2017 Pal Ile Sim and Inplant JPMs
ML22166A470
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/22/2017
From: Randy Baker
NRC/RGN-III/DRS/OLB
To:
Entergy Nuclear Operations
Baker R
Shared Package
ML17037C872 List:
References
Download: ML22166A470 (103)


Text

JPM SYSTEM A PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS A TITLE: Synchronize Main Turbine Generator to Grid CANDIDATE:

EXAMINER:

PALISADES NUCLEAR PLANT Page 1 of 13 FEBRUARY 2017

JPM SYSTEM A JOB PERFORMANCE MEASURE DATA PAGE Task: Synchronize Main Turbine Generator to Grid Alternate Path: No Facility JPM #: 2001 NRC Exam K/A: 045.A4.02 Importance: RO: 2.7 SRO: 2.6 K/A Statement: Ability to manually operate and/or monitor in the control room: T/G controls, including breakers.

Task Standard: Turbine/Generator has been synchronized to the grid, with both generator breakers closed Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

SOP-8, Main Turbine and Generating Systems GOP-4, MODE 2 to MODE 1 Validation Time: 30 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 13 FEBRUARY 2017

JPM SYSTEM A EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-8, Main Turbine and Generating Systems, completed up to Step 7.1.3.b.

GOP-4, Mode 2 to Mode 1 Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

Special Note: Assume that all Plant Requirements and Precautions and Limitations have been reviewed and complied with. You are NOT expected, nor are you required to consult the Plant Requirements and Precautions and Limitations section of any procedure for this JPM.

INITIAL CONDITIONS:

  • The plant is in MODE 2 and a Turbine/Generator startup is in progress. Main Turbine speed is 1800 RPM. All pre-op testing has been completed.
  • GOP-4 is in progress and GCL-4 is complete up to Step 4.3
  • SOP-8, Main Turbine and Generating Systems steps up to, and including SOP-8, Section 7.1.3.a (Placing Main Transformer Coolers in service) have been completed.

INITIATING CUES:

  • The Control Room Supervisor has directed you to synchronize the Main Generator to the grid, in accordance with SOP-8, Section 7.1.3.b, c, d, e, and f.
  • An operator is available to operate the primary systems, including the reactor.

PALISADES NUCLEAR PLANT Page 3 of 13 FEBRUARY 2017

JPM SYSTEM A Time Start: ________

Evaluator Cue: Provide candidate with a working copy of SOP-8 completed up to Step 7.1.3.b.

Proc.

Step TASK ELEMENT 1 STANDARD Grade Obtains copy of SOP-8 and refers to N/A Obtain current procedure. S U Section 7.1.3.b.

Comment:

Proc. Step TASK ELEMENT 2 STANDARD Grade CLOSE field breaker 341 and verify Field breaker switch 341/CS closed and 7.1.3.b.1 Main Generator terminal voltage terminal voltage at approx. 10 kV. S U stabilizes at approx. 10 kV.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade Adjust 370DC/CS Voltage Regulator Terminal voltage at approx. 22 kV, and 7.1.3.b.3 S U DC Adjuster to raise terminal voltage. NOT exceeding 23.1 kV Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 4 STANDARD Grade Directs NPO to RESET Loss of Sensing Ensure Loss of Sensing module is module by performing the following inside RESET (inside EC-281, Voltage Cabinet EC-281:

7.1.3.b.4 S U Regulator Cabinet - in the DEH

  • PRESS RESET pushbutton to reset room) module
  • VERIFY red LIGHT is extinguished.

Comment:

Evaluator Cue: Acknowledge applicants request for NPO to reset Loss of Sensing Module and reply The Loss of Sensing module has been reset and the red LED light is out PALISADES NUCLEAR PLANT Page 4 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 5 STANDARD Grade Place Voltage Regulator Control Voltage Regulator Control Switch in 7.1.3.b.5 S U Switch 390CS in TEST. TEST. AMBER light is LIT.

Comment:

Proc. Step TASK ELEMENT 6 STANDARD Grade Adjust the Voltage Regulator AC AC Adjuster control operated to change 7.1.3.b.6 Adjuster 390AC/CS to change the the Regulator Balance Meter indication to S U Regulator Balance Meter indication. between +5 and -5 volts.

Comment:

Evaluator Note: This step verifies the Voltage Regulator is operable.

Proc. Step TASK ELEMENT 7 STANDARD Grade Adjust the AC Adjuster 390AC/CS to Regulator Balance Meter indication is at 7.1.3.b.7 S U zero the Regulator Balance Meter. 0".

Comment:

Proc. Step TASK ELEMENT 8 STANDARD Grade Place Voltage Regulator Control Voltage Regulator Control Switch to 7.1.3.b.8 Switch 390CS to ON and verify S U ON and red lamp LIT.

red lamp lights.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 9 STANDARD Grade Check terminal voltage for Main Generator Terminal Voltage 7.1.3.b.9 S U stability. meter is checked for stable indication.

Comment:

Evaluator Cue: If applicant determines generator terminal voltage is low (~21.5kV), acknowledge report and have applicant continue to synchronize the Main Generator.

PALISADES NUCLEAR PLANT Page 5 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 10 STANDARD Grade If terminal voltage is NOT stable, Voltage Regulator Control Switch in return Voltage Regulator Control 7.1.3.b.10 TEST or OFF is terminal voltage is NOT S U Switch to TEST or OFF.

stable.

Comment:

Proc.

Step TASK ELEMENT 11 STANDARD Grade Ensure Turbine speed is near 1800 7.1.3.c Turbine speed near 1800 rpm. S U rpm.

Comment:

Proc. Step TASK ELEMENT 12 STANDARD Grade Locates removable sync switch handle and inserts in sync scope and turns to ON 7.1.3.d.1 Turn Sync Scope for 25F7 to ON. S U for Main Generator breaker 25F7.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 13 STANDARD Grade Uses AC Adjuster to raise or lower generator voltage such that Incoming Adjust Incoming voltage to match voltage and Running voltage are closely 7.1.3.d.2 S U Running voltage. matched. Monitors Main Generator terminal voltage to ensure it does not reach 23.1 kV.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 14 STANDARD Grade Uses Voltage Select Switch to check that Verify all three phases are closely 7.1.3.d.4 each of the three phase voltages differ by S U matched.

less than 1 kV.

Comment:

Proc. Step TASK ELEMENT 15 STANDARD Grade Request Transmission System Verifies with TSC that permission is given 7.1.3.e Coordinator (TSC) permission to S U to synchronize to the grid.

synchronize to the grid.

Comment:

Evaluator Note: It is acceptable if candidate obtains this information from the CRS Evaluator Cue: Transmission System Coordinator has given permission to synchronize to the grid Proc. Step TASK ELEMENT 16 STANDARD Grade Checks 25F7 and 25H9 GREEN lights 7.1.3.f.1&2 Ensure OPEN 25F7 and 25H9. S U ON and RED lights OFF on panel C-01.

Comment:

Evaluator Note: May also check indication on panel C-07, but this is NOT required.

Proc.

Step TASK ELEMENT 17 STANDARD Grade Checks 26H5 RED light ON and GREEN 7.1.3.f.3 Ensure CLOSED MOD 26H5. S U light OFF.

Comment:

Evaluator Note: May check indications on Panel C-07 Proc.

Step TASK ELEMENT 18 STANDARD Grade Ensure the Reactor Operator is ready Checks with Reactor Operator to ensure 7.1.3.f.4 S U to raise load. ready to raise load.

Comment:

Evaluator Note: A surrogate operator or instructor will function as the Reactor Operator.

PALISADES NUCLEAR PLANT Page 7 of 13 FEBRUARY 2017

JPM SYSTEM A Proc.

Step TASK ELEMENT 19 STANDARD Grade Adjust Turbine Speed to get Sync Sync Scope is turning slowly in the 7.1.3.f.5 Scope turning slowly in the clockwise S U clockwise (fast) direction.

(fast) direction Comment:

Proc.

Step TASK ELEMENT 20 STANDARD Grade Ensure Valve Position Limiter is at Checks DEH screen Valve Position 7.1.3.f.6 S U approximately 10%. Limiter indication at approximately 10%.

Comment:

Proc.

Step TASK ELEMENT 21 STANDARD Grade Ensure Turbine Bypass Controller Checks Turbine Bypass Controller in 7.1.3.f.7 PIC-0511 is in AUTO with a setpoint S U AUTO with setpoint at 900 psi.

of 900 psig.

Comment:

Proc.

