ML22034A511

From kanterella
Revision as of 11:21, 2 September 2023 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
American Centrifuge Plant and American Centrifuge Lead Cascade Facility - Annual Brief Summary of Facility Changes
ML22034A511
Person / Time
Site: 07007003, 07007004
Issue date: 01/27/2022
From: Karen Fitch
American Centrifuge Operating
To:
Office of Nuclear Material Safety and Safeguards
References
ACO22-0002
Download: ML22034A511 (54)


Text

  • *********
/C8ntrus
  • : : ** * *
  • Fueling the Future
  • * *
  • of Nuclear Power January 27, 2022 ACO22-0002 ATTN: Document Control Desk Mr. John W. Lubinski, Director Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 A~erican Centrifuge Plant and American Centrifuge Lead Cascade Facility Docket Numbers 70-7004 and 70-7003; License Numbers SNM-2011 and SNM-7003 Annual Brief Summary of Facility Changes

Dear Mr. Lubinski:

In accordance with 10 Code ofFederal Regulations (CFR) 70. 72(d)(2) a>>d U.S. Nuclear Regulatory Commission Materials License Conditions 16.c.ii (SNM-7003) and 24.c.ii (SNM-2011 ), Amedcan Centrifuge Operating, LLC (ACO) hereby submits a brief summary of the changes required by 10

' CFR 70.62(a)(2) for facility changes made during calendar year 2021.

Enclosure 1 provides the summary of facility changes for both the American Centrifuge Lead Cascade Facility and American Centrifuge Plant. The non-consecutive change evaluation numbering in the enclosure is a result of cancelled evaluations.

If you have any questions regarding this matter, please cont~.ct me at (740) 897-3859.

Sincerely,

~/Ji{d Kelly L. Fitch Regulatory Manager

Enclosure:

As Stated cc:

Y. Faraz, NRC HQ N. Pitoniak, NRC Region II L. Pitts, NRC Region II J. Tobin, NRC HQ T. Vukovinsky, NRC Region JI R. Womack, NRC Region II American Centrifuge Operating, LLC 3930 U.S. Route 23 South - P.O. Box 628 Piketon, OH 45661

/

Enclosure 1 to ACO 22-0002 Brief Summary of Facility Changes for the American Centrifuge Lead Cascade Facility .

and American Centrifuge Plant for Calendar Year 2021 Information Contained Within Does Not Contain ExP,ort Controlled Information Reviewing Official: #1038, ACO Date: 1/27/22

2021 Brief Summary of Changes for the American Centrifuge Lead Cascade Facility (LCF) and American Centrifuge Plant (ACP)

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 20-0046

Title:

4/6/2021 Yes ESO-3100-0007 No None of the criteria l PCE 20-0063 Revision to Engineering Service Order (ESQ) ESO-3100-0007, Cascade ECR-3100-0007-02 Rev. 1 listed in 10 CFR Nitrogen and ECR-3100-0007-02 70.72(c) are met.

Description of Change:

Revised ESQ in accordance with Engineering Change Record (ECR) ECR-3100-0007-02 which provides for the design, procurement, and construction of a nitrogen system to support process needs of the HALEU Demonstration program. The scope of this ESQ includes equipment and supporting structures, from the bulk nitrogen storage tank located outside the X-3001 building to the process tie-in point near the cascade.

Reason for the Change:

Clarify engineering requirements.

FCE'?0-0050

Title:

3/31/2021 Yes ESO-3100-0005 No None of the criteria PCE 20-0067 Revision to Engineering Service Order ESO-3100-0005, HALEU Cold Box listed in 10 CFR IROFS Panel 70. 72(c) are met.

Description of Change:

Revised ESO to add Set Point Calculations SPC-3101-0001 and SPC-3101-0002; and drawings X-3001-9520-ME-Z and X-3001-9526-ME-Z to expand on the original focus of Items Relied On For Safety (IROFS) panel in Revision O of the ESO, to include other components of the Tails Cold Box IROFS.

Reason for the Change:

Clarify engineering requirements.

NRC Report 2021 Page 1 of 52

ISA FCE Number -- Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? _/

Due to Change Required? Required/Comments FCE 20-0071

Title:

1/21/2021 Yes ESO-3100-0022, CFC #1 and No None of the criteria PCE 20-0091 Revision to Engineeriog Service Order ESO-3100-0022, Criticality Accident CFC#2 listed in 10 CFR Alarm System (CAAS); Certified For Construction (CFC #1), Electrical and 70.72(c) are met.

Instrumentation & Controls (l&C); and CFC #2, Installation and Final Ties Description of Change:

ESQ CFC #1 implements the design, procurement, and partial installation of the CAAS. Revision 1 of this Change Evaluation adds scope from CFC

  1. 2, to include installation of system components, such as detectors, speakers, Noisy Area Warning Lights (NAWL), CAAS panels, Uninterruptible Power Supply (UPS) battery enclosure, wiring connections to components, and power feed conduit and wiring as detailed in Statement of Work (SOW) SOW-3101-0029 and supporting documents.

Reason for the Change:

ESQ CFC #2 design package includes a comprehensive Design Verification Matrix (DVM) listing design requirements invoked by applicable Codes and Standards, License Application documents, Nuclear Criticality Safety Evaluations (NCSEs), Configuration Management, and other regulatory requirements, along with detailed descriptions and ties to implementing documents.

FCE 21-0001 0

Title:

1m2021 No ACD2-QM-001 Chg. 33 No None of the criteria Revision to Procedure ACD2-QM-001, Management Assessment Program listed in 10 CFR PCE 21-0001 0 Description of Change:

= 70.72(c) are met.

Revised procedure during the p~riodic review to update titles and make changes to support required assessments for the HALEU Demonstration program.

Reason for the Change:

Clarify procedure req!Jirements.

FCE 21-0002 0

Title:

1/14/2021 No ACD2-MA-002 Chg. 23 No None of the criteria PCE 21-0002 0 Revision to Procedure ACD2-MA-002, Work Control Process listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to add steps to address work on exposed energized electrical circuits.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 2 of 52

/

ISA FCE Number PCE Number Rev. Approval I Change* Documents Modified Summary Update Reason NRC Preapproval Not Date I to SSC? Due to Change Required? Required/Comments FCE21-0004 0

Title:

1/11/2021 No AC4-A0-008 Chg. 4 No None of the criteria PCE 21-0004 0 Revision to Procedure AC4-AO-008, (U) AC100M/1007800 Centrifuge listed in 10 CFR Assembly Procedure 70.72(c) are met.

Description of Change:

Revised procedure to remove and add sections applicable to the current centrifuge design.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0004 1

Title:

2/25/2021 No AC4-A0-008 Chg. 4 No None of the criteria PCE 21-0004 1 Revision to Procedure AC4-AO-008, (U) AC100M/1007800 Centrifuge listed in 10 CFR Assembly Procedure 70.72(c) are met.

Description of Change:

Revised form AC-001, Change Evaluation, to change the answer to Question 2B to "NO" and subsequently removed the answers that are no longer required to be answered for Questions 2B i-v. No change to the previous procedure change 4 that was reviewed/approved by Revision 0 of this change evaluation.

Reason for the Change:

To correct the Change Evlaluation.

FCE 21-0006 0

Title:

1/19/2021 No AC4-AO-008 Chg. 6 No None of the criteria NIA Revision to Procedure AC4-AO-008, (U) AC-100M/1007800 Centrifuge listed in 10 CFR Assembly 70.72(c) are met.

Description of Change:

,Revised procedure to reword steps and revise leak checking section for clarification.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0007 0

Title:

312/2021 No ACD2-HP-013 Chg. 0 No None of the criteria PCE21-0006 0 New Procedure ACD2-HP-013, Radiation Protection Program Self- listed in 10 CFR Assessments 70.72(c) are met.

Description of Change:

New procedure has been developed to provide direction for scheduling, planning, and conducting Radiological Protection self-assessments at the ACP.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 3 of 52

ISA FCE Number Rev.

- I Approval Change Documents Modified Summary Reason NRC Preapproval Not PCE Number Update Date to SSC? Due to Change Required? Required/Comments FCE 21-0008 0

Title:

3/15/2021 No ACD3-EG-406 Chg. 7 No None of the criteria PCE 21-0007 0 Revision to Procedure ACD3-EG-406, IROFS Boundary Documentation listed in 10 CFR 70.72(c) are met.

De~cription of Change:

Revised procedure to align with the recent changes to the license application and supporting documents for the ACP to support the HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0009 0

Title:

1/28/2021 No ACD2-EG-007 Chg. 5 No None of the criteria PCE 21-0009 0 Revision to Procedure ACD2-EG-007, ISA Methodology and Change listed in 10 CFR Process 70.72(c) are met.

Description of Change:

Revised procedure to align with the recent changes to the license application and supporting documents for the ACP to support the HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0011 0

Title:

1/26/2021 No AC4-AO-008 Chg. 7 No None of the criteria NIA Revision to Procedure AC4-AO-008 (U), AC100M/1007800 Centrifuge listed in 10 CFR Assembly Procedure 70.72(c) are met.

Description of Change:

Revised procedure to add clarifications and move/reword steps.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0012 0

Title:

1/28/2021 Yes ESO-3100-0019 No None of the criteria PCE 21-0011 o_ Revision to Engineering Service Order ESO-3100-0019, Portable Pump listed in 10 CFR Down Cart Certified For Construction 70.72(c) are met.

Description of Change:

This ESQ includes portable carts used for handling UF6 in the HALEU cascade, including pump down cart, calibration cart, and gulper. The scope of this ESQ is focused on the design package for the portable pump down cart being prepared for release as CFC.

Reason for the Change:

Successful operati_on of the HALEU Demonstration cascade will require the use of of a pump down cart, calibration cart, and gulper to support various

/

plant functions.

NRC Report 1011 Page 4 of 52

ISA I FCENumber Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments I

FCE 21-0013 0

Title:

1/28/2021 No ACD4-OP-181 Chg. 1 No None of the criteria PCE21-0012 0 Revision to Procedure ACD4-0P-181, CTTF Drying Station Operation listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure due to material changes to valves, to clarify procedure requirements due to lessons learned and update the procedure based on multiple ECRs.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0015 0

Title:

2/23/2021 No ACD4-ON-008 Chg. 0 No None of the criteria PCE 21-0014 0 New Procedures ACD4-ON-008, Loss of Instrument Air (YA); ACD4-OP- ACD4-OP-055 Chg. 0 listed in 10 CFR 055, Centrifuge Disconnect; ACD4-OP-025, Centrifuge Connections; and ACD4-OP-025 Chg. 0 70.72(c) are met.

ACD4-OP-102, Evacuation Vacuum Operating Procedure ACD4-OP-102 Chg. 0 Description of Change:

Previously approved Lead Cascade procedures AC4-ON-008, AC4-OP-055, AC4-OP-025, and AC4-OP-102 are being revised for applicability and use under the HALEU Demonstartion program, and converted to new dual use ACD designated procedures.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process. and allows use under the HALEU Demonstartion program.

FCE 21-0016 0

Title:

2/9/2021 No ACD4-OP-181 Chg. 2 No None of the criteria PCE 21-0015 0 Revision to Procedure ACD4-OP-181, CTTF Drying Station Operation listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to address ECR changes and incorporate operational knowledge gained during startup, testing and operation of the Drying Station.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 5 of52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0017 0

Title:

2/24/2021 No AC4-AO-009 Chg. 4 No None of the criteria PCE 21-0016 0 Revision to Procedure AC4-AO-009, (U) AC100M/1007800 Centrifuge listed in 10 CFR Disassembly Procedure 70.72(c) are met.

Description of Change: -

Revised procedure to update references to the diffusion pump; add sections for heat shield and molecular pump removal; revise the Helium Leak Detector (HLD) section; and provided clarification/editorial corrections throughout.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0018 0

Title:

2/23/2021 No ACD2-QM-002 Chg. 17 No None of the criteria PCE 21-0017 0 Revision to Procedure ACD2-QM-002, Quality Assurance Independent listed in 10 CFR Audit and Assesment Program 70.72(c) are met.

