ML16253A341
Letter Sequence Acceptance Review | |
---|---|
CAC:MF8301, (Approved, Closed) | |
Initiation Administration Questions
| |
MONTHYEARJAFP-16-0136, Alternative Examination Requirements Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-2412016-08-24024 August 2016
[Table View]Alternative Examination Requirements Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-241 Project stage: Other ML16253A3412016-09-14014 September 2016 Acceptance of Requested Licensing Action Relief Request for Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-241 Project stage: Acceptance Review ML16334A4402016-12-0606 December 2016 Relief from the Requirements of the ASME Code Case N-702 and BWRVIP-241 for Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Project stage: Approval 2016-08-24 |
ML16253A341 | |
Person / Time | |
---|---|
Site: | FitzPatrick |
Issue date: | 09/14/2016 |
From: | Render D L Plant Licensing Branch 1 |
To: | Brian Sullivan Entergy Nuclear Operations |
Render D L | |
References | |
CAC MF8301 | |
Download: ML16253A341 (3) | |
Similar Documents at FitzPatrick | |
---|---|
Category:Acceptance Review Letter
MONTHYEARML23261C3982023-09-0808 September 2023
[Table view]Acceptance Review of Amendment to Update the Fuel Handling Accident Analysis ML23244A2662023-09-0101 September 2023 Acceptance of Requested Licensing Action Amendment Request to Modify Surveillance Requirement 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance ML23194A1822023-08-0303 August 2023 Acceptance Review for LAR Re SRM 3.3.1.2 ML22063A4742021-11-29029 November 2021 Acceptance of Requested Licensing Action License Amendment Request to Eliminate Selected Response Time Testing ML21246A2072021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21246A2142021-06-23023 June 2021 Acceptance of Requested Licensing Action Regarding License Amendment Request to Adopt TSTF-264 ML21077A1772021-04-0808 April 2021 Withdrawal of Requested Exemption from Certain Requirement in 10 CFR 50.55a (Epids L-2021-LLE-0014, 0015, & 0016) ML21056A1992021-03-0101 March 2021 Acceptance of Requested Licensing Action Amendment Request Revising Surveillance Requirement 3.5.1.6 Involving Recirculation Pump Discharge Valves ML20217L3882020-08-0404 August 2020 Acceptance of Requested Licensing Action License Amendment Request to Modify Primary Containment Isolation Valve TS (EPID L-2020-LLA-0145) (E-Mail) ML20204A9692020-07-22022 July 2020 Acceptance of Requested Licensing Action License Amendment Request to Adopt-TSTF-478 Revision 2 ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML18354A9602018-12-20020 December 2018 License Amendment Request for TS Change to Remove UHS Bar Rack Heaters ML18064A3252018-03-12012 March 2018 Acceptance of License Amendment Request to Revise Emergency Action Level Schemes Based on NEI 99-01, Revision 6 ML17004A1352017-01-0909 January 2017 Acceptance of Requested Licensing Action Cyber Security Implementation Schedule ML16270A0462016-10-0303 October 2016 Acceptance of Requested Licensing Action Relief Request for Proposed Alternative for the Implementation of BWRVIP-05 ML16266A4832016-10-0303 October 2016 Plan: Acceptance of Requested Licensing Action Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment ML16266A4172016-10-0303 October 2016 Acceptance of Requested Licensing Action Application for Order to Transfer Master Decommissioning Trust, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify And. ML16260A0172016-09-21021 September 2016 Acceptance of Requested Licensing Action Revision of Technical Specifications Section 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies Amendment ML16250A4612016-09-19019 September 2016 Request for Withholding Information from Public Disclosure for James A. FitzPatrick Nuclear Power Plant ML16253A3412016-09-14014 September 2016 Acceptance of Requested Licensing Action Relief Request for Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-241 ML1202607432012-01-26026 January 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Acceptance Review Email, Amendment to Revise Quality Assurance Program Manual and Staff Qualification Technical Speci ML1125504082011-09-12012 September 2011 ME6877, E-mail to Licensee, Acceptance of LAR Changes to the Licensing Basis, Authorizing the Use of on Load Tap Changers for Reserve Station Service Transformer ML1123601152011-08-24024 August 2011 ME6755, E-mail to Licensee for Acceptance Review Adoption of TSTF-425 Rev 3 ML12227A5692011-07-25025 July 2011 R.E. Fitzpatrick Nuclear Power Plant - Acceptance Review for Amendment Request