Step TASK ELEMENT 22 STANDARD Grade Establish the following parameters (Reactor Operator):

  • Reactor Power less than or equal to 13% power (highest of T or NI Checks with Reactor Operator to ensure 7.1.3.f.8 power). the above parameters are met before S U
  • Tave less than or equal to 540°F synchronizing.
  • PIC-0511, Turbine Bypass Controller output signal greater than 60%.

Comment:

Proc.

Step TASK ELEMENT 23 STANDARD Grade Close 25F7 breaker as Sync scope 7.1.3.f.9 25F7 closed and closed light illuminated S U nears 1200 hours0.0139 days <br />0.333 hours <br />0.00198 weeks <br />4.566e-4 months <br />.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 8 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 24 STANDARD Grade Directs NPO to verify all three phase Locally verify closed all three phases 7.1.3.f.11 targets for 25F7 indicate RED. Sync S U of 25F7 and turn sync scope to OFF.

scope for 25F7 turned to OFF.

Comment:

Evaluator Cue: When requested as NPO to locally verify 25F7, report all three targets indicate RED Proc. Step TASK ELEMENT 25 STANDARD Grade Checks DEH screen indications or panel Verify the Generator has picked up a 7.1.3.f.13 C-01 Power meter indication and verifies S U minimum of 20MW load at least 20 MW.

Comment:

Proc. Step TASK ELEMENT 26 STANDARD Grade Verify Turbine Bypass Valve CV- Checks CV-0511 controller to verify valve 7.1.3.f.14 S U 0511 is closing. closing.

Comment:

Evaluator Note: Also acceptable to ask Reactor Operator if CV-0511 is closing.

Proc. Step TASK ELEMENT 27 STANDARD Grade Locates removable sync switch handle Turn Sync Scope for 25H9 to ON.

7.1.3.f.15 and inserts in sync scope and turns to S U ON for Main Generator breaker 25H9.

Comment:

Proc. Step TASK ELEMENT 28 STANDARD Grade 7.1.3.f.16 Close 25H9 breaker. 25H9 closed and closed light illuminated S U Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 9 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 29 STANDARD Grade Directs NPO to verify all three phase Locally verify closed 25H9 and turn 7.1.3.f.18 targets for 25H9 indicate RED. Sync S U sync scope to OFF.

scope for 25H9 turned to OFF.

Comment:

Evaluator Cue: When requested as NPO to locally verify 25H9, report all three targets indicate RED PALISADES NUCLEAR PLANT Page 10 of 13 FEBRUARY 2017

JPM SYSTEM A Proc. Step TASK ELEMENT 30 STANDARD Grade Informs Control Room Supervisor that Inform Control Room Supervisor of 7.1.3.f.19 Main Turbine/Generator has been S U completion.

synchronized to the grid at minimum load.

Comment:

Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 11 of 13 FEBRUARY 2017

JPM SYSTEM A SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-175 PALISADES NUCLEAR PLANT Page 12 of 13 FEBRUARY 2017

JPM SYSTEM A CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

Special Note: Assume that all Plant Requirements and Precautions and Limitations have been reviewed and complied with. You are NOT expected, nor are you required to consult the Plant Requirements and Precautions and Limitations section of any procedure for this JPM.

INITIAL CONDITIONS:

  • The plant is in MODE 2 and a Turbine/Generator startup is in progress. Main Turbine speed is 1800 RPM. All pre-op testing has been completed.
  • GOP-4 is in progress and GCL-4 is complete up to Step 4.3
  • SOP-8, Main Turbine and Generating Systems steps up to, and including SOP-8, Section 7.1.3.a (Placing Main Transformer Coolers in service) have been completed.

INITIATING CUES:

  • The Control Room Supervisor has directed you to synchronize the Main Generator to the grid, in accordance with SOP-8, Section 7.1.3.b, c, d, e, and f.
  • An operator is available to operate the primary systems, including the reactor.

PALISADES NUCLEAR PLANT Page 13 of 13 FEBRUARY 2017

JPM SYSTEM B PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS B TITLE: RESPOND TO SAFETY INJECTION TANK HIGH PRESSURE CANDIDATE:

EXAMINER:

PALISADES NUCLEAR PLANT Page 1 of 8 FEBRUARY 2017

JPM SYSTEM B JOB PERFORMANCE MEASURE DATA PAGE Task: Respond to Safety Injection Tank High Pressure Alternate Path: No Facility JPM #: N/A (new)

K/A: 006.A1.13 Importance: RO: 3.5 SRO: 3.7 K/A Statement: Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the ECCS controls including: Accumulator pressure (level, boron concentration).

Task Standard: Vent Safety Injection Tank T-82A to clear the high pressure alarms.

Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

ARP-8 SOP-3 Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 FEBRUARY 2017

JPM SYSTEM B EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-3, Safety Injection and Shutdown Cooling System Section 7.5.5 ARP-8, Safeguards Safety Injection and Isolation Scheme EK-13 (EC-13)

Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The Plant is at 25% power during initial power ascension.
  • Safety Injection Tank T-82A has received alarms for high pressure.

INITIATING CUES:

Respond to the Safety Injection Tank (SIT) pressure alarms and adjust pressure in SIT T-82A to clear the alarms.

PALISADES NUCLEAR PLANT Page 3 of 8 FEBRUARY 2017

JPM SYSTEM B Time Start: _______

Proc.

Step TASK ELEMENT 1 STANDARD Grade Respond to alarm(s) EK-1316 and/or Obtain ARP-8 and respond to alarm(s)

N/A S U EK-1317. Obtain ARP-8 EK-1316/1317 Comment:

Proc.

Step TASK ELEMENT 2 STANDARD Grade Check closed T-82A Nitrogen fill N/A CV-3040 closed S U valve CV-3040 Comment:

Proc.

Step TASK ELEMENT 3 STANDARD Grade Check T-82A tank level normal on Tank level is stable in normal band. Only N/A S U LIA-0365 pressure is high.

Comment:

Evaluator Cue: When applicant has obtained SOP-3 and identified Section 7.5.5 to vent the SIT, provide applicant with a working copy of SOP-3 Section 7.5.5.

Proc.

Step TASK ELEMENT 4 STANDARD Grade Informs CRS to review TS LCO 3.5.1 Informs CRS to review TS LCO 3.5.1 7.5.5.a S U applicability. applicability.

Comment:

Evaluator Cue: Inform applicant that CRS is reviewing TS applicability.

Proc.

Step TASK ELEMENT 5 STANDARD Grade Ensure closed SIT fill and drain 7.5.5.b valves for T-82A CV-3039 is closed S U

  • CV-3039 Comment:

Evaluator Note: Step 7.5.5.c is Not Applicable as the applicant should not be depressurizing the SIT to

< 200 psig (minimum nitrogen cover pressure for operability).

PALISADES NUCLEAR PLANT Page 4 of 8 FEBRUARY 2017

JPM SYSTEM B Proc.

Step TASK ELEMENT 6 STANDARD Grade Ensure open CWRT Vent Isolation Valves:

7.5.5.d CV-1064 and CV-1065 open S U

  • CV-1064
  • CV-1065 Comment:

Proc.

Step TASK ELEMENT 7 STANDARD Grade Prior to opening the vent valve, inform the CRS of inoperability of T- Inform the CRS of T-82A inoperability 7.5.5.e S U 82A due to the vent valve being upon opening the vent valve.

opened.

Comment:

Proc.

Step TASK ELEMENT 8 STANDARD Grade Open the vent valve for the SIT to be 7.5.5.e vented (T-82A): Open CV-3067 to begin the venting. S U

  • CV-3067 Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 9 STANDARD Grade Check Waste Gas Surge Tank T-67 Direct NPO to check Waste Gas Surge 7.5.5.f pressure and Primary System Drain Tank and Primary System Drain Tank S U Tank T-74 pressure. pressures.

Comment:

Evaluator Cue: Tank pressures are normal and an NPO is monitoring at the C-40 Panel.

PALISADES NUCLEAR PLANT Page 5 of 8 FEBRUARY 2017

JPM SYSTEM B Proc.

Step TASK ELEMENT 10 STANDARD Grade When venting is completed, close CV-3067 closed prior to reaching SIT 7.5.5.g S U CV-3067 inoperability of < 200 psig.

Comment:

CRITICAL STEP Time End: _______

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 8 FEBRUARY 2017

JPM SYSTEM B SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-177 PALISADES NUCLEAR PLANT Page 7 of 8 FEBRUARY 2017

JPM SYSTEM B CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The Plant is at 100% power
  • Safety Injection Tank T-82A has received alarms for high pressure.