Description of Change:

Revised procedure to perform periodic review, update titles, adjust the number of required assessments for HALEU Demonstration, and perform other minor updates.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0019 0

Title:

2/19/2021 No ACD4-OP-181 Chg. 3 No None of the criteria PCE 21-0018 0 Revision to Procedure ACD4-OP-181, CTTF Dryfng Station Operation listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to simplify the operation of the drying station and allow Operations personnel to utilize the Maintenance mode on the existing Programmable Logic Controller (PLC) to enhance pumpdown capabilities.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0021 0

Title:

2/18/2021 No AC4-AO-008 Chg. 11 No None of the criteria N/A Revision to Procedure AC4-AO-008, {U) AC100M/1007800 Centrifuge listed in 10 CFR Assembly Procedure 70.72(c) are met.

Description of Change:

Revised procedure to provide clarifications for HLD venting and disconnecting; rearrange/add steps for ease of use; and remove redundant recordings in the build book.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 6 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0022 0

Title:

3/3/2021 No ACD2-SH-028 Chg. 13 No None of the criteria PCE 21-0020 0 Revision to Procedure ACD2-SH-028, Welding, Burning, and Hot Work listed in 10 CFR Practices 70.72(c) are met.

Description of Change:

Revised procedure to update Fire Watch posting times and perform organizational title changes.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0023 0

Title:

3/3/2021 No JFl-2303-0036 Rev.a No None of the criteria PCE 21-0023 0 New Job Field Instruction (JFI) JFl-2303-0036, Removal of Weld listed in 10 CFR Protrusions from Casing Interior 70.72(c) are met.

Description of Change:

This JFI implements rework to remove several weld protrusions from the inside surface of a casing.

Reason for the Change:

This JFI was developed to correct an issue noted in Condition Notification

  1. 9712 which documented a casing found to have visible weld protrusions extending from the inside surface of the casing.

FCE 21-0024 0

Title:

5/20/2021 No ACD2-RG-001 Chg. 20 No None of the criteria PCE 21-0024 0 Revision to Procedures ACD2-RG-001, Change Evaluation; ACD2-RG-002, ACD2-RG-002 Chg. 11 listed in 10 CFR Application Change eontrol and License Amendment Request; and ACD2- ACD2-RG-003 Chg. 20 70.72(c) are met.

RG-003, Regulatory Communications Description of Change:

Revised procedures to update references, incorporate changes to various licensing documents, update forms and perform needed editorial changes.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0025 0

Title:

3/8/2021 No ACD2-SP-017 Chg. 23 No None of the criteria PCE 21-0025 0 Revision to Procedures ACD2-SP-017, Badge lssueNisitor Control ACD2-SP-034 Chg. 12 listed in 10 CFR Program; ACD2-SP-034, Portal Operations; ACD2-SP-044, Limiting ACD2-SP-044 Chg. 2 70.72(c) are met.

Access to Classified Information and Escorting; ACD2-SP-046, Security ACD2-SP-046 Chg. 2 Access Control and Alarm System; ACD3-SP-035, Security Inspections; ACD3-SP-035 Chg. 15 and ACD3-SP-036, Post Orders ACD3-SP-036 Chg. 16 Description of Change:

Revised procedures to address corrective actions as a part of Condition Notification #9691 and to clarify escorting responsibilities.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 7 of52

I I ISA FCENumber Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments I

FCE21-0026 0

Title:

5/19/2021 No LA-2605-0001 TOG, Sections No None of the criteria PCE 21-0027 0 Organizational Structure Changes 2.1, 2.1.1, 2.1.2, 2.1.2.1, listed in 10 CFR 2.12.1.1, 2.1.2.2, 2.1.2.3, 70.72(c) are met.

Description of Change: 2.1.2.3.4, 2.1.2.3.5, Changes were made to the American Centrifuge Operating (ACO), LLC 2.1.2.3.5.1, 2.1.2.4, 2.1.2.4.2, organization structure contained within the Lead Cascade and ACP license 2.1.2.4.3, 2.1.3, 2.1.3.1, 2.1.4,

, applications and supporting documents. 2.1.5, 2.1.6.1, 2.2.1. 4.2.

Reason for the Change: 4.2.1, 4.3, 5.2.1 and Figure These management organization and title changes were made to support 2.1-1 corporate initiatives. As activities and operations increase in support of the NR-2605-0003 Section 3.1 HALEU program and as Centrus continues to grow and plan for the future, LA-3605-0001 TOG, Sections management desires to align the organization structure with this future 2.1, 2.1.1, 2.1.2, 2.1.2.1, vision. 2.1.2.1.1, 2.1.2.2, 2.1.2.3, 2.1.2.3.3, 2.1.2.3.4, 2.1.2.3.5, 2.1.2.3.5.1, 2.1.2.3.4, 2.1.2.4, 2.1.2.4.2, 2.1.2.4.3, 2.1.3, 2.1.3.1, 2.1.4, 2.1.5, 2.1.6.1, 2.2.1, 4.2, 4.2.1, 4.3, 4.7.3, 5.2.1 and Figure 2.1-1 NR-3605-0005 Sections 3.1, 3.2.1, and Figure 3-1 NR-3605-0005A Sections 11.3, 11.3.2, 11.3.3; and

( 11.3.6 NR-3605-0005B Section 3.1 and Figure 3-1 NR-3605-0005C Sections 11.3.1, 11.3.2; and 11.3.3 NR-3605-0003 Section 3.1 SP-3605-0041 Sections 1.2.7 and 1.3 NR-3605-0008 Section 4.1 FCE 21-0027 0

Title:

3/16/2021 No ACD4-OP-181 Chg. 4 No None of the criteria PCE 21-0028 0 Revision to Procedure ACD4-OP-181, CTTF Drying Station Operation listed in 10 CFR Procedure 70.72(c) are met.

Description of Change:

Revised procedure to allow for additional manipulation of valves in drying mode and direct specific checks for Operations personnel throughout the extended drying process ..

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 8 of52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0028 0

Title:

3/25/2021 No ACD4-OP-101 Chg. 0 No None of the criteria PCE 21-0029 0 New Procedures ACD4-OP-101, Purge Vacuum Operating Procedure, and ACD4-OP-167 Chg. 0 listed in 10 CFR ACD4-OP-167, Operation of the Cascade 131 DCS 70.72(c) are met.

Description of Change:

Previously approved procedures AC4-OP-101 and AC4-OP-167 have been reformatted, updated, and are being transitioned to new ACD4 level procedures.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program.

FCE 21-0029 0

Title:

3/23/2021 No ACD2-PS-001 Chg. 17 No None of the criteria PCE 21-0031 0 Revision to Procedures ACD2-PS-001, Document Control Process, and ACD2-PS-002 Chg. 16 listed in 10 CFR ACD2-PS-002, Records Management Process 70.72(c) are met.

Description of Change:

Revised procedures to address eSignature Policy Changes and align the procedures with changes to the Quality Assurance Program Description. -

Reason for the Change:

Clarify procedure requirements.

FCE 21-0030 0

Title:

5/11/2021 No ACD2-RG-044 Chg. 17 No None of the criteria PCE 21-0035 0 Revision to Procedure ACD2-RG-044, Regulatory and Security Event listed in 10 CFR Notification and Reporting 70.72(c) are met.

Description of Change:

Revised procedure to add source references, update Appendix B reporting criteria, updates to the Plant Shift Superintendent (PSS) when reviewing Oak Ridge security issues flowdown, and formatting changes throughout the document.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0031 0

Title:

4/12/2021 No ACD4-OP-181 Chg. 6 No None of the criteria PCE 21-0037 0 Revision to Procedure ACD4-OP-181, CTTF Drying Station Operation listed in 10 CFR Procedure 70.72(c) are met.

Description of Change:

Revised procedure to clarify routine operations during Centrifuge drying and to perform minor formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 9 of 52

ISA Summary Reason NRC FCE Number -

Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0035 0

Title:

' 5/6/2 021 No ACD2-RG-004 Chg. 15 No None of the criteria PCE 21-0044 0 Revision to Procedure ACD2-RG-004, Corrective Action Process listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update references, provide clarifications, add corrections, and forrnatiing throughout the document.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0036 0

Title:

5/4/2 021 No ACD4-OP-003 Chg. 0 No None of the criteria PCE 21-0045 0 New Procedures ACD4-OP-003, Machine Cooling Water Normal ACD4-OP-079 Chg. 0 listed in 10 CFR Operations; ACD4-OP-079, MDU Operations; ACD4-OP-006, Vacuum ACD4-ON-015 Chg. 0 70.72(c) are met.

,_ Cooling Water; ACD4-OP-073, Nitrogen System Operations; ACD4-ON- ACD4-OP-006 Chg. 0 015, Complete Loss of PV; and ACP4-OP-178, Cascade 131 Charging with ACD4-OP-073 Chg. 0 UF6 ACD4-OP-178, Chg. 0 Description of Change:

Previously approved Lead Cascade procedures AC4-OP-003, AC4-OP-079, and AC4-ON-015, were converted new dual use. New procedure ACD4-OP-006 provides guidance on operation of the Vacuum Cooling Water ,YCW) system. New procedure ACD4-OP-073 provides guidance on the nitrogen system operations. New procedure ACP4-OP-178 provides guidance on charging cascade 131 with UF6.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program.

FCE21-0037 0

Title:

6/3/2 021 No ACP2-OP-037 Chg. 0 No None of the criteria PCE21-0046 0 New Procedure ACP2-OP-037, Requirements For Use of Service Carts listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure was developed to provide the Nuclear Criticality Safety (NCS) requirements for Service Carts which includes Calibration Carts, Pumpdown Carts, and HLD Carts.

Reason for the Change:

Provide implementation requirements.

~

- NRC Report 2021 Page 10 of 52

_J

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0038 0

Title:

5/24/2021 No ACD4-OP-112 Chg. 2 No None of the criteria PCE 21-0047 0 Revision to Procedure ACD4-0P-112, X-3012 ASG listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to correct valve alignments in section 7.9, frequency setpoint in step 7.3.4, add a caution box prior to opening PSB-ASG-W2RE1, and other editorial corrections.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0039 0

Title:

5/11/2021 No ACD2-SP-047 Chg. 0 No None of the criteria PCE21-0048 0 New Procedure ACD2-SP-047, Classified Matter Sanitization listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides instructions for the sanitization of various types of classified matter to ensure the adequate disposal and prevention of unauthorized access to classified matter.,

Reason for the Change:

Provide implementation requirements.

FCE21-0040 0

Title:

5/20/2021 No ACP2-CM-001 Chg. 0 No None of the criteria PCE21-0051 0 New Procedure ACP2-CM-001, Chemical Trap Media Change listed in 10 CFR 70.72(c) are met.

Description of Change:

Previously approved Lead Cascade procedure AC4-CM-001 was converted to procedure ACP2-CM-001, Chemical Trap Change for use under the ACP license.

Reason for the Change:

Conversion of procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program.

FCE 21-0041 0

Title:

5/20/2021 Yes ESO-3100-0005 No None of the criteria PCE21-0053 0 Revision to Engineering Service Order ESO-3100-0005/ECR-3100-0005- ECR-3100-0005-60 Rev. 0 listed in 10 CFR 60, change to the installation of a Residual Gas Analyzer (RGA) 70.72(c) are met.

Description of Change:

  • ESO-3100-0005/ECR-3100-0005-60 proposed a change for installation of a Residual Gas Analyzer (RGA).

Reason for the Change:

RGA is required to analyze gas samples.

NRC Report 2021 Page 11 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0042 0

Title:

6/22/2021 No ACP2-CM-002 Chg. 0 No None of the criteria PCE 21-0055 0 New Procedure ACP2-CM-002, Removal, Handling, and Storage of listed in 10 CFR Uranium Contaminated Process Equipment 70.72(c) are met.

Description of Change:

New procedure provides guidance on the removal, handling, and storage of used contaminated process equipment under the ACP license.

Reason for the Change:

Provide implementation requirements.

FCE 21-0044 0

Title:

6/3/2021 No ACD4-AR-103 Chg. 0 No None of the criteria PCE21-0058 0 New Procedures ACD4-AR-103, Evacuation Vacuum System Alarms and ACD4-AR-104 Chg. 0 listed in 10 CFR Responses; ACD4-AR-104, Purge Vacuum System Alarms and ACD4-ON-004 Chg. 0 70.72(c) are met.