for Approval of Cyber Security Plan Implementation Schedule ML1103500882011-02-0404 February 2011 ME5323, Acceptance of LAR Revision of License Condition 2C(3), Fire Protection Plan ML1021400902010-08-0202 August 2010 ME4267, Acknowledgment of Withdrawal of LAR Dated November 23, 2009, and Acceptance of Revised LAR Dated July 15, 2010 - Cyber Security Plan ML1019300082010-07-0909 July 2010 ME4124, Acceptance Review-Draft Requests for Information Required ML1013301712010-05-13013 May 2010 Acceptance Review for FitzPatrick TAC ME3786 ML1012004922010-04-30030 April 2010 Acceptance Review for FitzPatrick TAC No. ME3787 ML0935108212009-12-17017 December 2009 ME2809 & ME2810, Acceptance Review of License Amendment Requests SRV Testing and ASME Codes ML0931703722009-11-13013 November 2009 Acceptance Review of Entergy'S Request to Extend Orders (TAC ME1515 - ME2522) ML0914704832009-05-27027 May 2009 Acceptance Review for Entergy'S Request to Extend Effectiveness of July 28, 2008, Orders ML0913200592009-05-12012 May 2009 Entergy - Acceptance Review for License Amendment Request (TAC Nos. ME1198 - ME1207) 2023-09-08 Category:Code Relief or Alternative MONTHYEARML23278A1292023-12-14014 December 2023
[Table view]Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML21299A0032021-10-28028 October 2021 and Waterford Steam Electric Station, Unit 3 - Approval of Request for Alternative EN-20-RR-003 from Certain Requirements of the ASME Code ML21230A2062021-09-0303 September 2021 Proposed Alternative to Use ASME OM Code Case OMN-28 ML21216A2202021-08-0505 August 2021 Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20099D9552020-04-17017 April 2020 Request to Use Provisions in the 2013 Edition of the ASME Boiler and Pressure Vessel Code for Performing Non-Destructive Examinations ML19269C5342019-09-27027 September 2019 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML19135A4442019-06-21021 June 2019 Issuance of Relief Request I4R-22 Relief from the Requirements of the ASME Code ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19098A0342019-04-30030 April 2019 Units 1 and 2; Limerick, Units 1 and 2; Peach Bottom, Units 2 and 3, and Quad Cities, Units 1 and 2 - Revision to Approved Alternative to Use BWR Vessel and Internal Proj Guidelins JAFP-19-0023, Relief Request Associated with the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography for Ferritic and Austenitic Piping Welds2019-02-15015 February 2019 Relief Request Associated with the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography for Ferritic and Austenitic Piping Welds JAFP-18-0076, End of Interval Relief Request Associated with the Fourth Ten-Year Lnservice Inspection (ISI) Interval2018-07-26026 July 2018 End of Interval Relief Request Associated with the Fourth Ten-Year Lnservice Inspection (ISI) Interval ML18039A8542018-05-30030 May 2018 Relief Requests I5R-02, I5R-03, I5R-04 from ASME Code Requirements for Reactor Vessel Internals, Ferretic Piping Repair/Replacement, and RPV Flange Welds, 5th 10-Year Inservice Inspection Interval (MG0116-MG0118; L-2017-LLR-0083 to 0085) JAFP-18-0053, Proposed Alternative to Utilize Code Cases N-878 and N-8802018-05-30030 May 2018 Proposed Alternative to Utilize Code Cases N-878 and N-880 JAFP-18-0052, Proposed Alternative to Utilize Code Case N-8792018-05-30030 May 2018 Proposed Alternative to Utilize Code Case N-879 ML18044A9932018-04-13013 April 2018 Request for Alternatives PRR-01, PRR-02, PRR-04, VRR-02, VRR-03, and VRR-04 from ASME OM Code Requirements for Various Pumps and Valves, Fifth 10-Year Inservice Testing Interval (CAC MG0052-MG0061; EPID L-2017-LLR-0067 to L-2017-LLR-0074) ML17289A0752017-12-12012 December 2017 Issuance of Relief Request for Proposed Alternative to Use ASME Code Case N-789-1 (CAC No. MF9692; EPID L-2017-LLR-0027) Note Correction Safety Evaluation See ML18003B382 ML17219A4282017-12-11011 December 2017 Issuance of Relief Request-Alternative to Certain Requirements of the ASME Code Regarding Use of ASME Code Case N-513-4 (CAC No. MF9641; EPID L-2017-LLR-0023) ML17223A2802017-08-10010 August 2017 Submittal of Relief Requests Associated with the Fifth Lnservice Inspection (ISI) Interval ML17090A1682017-04-12012 April 2017 Alternative to ASME Code Requirements for Weld Overlay Repair ML16355A4292017-01-0606 January 2017 Relief Request for Proposed Alternative for the Implementation of BWRVIP-05 ML16334A4402016-12-0606 December 2016 Relief from the Requirements of the ASME Code Case N-702 and BWRVIP-241 for Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii