATED MARCH 28, 2017 DISTRIBUTION: PUBLIC LPL3 r/f RidsACRS_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl3 Resource RidsNrrPMDavisBesse Resource RidsNrrLASRohrer Resource RidsOpaMail Resource RidsRgn3MailCenter Resource TBriley, Riii ADAMS Accession No. ML 17087A188 DMills, Riii DGordon, NSIR DHuyck, NSIR ARivera, NSIR JFrost, NSIR FSullivan, NSIR JPetrucelli, NSIR TWertz, NRR JBowen, EDO Region Ill VMitlyng, OPA Region Ill OFFICE N RR/DORL/LPL3/PM N RR/DORL/LPL3/LA NRR/DORL/LPL3/BC NAME BPurnell SRohrer DWrona DATE 3/28/2017 3/28/2017 3/28/2017 OFFICIAL RECORD N RR/DORL/LPL3/PM BPurnell 3/28/2017