Responses; ACD4-ON-004, Loss of Machine Cooling Water; ACD3-FO- ACD3-FO-002 Chg. 0 002, Out of Service/Inoperable IROFS System, Structure, and Component ACD4-ON-218 Chg. 0 Tracking; and New Procedure ACD4-ON-218, Loss of Vacuum Cooling Water Description of Change:

Previously approved Lead Cascade procedures AC4-AR-103, AC4-AR-104, AC4-ON-004 and AC3-FO-002 have been transitioned to dual use under the ACP plant license. New procedure ACD4-ON-218 was developed to provide off normal responses to a loss of Vacuum Cooling Water.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure _change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program. New procedure ACD4-ON-218 provides implementation requirements.

FCE 21-0046 0

Title:

6/14/2021 No ACD2-RG-044 Chg. 18 No None of the criteria PCE 21-0060 0 Revision to Procedure ACD2-RG-044, Regulatory and Security Event listed in 10 CFR Notification and Reporting 70.72(c) are met.

Desc'ription of Change:

Revised procedure to add a commitment reference and update appendix B reporting criteria.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 12 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update, Preapproval Not PCENumber Date to SSC? Due to Change Required? Required/Comments FCE 21-0047 0

Title:

5/25/2021 No ACD3-EG-203 Chg. 9 No None of the criteria PCE 21-0061 0 Revision to Procedure ACD3-EG-203, Engineering Drawing Controls listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update references and instructions and make various grammar and punctuation corrections throughout the procedure.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0048 0

Title:

6/10/2021 No ACD4-ON-001 Chg. 0 No None of the criteria PCE 21-0062 New Procedures ACD4-ON-001, Post Wreck Centrifuge Operations, and ACD3-OP-003 Chg. 0 listed in 10 CFR 0

ACD3-OP-003, Post Wreck Operations 70.72(c) are met.

Description of Change:

Previously approved Lead Cascade procedures AC4-ON-001 and AC3-OP-003 have been revised to support the HALEU Demonstration program and converted to new dual use procedures.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program.

FCE 21-0049 0

Title:

6/10/2021 No ACD2-TP-001 Chg. 22 No None of the criteria PCE 21-0063 0 Revision to Procedure ACD2-TP-001, Procedure Process listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to eliminate the use of the specific designator "ACP" for Commercial Plant forms and utilize the designator "AC" for all form numbers.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0050 0

Title:

6/16/2021 No ACD4-SP-009 Chg. 0 No None of the criteria PCE21-0064 0 New Procedures ACD4-SP-009, Special Nuclear Material Post Orders, and ACD2-SP-037 Chg. 0 listed in 10 CFR ACD2-SP-037, Operations & Maintenance Activities Regarding Protection_ 70.72(c) are met.

of Special Nuclear Material Description of Change:

New procedures have been developed to identify specific requirements and duties by Protective Personnel, Central Alarm Station, Operations personnel, and Maintenance personnel.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 13 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0052 0

Title:

6/28/2021 No ACD2-MA-002 Chg. 25 No None of the criteria PCE 21-0077 0 Revision to Procedure ACD2-MA-002, Work Control Process listed in 10 CFR i0.72(c) are met.

Description of Change:

Revised procedure to provide additional information for identifying, scheduling, planning, and implementing maintenance and modification activities performed at the ACP and for HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE21-0053 0

Title:

7/1/2021 No ACD2-MA-001 Chg. 12 'No None of the criteria PCE 21-0078

  • 0 Revision to Procedure ACD2-MA-001, Control of Measuring and Test listed in 10 CFR Equipment 70.72(c) are met.

Description of Change:

Revised procedure to provide updates for procedure use with the HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0054 0

Title:

7/21/2021 No ACD2-PM-001 Chg. 12 No None of the criteria PCE 21-0079 0 Revision to Procedure ACD2-PM-001, Preventive Maintenance Program listed in 10 CFR 70.72{c) are met.

Description of Change: .

\

Revised procedure to provide updates for procedure use with the HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0055 0

Title:

7/19/2021 No ACD4-PM-001 Chg. 7 No None of the criteria PCE 21-0080 Revision to Procedure ACD4-PM-001, Crane and Hoist Preventative listed in 10 CFR 0

Maintenance 70.72(c) are met.

Description of Change:

Revised procedure to provide updates for procedure use with the HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 14 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0056 0

Title:

6/28/2021 No ACP4-OP-178 Chg. 1 No None of the criteria PCE 21-0193 0 Revision to Procedure ACP4-OP-178, Cascade 131 Charging with UF6 listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to clarify additional NCS requirements and ensure the procedure aligns with operation of the DCS.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0057 0

Title:

7/1/2021 No ACD4-OP-024 Chg. 0 No None of the criteria PCE 21-0081 0 New Procedures ACD4-OP-024, Centrifuge Pumpdown, and ACP2-OP- ACP2-OP-217 Chg. 0 listed in 10 CFR 217, Operation of the CAAS 70.72(c) are met. -

Description of Change:

Previously approved Lead Cascade procedure AC4-OP-024 was converted to a new dual use and revised for specific HALEU Demonstration program use. New procedure ACP2-OP-217 provides guidance for CAAS operations.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requir~ments of ACD2-TP-001, Procedure Process, and allows use under the HALE!-) Demonstration program. ACP2-OP-217 was developed to provide implementation requirements.

F;CE 21-0058 0

Title:

7/28/2021 No ACP2-CM-004 Chg. 0 No None of the criteria PCE 21-0084 0 New Procedure ACP2-CM-004, Field Decontamination listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides guidance and direction for performing field decontamination activities performed at the ACP and for HALEU Demonstration program.

Reason for the Change:

Provide Implementation requirements.

FCE 21-0059 0

Title:

7/20/2021 No ACD2-RG-004 Chg. 17 No None of the criteria PCE 21-0085 o' Revision to Procedure ACD2-RG-004, Corrective Action Process listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to add guidance on tracking Initiating Events; update verbage for NCS and Security realted issues; and add additional Use and Source References.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 15 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0060 0

Title:

7/22/2021 No ACD2-MA-003 Chg. 9 No None of the criteria PCE 21-0089 0 Revision to Procedure ACD2-MA-003, Calibration Program listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to provide specific implementation guidance and requirements for controlling the Calibration Program at the ACP and for HALEU Demonstration program.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0061 0

Title:

7/21/2021 No ACD4-ON-073 Chg. 0 No None of the criteria PCE 21-0090 0 New Procedures ACD4-ON-073, Loss of Nitrogen, and ACP4-OP-173, ACP4-OP-173 Chg. 0 listed in 10 CFR Cascade 131 Operations 70.72(c) are met.

Description of Change:

Previously approved Lead Cascade procedure AC4-OP-173 was converted to a new ACP use and revised for specific HALEU Demonstration program use. New procedure ACD4-ON-073 provides guidance for Off-Normal events for Loss of the Nitrogen System.

Reason for the Change:

Conversion of Operations procedures to the ACP use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program. ACD4-ON-073 was developed to provide implementation requirements.

FCE21-0062 0

Title:

7/21/2021 No ACD3-EG-103 Chg. 6 No None of the criteria PCE 21-0091 0 Revision to Procedure ACD3-EG-103, Engineering Software Controls listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to remove references to the Lead Cascade, update/align with Material License Condition 19 requirements approved under Engineering Evaluation EE-3901-0077 Revision 2, and add clarification/guidance for DCS software changes.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 16 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0063 0

Title:

- 7/15/2021 No ACD2-FO-003 Chg. 1 No None of the criteria PCE21-0093 0 Revision to Procedure ACD2-FO-003, Vehicle Control Within ACP Facilities listed in 10 CFR

70. 72(c) are met.

Description of Change:

Revised procedure to include new Integrated Safety Analysis (ISA) language on the use of fossil-fueled vehicles in the X-3001 Process Building and other ACP facilities.

Reason for the Change:

Provide implementation requirements.

FCE 21-0064 0

Title:

9/3/2021 No ACD2-MM-001 Chg_ 17 No None of the criteria*

PCE 21-0095 0 Revision to Procedure ACD2-MM-001, Control of Material listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to remove references to the Lead Cascade, Radioactive Material Receipt, and handling and delivery of demobilization inventory.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0065 0

Title:

8/3/2021 No ACP4-ON-006 Chg. 0 No None of the criteria PCE 21-0098 0 New Procedures ACP4-ON-006, MDU Replacement at an Operating ACP4-OP-049 Chg. 0 listed in 10 CFR Position; ACP4-OP-049, Centrifuge Acceleration and Deceleration; ACP4- ACP4-OP-051 Chg. 0 70. 72(c) are met.

OP-051, Inventory Removal; and ACD4-OP-060, Helium Leak Detector ACD4-OP-060 Chg. 0 Description of Change:

New procedure ACP4-ON-006 provides guidance for,MDU Replacement at an Operating Position. New procedure ACP4-OP-049 provides guidance for Centrifuge Acceleration and Deceleration. New procedure ACP4-OP-051 provides guidance for Removing Centrifuge Inventory. New procedure ACD4-OP-060 provides guidance for operating the Varian Model 959 Helium Leak Detector.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 17 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0066 0

Title:

12/16/2021 No JFI-DE-2021-0001 Rev. 0 No None of the criteria PCE 21-0103 0 X-5000 Transfer Trip Tone Equipment Conversion to Fiber Optic 1/0 JFI-DE-2021-0002"Rev. 0 listed in 10 CFR Modules and Cables JFI-DE-2021-0003 (FBP) 70.72(c) are met.

Rev. 0 Description of Change:

The change being performed is to disconnect the existing transfer trip Tone Equipment and signal cabling between the X-5001 Substation and X530A Switchyard and install new Fiber Optic Input/Output Modules and new fiber optic cabling using Job Field Instructions (JFI) for Lines 501 (JFI-DE-2021-0003), 502 (JFI-DE-2021-0001), and 503 (JFI-DE-2021-0002).

Reason for the Change:

The X-5000, Transfer Trip equipment functions as a means of electrical signal communication between the X-5001 Substation and X-530A switchyard. The original routing of the transfer trip signal cable is via an instrument duct-bank that runs through the DOE/Fluor-BWXT Portsmouth (FBP) "5-Unit" Plume. FBP site decommissioning activities will excavate the instrument duct-bank and thus the existing connections will be removed requiring a change to the routing and equipment.

The original routing of the transfer trip signal cable is via an instrument duct-bank that runs through the DOE/FBP "5-Unit" Plume. FBP site decommissioning activities will excavate the instrument duct-bank and thus the existing connections will be removed requiring a change to the routing and equipment. Therefore, the original tone function cabling and components are being replaced-with up-to-date current technology Fiber-Optic Transfer Tone Trip equipment.

FCE 21-0067 0

Title:

8/4/2021 No ACD4-OP-006 Chg. 1 No None of the criteria PCE 21-0104 0 Revision to Procedure ACD4-OP-006, Vacuum Cooling Water Normal listed in 10 CFR Operations 70.72(c) are met.

Description of Change:

Revised procedure to reflect operations based on current plans, update pump flow rates, and add a step to check for leaks.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 18 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0068 0

Title:

8/11/2021 No ACP2-ON-217 Chg. 0 No None of the criteria PCE 21-0105 0 New Procedures ACP2-ON-217, CAAS Off-Normal Operations; ACP2-AR- ACP2-AR-217 Chg. 0 listed in 10 CFR 217, CAAS Alarm Response; ACP4-ON-102, Loss of Evacuation Vacuum; ACP4-ON-102 Chg. 0 70.72(c) are met.

ACD2-OP-057, Machine Position Requalification; and ACD2-OP-033, ACD2-OP-057 Chg. 0 Operation of the Portable Mini-Gulper ACD2-OP-033 Chg. 0 Description of Change:

New procedures ACP2-ON-217 provides off-normal instructions for the CAAS. New procedure ACP2-AR-217 provides CAAS system alarm responses. New procedure ACP4-ON-102 provides off normal responses to a loss of the Evacuation Vacuum system. Previously approved Lead Cascade procedure AC2-OP-057 was converted and updated to new dual use ACD2-OP-057 for Machine Position Requalification and AC2-OP-033 was converted and updated to new dual use ACD2-OP-033 for Operation of the Portable Mini-Gulper.