ML16270A0462016-10-0303 October 2016 Acceptance of Requested Licensing Action Relief Request for Proposed Alternative for the Implementation of BWRVIP-05 ML16253A3412016-09-14014 September 2016 Acceptance of Requested Licensing Action Relief Request for Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-241 ML16180A2892016-06-29029 June 2016 Inservice Inspection Program Alternative for Safety Relief Valves ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16077A3522016-03-22022 March 2016 Withdrawal of Relief Request No. 19 from the Fourth Inservice Inspection Interval JAFP-15-0122, Withdrawal of Application for Alternative Examination Requirements for James A. FitzPatrick Nuclear Power Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-2412015-11-20020 November 2015 Withdrawal of Application for Alternative Examination Requirements for James A. FitzPatrick Nuclear Power Plant Nozzle-to-Vessel Welds and Nozzle Inner Radii Using ASME Code Case N-702 and BWRVIP-241 ML15230A3502015-08-18018 August 2015 J.A Fitzpatrick Nuclear Power Plant - Requests Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1), Implementation of BWRVIP-05 (GL 98-05) CNRO-2015-00017, Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, D2015-06-0505 June 2015 Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, Division ML12279A2482012-10-17017 October 2012 Issuance of Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code JAFP-11-0112, Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP2011-10-0303 October 2011 Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP ML0803902232008-03-13013 March 2008 Relief Request No. 5, Use of Performance Demonstration Initiative in Lieu of ASME Code Section XI, Appendix Viii, Supplement 11 Requirement ML0803003072008-02-28028 February 2008 Relief Request No. RR-6, Implementation of BWRVIP Guidelines in Lieu of ASME Section XI Code Requirements on Reactor Vessel Internals Components Inspection ML0803700802008-02-25025 February 2008 Relief Request No. 2 (RR-2) from the Requirements of American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Appendix Viii, Supplement 10 ML0804204272008-02-22022 February 2008 Relief Request No. 3 (RR-3) Risk-Informed Inservice Inservice Inspection Program ML0520700472005-08-0909 August 2005 Relief Request for Temporary Non-Code Repair of a Shutdown Cooling Pipe JAFP-05-0105, Request for Approval of Relief Request No. RR-38, Proposed Alternative to Perform a Temporary Non-Code Repair in Accordance with 10 CFR 50.55a(a)(3)(ii)2005-07-0909 July 2005 Request for Approval of Relief Request No. RR-38, Proposed Alternative to Perform a Temporary Non-Code Repair in Accordance with 10 CFR 50.55a(a)(3)(ii) ML0427406642004-10-14014 October 2004 Relief Request Nos. R-33, R-71, R 3-40(A) and R-41, James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Unit Nos. 2 and No. 3 and Pilgrim Nuclear Power Station ML0420301572004-07-20020 July 2004 Relief, Relief Request No. 30 for Third 10-Year Inservice Inspection (ISI) Program Interval ML0410700882004-07-0606 July 2004 Relief Request to Use American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) Case N-600 ML0417401842004-07-0606 July 2004 Relief Request, Nos. RR-34 and PRR for the Third 10-Year Inservice Inspection (ISI) Interval, MC1999 and MC2006 ML0405406932004-04-12012 April 2004 Relief Request Review, Relief Request VRR-08 Related to the Third 10-Year Inservice Testing (IST) Ubtervak JPN-03-020, Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-6002003-08-11011 August 2003 Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-600 JAFP-03-0111, Proposed Alternatives in Accordance with 10CFR50.55a(g)(6)(ii)(A)(5) and Relief from ASME Section XI Code Regarding Inspection of RPV Vertical Shell Welds Pursuant to 10 CFR 50.55a (g)(6)(i)2003-08-0404 August 2003 Proposed Alternatives in Accordance with 10CFR50.55a(g)(6)(ii)(A)(5) and Relief from ASME Section XI Code Regarding Inspection of RPV Vertical Shell Welds Pursuant to 10 CFR 50.55a (g)(6)(i) ML0306502552003-04-0101 April 2003 Relief Request Review, Third 10-Year Pump and Valve Inservice Testing Program, Revision of Relief Request VRR-04 ML0231804962002-11-14014 November 2002 Relief, Request for Relief No. RR-28 for the Third 10-Year Inservice Inspection Interval Program Plan for the FitzPatrick Power Plant JAFP-02-0194, Proposed Revision of Relief Request VRR-06 for In-Service Testing Program2002-09-30030 September 2002 Proposed Revision of Relief Request VRR-06 for In-Service Testing Program JPN-02-011, Request for Relief RR-29, Third 10-Year Inservice Inspection Interval Program Plan2002-05-0808 May 2002 Request for Relief RR-29, Third 10-Year Inservice Inspection Interval Program Plan JPN-02-010, Relief Request RR-28, Revision 1 for the Third 10-Year Inservice Inspection Interval Program Plan2002-05-0808 May 2002 Relief Request RR-28, Revision 1 for the Third 10-Year Inservice Inspection Interval Program Plan 2023-12-14 Category:Letter MONTHYEARIR 05000333/20230042024-02-0707 February 2024
