Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010
ML23186A206
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 07/06/2023
From: Matthew Domke
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023010
Download: ML23186A206 (1)


Text

July 6, 2023

SUBJECT:

LASALLE COUNTY STATION, UNIT 2 - INFORMATION REQUEST FOR A NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL 05000374/2023010

Dear David Rhoades:

On September 11, 2023, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-Approval Site Inspection for License Renewal at Lasalle County Station, Unit 2. This inspection will be performed in accordance with NRC Inspection Procedure (IP) 71003. This inspection will focus on verifying that license conditions added as part of your renewed license and a sample of license renewal commitments have been implemented.

In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:

The first group lists information necessary for our initial inspection scoping and in-office preparation activities. During the in-office preparation activities, the team will identify as much as possible the information and activities to be reviewed during the inspection.

This information should be provided to the lead inspector by August 21, 2023.

The second group includes the additional information required for the team to review selected activities. This information should be available to the team onsite September 11, 2023. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated.

The lead inspector for this inspection is Mr. Matthew Domke. We understand that our licensing contact for this inspection is Mr. Jereme Greenblott of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9562. This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.

In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390 of the NRC's

"Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, Signed by Domke, Matthew on 07/06/23 Matthew Domke, Reactor Inspector Engineering Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure:

Post-Approval Site Inspection License Renewal Request for Information cc: Distribution via LISTSERV