Reason for the Change:

Clarify procedure requirements.

FCE21-0069 0

Title:

8/9/2021 No ACD4-OP-110 Chg. 1 No None of the criteria PCE 21-0106 0 Revision to Procedure ACD4-OP-110, X-3001 Trains 2, 3, 4, & X-3012 listed in 10 CFR Auxiliary Power Substations 70.72(c) are met Description of Change:

Revised procedure to provide editorial updates; revise steps in the procedure and the Divided Fuse Location Appendix as an error reduction effort; and add notes allowing SYNC MODE operations to be marked as NIA Reason for the Change:

Clarify procedure requirements.

FCE 21-0070 0

Title:

9/9/2021 No ACP3..ST-001 Chg. 0 No None of the criteria PCE 21-0107 0 New Procedure ACP3-ST-001, HALEU Nitrogen System IROFS listed in 10 CFR Surveillance Testing and Calibration 70.72(c) are met.

Description of Change:

New procedure provides guidance and direction for performing testing and calibration of the HALEU Nitrogen System IROFS activities performed at the ACP and for HALEU Demonstration program.

Reason for the Change:

Provide implementation requirements.

NRG Report 2021 Page 19 of52

I ISA FCE Number PCE Number Rev. I Approval Date Change to SSC?

Documents Modified Due to Change Summary Update Required?

ReasonNRC Preapproval Not Required/Comments FCE21-0071 0

Title:

8/17/2021 No ACP4-OP-074 Chg. 0 No None of the criteria PCE21-0108 0 New Procedures ACP4-OP-074, Cold Box Withdrawal Mode Operations, ACD4-OP-026 Chg. 0 listed in 10 CFR and ACD4-0P-026, Centrifuge Connections Leak Checking ~ 70.72(c) are met.

Description of Change:

New procedure ACP4-OP-074 provides direction for Product and Tails Cold Box withdrawal mode changes. New procedure ACD4-OP-026 describes the actions required to perform leak checks of the process and purge connections of a centrifuge prior to operation.

Reason for the Change:

Provide implementation requirements.

FCE21-0072 0

Title:

8/16/2021 No ACD4-OP-003 Chg. 1 No None of the criteria PCE21-0109 0 Revision to Procedure ACD4-OP-003, MCW Normal Operations listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update and provide clarification to a number of steps, add instructions to vent the supply pumps, and update Appendix A to reflect current plans.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0073 0

Title:

8/18/2021 No ACD2-RG-044 Chg. 20 , No None of the criteria PCE 21-0111 0 Revision to Procedure ACD2-RG-044, Regulatory and Security Event listed in 10 CFR Notification and Reporting 70.72(c) are met.

Description of Change:

Revised procedure to perform pediodic review, update formatted, change retention of lifetime records, and update Appendix C to match updated 361A form.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 20 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0074 0

Title:

8/18/2021 No ACD2-RG-001 Chg. 21 No None of the criteria PCE21-0112 0 Revision to Procedures ACD2-RG-001, Change Evaluation; ACD2-RG-002, ACD2-RG-002 Chg. 12 listed in 10 CFR Application Change Control and License Amendment Requests; and ACD2- ACD2-RG-003 Chg. 21 70.72(c) are met.

RG-003, Regulatory Communications Description of Change:

Revised procedure ACD2-RG-001 and ACD2-RG-002 to update position title; references' and provide minor editorial and grammatical changes throughout. Revised ACD2-RG-003 to update position titles in the procedure and associated form AC-005; correct names of Addressee/Distrigution for various reports in Appendix B; add HALEU specific procedur~s for NMC&A reports; and provide minor ediliorial and grammatical changes throughout.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0075 0

Title:

8/19/2021 No ACD2-RG-044 Chg. 21 No None of the criteria PCE 21-0113 0 Revision to Procedure ACD2-RG-044, Regulatory and Security Event listed in 10 CFR Notification and Reporting 70.72(c) are met.

Description of Change:

Revised.procedure to add SP-3605-0043, Classified Distributed Control System (DCS) Information System Security Plan (ISSP) to the Reference Source and Commitment Sections and update Appendix B.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0076 0

Title:

8/17/2021 No ACD4-OP-003 Chg. 2 No None of the criteria PCE 21-0115 0 Revision to Proc~dure ACD4-OP-003, MCW Normal Operations listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update Appendix A, clarify instructions on filling the Machine Cooling Water (MCW) tank, and add steps to provide user checks when placing the system in automatic.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 21 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0077 0

Title:

8/24/2021 No ACD4-ON-110 Chg. 0 No None of the criteria PCE 21-0116 o New Procedures ACD4-ON-110, Loss of DCS and, ACD4-AR-111, DCS ACD4-AR-111 Chg. 0 listed in 10 CFR System Alarms and Responses 70.72(c) are met.

Description of Change:

Previously approved Lead Cascade procedure AC4-ON-110 was revised for applicability and use under the HALEU Demonstration program to facilitate implementing into use for Cascade 131. ACD4-AR-111 is a new procedure to provide direction for DCS Alarms.

Reason for the Change:

Conversion of Operations procedure to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program. New procedure ACD4-AR-111 provides implementation requirements.

FCE 21-0078 0

Title:

8/18/2021 No ACP4-OP-028 Chg. 1 No None of the criteria PCE 21-0117 o Revision to Procedures ACP4-OP-028, Transport and Storage of UF6 ACP4-OP-029 Chg. 1 listed in 10 CFR Cylinders within the Process Building; ACP4-OP-029, Inspection and ACP4-OP-034 Chg. 1 70.72(c) are met.

Operation of UF6 Cylinder Handling Hoists and Lifting Fixtures; and ACP4-OP-034, Inspection and Rejection of Small and Large UF6 Cylinders Description of Change:

Revised procedure ACP4-OP-028 to change the procedure title; add storage to the Scope and Applicability section; add steps to flow down NCSE information; and provide editorial and formatting corrections.

Revised procedure ACP4-OP-029 to remove exceptions in section 2 for use of fissile material; provide clarifications to steps; add flow down from IROFS; and make editorial corrections and clarifications throughout procedure. Revised procedure ACD4-OP-034 to remove exception in step 2.2.3 that prohibited fissile material; add steps; and update formatting throughout.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 22 of 52

ISA FCE Number Summary ReasonNRC PCE Number Rev. Approval Change Documents Modified Update Preapproval Not Date to SSC? Due to Change Required? Required/Comments FCE 21-0079 0

Title:

8/24/2021 No ACP2-OP-034 Chg. 0 No None of the criteria PCE21-0120 0 New Procedures ACP2-OP-034, Generation, Handling, Transportation and ACP3-ON-016 Chg. 0 listed in 10 CFR Storage for Fissile Containers; ACP3-ON-016, Response to Off-Normal ACP4-OP-066 Chg. 0 70.72(c) are met Cold Box Operation; and ACP4-OP-066, Mass Spectromer Operation Description of Change:

New procedure ACP2-OP-034 provides direction for the Generation, Handling, Transportation, and Storage for Fissile Containers; ACP3-ON-016 provides direction to respond to off-normal events with cold box operation; and ACP4-OP-066 (Formerly AC4-OP-066) provides direction on operation of the mass spectrometer .

Reason for the Change:

Conversion of Operations procedure to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program. New procedures ACP2-OP-034 and ACP3-ON-016 provide implementation requirements.

FCE 21-0080 0

Title:

8/23/2021 No ACP4-OP-178 Chg. 2 No None of the criteria PCE 21-0122 0 Revision to Procedure ACP4-OP-178, Cascade 131 Charging with UF6 listed in 10 CFR I 70.72(c) are met.

Description of Change:

Revised procedure to add a step to ensure NMC&A concurrence is obtained prior to feed cylinder connection and provide minor grammar and formatting changes.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0081 0

Title:

8/23/2021 No ACD4-0P-181 Chg. 7 No None of the criteria PCE 21-0123 0 Revision to Procedure ACD4-0P-181, CTTF Drying Station Operation listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to the daily capturing of temperatures and pressures; allow for not taking temperatures if completion criteria has been met; update Reference Use section; revise Appendix D; add NCS flowdowns; and add add references.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page23of52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0082 0

Title:

8/26/2021 No ACP4-AR-074 Chg. 0 No None of the criteria PCE21-0124 0 New Procedures ACP4-AR-074, Cold Box IROFS Alarm Response; ACP4- ACP4-OP-031 Chg. 0 listed in 10 CFR OP-031, Tails Cold Box Operation; and ACP4-0P-032, Product Cold Box ACP4-OP-032 Chg. 0 70.72(c) are met.

Operation Description of Change:

New procedure ACP4-AR-074 provides instructions for Cold Box IROFS alarms. New procedure ACP4-OP-031 provides direction on inspection, loading, connecting, and disconnecting UF6 cylinders; and operation of the Tails Cold Boxes. ACP4-OP-032 provides direction on inspection, loading, connecting, and disconnection UF6 cylinders; and operation of the product cold boxes.

Reason for the Change:

Provide implementation *requirements.

FCE 21-0083 0

Title:

8/26/2021 No ACP4-OP-078 Chg. 0 No None of the criteria PCE21-0125 0 New Procedure ACP4-OP-078, PCC Operations listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides the steps necessary for installing/removing a Power and Control Cabinet (PCC) at a centrifuge position.,

Reason for the Change:

Provide implementation requirements.

FCE 21-0084 0

Title:

9/9/2021 No ACP3-ST-003 Chg. 0 No None of the criteria PCE21-0128 0 New Procedure ACP3-ST-003, Vent Monitor Plant Air Fail-Safe Isolation listed in 10 CFR Valve Surveillance Testing 70.72(c) are met.

Description of Change:

New procedure provides instructions for performing testing and calibration of the HALEU Vent Monitor Plant Air Fail-Safe Isolation Valve IROFS.

Reason for the Change:

Provide implementation requirements.

/

__)

NRC Report 2021 Page 24 of 52

ISA FCE Number Summary Reason NRC PCENumber Rev. ( Approval Change Documents Modified Update Preapproval Not Date to SSC? Due to Change Required? Required/Comments FCE21-0086 0

Title:

9/13/2021 No ACP3-ST-002 Chg. 0 No None of the criteria PCE21-0134 0 New Procedure ACP3-ST-002, HALEU Tails Cold Box IROFS Surveillance listed in 10 CFR Test and Calibration 70.72(c) are met.

Description of Change:

New procedure provides guidance and direction for performing testing and calibration of the HALEU Tails Cold Box System IROFS activities performed at the ACP and HALEU Demonstration program.

Reason for the Change:

Provide implementation requirements.

FCE 21-0087 0

Title:

9/13/2021 No ACD4-OP-101 Chg. 1 No None of the criteria PCE21-0135 0 Revision to Procedures ACD4-OP-101, Purge Vacuum Operating ACD4-OP-102 Chg. 1 listed in 10 CFR Procedure, and ACD4-OP-102, Evacuation Vacuum Operating Procedure 70.72(c) are met.

Description of Change:

Revised procedures ACD4-OP-101 and ACD4-OP-102 to remove exception statements to allow for use during fissile operations, make corrections based on new technical data in seal purge use,,correct various sections based off new engineering guidance on pump operation, and adjusted tolerances/requirements for nitrogen supply and VCW operating ranges.

Reason for the Change:

Clarify procedure requirements.

FCE21-0088 0

Title:

9/28/2021 No ACD4-OP-035 Chg. 0 No None of the criteria PCE21-0136 0 New Procedures ACD4-OP-035, Operation of Adventurer Balances Sample ACP4-OP-026 Chg. 0 listed in 10 CFR Scale AX2202; ACP4-OP-026, Small Container Scale Operations; ACP4- ACP4-OP-027 Chg. 0 70.72(c) are met.

