Notice of Violation from Insp on 930606-0710.Violation Noted:Mut Hydrogen Regulator Adjusted W/O Required Safety Evaluation Being Performed
ML20056E986
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/09/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20056E984 List:
References
50-302-93-17, NUDOCS 9308250380
Download: ML20056E986 (1)


Text

_ . _ _ _ _ _ _ . _ _ _ _ _ _ - - . -

I i

ENCLOSURE 1 l NOTICE OF VIOLATION Florida Power Corporation Docket No. 50-302 l Crystal River Unit 3 License No. DPR-72 l During an NRC inspection conducted on June 6 - July 10,- 1993, violations of i NRC requirements were identified. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violations are listed below:

l 10 CFR 50.59(b)(1) requires that the licensee maintain records of l changes in the facility and of changes in procedures made pursuant to l this section, to the extent that these changes constitute changes is the ,

facility as described in the SAR.... These records must include a  !

written safety evaluation which provides the basis for the determination that the change, test, or experiment does not involve an unreviewed  ;

safety question.  !

l Contrary to the above, sometime prior to March 12, 1993, the MUT  ;

hydrogen regulator was adjusted, without the required safety evaluation '

performed, to greater than twenty pounds per square inch which is outside the required range of 5-15 pounds per square inch stated in FSAR, Section 9-1. The regulator remained improperly adjusted until June 28, 1993, when the licensee questioned the setting and returned the .

regulator to a setting of ten pounds per square inch. #

l This is a Severity Level IV Violation (Supplement 1).

Pursuant to the provisions of 10 CFR 2.201, Florida Power Corporation is hereby required to submit a written statement or explanation to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector, at the facility that is the subject of this Notice, '

within 30 days of the date of the letter transmitting this Notice of Violation -

(Notice). This reply should be clearly marked as a " Reply to a Notice of Violation" and should include for each violation: (1) the reason for the violation or, if contested, the basis for disputing the violation, (2) the ,

corrective steps that have been taken and the results achieved, (3) the i corrective steps that will be taken to avoid further violations, and (4) the ,

date when full compliance will be achieved. If an adequate reply is not l

! received within the time specified in this Notice, an order or demand for  ;

l information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be  ;

taken. Where good cause is shown, consideration will be given to extending l the response time. ,

i Dated at Atlanta, Georgia this 9th day of August 1993 l

93082503e0 930809  ??

PDR ADOCK 0S000302  !