INITIATING CUES:

Respond to the Safety Injection Tank (SIT) pressure alarms and adjust pressure in SIT T-82A to clear the alarms.

PALISADES NUCLEAR PLANT Page 8 of 8 FEBRUARY 2017

JPM SYSTEM C PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO SYS C TITLE: Respond to Control Room Outside Air Intake Radiation Monitor Alarms CANDIDATE:

EXAMINER:

PALISADES NUCLEAR PLANT Page 1 of 9 FEBRUARY 2017

JPM SYSTEM C JOB PERFORMANCE MEASURE DATA PAGE Task: Respond to Control Room Outside Air Intake Radiation Monitor Alarms Alternate Path: No Facility JPM #: N/A (new)

K/A: 061.AA1.01 Importance: RO: 3.6 SRO: 3.6 K/A Statement: Ability to operate and/or monitor the following as they apply to the Area Radiation Monitoring (ARM) System Alarms: Automatic actuation Task Standard: Respond to a Control Room Outside Air Intake Radiation Monitor alarm by placing the operating CR HVAC train in emergency mode.

Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

ARP-33, Auxiliary Systems Scheme SOP-24, Ventilation and Air Conditioning System Validation Time: 9 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 FEBRUARY 2017

JPM SYSTEM C EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

ARP-33, Auxiliary Systems Scheme SOP-24, Ventilation and Air Conditioning System Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The reactor is critical with power at the POAH
  • MSIV Bypass valves, MO-0501 and MO-0510, are open
  • Vacuum is established on the Main Turbine and the secondary plant is in the process of being started up INITIATING CUES:

You are the NCO-T operator and the Control Room Supervisor has directed you to respond to alarm EK-0239 CR HVAC TRAIN A RIA-1818A HI RAD/FAIL and perform the applicable actions.

PALISADES NUCLEAR PLANT Page 3 of 9 FEBRUARY 2017

JPM SYSTEM C Time Start: _______

Proc.

Step TASK ELEMENT 1 STANDARD Grade N/A Obtain current procedure. Obtains copy of ARP-33 for EK-0239. S U Comment:

Proc.

Step TASK ELEMENT 2 STANDARD Grade Place operating CR HVAC train (A) in Refers to SOP-24 Section 7.7.9 N/A S U emergency mode per SOP-24 Comment:

Proc.

Step TASK ELEMENT 3 STANDARD Grade N/A Obtain a copy of SOP-24 Section 7.7.9 Obtain a copy of SOP-24 Section 7.7.9 S U Comment:

Evaluator Cue: When applicant has obtained SOP-24 Section 7.7.9, provide a clean copy of the procedure section.

Proc. Step TASK ELEMENT 4 STANDARD Grade Ensure operating V-95 Train A Control 7.7.9.a.1 Verify V-95 is operating. S U Room Ventilation Main Supply Fan Comment:

Proc. Step TASK ELEMENT 5 STANDARD Grade Place V-26A Air Filter VF-26A Fan 7.7.9.a.2 Start V-26A S U handswitch to ON Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 FEBRUARY 2017

JPM SYSTEM C Proc.

Step TASK ELEMENT 6 STANDARD Grade Ensure open Train A Outside Air Damper 7.7.9.b Verify D-7 open S U D-7 Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 7 STANDARD Grade Ensure closed Train B Outside Air Verify Train B (not in service) damper D-14 7.7.9.c S U Damper D-14 closed Comment:

Proc.

Step TASK ELEMENT 8 STANDARD Grade Verify Outside Air Damper OR Modulating Damper for each CR HVAC Verify the following dampers are closed:

7.7.9.d Train is closed.

  • D-1 OR D-2 S U
  • D-1 OR D-2 (Train A)
  • D-8 OR D-9
  • D-8 OR D-9 (Train B)

Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 9 STANDARD Grade Verify at least one V-16, Toilet Exhauster, Damper is closed 7.7.9.e Verify damper D-18 or D-17 closed. S U

  • D-18 (Train A)
  • D-17 (Train B)

Comment:

Proc.

Step TASK ELEMENT 10 STANDARD Grade Verify at least one V-94, Control Room Purge Exhaust Fan, Damper is closed:

7.7.9.f Verify damper D-15 or D-16 closed. S U

  • D-15 (Train A)
  • D-16 (Train B)

Comment:

PALISADES NUCLEAR PLANT Page 5 of 9 FEBRUARY 2017

JPM SYSTEM C Proc.

Step TASK ELEMENT 11 STANDARD Grade Verify the following components: Verify the following components:

  • VHX-26A ON
  • VHX-26A ON
  • D-5 Open
  • D-5 Open
  • D-6 Open
  • D-6 Open 7.7.9.g
  • D-20 Modulating
  • D-20 Modulating S U
  • V-26A ON
  • V-26A ON
  • D-3 Open
  • D-3 Open
  • D-4 Open
  • D-4 Open
  • V-95 ON
  • V-95 ON Comment:

Proc.

Step TASK ELEMENT 12 STANDARD Grade Ensure V-94, Control Room Purge 7.7.9.h Verify V-94 OFF S U Exhaust Fan, is OFF Comment:

Proc.

Step TASK ELEMENT 13 STANDARD Grade Ensure V-47, Viewing Gallery &

7.7.9.i Verify V-47 OFF S U Switchgear Rm Emer Ex Fan, is OFF Comment:

Proc.

Step TASK ELEMENT 14 STANDARD Grade With CHP/CHR signal NOT present, 7.7.9.j Verify VC-11 in AUTO S U Place VC-11 control switch to AUTO.

Comment:

Proc.

Step TASK ELEMENT 15 STANDARD Grade As soon as possible following a valid Direct an NPO to verify door positions and 7.7.9.k CAM alarm, verify door functionality and S U functionality per SOP-24 Step 7.7.9.k positions.

Comment:

Evaluator Cue: Inform applicant that another operator will perform door functionality and position checks.

PALISADES NUCLEAR PLANT Page 6 of 9 FEBRUARY 2017

JPM SYSTEM C Proc.

Step TASK ELEMENT 16 STANDARD Grade Verify redundant CRHVAC train in N/A Verify B CRHVAC train not in operation. S U operation.

Comment:

Proc.

Step TASK ELEMENT 17 STANDARD Grade Notify HP to determine validity of CAM N/A Notify HP to determine validity of CAM alarm. S U alarm.

Comment:

Evaluator Cue: Another operator will notify HP to determine validity of CAM alarm.

Time End: ______

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 FEBRUARY 2017

JPM SYSTEM C SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-178 PALISADES NUCLEAR PLANT Page 8 of 9 FEBRUARY 2017

JPM SYSTEM C CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

Special Note: Assume that all Plant Requirements and Precautions and Limitations have been reviewed and complied with. You are NOT expected, nor are you required to consult the Plant Requirements and Precautions and Limitations section of any procedure for this JPM.

INITIAL CONDITIONS:

  • The reactor is critical with power at the POAH
  • MSIV Bypass valves, MO-0501 and MO-0510, are open
  • Vacuum is established on the Main Turbine and the secondary plant is in the process of being started up INITIATING CUES:

You are the NCO-T operator and the Control Room Supervisor has directed you to respond to alarm EK-0239 CR HVAC TRAIN A RIA-1818A HI RAD/FAIL and perform the applicable action PALISADES NUCLEAR PLANT Page 9 of 9 FEBRUARY 2017

JPM SYSTEM D PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS D TITLE: Shift 4160VAC Busses from Startup Power to Station Power CANDIDATE: ______________________________________________

EXAMINER: ______________________________________________

PALISADES NUCLEAR PLANT Page 1 of 11 FEBRUARY 2017

JPM SYSTEM D JOB PERFORMANCE MEASURE DATA PAGE Task: Shift 4160VAC busses from Startup Power to Station Power.

Alternate Path: No Facility JPM #: N/A (new)

K/A: 062.A4.07 Importance: RO: 3.1 SRO: 3.1 K/A Statement: Ability to manually operate and/or monitor in the control room:

Synchronizing and paralleling of different ac supplies.

Task Standard: Transfer 4160VAC busses from Startup Power to Station Power in accordance with SOP-30, Station Power.

Preferred Evaluation Location: Simulator __X__ In Plant ______

Preferred Evaluation Method: Perform __X__ In Plant ______

References:

SOP-30, Station Power Validation Time:15 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 11 FEBRUARY 2017

JPM SYSTEM D EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • SOP-30, section 7.2.1 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The plant is at 25% reactor power with GCL 5.1 of GOP-5 in progress at step 2.12.a.