OP-027, 30-Series Scale Operations; and ACP4-OP-030, Operation of the ACP4-0P-030 Chg. 0 Mettler Toledo PKF9-/(X-T4) Scale for weighing 5" and 12" UF6 cylinders Description of Change:

New procedures ACD4-OP-035, ACP4-OP-026, ACP4-OP-027, and ACP4-OP-030 provide instruction on scale operations and weighing various containers, samples, cylinders, and standards.

Reason for the Change:

Provide implementation requirements:

NRC Report 2021 Page 25 of52

ISA FCENumber Summary Reason NRC PCENumber Rev. Approval Change Documents Modified Update Preapproval Not Date to SSC? Due to Change Required? Required/Comments FCE21-0089 0

Title:

9/13/2021 No ACP3-ST-004 Chg. 0 No None of the criteria PCE21-0137 0 New Procedure ACP3-ST-004, HALEU Product Cold Box IROFS listed in 10 CFR' Surveillance Testing and Calibration 70.72(c) are met.

Description of Change:

New procedure provides guidance and direction for performing testing and calibration of the HALEU Product Cold Box IROFS activities performed at the ACP and for HALEU Demonstration program.

Reason for the Change:

Provide implementation requirements.

FCE 21-0090 0

Title:

9/16/2021 No ACD4-AR-101 Chg. 0 No None of the criteria PCE 21-014.1 0 New Procedure ACD4-AR-101, Centrifuge Alarms and Responses, and AC4-AR-101 Chg. 16 listed in 10 CFR Cancellation of Procedure AC4-AR-101, Cascade. 131 Machine Alarms and 70.72(c) are met.

Responses Description of Change:

New procedure ACD4-AR-101 provides the actions required to respond to centrifuge alarms. AC4-AR-101, was a previously approved similar procedure, on hold, that is now being concurrently cancelled.

Reason for the Change:

Provide implementation requirements.

FCE21*0095 0

Title:

9/30/2021 No SOW-2518-0011-Rev. 0 No None of the criteria PCE21-0148 0 New Statement of Work SOW-2518-0011, ACP Temporary Fuel Station listed in 10 CFR 70.72(c) are met.

Description of Change:

To assess the extension of the end date for the temporary fuel station utilized for the ACP. Due to demobilization of the ACP construction activities in the summer of 2009, it was necessary to continue utilizing the temporary satellite fuel station located adjacent to the X-1107EP portal.

Also, the HALEU Demonstration program is presentiy ongoing and warrants continued use of the temporary satellite fuel station but does not include the scope to add a permanent fuel station at this time.

Reason for the Change:

The temporary satellite fuel station provides fueling services to site located

/

equipment and vehicles that support ACP activities.

NRC Report 2021 Page 26 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE21-0096 0

Title:

10/21/2021 No ACD2-PS-005 Chg. 1 No None of the criteria PCE21-0149 0 Revision to Procedure ACD2-PS-005, Handling and Processing of listed in 10 CFR Classified Documents for Offsite Deliveries and Receipts 70.72(c) are met.

Description of Change:

Revised procedure to remove the requirements for handling and processing Safeguards Information from the procedure to flow down a recent change in NRC commitment.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0097 0

Title:

10/7/2021 No ACD4-OP-073 Chg. 1 No None of the criteria PCE21-0152 0 Revision to Procedure ACD4-OP-073, Nitrogen System Operations listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to better address proper Nitrogen System startup based on recent engineering changes and lessons learned from Test Plan, added Section 7.8 to detail Nitrogen Backfill operations, and removed exception statement to allow for fissile operations.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0098 0

Title:

10/7/2021 No ACD4-OP-003 Chg. 4 No None of the criteria PCE 21-0155 0 Revision to Procedures ACD4-OP-003, Machine Cooling Water Normal ACD4-OP-006 Chg. 2 listed in 10 CFR Operations; ACD4-OP-006, Vacuum Cooling Water Normal Operations; ' ACD4-ON-004 Chg. 1 70.72(c) are met.

ACD4-ON-004, Loss of Machine Cooling Water; and ACD4-ON-218, LO!!S ACD4-ON-218 Chg. 2 of Vacuum Cooling Water Description of Change:

Revised procedures ACD4-OP-003 and ACD4-OP-006 to reformat procedures to align more efficiently with equipment and components of the MCW skid, add prerequisites, clarify instructions throughout, and add notes in Appendix A and B to assist with valve lineups. Revised procedures ACD4-ON-004 and ACD4-ON-218 to add a number of immediate and supplemental actions for various off normal events .

. Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 27 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0099 0

Title:

10/22/2021 No ACP2-CM-001 Chg. 1 No None of the criteria PCE 21-0160 0 Revision to Procedure ACP2-CM-001, Chemical Trap Change listed in 10 CFR

70. 72(c) are met.

Description of Change:

Revised procedure to correct procedure references, add clarifications for NCS approved containers, and perform editorial corrections thorughout.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0100 0

Title:

10/22/2021 . No ACP2-CM-004 Chg. 1 No None of the criteria PCE 21-0162 0 Revision to Procedure ACP2-CM-004, Field Decontamination listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update references and provide clarification on NCS approved containers.

Reason for the Change:

Clarify procedure requirements. "

FCE 21-0101 0

Title:

10/22/2021 No ACP2-CM-002 Chg. 1 No None of the criteria PCE 21-0163 0 Revision to Procedure ACP2-CM-002, Removal, Handling, and Storage of listed in 10 CFR Uranium Contaminated Process Equipment 70.72(c) are met.

Description of Change:

Revised procedure to update references, clarify the use of NCS approved containers, and change step 7.2.13 to clarify the Safe Volume Container (SVC) is expected to be a value exempt from Item Control for NMC&A.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0102 0

Title:

10/26/2021 No ACD2-TP-001 Chg. 24 No None of the criteria PCE 21-0168 0 Revision to Procedure ACD2-TP-001, Procedure Process listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to include additional criteria to be considered before a procedure Approval Authority selects an Effective Date for a given procedure. Revised for AC-006 adding block 9 for recording procedure activity Effective Date.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 . Page 28 of 52

FCE Number

- ISA Summary ReasonNRC Rev. - Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0105 0

Title:

11/2/2021 No ACD2-MP-003 Chg. 9 No None of the criteria PCE21-0177 0 Revision to Procedure ACD2-MP-003, Employee Concerns Program listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to align with the Centrus Energy Corp. Employee Concerns Program Policy.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0106 0

Title:

11/1/2021 No ACD3-EG-203 Chg. 10 No None of the criteria PCE 21-0178 0 Revision to Procedure ACD3-EG-203, Engineering Drawing Controls listed in 10 CFR

70. 72(c) are met.

Description of Change:

Revised procedure to add the definition of "Approval Authority" and clarify the definitions of "Drawing Check" and 'Technical Review" in Appendix A; provide clarifications throughout; add the electronic signature option for signing to Appendix L; add the 9500 sequence for new HALEU drawing numbers in Appendix P; and rearranged the order of certain steps to follow the actual process in Appendix L.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0107 0

Title:

11/4/2021 No ACD4-AR-106 Chg, 0 No None of the criteria PCE21-0179 0 New Procedures ACD4-AR-106, Cascade Alarms and Responses; ACP2- ACP2-OP-059 Chg. 0 listed In 10 CFR OP-059, Operation of the Safe Geometry Vacuum; and ACP3-OP-002, ACP3-OP-002 Chg. 0 70.72(c) are met.

Operation of the Pump Down Cart Description of Change:

Previously approved Lead Cascade procedure AC4-AR-106 was revised for applicability and use under the ACP and HALEU Demonstration program.

New procedure ACP2-OP-059, was developed to accommodate actions specific to Safe Geometry Vacuum configuration and incorporate HALEU flow down from NCSE-GEN-002. New procedure ACP3-OP-002, was developed to accommodate actions specific to Pump Down Cart operation and to incorporate HALEU flow down from NCSE-FWS-002, NCSE-GEN-002, NCSE-GEN-008, NCSE-GEN-006, and NCSE-CAS-001.

Reason for the Change:

Conversion of Operations procedures to the dual use category constitutes a new procedure change under the requirements of ACD2-TP-001, Procedure Process, and allows use under the HALEU Demonstration program. New procedures ACP2-OP-059 and ACP3-0P-002 provide implementation requirements.

NRC Report 2021 Page 29 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments FCE 21-0109 0

Title:

11/8/2021 No ACD2-MP-001 Chg. 18 No None of the criteria PCE 21-0183 0 Revision to Procedure ACD2-MP-001, Safety Review Committee listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to provide a periodic review, make minor formatting/editorial changes, and add clarification.

Reason for the Change:

Clarify procedure requirements.

FCE 21-0110 0

Title:

12/14/2021 No ACP2-CM-001 Chg. 2 No None of the criteria PCE 21-0186 0 Revision to Procedur~s ACP2-CM-001, Chemical Trap Change; ACP2-CM- ACP2-CM-004 Chg. 2 listed in 10 CFR 004, Field Decontamination; and ACP2-CM-002, Removal, Handling, and ACP2-CM-002 Chg. 2 70.72(c) are met.

Storage of Uranium Contaminated Process Equipment Description of Change:

Revised procedures ACP2-CM-001, ACP2-CM-002, and ACP2-CM-004 to update the Precautions and Limitations sections to slate "Activities covered by this procedure shall only be performed in areas of the X-3001 Process Building which have Criticality Accident Alarm System (CAAS) coverage.

Removed equipment shall be stored inside CAAS coverage."

Reason for the Change:

Clarify procedure requirements.

FCE 21-0112 0

Title:

12/16/2021 No ACD4-ON-009 Chg. 1 No None of the criteria PCE 21-0190 0 Revison to Procedure ACD4-ON-009, Response to L9ss of Power listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to update Operations Manager name, references, correct formatting, update various sections for HALEU deomonstration, and add appendices with instructions for monitoring UPS battery life.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

2/24/2021 No ACP2-FS-001 Chg. 0 No None of the criteria PCE 21-0003 0 New Procedure ACP2-FS-001, Combustible Material Control Program listed in 10 CFR Procedure 70.72(c) are met.

Description of Change:

New procedure implements a program for the control of combustable materials that are utilized in the ACP facilities.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 30 of 52

ISA FCE Number Summary Reason NRC I

Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

2/25/2021 No ACP2-FS-002 Chg. 0 No None of the criteria PCE 21-0005 0 New Procedure ACP2-FS-002, Flammable and Combustible Liquids listed in 10 CFR Procedure 70.72(c) are met.

Description of Change:

New procedure describes the use, storage, and handling of flammable and combustible liquids.

  • Reason for the Change:

Provide implementation requirements.

N/A

Title:

4/6/2021 No ACP2-EG-017 Chg. 0 No None of the criteria PCE 21-0008 0 New Procedure ACP2-EG-017, IROFS Surveillance Program listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides guidance for evaluating, documenting, and performing IROFS Surveillances at the ACP and HALEU Demonstration.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 31 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments NIA

Title:

5/6/2021 No ACP2-NM-101 Chg. 0 No None of the criteria PCE 21-0026 o New Procedures ACP2-NM-101, Accounting for Nuclear Materials; ACP2- ACP2-NM-102 Chg. 0 listed in 10 CFR NM-102, Administration of Material Balance Areas; ACP2-NM-103, ACP2-NM-103 Chg. 0 70.72(c) are met.