[Table view]Integrated Inspection Report 05000333/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200012/2023001 ML24037A0102024-02-0606 February 2024 Requalification Program Inspection ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML24004A2302024-01-0808 January 2024 Project Manager Reassignment ML23356A0832024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0058 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines JAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20234012023-12-0808 December 2023 Cybersecurity Inspection Report 05000333/2023401 (Cover Letter Only) RS-23-126, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use IR 05000333/20230032023-11-13013 November 2023 Integrated Inspection Report 05000333/2023003 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000333/20230102023-10-26026 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000333/2023010 JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use IR 05000333/20233012023-10-19019 October 2023 Initial Operator Licensing Examination Report 05000333/2023301 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20230022023-08-0707 August 2023 Integrated Inspection Report 05000333/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance ML23208A1622023-07-27027 July 2023 Operator Licensing Examination Approval IR 05000333/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000333/2023402 IR 05000333/20230112023-07-25025 July 2023 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000333/2023011 IR 05000333/20235012023-07-20020 July 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000333/2023501 JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation IR 05000333/20234202023-06-26026 June 2023 Security Baseline Inspection Report 05000333 2023420 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report IR 05000333/20230012023-05-0303 May 2023 Integrated Inspection Report 05000333/2023001 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report IR 05000333/20230122023-04-13013 April 2023 Quadrennial Fire Protection Inspection Report 05000333/2023012 ML23095A3722023-04-0505 April 2023 2023 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000333/20220042023-03-20020 March 2023 Integrated Inspection Report 05000333/2022004 JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 2024-02-07 |
Text
Mr. Brian Sullivan Site Vice President UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 14, 2016 Entergy Nuclear Operations, Inc. James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 SUBJECT: JAMES A. FITZPATRICK NUCLEAR POWER PLANT-ACCEPTANCE OF REQUESTED LICENSING ACTION RE: RELIEF REQUEST FOR PLANT NOZZLE-TO-VESSEL WELDS AND NOZZLE INNER RADII USING ASME CODE CASE N-702 AND BWRVIP-241 (CAC NO. MF8301} Dear Mr. Sullivan: By application dated August 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16238A004}, Entergy Nuclear Operations, Inc., submitted a relief request for James A. FitzPatrick Nuclear Power Plant. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Pursuant to Section 50.55a(z)(1) of Title 1 O of the Code of Federal Regulations (1 O CFR), the applicant shall demonstrate that the proposed alternative would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety. The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
B. Sullivan -2 -If you have any questions, please contact me at (301) 415-3629. Docket No. 50-333 cc: Distribution via Listserv Diane Render, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation B. Sullivan -2 -If you have any questions, please contact me at (301) 415-3629. Docket No. 50-333 cc: Distribution via Listserv DISTRIBUTION: PUBLIC Branch Reading File RidsACRS_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlDpr Resource RidsNrrDorllpl1-1 Resource RidsNrrLAKGoldstein Resource RidsNrrPMFitzPatrick Resource RidsRgn1 MailCenter Resource Sincerely, /RAJ Diane Render, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation ADAMS Accession No. ML 16253A341 OFFICE LPL 1-1/PM LPL 1-1/LA LPL 1-1/BC LPL 1-1/PM NAME DRender KGoldstein TT ate DRender DATE 09/09/16 09/12/16 09/12/16 09/14/16 OFFICIAL RECORD COPY