INITIATING CUES:

The Control Room Supervisor (CRS) has directed you to transfer the power supply for all 4160VAC Busses from Startup Power to Station Power.

PALISADES NUCLEAR PLANT Page 3 of 11 FEBRUARY 2017

JPM SYSTEM D Time Start: ________

Proc.Step TASK ELEMENT 1 STANDARD Grade Locate SOP-30 and determine applicable Obtain a copy of SOP-30, Station Power N/A section 7.2.1 to transfer from Startup Power S U procedure.

to Station Power.

Comment:

Evaluator Cue: When applicant opens SOP-30 Section 7.2.1, provide a clean copy of SOP-30 Section 7.2.1 Proc.Step TASK ELEMENT 2 STANDARD Grade At EC-04, verify Bus 1A and Bus 1B Bus 1A and Bus 1B control power lamps 7.2.1.a.1 S U control power lamps illuminated. illuminated.

Comment:

Evaluator Note: All 4 ED-11-1 and ED-21-1 lights illuminated Proc.Step TASK ELEMENT 3 STANDARD Grade At EC-04, check Startup Xfmr UV aux. Check Startup Xfmr UV aux. relays 227X-5 7.2.1.a.2 S U relays 227X-5 and 227X-6 reset. and 227X-6 reset.

Comment:

Proc.Step TASK ELEMENT 4 STANDARD Grade Check EX-01 Station Power Xfmr No 1-1 Check EX-01 Station Power Xfmr 1-1 Trouble 7.2.1.a.3 Trouble lamp functional by depressing red S U lamp functional by depressing red pushbutton pushbutton Comment:

Proc.Step TASK ELEMENT 5 STANDARD Grade Check voltage on Station Power Xfmr No Check voltage on Station Power Xfmr 1-1 at 7.2.1.a.4 S U 1-1 at ~4160VAC. ~4160VAC Comment:

PALISADES NUCLEAR PLANT Page 4 of 11 FEBRUARY 2017

JPM SYSTEM D Proc.Step TASK ELEMENT 6 STANDARD Grade At EC-106, check Bus 1F and Bus 1G Bus 1F and Bus 1G control power lamps 7.2.1.b.1 S U control power lamps illuminated. illuminated.

Comment:

Proc.Step TASK ELEMENT 7 STANDARD Grade Check voltage on EX-6 Station Power Check voltage on EX-6 Station Power Xfmr 7.2.1.b.2 S U Xfmr 1-3 at ~4160VAC 1-3 at ~4160VAC.

Comment:

Proc.Step TASK ELEMENT 8 STANDARD Grade Direct NPO to check all relays cut in and Direct NPO to check all relays cut in and targets reset on bus and feeder breakers targets reset on bus and feeder breakers for:

for:

7.2.1.c

  • Bus 1A
  • Bus 1A S U
  • Bus 1B
  • Bus 1B
  • Bus 1F
  • Bus 1F
  • Bus 1G
  • Bus 1G Comment:

Evaluator Cue: NPO reports "All relays cut in and targets are reset on bus feeder breakers."

Evaluator Note: Steps 7.2.1.d.1 through 7.2.1.d.6 are repeated for Busses 1A, 1B, 1F, and 1G Proc.Step TASK ELEMENT 9 STANDARD Grade Scope and close Station Power Incoming Scope and close Station Power Incoming 7.2.1.d.1 S U breaker for Bus 1A, 252-101. breaker for Bus 1A, 252-101.

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 10 STANDARD Grade Verify Startup Power Incoming breaker Verify Startup Power Incoming breaker opens 7.2.1.d.2 S U opens on Bus 1A, 252-102 on Bus 1A, 252-102.

Comment:

PALISADES NUCLEAR PLANT Page 5 of 11 FEBRUARY 2017

JPM SYSTEM D Proc.Step TASK ELEMENT 11 STANDARD Grade Place synchscope switch to OFF and Place synchscope switch to OFF and 7.2.1.d.3 S U remove handle. remove handle.

Comment:

Proc.Step TASK ELEMENT 12 STANDARD Grade Verify WHITE Springs Charged lamp lit Verify WHITE Springs Charged lamp lit for 7.2.1.d.4 S U for breaker 252-101. breaker 252-101.

Comment:

Proc.Step TASK ELEMENT 13 STANDARD Grade Match targets on breaker 252-102 by Place breaker 252-102 C/S to trip and verify 7.2.1.d.6 S U taking the C/S momentarily to trip. targets matched.

Comment:

Proc.Step TASK ELEMENT 14 STANDARD Grade Scope and close Station Power Incoming Scope and close Station Power Incoming 7.2.1.d.1 S U breaker for Bus 1B, 252-201. Brkr for Bus 1B, 252-201.

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 15 STANDARD Grade Verify Startup Power Incoming breaker Verify Startup Power Incoming breaker opens 7.2.1.d.2 S U opens on Bus 1B, 252-202. on Bus 1B, 252-202.

Comment:

Proc.Step TASK ELEMENT 16 STANDARD Grade Place synchscope switch to OFF and Place synchscope switch to OFF and 7.2.1.d.3 S U remove handle. remove handle.

Comment:

PALISADES NUCLEAR PLANT Page 6 of 11 FEBRUARY 2017

JPM SYSTEM D Proc.Step TASK ELEMENT 17 STANDARD Grade Verify WHITE Springs Charged lamp lit for Verify WHITE Springs Charged lamp lit for 7.2.1.d.4 S U breaker 252-202. breaker 252-202.

Comment:

Proc.Step TASK ELEMENT 18 STANDARD Grade Match targets on breaker 252-202 by Place breaker 252-202 C/S to trip and verify 7.2.1.d.6 S U taking the C/S momentarily to trip. targets matched.

Comment:

Proc.Step TASK ELEMENT 19 STANDARD Grade Scope and Close Station Power Incoming Scope and Close Station Power Incoming 7.2.1.d.1 S U breaker for Bus 1F, 252-301. breaker for Bus 1F, 252-301.

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 20 STANDARD Grade Verify Startup Power Incoming breaker Verify Startup Power Incoming breaker opens 7.2.1.d.2 S U opens on Bus 1F, 252-302. on Bus 1F, 252-302.

Comment:

Evaluator Note: Applicant may check ARP; no actions to take.

Proc.Step TASK ELEMENT 21 STANDARD Grade Place synchscope switch to OFF and Place synchscope switch to OFF and 7.2.1.d.3 S U remove handle. remove handle.

Comment:

PALISADES NUCLEAR PLANT Page 7 of 11 FEBRUARY 2017

JPM SYSTEM D Proc.Step TASK ELEMENT 22 STANDARD Grade Verify WHITE Springs Charged lamp lit for Verify WHITE Springs Charged lamp lit for 7.2.1.d.4 S U breaker 252-302, breaker 252-302, Comment:

Proc.Step TASK ELEMENT 23 STANDARD Grade Match targets on breaker 252-302 by Place breaker 252-302 C/S to trip and verify 7.2.1.d.6 S U taking the C/S momentarily to trip. targets matched.

Comment:

Proc.Step TASK ELEMENT 24 STANDARD Grade Scope and Close Station Power Incoming Scope and Close Station Power Incoming 7.2.1.d.1 S U breaker for Bus 1G, 252-401. breaker for Bus 1G, 252-401.

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 25 STANDARD Grade Verify Startup Power Incoming breaker opens Verify Startup Power Incoming breaker 7.2.1.d.2 on Bus 1G, 252-402. Acknowledge expected S U opens on Bus 1G, 252-402.

alarm EK-3310.

Comment:

Evaluator Note: Applicant may check ARP; no actions to take.

Proc.Step TASK ELEMENT 26 STANDARD Grade Place synchscope switch to OFF and Place synchscope switch to OFF and 7.2.1.d.3 S U remove handle. remove handle.

Comment:

Proc.Step TASK ELEMENT 27 STANDARD Grade PALISADES NUCLEAR PLANT Page 8 of 11 FEBRUARY 2017

JPM SYSTEM D Verify WHITE Springs Charged lamp lit for Verify WHITE Springs Charged lamp lit for 7.2.1.d.4 S U breaker 252-402, breaker 252-402, Comment:

Proc.Step TASK ELEMENT 28 STANDARD Grade Match targets on breaker 252-402 by Place breaker 252-402 C/S to trip and verify 7.2.1.d.6 S U taking the C/S momentarily to trip. targets matched.