Sampling and Measurement of Nuclear Materials; ACP2-NM-104, Nuclear ACP2-NM-104 Chg. 0 Material Measurement Controls; ACP2-NM-105, Control of Nuclear Material ACP2-NM-105 Chg. 0 Items; ACP2-NM-106, Performance of Nuclear Material Inventories; ACP2- ACP2-NM-106 Chg. 0 NM-107, Shipper/Receiver Difference Monitoring; ACP2-NM-108, ACP2-NM-107 Chg. 0 Investigation and Resolution of Indicators of Missing Uranium or ACP2-NM-108 Chg. 0 Unauthorized EnrichmenUProduction Activities; ACP2-NM-109, Statistical ACP2-NM-109 Chg. 0 Applications in Nuclear Material Control and Accountability; ACP2-NM-110, ACP2-NM-110 Chg. 0 Independent Assessment of the Nuclear Material Control and ACP2-NM-111 Chg. 0 Accountability Program; ACP2-NM-111, Control and Usage ofTamper ACP2-NM-112 Chg. 0 Indicating Devices; ACP2-NM-112, Monitoring to Detect Unauthorized ACP2-NM-113 Chg. 0 EnrichmenUProduction Activities; ACP2-NM-113, Nuclear Material Control ACP2-NM-114 Chg. 0

& Accountability Software Configuration Management; ACP2-NM-114, ACP2-NM-115 Chg. 0 Accounting for Receipts and Shipments of Nuclear Materials; ACP2-NM- ACP2-NM-116 Chg. 0 115, Cascade Transactions and ACP2-NM-116, UF6 Cylinder Transactions Description of Change:

New ACP2 procedures implement the Fundamental Nuclear Material Control Plan (FNMCP) and Addendum 1 of the FNMCP requirements for Nuclear Material Control and Accountability (NMC&A) procedures for the HALEU Demonstration program.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 32 of 52

ISA Summary ReasonNRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comme11ts NIA

Title:

5/11/2021 No ACP4-NM-201 Chg. 0 No None of the criteria PCE 21-0036 o New Procedures ACP4-NM-201, Statistical Trend Analysis of Inventory ACP4-NM-205 Chg. 0 listed in 10 CFR Differences and Shipper-Receiver Data; ACP4-NM-205, Non-UF6 ACP4-NM-206 Chg. 0 70.72(c) are met.

Transactions; ACP4-NM-206, Cascade Dynamic Physical Inventory; ACP4- ACP4-NM-207 Chg. 0 NM-207, Preparation of the Nuclear Material Transaction Report ACP4-NM-208 Chg. 0 (DOE/NRG Farm 741) for NMMSS Reporting; ACP4-NM-208, Preparation ACP4-NM-209 Chg. 0 and Issuance of Material Balance Reports and Inventory Reports ACP4-NM-210 Chg. 0 (DOE/NRG Form 742/742C); ACP4-NM-209, Preparation and Issuance of ACP4-NM-211 Chg. 0 NRG Form 327, ACP4-NM-210, Tracking/Monitoring of Nuclear Material ACP4-NM-212 Chg. 0 Measurement System; ACP4-NM-211, Monitoring the Performance of Mass ACP4-NM-213 Chg. 0 Measurement Systems; ACP4-NM-212, Monitoring the Performance of ACP4-NM-214 Chg. 0 Analytical/NOA Measurement Systems; ACP4-NM-213, Monitoring the ACP4-NM-215 Chg. 0 Performance of Process Instrumentation; ACP4-NM-214, Stratification and ACP4-NM-216 Chg. 0 the Statistical Estimation of the SEID; ACP4-NM-215, Item Monitoring ACP4-NM-217 Chg. 0 Program; ACP4-NM-216, Bias Correction of NMC&A Measurements; and ACP4-NM-217, Journal Entries Description of Change:

New ACP4 procedures implement the ACP FNMCP and Addendum 1 of the FNMCP requirements for the NMC&A procedures for the HALEU Demonstration progran;i.

Reason for the Change:

Provide implementation requirements.

NIA

Title:

4/14/2021 No ACP4-EG-704 Chg. 0 No None of the criteria PCE 21-0038 o New Procedure ACP4-EG-704, Nuclear Criticality Safety Incident Response listed ii') 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides direction to NCS for assessing and categorizing off normal NCS events and other conditions that could result in the reduction of NCS.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 33 of 52

ISA J

FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

4/14/2021 Yes Oak Ridge ESO-00145 No None of the criteria PCE 21-0040 0 New Engineering Service Order ESO-00145, Install Ductwork Through listed in 10 CFR ACO-OR Security Wall 70. 72(c) are met.

Description of Change:

Ductwork is to be routed through an exterior wall to be used for cooling test equipment located in the adjacent area inside the facility.

Reason for the Change:

Ductwork is required to penetrate the existing walls currenUy described in NR-SP-ACO-OR-001. The physical changes to these areas do not alter the areas as described in NR-SP-ACO-OR-001.

NIA

Title:

6/16/2021 No LA-3605-0001 Sections 2.1.8 No None of the criteria ,

PCE 21-0042 0 Revision to LA-3605-0001, License Application for the American Centrifuge and 8.1.1 listed in 10 CFR Plant 70.72(c) are met.

Description of Change:

Revised LA-3605-0001 to update Shift Crew Composition and Emergency Operations Center Activation in Chapters 2.0 and 8.0.

/'

Reason for the Change:

Contractor FBP has traditionally provided Industrial Hygiene personnel for Shift Crew composition. FBP no longer maintains Industrial Hygiene personnel on site 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day/seven days a week.

N/A

Title:

6/16/2021 No ACP2-SH-002 Chg. 0 No None of the criteria PCE 21-0049 0 New Procedure ACP2-SH-002, ACO Site Response Actions listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure ACP2-SH-002 was developed to provide clear instruction for actions to be taken during emergency events at the ACP and enable proper integration/transition to the FBP site emergency response.

Reason for the Change:

Provide implementation requirements.

N/A

Title:

10/5/2021 No LA-3605-0001 TOC, Sections No None of the criteria PCE 21-0052 0 Revision to LA-3605-0001, License Application for the American Centrifuge 1.1.3.3.3, 1.4.3 D, 1.6, listed in 10 CFR Plant 2.1.2.2.1, 2.1.2.2.2 and 70.72(c) are met.

figures 1.1-4, 1.1-5a, 1.1-5b, Description of Change:

-, l.1-5c, l.1-5d, l.1-5e, 1.1-6, 1.1-Revised license application to provide editorial and administrative 7, 1.1-8 and 1.1-10 corrections.

Reason for the Change:

Clarify licensing documentation.

NRC Report 2021 Page 34 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments NIA

Title:

5/20/2021 Yes ESO-2501-0024 No None of the criteria PCE 21-0054 o Revision to ESO-2501-0024, Upgrade of the Security Access Control and listed in 10 CFR Alarm System (SAGAS) for the HALEU Demonstration Program. 70. 72(c) are met.

Description of Change:

The ESQ is for physical construction modifications in support of the SAGAS upgrades for the ACP and the HALEU Demonstration program.

Reason for the Change:

Provide upgrades to the existing SAGAS equipment and structures.

N/A

Title:

6/17/2021 No NCSE-CAS-004 Rev. 2 Yes None of the criteria PCE 21-0056 o Revision to NCSE-CAS-004, Nuclear Criticality Safety Evaluation for Mass NCSE-GEN-008 Rev. 2 listed in 10 CFR Spectrometry Stations, and NCSE-GEN-008, Nuclear Criticality Safety LA-3605-0003A Sections 70.72(c) are met.

Evaluation for Service Carts 7.3.6.2.1.4, 7.3.6.3.1.4.3, 7.3.6.12.1.1.7, Description of Change:

7.3.6.12.1.1.13, Revised NCSE-CAS-004 to evaluate a change in the dimensions of the 7.3.6.12.1.1.14, mass selective detector (MSD). Revised NCSE-GEN-008 to remove the 7.3.6.12.1.4.3, 7.3.6.12.3.3, geometric directional limitation for the transfer standard component of the 7.5, and Tables C-2-3 and C-calibration cart, to require the item being calibrated to be isolated from the 2-12 cascade, to provide clarification that the calibration cart flexible connection hose may be used with the pump down cart when the pump down cart is used independently of the calibration cart, and to revise the discussion and control for common cart components.

Reason for the Change:

Clarify NCSE requirements.

-7 NIA

Title:

8131/2021 No ACP2-SH-001 Chg. 0 No None of the criteria PCE 21-0057 o New Procedure ACP2-SH-001, Actions To Be Taken During a UF6 or Other listed in 10 CFR Hazardous Materials Release 70.72(c) are met.

Description of Change:

New procedure procedure provides instructions for actions to be taken during a UF6 or other hazardous materials release.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 35 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update - Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

6/29/2021 Yes ESO-3100-0006 Yes None of the criteria PCE21-0065 0 Revision to Engineering Service Order ESO-3100-0006, MachineNacuum LA-3605-0001 Section listed in 10 CFR Cooling Water System 1.1.5,6.3 and Figure 1.1-16 70.72(c) are met.

LA-3605-0003A Section 3.9.3 Description of Change:

and Figure 3.9-2 The ESQ is for the installation of the MCW and VCW systems for the HALEU demonstration project per ESO-3100-0006. The previous Change Evaluations were performed "at-risk" due to the design being incomplete and also due to NRC prior approval being required for _associated License Application/lSA Summary changes for HALEU Demonstration.

ESO design has been completed and NRC approval has been obtained for the HALEU Demonstration changes. Therefore, this Change Evaluation supersedes all previous "At Risk" Change Evaluations (e.g., FCE 20-0070 Rev. 0/PCE 20-0090 Rev. 0) and evaluates the final ESQ design of the HALEU MCW and VCW systems against the current approved design basis as revised for HALEU Demonstration.

Reason for the Change:

The purpose of the ESQ is to install the MCW and VCW systems to support HALEU Demonstration operations.

N/A

Title:

6/29/2021 Yes ESO-3100-0010 No None of the criteria PCE21-0066 0 Revision to Engineering Service Order ESO-3100-0010, HALEU Cascade listed in 10 CFR Mass Spectrometer 70.72(c) are met.

Description of Change:

The ESQ is the installation of mass spectrometers in an enclosed room near the withdrawal cold boxes in X-3001 for HALEU Demonstration.

Previous Change Evaluations for this system were performed "At Risk" due to the design being incomplete and also due to NRC prior approval being required for associated License Application/lSAS changes for HALEU Demonstration.

ESQ design has been completed and NRC approval has been obtained for the HALEU Demonstration changes. Therefore, this Change Evaluation supersedes all previous "At Risk" Change Evaluations (e.g., FCE 20-0055 Rev. 0/FCE 20-0073 Rev. 0) and evaluates the final ESQ design of the HALEU Cascade Mass Spectrometer against the current approved design basis as revised for HALEU Demonstration.

Reason for the Change:

The purpose of the ESQ is to install new mass spectrometers in an enclosed room to support HALEU Demonstration operations.

NRC Report 2021 Page 36 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

6/24/2021 Yes ESO-3100-0019 No None of the criteria PCE 21-0067 0 Revision to Engineering Service Order ESO-3100-0019, Portable Carts listed in 10 CFR Used for UF6 Handling for HALEU 70. 72(c) are met.

Description of Change:

FCE 21-0012 Rev. 0 / PCE 21-0011 Rev. 0 was previously approved and evaluated portable carts; however, Revision O focused on the portable Pump Down Cart. The purpose of this Change Evaluation is to supersede the previous "At-Risk" CE, include the other portable service carts that are now covered by ESO-3100-0019, and evaluate*a11 portable service carts for activities such as design, procurement, fabrication, installation, testing, implementation, and operation. ESO-3100-0019 also includes the Calibration Cart, the Gulper, and the Safe Geometry Vacuum.

Reason for the Change:

ACP operations require vacuum calibration equipment and pump-down equipment to perform testing on sections of piping, equipment, and instrumentationI to calibrate the instrumentation.

N/A

Title:

7/6/2021 No ACP2-EG-026 Chg. 0 No None of the criteria PCE 21-0069 0, New Procedure ACP2-EG-026, Spacing Exempt and NCS Program listed in 10 CFR Exclusions 70.72(c) are met.

Description of Change:

New procedure provides instructions for independent verification of enrichment data, visual inspection, radiation survey, and waste stream source information to establish the applicability of NCS spacing requirements or the exclusion from the NCS program requirements.

Reason for the Change:

Provide implementation requirements.

'N/A

Title:

6/10/2021 No LA-3605-0001 Table 1.2-2 No None of the criteria PCE 21-0071 0 Revision to LA-3605-0001, License Application for the American Centrifuge listed in 10 CFR Plant 70.72(c) are met.

Description of Change:

Revised Table 1.2-2, HALEU Demonstration program Posssesion Limits for NRC Regulated Materials and Substances, to correct a statement that would have allowed Uranium enriched in isotope 235 to 20 percent or greater by weight to state "Uranium enriched in isotope 235 from 20 percent up to 25 percent by weight".

Reason for the Change:

This change is being made to conform to the proposed HALEU authorized uses of NRC Regulated Materials identified in Table 1.2-4 of LA-3605-0001.

NRC Report 2021 Page 37 of 52

ISA Summary Reason NRC FCE Number Rev. Approval Change Documents Modified Update Preapproval Not PCE Number -

- Date to SSC? Due to Change Required? Required/Comments NIA

Title:

6/15/2021 No PLD1-SP-032 Rev. 6 No None of the criteria PCE 21-0073 0 Revision to Procedure PLD1-SP-032, Personnel Security Procedure listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to incorporate additional human performance error reduction tools following an Incident of Security Concern (IOSC).

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

6/30/2021 Yes ESO-3100-0015 No None of the criteria PCE 21-0075 0 Revision to Engineering Service Order ESO-3100-0015, HALEU Distributed listed in 10 CFR Control System 70.72(c) are met.

Description of Change:

The ESQ is the installation of a new DCS for HALEU Demonstration.

Previous Change Evaluations for this system were performed "At Risk" due to the design being incomplete and also due to NRG prior approval being required for associated License Application/lSA Summary changes for HALEU Demonstration.

ESO-3100-0015 design has been completed and NRC approval has been obtained for the HALEU Demonstration changes. This Change Evaluation is evaluating all changes made to remove the "At Risk" status since the previous "At Risk" Change Evaluations (e.g., FCE 20-0056 Rev. O/ PCE 20-0075 Rev. O and FCE 20-0069 Rev. O/ PCE 20-0089 Rev. 0) were completed. Therefore, this Change Evaluation will be the final evaluation of the ESO-3100-0015 design of the HALEU Cascade DCS against the current approved design basis as revised for HALEU Demonstration.

Reason for the Change:

The purpose of the proposed change is to install a new DCS to support HALEU Demonstration operations.

N/A

Title:

6/24/2021 No PLD1-SP-012 Rev. 8 No None of the criteria PCE 21-0076 0 Revision to Procedure PLD1-SP-012, Visitor Control and Badging listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to incorporate additional human performance error reduction tools following an IOSC.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 38 of 52

ISA FCE Number Summary Reason NRC PCE Number Rev. Approval Date Change to SSC?

Documents Modified Due to Change I Update Required?

Preapproval Not Required/Comments i

j i

NIA

Title:

7120/2021 No ACP2-NM-103 Chg. 2 No None of the criteria PCE 21-0082 0 Revision to Procedure ACP2-NM-103 Sampling and Measurement of listed in 10 CFR Nuclear Materials 70.72(c) are met.

Description of Change:

Revised procedure to respond to comments from the Internal Readiness Review (IRR) completed in June 2021. This procedure revision also included changes to provide a better procedure flow, more descriptive detail, and minor editorial corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

7/2212021 No ACP2-NM-104 Chg. 1 No None of the criteria PCE 21-0083 0 Revision to Procedure ACP2-NM-104, Nuclear Material Measurement listed in 10 CFR Controls 70.72(c) are met.

Description of Change:

Revised procedure to respond to comments from the IRR completed in June 2021. This procedure revision also included changes to provide a better procedure flow, more descriptive detail, and minor editorial corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

--.., 7n/2021 Yes ESO-3100-0023 No None of the criteria PCE21-0086 0 Revision to Engineering Service Order ESO-3100-0023, HALEU Fissile listed in 10 CFR Material Storage Area

  • 70.72(c) are met.

Description of Change:

The ESO is for the installation of a Fissile Material Storage Area.

Reason for the Change:

To provide an area to be used for the activities associated with storage and transportation of fissile materials and associated equipment.

NIA

Title:

7126/2021 No ACP2-NM-106 Chg. 1 No None of the criteria PCE 21-0087 0 Revision to Procedure ACP2-NM-106, Performance of Nuclear Material listed in 10 CFR Inventories 70.72(c) are met.

Description of Change:

Revised procedure to reorganize, provide for a better procedure flow, more descriptive details, and minor editorial changes. Form AC-750, Nuclear Materials Inventory Form was also established with this change.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 39 of52

ISA FCE Number Summary Reas on NRC Rev. Approval Change Documents Modified Update Preapp roval Not PCE Number Date to SSC? Due to Change Required? Required {Comments N/A

Title:

7/13/2021 No PLD1-SP-009 Rev. 5 No None of the criteria PCE 21-0092 0 Revision to Procedure PLD1-SP-009, Foreign National Visits and listed i n 10 CFR Assignments 70.72(c ) are met.

Description of Change:

Revised procedure due to a periodic review, removed Department of Energy (DOE) and added NRC or Cognizant Security Authority (CSA) as appropriate throughout procedure, added additional source references; and made minor corrections/clarifications throughout procedure.

Reason for the Change:

Clarify proceaure requirements.

N/A

Title:

7/19/2021 Yes ESO-3100-0019 No None of the criteria PCE 21-0094 0 Revision to Engineering Service Order ESO-3100-0019, Addition of Helium ECR-3100-0019-03, Rev. 0 listed i n 10 CFR Leak Detectors 70.72(c) are met.

Description of Change:

The purpose of this Change Evaluation is to include HLDs in the scope of ESO-3100-0019 using ECR-3100-0019-03.

Reason for the Change:

ACP operations require HLDs to perform leak testing on machine connections and sections of piping, equipment, and instrumentation.

N/A

Title:

7/26/2021 No ACP2-NM-107 Chg. 1 No None ofthe criteria PCE 21-0096 0 Revision to Procedure ACP2-NM-107, Shipper/Receiver Difference listed in 10 CFR Monitoring 70.72(c) are met.

Description of Change:

Revised procedure to respond to COf1lments from the IRR completed in June 2021. This procedure revision also included changes to provide a better procedure flow, more descriptive detail, and minor editorial corrections.

Reason for the Change: ,

Clarify procedure requirements.

NRC Report 2021 Page 40 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

7/27/2021 No ACP2-NM-108 Chg. 1 No None of the criteria PCE 21-0097 0 Revision to Procedure ACP2-NM-108, Investigation and Resolution of listed in 10 CFR Indicators of Missing Uranium or Un_authorized EnrichmenVProduction 70.72(c) are met.

Activities Description of Change:

Revised procedure to respond to comments from the IRR completed in June 2021. This procedure revision also included changes to provide a better procedure flow, more descriptive details, and editorial corrections.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

8/5/2021 No ACP2-NM-112 Chg. 1 No None of the criteria PCE 21-0099 0 Revision to Procedure ACP2-NM-112, Monitoring to Detect Unauthorized listed in 10 CFR EnrichmenVProduction Activities 70.72(c) are met.

Description of Change:

Revised procedure to respond to comments from the IRR completed in June 2021. This procedure revision also included changes to provide a better procedure flow, more descriptive details, and minor editorial changes.

Reason-for the Change:

Clarify procedure requirements.

NIA

Title:

12/15/2021 No ESE-3100-0001 Rev. 0 No None of the criteria PCE 21-0100 0 Equivalency Substitution Evaluation of ANSI N14.1-2019 Edition for 2012 listed in 10 CFR Edition 70.72(c) are met.

Description of Change:

This ESE evaluates the proposed change in code edition from ANSI N14.1-2012 to ANSI N14.1-2019.

Reason for the Change:

Section 1.4 of LA-3605-0001 states: "Any deviations from the codes and standards of record will be evaluated and documented in accordance with the Configuration Management Program as described in Section 11.1 of this license application." The Code Reconciliation concluded that the 2019 edition meets all requirements of the 2012 edition, with additional or updated requirements that affect cylinder or component manufacturers.

NRC Report 2021 Page41 of 52

ISA I

FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

8/5/2021 No ACP2-EG-010 Chg. 7 No None of the criteria PCE 21-0101 0 Revision to Procedures ACP2-EG-010, Nuclear Criticality Safety Program, ACP3-EG-701 Chg. 7 listed in 10 CFR and ACP3-EG-701, Nuclear Criticality Safety Engineering 70.72(c) are met.

Description of Change:

Revised procedures ACP2-EG-010 and ACP3-EG-701 to split NCSE implementation activities into two parts. Part A was created for the Fissile Material Operations Manager, Engineering, and the NCS Implementing Engineer. Part B was created for the NCS Implementing Engineer to document CMS requirements are met and any license changes are approved.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

8/9/2021 No NR-3605-0005C Sections No None of the criteria PCE 21-0102 0 Proposed Change to NR-3605-0005C, (U) Program for Precluding and 11.1-11.7, Tables 11.2, 11.3, listed in 10 CFR Detecting Unauthorized Production/Enrichment and Diversion Activities for 11.4; and 11.5 70.72(c) are met.

the HALEU Demonstration Centrifuge Facility Description of Change:

Proposed change to NR-3605-0005C is being made to address deficiencies identified in ACP-IRR-2021-05, Nuclear Material Control and Accountability Program Independent Readiness Review.

Reason for the Change:

Clarify plan requirements.

NRC Report 2021 Page 42 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments NIA

Title:

8/17/2021 Yes ECR-3100-0006-07, Rev. 0 No None of the criteria PCE21-0114 0 ECR-3100-0006c07, Sanitary Water Supply and Tower Cooling Water listed in 10 CFR Return Change, At Risk Installation and Testing 70.72(c) are met.

Description of Change:

The proposed change is the At Risk ECRa3100-0006-07 to the )

MachineNacuum Cooling Water System. This evaluation covers the /

/

continued installation and testing of the MachineNacuum Cooling Water System as modified by ECR-3100-0006-07. This evaluation does NOT address the operation of the modified system. An additional Change Evaluation will need to be performed against the final system design prior to placing the system into operation.

ECR-3100-0006-07 addresses the reroute of sanitary water supply line and

--, sanitary drain line from constructed installation per X-3001-9571-MP to tie-in point used during previous project on X-3001 north building wall column

  • line 1 for sanitary water supply and to tie-in point tower cooling water return (TCWR) line between columns B2-1.6 and B2-1.

ISA Summary Addendum 1 d~scribes the HALEU MCW and VCWsystems in Section 3.9.3. Additionally, the License Application provides a description of the MCW in Section 1.1.5.6.3 and Figure 1.1-16. The final approved system design, as modified by ECR-3100-0006-07, will be required to be reviewed against these sections prior to placing the system into operation.

Any required changes to these sections will be addressed by a future change evaluation.

Reason for the Change:

Piping is required to be rerouted due to insufficient sanitary water drain capacity per original design and additional requirement for a backllow preventer on the sanitary water supply line.

NIA

Title:

8/26/2021 No ACP2-PT-009 Chg. 0 No None of the criteria PCE 21-0118 0 New Procedure ACP2-PT-009, On-Site Transportation of Inventory and

  • listed in 10 CFR Radioactive Material Shipment and Receipt 70.72(c) are met.

Description of Change:

New procedure provides the flow down of requirement 7.3.9.2 contained LA-3605-0003A and controls the limits for on-site transportation, outside of ACP buildings, and off-site shipment or receipt of radioactive materials.

.J Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 43 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments NIA

Title:

8/31/2021 N~ ACP4-FS-001 Chg. 0 No None of the criteria PCE 21-0121 0 New procedure ACP4-FS-001, Surveillance of the Items Relied On For listed in 10 CFR Safety Fire Suppression Systems 70.72(c) are met.

Description of Change:

New procedure provides the requirements for surveillance of the IROFS fire suppression systems.

Reason for the Change:

Provide implementation requirements.

NIA

Title:

12/2/2021 No NR-3605-0008 TOG, Section No None of the criteria PCE 21-0126 0 Change in Markings for NR-3605-0008, Emergency Plan for the American 2.0, Appendix A, B, C, and listed in 10 CFR Centrifuge Plant new Appendix G 70.72(c) are met.

Description of Change: -

Revised NR-3605-0008 to move tables from Appendix A, B, and C to Appendix G.

Reason for the Change:

Clarify appendix information.

NIA

Title:

10/1/2021 No ECR-3100-0006-07 Rev. 1 Yes None of the criteria PCE21-0130 0 Revision to ECR-3100-0006-07, Sanitary Water Supply and Tower Cooling LA-3605-0003A Section 3.9.3 listed in 10 CFR Water Return Change and Figures 3.9-2 and 3.9-3 70.72(c) are met.