Comment:

Time End: ________

END OF TASK PALISADES NUCLEAR PLANT Page 9 of 11 FEBRUARY 2017

JPM SYSTEM D SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-177 PALISADES NUCLEAR PLANT Page 10 of 11 FEBRUARY 2017

JPM SYSTEM D CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

Special Note: Assume that all Plant Requirements and Precautions and Limitations have been reviewed and complied with. You are NOT expected, nor are you required to consult the Plant Requirements and Precautions and Limitations section of any procedure for this JPM.

INITIAL CONDITIONS:

The plant is at 25% reactor power with GCL 5.1 of GOP-5 in progress at step 2.12.a.

INITIATING CUES:

The Control Room Supervisor (CRS) has directed you to transfer the power supply for all 4160VAC Busses from Startup Power to Station Power.

PALISADES NUCLEAR PLANT Page 11 of 11 FEBRUARY 2017

JPM SYSTEM E PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS E TITLE: OPEN MAIN STEAM ISOLATION VALVES AFTER REACTOR IS CRITICAL CANDIDATE: _____________________________________________

EXAMINER: _____________________________________________

PALISADES NUCLEAR PLANT Page 1 of 9 FEBRUARY 2017

JPM SYSTEM E JOB PERFORMANCE MEASURE DATA PAGE Task: Open MSIVs Alternate Path: Yes Facility JPM #: 2010 NRC Exam K/A: 035 K6.01 Importance: RO: 3.2 SRO: 3.6 K/A Statement: Knowledge of the effect of a loss or malfunction of the following will have on the S/Gs: MSIVs Task Standard: Both MSIVs Open, MSIV bypasses closed, ADVs and TBV in AUTO Preferred Evaluation Location: Simulator _X__ In Plant ______

Preferred Evaluation Method: Perform _X__ Simulate ______

References:

SOP-7, Main Steam System Validation Time:15 minutes Time Critical: NO Candidate: _________________________________________

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 FEBRUARY 2017

JPM SYSTEM E EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-7, "Main Steam System" Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The reactor is critical with power at the Point of Adding Heat
  • MSIV Bypass valves, MO-0501 and MO-0510, are open
  • Vacuum is established on the Main Turbine and the secondary plant is in the process of being started up INITIATING CUES:

The Control Room Supervisor directs you to open the MSIVs per SOP-7, starting at step 7.2.2.c.

PALISADES NUCLEAR PLANT Page 3 of 9 FEBRUARY 2017

JPM SYSTEM E Time Start: ______

Evaluator Cue: Provide candidate a working copy of SOP-7, section 7.2.2.

Proc.

Step TASK ELEMENT 1 STANDARD Grade Applicant contacts NPO to latch all MSIV 7.2.2.c LATCH MSIV solenoid valves. solenoids in the turbine building and 'D' bus S U area.

Comment:

Simulator Operator: Use MS36 on P&ID MS02, DO NOT latch 'A' MSIV (MS25) but report that it is complete.

Proc.

Step TASK ELEMENT 2 STANDARD Grade IF MSIVs opened after performance of Applicant determines that CV-0510, 'A' S/G 7.2.2.d S U Step 7.2.2c, THEN GO TO Step 7.2.2q. MSIV, did not open. Proceeds to step 7.2.2.e Comment:

Evaluator Cue: If applicant questions the CRS, then direct applicant to proceed to step 7.2.2.e.

CRITICAL STEP Proc.

Step TASK ELEMENT 3 STANDARD Grade Applicant performs the following:

Establish conditions to open CV-0511, 7.2.2.e

  • ENSURE CV-0511 is open slightly S U Turbine Bypass to Condenser:
  • Quickly CLOSE CV-0511 Comment:

Proc.

Step TASK ELEMENT 4 STANDARD Grade Applicant performs the following:

ENSURE CV-0511, Turbine Bypass to

  • Sets PIC-0511, Turbine Bypass Control 7.2.2.f Condenser, remains CLOSED by Valve to CLOSE. S U performing the following:
  • Have NPO Close MV-CA390, Turbine Bypass CV-0511 A/S Isolation.

Comment:

Simulator Operator: Use MS35 on PIDMS03 to close air supply to CV-0511, then notify as NPO that air supply is closed and accumulator is bled down PALISADES NUCLEAR PLANT Page 4 of 9 FEBRUARY 2017

JPM SYSTEM E Proc.

Step TASK ELEMENT 5 STANDARD Grade PERFORM the following notifications of Applicant informs CRS to notify Chemistry and 7.2.2.g S U impending Steam Dump operation: to refer to ADMIN 4.00.

Comment:

Evaluator Cue: Inform applicant that the Shift Engineer will perform these notifications.

Proc.

Step TASK ELEMENT 6 STANDARD Grade Applicant directs NPO to close the following CLOSE three of the four Steam Dump Air valves in the ADV control cabinet:

7.2.2.h Supplies for the MSIV to be opened,

  • MV-CA779 S U listed below:
  • MV-CA780
  • MV-CA781 OR MV-CA782 Comment:

Evaluator Cue: LCO 3.7.4.A is applicable. If applicant asks, notify them that the CRS will address LCO 3.7.4.

Simulator Operator: Use MS18, MS19, MS20 (or MS21) on PID MS01 to close these valves CRITICAL STEP Proc. Step TASK ELEMENT 7 STANDARD Grade

  • Places HIC-0780A in Manual MANUAL.

7.2.2.i & j

  • Operates manual output lever to open S U
  • OPERATE HIC-0780A toward 100%

ADV until MSIV CV-0510 opens.

OPEN position to equalize DP across MSIV.

Comment:

Evaluator Cue: If applicant asks, inform them that the required notifications are made.

Evaluator Note: CV-0510 will latch when HIC-0780A reaches ~25% output.

CRITICAL STEP Proc.

Step TASK ELEMENT 8 STANDARD Grade WHEN MSIV opens, THEN PLACE 7.2.2.k Operates manual output lever to close ADV. S U HIC-0780A to CLOSE position.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 9 FEBRUARY 2017

JPM SYSTEM E Proc.

Step TASK ELEMENT 9 STANDARD Grade Directs NPO to open:

OPEN Steam Dump Air Supplies closed

  • MV-CA779 7.2.2.l S U in Step 7.2.2g above.
  • MV-CA780
  • MV-CA781 OR MV-CA782 Comment:

Simulator Operator: Use MS18, MS19, MS20 (or MS21) on PID MS01 to open the valves that were closed in Task Element #6.

CRITICAL STEP Proc.

Step TASK ELEMENT 10 STANDARD Grade IF both MSIVs did NOT open, THEN Determines this step is N/A because both 7.2.2.m REPEAT Steps 7.2.2g through 7.2.2k for S U MSIVs are now open.

affected MSIV.

Comment:

Proc. Step TASK ELEMENT 11 STANDARD Grade

valve.

  • OPEN MV-CA390, Turbine Bypass
  • OPEN MV-CA390, Turbine Bypass CV-0511 A/S Isol. CV-0511 A/S Isol.

Comment:

Simulator Operator: Use MS35 on PIDMS03 to open air supply to CV-0511.

CRITICAL STEP Proc. Step TASK ELEMENT 12 STANDARD Grade

  • RETURN HIC-0780A to AUTO or the AS FOUND position. Places HIC-0780A and CV-0511 in AUTO by 7.2.2.p&q depressing the 'A' button on their controllers S U
  • RETURN PIC-0511 to AUTO or the and verifying the 'A' button lights.

AS FOUND position.

Comment:

Evaluator Cue: If asked, inform candidate that PIC-0511 and HIC-0780A should be placed back in AUTO.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 9 FEBRUARY 2017

JPM SYSTEM E Proc.

Step TASK ELEMENT 13 STANDARD Grade CLOSE the following valves:

  • MO-0501, MSIV CV-0501 Bypass Closes MO-0501 and MO-0510 by holding 7.2.2.r (MZ-3) switch in the CLOSE position until associated S U
  • MO-0510, MSIV CV-0510 Bypass Green light is ON and Red light is OFF.

(MZ-2)

Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 14 STANDARD Grade Applicant informs the CRS that the N/A MSIVs are open and the MSIV bypasses CRS informed. S U are closed.

Comment:

Time Stop: _____

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 FEBRUARY 2017

JPM SYSTEM E SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-178
  • Load Schedule E PALISADES NUCLEAR PLANT Page 8 of 9 FEBRUARY 2017

JPM SYSTEM E CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The reactor is critical with power at the Point of Adding Heat
  • MSIV Bypass valves, MO-0501 and MO-0510, are open
  • Vacuum is established on the Main Turbine and the secondary plant is in the process of being started up INITIATING CUES:

The Control Room Supervisor directs you to open the MSIVs per SOP-7, starting at step 7.2.2.c.

PALISADES NUCLEAR PLANT Page 9 of 9 FEBRUARY 2017

JPM SYSTEM F PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS F TITLE: PCS Inventory Control CANDIDATE:

EXAMINER:

PALISADES NUCLEAR PLANT Page 1 of 10 FEBRUARY 2017

JPM SYSTEM F JOB PERFORMANCE MEASURE DATA PAGE Task: Establish the Containment Sump as the ECCS suction source following a Large Break LOCA Alternate Path: Yes Facility JPM #: 2005 NRC Exam (modified)

K/A: 013A4.03 Importance: RO: 4.5 SRO: 4.7 K/A Statement: Ability to manually operate and/or monitor in the control room: ESFAS initiation Task Standard: Obtain and utilize EOP Supplement 42, Post-RAS Actions, to realign the ECCS flow paths to the Containment Sump.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

EOP Supplement 42, Pre and Post RAS Actions Validation Time:15 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 10 FEBRUARY 2017

JPM SYSTEM F EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • EOP Supplement 42, Pre and Post RAS Actions
  • EOP-4.0, Loss of Coolant Accident Recovery Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • A large break LOCA has occurred.
  • The Plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed.
  • EOP-4.0, Loss of Coolant Accident Recovery, has been entered.
  • SIS and CHP have actuated.
  • Pre-RAS actions have been taken per EOP Supplement 42.
  • RAS is imminent.

INITIATING CUES:

During performance of EOP-4.0 step 52, the Control Room Supervisor directs you to perform Post-RAS actions in accordance with EOP Supplement 42, step 2.0 when RAS occurs.

PALISADES NUCLEAR PLANT Page 3 of 10 FEBRUARY 2017

JPM SYSTEM F Time Start: _____

Evaluator Cue: If requested, provide applicant with working copy of EOP-4.0.

Proc.

Step TASK ELEMENT 1 STANDARD Grade When applicant indicates where to find current Obtain a copy of EOP Supplement 42, N/A copy of procedure PROVIDE a copy of EOP S U POST-RAS Actions.

Supplement 42.

Comment:

Evaluator Cue: When applicant has located EOP Supplement 42, provide them with a working copy of the procedure.

Proc.

Step TASK ELEMENT 1 STANDARD Grade When SIRWT level lowers to < 2%,

Start Step 2.0 of EOP Supplement 42, Post-2.1 perform Step 2.0 of EOP Supp. 42, Post- S U RAS Actions when SIRWT is < 2%.

RAS Actions.

Comment:

Proc.

Step TASK ELEMENT 2 STANDARD Grade When SIRWT level lowers to below 2%,

2.1.a.1 Verify both LPSI pumps trip on the RAS. S U verify both LPSI pumps trip.

Comment:

Proc.

Step TASK ELEMENT 3 STANDARD Grade Check open both Containment Sump Verify:

Isolation Valves:

  • CV-3030 opened 2.1.b S U
  • CV-3030
  • CV-3029 failed to open.
  • CV-3029 Comment:

Evaluator Cue: If applicant notifies CRS of CV-3029 failing to open, acknowledge the failure and direct applicant to continue performing post-RAS actions.

PALISADES NUCLEAR PLANT Page 4 of 10 FEBRUARY 2017

JPM SYSTEM F Proc.

Step TASK ELEMENT 4 STANDARD Grade With CV-3029 failing to open,

  • Trip CS Pump P-54A
  • Stop CS Pump P-54A 2.1.b.2
  • Identifies CV-3071, P-66A Subcooling S U
  • Ensure open CV-3071, P-66A valve will NOT open Subcooling valve (Key: 152)

Comment:

Evaluator Note: CV-3071 will not open due to mechanical binding.

Evaluator Cue: If applicant notifies CRS of CV-3071 failing to open, acknowledge the failure and direct applicant to continue performing post-RAS actions.

CRITICAL STEP: Critical step is to trip CS Pump P-54A.

Proc.

Step TASK ELEMENT 5 STANDARD Grade Verify closed both SI Pump Minimum flow Stop Ensure closed both SIRWT Isolation Valves:

Valves:

2.1.d

  • CV-3031 S U
  • CV-3031 (Key: 149)
  • CV-3057
  • CV-3057 (Key: 150)

Comment:

Proc.

Step TASK ELEMENT 6 STANDARD Grade Verify closed both SI Pump Minimum flow Stop Ensure closed both SI Pump Minimum Valves:

Flow Stop Valves:

2.1.d

  • CV-3027 S U
  • CV-3027 (Key: 28)
  • CV-3056
  • CV-3056 (Key: 27)

Comment:

Proc.

Step TASK ELEMENT 7 STANDARD Grade Verify open both CCW Hx Service Water Outlet Ensure open both CCW Hx Service Water valves:

Outlet valves:

2.1.e

  • CV-0826 S U
  • CV-0826
  • CV-0823
  • CV-0823 Comment:

PALISADES NUCLEAR PLANT Page 5 of 10 FEBRUARY 2017

JPM SYSTEM F Proc.

Step TASK ELEMENT 8 STANDARD Grade Ensure closed both CCW Hx TCVs: Verify closed both CCW Hx TCVs:

2.1.f

  • CV-0822
  • CV-0822 S U
  • CV-0821
  • CV-0821 Comment:

Evaluator Note: Both CCW Hx TCVs indicate closed when green light is lit above HS-0828.

Proc.

Step TASK ELEMENT 9 STANDARD Grade Ensure at least one Containment Spray Verifies P-54A CS Pump is not operating and P-2.1.g Pump operating for each operating HPSI S U 66A HPSI Pump is operating.

Pump Comment:

Proc.

Step TASK ELEMENT 10 STANDARD Grade Verify open HPSI Subcooling Valve for Verifies any operating HPSI Pump 2.1.g

  • P-66A is operating with CV-3071 closed. S U
  • CV-3070 (P-66B)
  • P-66B is operating with CV-3070 open.
  • CV-3071 (P-66A)

Comment:

Proc.

Step TASK ELEMENT 11 STANDARD Grade IF any HPSI pump is operating with Trips P-66A HPSI Pump due to CV-3071 failing 2.1.h subcooling valve closed, then trip the S U to open.

associated pump.

Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 12 STANDARD Grade With 2 CS Pumps operating, ensure both 2.1.i Containment Spray Valves are in the Verifies CV-3001 and CV-3002 are throttled. S U THROTTLE position.

Comment:

PALISADES NUCLEAR PLANT Page 6 of 10 FEBRUARY 2017

JPM SYSTEM F Proc.

Step TASK ELEMENT 13 STANDARD Grade If one Containment spray valve is closed 2.1.j Determines that this step is not applicable. S U and one is throttled Comment:

Proc.

Step TASK ELEMENT 14 STANDARD Grade If only one Containment Spray Pump is 2.1.k Determines that this step is not applicable. S U operating Comment:

Proc.

Step TASK ELEMENT 17 STANDARD Grade With Containment Sump isolation valve 2.1.l CV-3029 failing to open: Place HS-3029A to the open position S U

  • Place HS-3029A to open (Key: 148)

Comment:

Evaluator Cue: If applicant asks CRS if CV-3029 should be opened, question applicant for recommended action. Concur with applicants recommendation (CV-3029 will not open when attempted).

Proc.

Step TASK ELEMENT 18 STANDARD Grade If operation of additional spray pumps or 2.1.m Determines that this step is not applicable. S U HPSI pumps is desired Comment:

Evaluator Cue: Cue Operator that no other pumps are desired to be placed in operation.

Proc.

Step TASK ELEMENT 20 STANDARD Grade 2.1.n Monitor for sump screen clogging. Sump screen monitored for clogging S U Comment:

Evaluator Cue: Cue Operator that another Operator will monitor for sump clogging.

PALISADES NUCLEAR PLANT Page 7 of 10 FEBRUARY 2017

JPM SYSTEM F Proc.

Step TASK ELEMENT 21 STANDARD Grade IF EITHER of the following exist:

  • P-54A OFF Then Crosstie ESS suction headers Comment:

Evaluator Cue: Cue Operator that another Operator will crosstie ESS suction headers.

Proc.

Step TASK ELEMENT 22 STANDARD Grade 2.1.p Initiate refill of the SIRW Tank. Notifies CRS of need to refill SIRW Tank. S U Comment:

Evaluator Cue: Cue Operator that another Operator will refill SIRW Tank.

Proc.