Description of Change: 1, Revision to this ECR is required to be reviewed against the final system design prior to placing the system into operation. This ECR addresses the reroute of sanitary water supply line and sanitary drain line due to insufficient sanitary water drain capacity per original design and additional requirement for a backflow preventer on the sanitary water supply line.,

LA-3605-0003A was revised to reflect that the Tower Water Cooling Return will be used for sanitary water discharge rather than the sanitary drain during emergency dump mode of operation.

Reason for the Change:

Clarify engineering requirements.

NRC Report 2021 Page 44 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified . Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments NIA

Title:

9/9/2021 No ACP2-EG-026 Chg. 1 No None of the criteria PCE 21-0131 0 Revision to Procedure ACP2-EG-026, Spacing-Exempt and NCS Program listed in 10 CFR Exclusions 70.72(c) are met.

Description of Change:

Revised procedure to correct procedure number reference; to change terminology from "radiation survey to "contamination survey"; clarify interface with NMC&A regarding measurement uncertainty; and add a row to Appendix C for air and nitrogen system piping.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

9/16/2021 No LA-3605-0001 Section 11.7.5 No None of the criteria PCE 21-0132 0 Proposed Changes to NR-3605-0005, Fundamental Nuclear Material NR-3605-0005 Sections 1 - listed in 10 CFR Control Plan for the American Centrifuge Plant; NR-3605-0005B, 17; Tables 4.1; 4.2; 5.1; 5.2; 70.72(c) are met.

Addendum 1 of the Fundamental Nuclear Material Control Plan for the and 6.1 American Centrifuge Plant - HALEU Demonstration; and LA-3605-0001, NR-3605-0005B Sections 1 -

License Application for the American Centrifuge Plant 17; Tables 2.1; 5.1; 5.2; and 5.3 Description of Change:

Proposed changes made to NR-3605-0005, NR-3605-0005B and LA-3605-0001 are administrative changes to standardize terminology/acronyms throughout all documents.

Reason for the Change:

Clarify plan requirements.

N/A

Title:

9/15/2021 No ACP2-EG-010 Chg. 8 No None of the criteria PCE 21-0140 0 Revision to Procedure ACP2-EG-010, Nuclear Criticality Safety Program listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to include two exceptions for including a flowdown procedure step prohibiting use with fissile material when a procedure needs to be made effective before implementation of the NCSE.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 45 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

10/1/2021 No ACP2-NM-111 Chg. 1 No None of the criteria PCE 21-0142 0 Revision to Procedure ACP2-NM-111, Control and Usage of Tamper LA-3605-0001 Acronyms listed in 10 CFR Indicating Devices 70.72(c) are met.

Description of Change:

Revised procedure to make global changes to terminology; update acronyms; revise form AC-706, Tamper Indicating Device (TID); and perform editorial/grammatical corrections.

Revised LA-3605-0001 Acronyms list to show NDA defined as Non-Destructive Analysis.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

9/23/2021 No ACP4-OP-066 Chg. 1 No None of the criteria PCE 21-0144 0 Revision to Procedure ACP4-OP-066, Mass Spectrometer Operation listed iri 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to resolve NMC&A comments regarding the addition of a form and to ensure tails withdrawal requirement is performed and documented.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

9/22/2021 No* PLD1-SP-011 Rev. 5 No None of the criteria PCE 21-0145 0 Revision to Procedure PLD1-SP-011, Electronic/Photographic/Audio listed in 10 CFR Recording/Medical Devices 70.72(c) are met.

/

Description of Change:

Revised procedure to include medical devices in the electronic device review and approval process. Form F-ACP-OR-316 was also revised.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

1017/2021 No ACP2-NM-101 Chg. 1 No None of the criteria PCE 21-0150 0 Revision to Procedure ACP2-NM-101, Accounting for Nuclear Materials listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform gener_al editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page46 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

10/7/2021 No ACP4-NM-217 Chg. 0 No None of the criteria PCE 21-0151 0 Cancellation of Procedure ACP4-NM-217, Journal Entries listed in 10 CFR 70.72(c) are met.

Description of Change:

Cancelled procedure due to utilizi~g the Nuclear Materials Accounting System to record and adjust various nuclear material data. The requirements from this procedure are covered in other NMC&A approved procedures.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

10/20/2021 No ACP2-NM-105 Chg. 1, No None of the criteria PCE 21-0153 0 Revision to Procedure ACP2-NM-105, Control of Nuclear Material Items listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

10/27/2021 No ACP2-NM-114 Chg. 1 No None of the criteria PCE 21-0154 0 Revision to Procedure ACP2-NM-114, Accounting for Receipts and listed in 10 CFR Shipments of Nuclear Materials 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

10/20/2021 No ACP4-ON-066 Chg. 0 No None of the criteria PCE 21-0156 0 New Procedure ACP4-ON-066, Mass Spectrometer Off-Normal Operations listed in 10 CFR 70.72(c) are met.

Description of Change:

New procedure provides responses for Off-Normal events.

Reason for the Change:

Provide implementation requirements.

NRC Report 2021 Page 47 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

11/4/2021 No EE-3100-0003 Rev. 2 Yes None of the criteria PCE 21-0158 0 Revision to Engineering Evaluation EE-3100-0003, Summary of ACP LA-3605-0001 Sections 1.6 listed in 10 CFR Seismic Design Values and 3.6 70.72(c) are met.

LA-3605-0003 Sections 1.9, Description of Change:

2.7, and 6.2 Revised Engineering Evaluation to reference the ASCE 7 standard for seismic analysis procedures and the development of relevant seismic forces for each procedure.

Revised LA-3605-0001 and LA-3605-0003 to reflect the updated Engineering Evaluation as it is referenced in both documents.

Reason for the Change:

Clarify engineering standards.

NIA

Title:

10/13/2021 No ACP2-NM-107 Chg. 1 No None of the criteria PCE 21-0159 0 Revision to Procedure ACP2-NM-107, Shipper/Receiver Difference listed in 10 CFR Monitqring 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

~

N/A

Title:

10/27/2021 No ACP2-NM-103 Chg. 2 No None of the criteria Revison to Procedure ACP2-NM-103, Sampling and Measurement of listed in 10 CFR

- PCE21-0164 0 Nuclear Materials 70._72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 48 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number - Date to SSC? Due to Change Required? Required/Comments NIA

Title:

10/27/2021 No ACP2-NM-101 Chg. 2 No None of the criteria PCE 21-0165 0 Revision to Procedure ACP2-NM-101, Accounting for Nuclear Materials listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize j' terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

10/27/2021 No ACP2-NM-113 Chg. 1 No None of the criteria PCE 21-0166 0 Revision to Procedure ACP2-NM-113, Nuclear Material Control & listed in 10 CFR Accountability Software Configuration Management* 70.72(c) are met.

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

10/20/2021 No ACP4-NM-215 Chg. 1 No None of the criteria PCE 21-0167 0 Revision to Procedure ACP4-NM-215, Item Monitoring Program listed in 10 CFR 70.72(c) are met.

Description of Change:

- Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

10/27/2021 No ACP2-NM-106 Chg. 2 No None of the criteria PCE 21-0169 0 Revision to Procedure ACP2-NM-106, Performance of Nuclear Material listed in 10 CFR Inventory 70.72(c) are met.

Description of Change:

Revised procedure to*perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 49 of 52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

10/22/2021 No ACP2-EG-010 Chg. 9, No None of the criteria PCE 21-0170 0 Revision to Procedure ACP2-EG-010, Nuclear Criticality Safety Program listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to provide an additional allowance for controlling operations as non-fissile when procedures are made effective prior to the NCSE effective date.

Reason for the Change:

Clarify procedure requirements.

N/A

Title:

11/1/2021 No MCRs 9688, 10206 No None of the criteria PCE 21-0176 0 Evaluation of Use-As-ls dispositions for Material Concern Reports (MGR) MGR CAPA 01529 listed in 10 CFR 9688, 10206, and MGR Corrective Action Preventative Action (CAPA) 70.72(c) are met.

01529 Description of Change:

MCRs 9688, 10206, and MGR CAPA 01529 are dispositioned Use-As-ls.

MGR 9688 was issued for fingerprints on centrifuge parts. MGR 10206 was issued for a centrifuge vacuum flex line with a small dent on the bellows surface. MCR CAPA 01529 waives certain centrifuge leak test requirements listed in Engineering Process Specification EPS-00137.

ACD2-QM-107, Control of Nonconforming Items requires a Change Evaluation for dispositions of Use-As-ls on MCRs.

Reason for the Change:

Evaluation for dispositions of Use-As-ls on MCRs.

N/A

Title:

11/16/2021 No ACP2-NM-115 Chg. 1 No None of the criteria PCE 21-0181 0 Revision to Procedure ACP2-NM-115, Cascade Transactions listed in 10 CFR 70.72(c) are met.

DescripJion of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; organizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 50 of-52

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change Required? Required/Comments N/A

Title:

11/16/2021 No ACP2-NM-116 Chg. 1 No None of the criteria PCE 21-0182 0 Revision to Procedure ACP2-NM-116, UF6 Cylinder Transactions listed in 10 CFR 70.72(c) are met.*

Description of Change:

Revised procedure to perform global changes to standardize terminology/acronyms; rganizational clarifications; and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify pro~ure requirements.

NIA

Title:

11/16/2021 No ACP2-NM-109 Chg. 1 No None of the criteria PCE 21-0184 0 Revision to Procedure ACP2-NM-109, Statistical Applications in Nuclear listed in 10 CFR Material Control and Accountability 70.72(c) are met.

Description of Change:

Revised procedure to perform a number of global changes to standardize terminology/acronyms, organizational clarifications and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

11/23/2021 No ACP4-NM-205 Chg. 1 No None of the criteria PCE 21-0185 0 Revision to Procedure ACP4-NM-205, NonsUF6 Transactions listed in 10 CFR 70.72(c) are met.

Description of Change:

Revised procedure to perform a number of global changes to standardize terminology/acronyms, organizational clarifications and perform general editorial, order of steps, capitalization/grammatical/formatting corrections.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 51 of 52

~

ISA FCE Number Summary Reason NRC Rev. Approval Change Documents Modified Update Preapproval Not PCE Number Date to SSC? Due to Change ,Required? Required/Comments NIA

Title:

12/10/2021 No ACP2-OP-037 Chg. 1 No None of the criteria PCE 21-0188 0 Revision to Procedures ACP2-OP-037, Requirements for Use of Service ACP4-OP-031 Chg. 1 listed in 10 CFR Carts; ACP4-OP-031, Tails Cold Box Operation; and ACP4-OP-032, ACP4-OP-032 Chg. 1 70.72(c) are met.

Pro9uct Cold Box Operation Description of Change:

Revised procedure ACP2-OP-037 to add IROFS requirements for various carts and HLD; add references/acronyms; and add Post Work Activity guidance from ACP2-EG-026. Revised procedure ACP4-OP-031 to provide added direction and procedure steps. Revised ACP4-OP-032 to update form AC-764 and add steps to provide additional direction.

Reason for the Change:

Clarify procedure requirements.

NIA

Title:

12/28/2021 No Oak Ridge Work Order WO- No None of the criteria PCE 21-0191 0 Work Order WO-21-0605, Relocating Field Panel 21-0605 Rev. O listed fn 10 CFR 70.72(c) are met.

Description of Change:

A field panel is being relocated at the Technology and Manufacturing Center (TMC).

Reason for the Change:

Relocation of the field panel is required for upcoming projects in Oak Ridge, TN NIA

Title:

12/29/2021 No PLD2-SP-002 Rev. 4 No None of the criteria

-PCE 21-0192 0 Revision to Procedure PLD2-SP-002, Security Systems Maintenance and listed in 10 CFR Testing Procedure 70.72(c) are met.

Description of Change:

Revised procedure to perform a periodic review; remove the term DOE and replace with NRC as applicable throughout document; correct titles throughout document; update references and revised and added steps to clarify procedure requirements for testing.

Reason for the Change:

Clarify procedure requirements.

NRC Report 2021 Page 52 of 52