Step TASK ELEMENT 23 STANDARD Grade Verify 1-2 Startup Transformer is not Verify 1-2 Startup Transformer is not supplying 2.1.q S U supplying Bus 1C or 1D. Bus 1C or 1D.

Comment:

Proc.

Step TASK ELEMENT 24 STANDARD Grade Notify the CRS that the post RAS actions CRS notified that the post RAS actions have N/A S U have been completed. been completed.

Comment:

Evaluator Cue: Repeat back notification.

Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 8 of 10 FEBRUARY 2017

JPM SYSTEM F SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-179 PALISADES NUCLEAR PLANT Page 9 of 10 FEBRUARY 2017

JPM SYSTEM F CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • A large break LOCA has occurred.
  • The plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed.
  • EOP-4.0, Loss of Coolant Accident Recovery, has been entered.
  • SIS and CHP have actuated.
  • Pre-RAS actions have been taken per EOP Supplement 42.
  • RAS is imminent.

INITIATING CUES:

During performance of EOP-4.0 step 52, the Control Room Supervisor directs you to perform Post-RAS actions in accordance with EOP Supplement 42, step 2.0 when RAS occurs.

PALISADES NUCLEAR PLANT Page 10 of 10 FEBRUARY 2017

JPM SYSTEM G PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS G TITLE: Containment Air Cooler Service Water Leak CANDIDATE:

EXAMINER:

PALISADES NUCLEAR PLANT Page 1 of 8 FEBRUARY 2017

JPM SYSTEM G JOB PERFORMANCE MEASURE DATA PAGE Task: Diagnose and isolate a Containment Air Cooler Service Water leak.

Alternate Path: No Facility JPM #: N/A (new)

K/A: 022.A2.05 Importance: RO: 3.1 SRO: 3.5 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the CCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Major leak in CCS.

Task Standard: Determine which Containment Air Cooler has a Service Water leak by performing Annunciator Response actions to diagnose and isolate the leak.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

ARP-8, Safeguards Safety Injection and Isolation Scheme SOP-17B, Dirty Radioactive Waste System Validation Time:20 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 FEBRUARY 2017

JPM SYSTEM G EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • ARP-8, Safeguards Safety Injection and Isolation Scheme
  • SOP-17B, Dirty Radioactive Waste System Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The plant is in MODE 2 and a Turbine/Generator startup is in progress.
  • GOP-4 is in progress and GCL-4 is complete up to Step 4.3 INITIATING CUES:

You are the on-shift NCO-R operator. You are to address alarm EK-1347, Containment Air Coolers Serv Water Leak and address any additional panel C-13 alarms received.

PALISADES NUCLEAR PLANT Page 3 of 8 FEBRUARY 2017

JPM SYSTEM G Time Start: _____

Proc.

Step TASK ELEMENT 1 STANDARD Grade Obtains ARP-8 and identifies page associated N/A Obtain a copy of ARP-8 for EK-1347 S U with EK-1347 Comment:

Evaluator Cue: When applicant has located ARP-8 for EK-1347, provide them with a working copy of the procedure.

Evaluator Note: Task Element 2-5 may be performed in any order per ARP-8 until Task Element 4 is completed satisfactorily and the leak is isolated. Tasks 2, 3, and 5 may not be performed once the leak is isolated by performing Task 4.

Proc.

Step TASK ELEMENT 2 STANDARD Grade For VHX-1: Verify the SW leak is not in VHX-1 CAC:

  • Close CV-0862, VHX-1 SW Inlet
  • Close CV-0862, VHX-1 SW Inlet N/A S U
  • Verify EK-1347 did not clear
  • Verify EK-1347 did not clear
  • Open CV-0862, VHX-1 SW Inlet
  • Open CV-0862, VHX-1 SW Inlet Comment:

Proc.

Step TASK ELEMENT 3 STANDARD Grade For VHX-2: Verify the SW leak is not in VHX-2 CAC:

  • Close CV-0865, VHX-2 SW Inlet
  • Close CV-0865, VHX-2 SW Inlet N/A S U
  • Verify EK-1347 did not clear
  • Verify EK-1347 did not clear
  • Open CV-0865, VHX-2 SW Inlet
  • Open CV-0865, VHX-2 SW Inlet Comment:

Proc.

Step TASK ELEMENT 4 STANDARD Grade For VHX-3:

Verify the SW leak is in VHX-3 CAC:

  • Close CV-0870, VHX-3 SW Inlet
  • Close CV-0870, VHX-3 SW Inlet N/A
  • Verify alarm EK-1347 cleared S U
  • Verify alarm EK-1347 cleared
  • Notify CRS of SW leak in VHX-3
  • Notify CRS of SW leak in VHX-3 CAC CAC Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 FEBRUARY 2017

JPM SYSTEM G Proc.

Step TASK ELEMENT 5 STANDARD Grade For VHX-4: Verify the SW leak is not in VHX-4 CAC:

  • Close CV-0869, VHX-4 SW Inlet
  • Close CV-0869, VHX-4 SW Inlet N/A S U
  • Verify EK-1347 did not clear
  • Verify EK-1347 did not clear
  • Open CV-0869, VHX-4 SW Inlet
  • Open CV-0869, VHX-4 SW Inlet Comment:

Proc.

Step TASK ELEMENT 6 STANDARD Grade Notifies CRS of TS LCO 3.6.1 and 3.6.6 Informs CRS of potential TS LCO 3.6.1 and N/A S U potential applicability. 3.6.6 applicability.

Comment:

Proc.

Step TASK ELEMENT 7 STANDARD Grade Addresses alarm EK-1351 to drain Obtains and reviews ARP-8 for EK-1351.

N/A containment sump to dirty waste per Determine the need to drain the containment S U SOP-17B. sump to dirty waste per SOP-17B.

Comment:

Evaluator Note: When applicant states the need to drain the containment sump to dirty waste, inform the applicant that the CRS directs the sump drained per Section 7.11.1 of SOP 17B. When applicant locates SOP 17B, provide them with a working copy of Section 7.11.1 of the procedure.

Evaluator Cue: Inform the applicant that an NPO has completed Steps 7.11.1 a through c, and there is sufficient room in the dirty waste tanks to drain the sump.

Proc.

Step TASK ELEMENT 8 STANDARD Grade Determine the final DWDT levels for the 7.11.1.d Calculates the final DWDT levels S U I/S tanks per Steps 7.11.1 d.

Comment:

Evaluator Cue: Inform the applicant that both DWDTs T-60A/B are in-service at 25% and are cross-tied.

Evaluator Note: Applicant obtains containment sump level from C-13 Panel (the level may be different for each candidate depending on the time it takes to isolate the CAC SW leak).

PALISADES NUCLEAR PLANT Page 5 of 8 FEBRUARY 2017

JPM SYSTEM G Proc.

Step TASK ELEMENT 9 STANDARD Grade Drain the containment sump to the dirty waste drain tanks:

  • Open CV-1103, MZ-52 Cont Sump Initiate draining the containment sump to dirty Drain to Sump Tank Isol. waste:

7.11.1.e

  • Open CV-1104, MZ-52 Cont Sump
  • Open CV-1103; S U Drain to Sump Tank Isol.
  • Open CV-1104;
  • Log the following:
  • Log data.

Start time; Initial level of DWDTs; CTMT sump level Comment:

Evaluator Cue: Acknowledge the applicant log entry.

CRITICAL STEP Proc. Step TASK ELEMENT 10 STANDARD Grade Pump down DWDTs as required per Section 7.1.4, and Applicant determines that these steps are N/A 7.11.1.f/g S U Obtain grab sample from MV-DRW511 per the evaluators Cue.

while draining the sump if desired.

Comment:

Evaluator Cue: Inform the applicant that the DWDTs will not need to be pumped down during the evolution and that grab samples are not required.

Evaluator Cue: Inform the applicant that (using time compression) the containment sump has been drained to the desired level. Containment sump high level alarm may not clear and sump indication will show that draining is still required.

Proc.

Step TASK ELEMENT 11 STANDARD Grade Secure draining the containment sump to the dirty waste drain tanks by: Secure draining the containment sump to dirty

  • Close CV-1103, MZ-52 Cont Sump waste:

7.11.1.h Drain to Sump Tank Isol.

  • Close CV-1103; S U
  • Close CV-1104, MZ-52 Cont Sump
  • Close CV-1104; Drain to Sump Tank Isol.
  • Log the stop time.
  • Log the stop time.

Comment:

CRITICAL STEP Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 8 FEBRUARY 2017

JPM SYSTEM G SIMULATOR OPERATOR INSTRUCTIONS

  • Reset to IC-175 PALISADES NUCLEAR PLANT Page 7 of 8 FEBRUARY 2017

JPM SYSTEM G CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The plant is in MODE 2 and a Turbine/Generator startup is in progress.
  • GOP-4 is in progress and GCL-4 is complete up to Step 4.3 INITIATING CUES:

You are the on-shift NCO-R operator. You are to address alarm EK-1347, Containment Air Coolers Serv Water Leak and address any additional panel C-13 alarms received.

PALISADES NUCLEAR PLANT Page 8 of 8 FEBRUARY 2017

JPM SYSTEM H PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS H TITLE: HOT LEG INJECTION USING P-66B AND SPLIT FLOW CANDIDATE: _____________________________________________

EXAMINER: _____________________________________________

PALISADES NUCLEAR PLANT Page 1 of 9 FEBRUARY 2017

JPM SYSTEM H JOB PERFORMANCE MEASURE DATA PAGE Task: Establish Hot Leg Injection per in-use EOP Alternate Path: Yes Facility JPM #: 2009 NRC Exam (modified)

K/A: 006A2.02 Importance: RO:3.9 SRO: 4.3 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the ECCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: loss of flow path Task Standard: Hot Leg Injection flow established via HPSI Pump P-66B using EOP Supplement 20 split flow method.

Preferred Evaluation Location: Simulator _X__ In Plant ______

Preferred Evaluation Method: Perform _X__ Simulate ______

References:

EOP Supplement 20, Hot Leg Injection Via PZR EOP Supplement 4, HPSI and LPSI Flow Curves EOP-4.0, Loss of Coolant Accident Recovery Validation Time: 25 minutes Time Critical: NO Candidate: ________________________________________________

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 FEBRUARY 2017

JPM SYSTEM H EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • EOP-4.0, Loss of Coolant Accident Recovery
  • EOP Supplement 20, Hot Leg Injection Via PZR
  • EOP Supplement 4, HPSI and LPSI Flow Curves Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • Plant was tripped from 100% power.
  • EOP-4.0 (Loss of Coolant Accident) has been entered.
  • Conditions for initiating Hot Leg Injection per Step 60 are met.
  • HPSI Pump P-66A was manually tripped during post-RAS actions due to CV-3029 and CV-3071 failing to open.

INITIATING CUES:

The CRS has directed you to establish hot leg injection using EOP-4.0 Step 60.

PALISADES NUCLEAR PLANT Page 3 of 9 FEBRUARY 2017

JPM SYSTEM H Time Start: ______

Proc.

Step TASK ELEMENT 1 STANDARD Grade N/A Candidate locates EOP-4.0 Step 60 EOP-4.0 Step 60 is in hand. S U Comment:

Evaluator Cue: Provide candidate with a working copy of EOP-4.0 Step 60 Evaluator Cue: If applicant asks, inform applicant to review initial conditions.

Proc.

Step TASK ELEMENT 2 STANDARD Grade Close HPSI Train 2 to Cold Leg Valve, Attempts to close MO-3080 and identifies 60.a S U MO-3080 (Key: 117) failure of the valve to close.

Comment:

Evaluator Cue: If Applicant informs CRS, acknowledge applicants report of MO-3080 failure.

Proc.

Step TASK ELEMENT 3 STANDARD Grade Determines the following:

  • Hot leg injection cannot be Refers to EOP Supplement 20 and determines 60.RNO established through normal path Section 2.0 Hot Leg Injection Using P-66B S U
  • Refers to EOP Supplement 20 and Split Flow is necessary.
  • The inability to use P-66A (tripped)

Comment:

Evaluator Cue: When the applicant has EOP Supplement 20 in hand, provide a clean working copy of the procedure.

Proc.

Step TASK ELEMENT 4 STANDARD Grade

  • Notes this requirement for future action in this JPM.

Record each occurrence of PZR Spray

  • Notes current temperatures for vapor 2.0.1 operation with a T greater than 200°F in S U phase, spray lines, and charging the Reactor Logbook.
  • Determines requirement is currently not applicable.

Comment:

PALISADES NUCLEAR PLANT Page 4 of 9 FEBRUARY 2017

JPM SYSTEM H Proc.

Step TASK ELEMENT 5 STANDARD Grade Ensure P-66B is operating within the Verifies P-66B flow is within EOP Supplement 2.0.2 S U limits of EOP Supplement 4. 4 Comment:

Proc.

Step TASK ELEMENT 6 STANDARD Grade Ensure open the following valves: Places hand switches for the following valves

  • CV-2111 , Chg Line Stop to OPEN and verifies valves open:
  • CV-2117, Aux Spray
  • CV-2111 2.0.3 S U
  • MO-3072, Chg Pump Dis. to Train 2
  • CV-2117
  • CV-3018, HPSI Pump B Dis. to Train
  • MO-3072 2
  • CV-3018 Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 7 STANDARD Grade Applicant determines all three Charging Pumps are operating and have electrical 2.0.4 Stop ALL Charging Pumps S U power available.

  • Stop P-55A, P-55B, and P-55C.

Comment:

Evaluator Note: Applicant may also place Auto/Manual switches on Panel C-12 to MANUAL (this is not required to meet Standard).

CRITICAL STEP Proc.

Step TASK ELEMENT 8 STANDARD Grade Places hand switches for the following valves CLOSE the following valves:

to CLOSE and verifies valves close:

  • CV-2113, Loop 1A
  • CV-2113 2.0.5
  • CV-2115, Loop 2A S U
  • CV-2115
  • CV-1057, Spray
  • CV-1057
  • CV-1059, Spray
  • CV-1059 Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 9 FEBRUARY 2017

JPM SYSTEM H Proc.

Step TASK ELEMENT 9 STANDARD Grade Ensure open the following HPSI Train 1 Verifies open the following valves:

valves:

  • MO-3007
  • MO-3007, HPSI Train 1 Loop 1A 6
  • MO-3009 S U
  • MO-3009, HPSI Train 1 Loop 1B
  • MO-3011
  • MO-3011, HPSI Train 1 Loop 2A
  • MO-3013
  • MO-3013, HSPI Train 1 Loop 2B Comment:

Proc.

Step TASK ELEMENT 10 STANDARD Grade Places and holds hand switches for the CLOSE the following valves: following valves to CLOSE and verifies valves

  • MO-3062, HPSI Train 2 Loop 2B close:

7

  • MO-3064, HPSI Train 2 Loop 2A
  • MO-3062 S U
  • MO-3066, HPSI Train 2 Loop 1B
  • MO-3064
  • MO-3068, HSPI Train 2 Loop 1A
  • MO-3066
  • MO-3068 Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 11 STANDARD Grade Ensure HPSI flow of greater than or equal to 100 gpm to the Pressurizer Applicant checks flow is indicated on FIA-0212 8 S U through the charging line is indicated on greater than 100 gpm.

FIA-0212.

Comment:

Proc.

Step TASK ELEMENT 12 STANDARD Grade Applicant informs the CRS that the Hot Leg Injection using P-66B and split flow CRS informed that Hot Leg Injection using P-N/A S U has been established per EOP 66B and split flow has been established Supplement 20 section 2.0.

Comment:

Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 9 FEBRUARY 2017

JPM SYSTEM H PALISADES NUCLEAR PLANT Page 7 of 9 FEBRUARY 2017

JPM SYSTEM H SIMULATOR OPERATOR INSTRUCTIONS

  • Initialize IC-179
  • Enter Override for MO-3080 to ON on PNL C-03.

PALISADES NUCLEAR PLANT Page 8 of 9 FEBRUARY 2017

JPM SYSTEM H CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • Plant was tripped from 100% power.
  • EOP-4.0 (Loss of Coolant Accident) has been entered.
  • Conditions for initiating Hot Leg Injection per Step 60 are met.
  • HPSI Pump P-66A was manually tripped during post-RAS actions due to CV-3029 and CV-3071 failing to open.

INITIATING CUES:

The CRS has directed you to establish hot leg injection using EOP-4.0 Step 60.

PALISADES NUCLEAR PLANT Page 9 of 9 FEBRUARY 2017

JPM SYSTEM I PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYSTEM I TITLE: RESPOND TO RADIATION MONITOR RIA-1810 LOW SAMPLE FLOW RATE CANDIDATE: _____________________________________________

EXAMINER: _____________________________________________

PALISADES NUCLEAR PLANT Page 1 of 7 FEBRUARY 2017

JPM SYSTEM I JOB PERFORMANCE MEASURE DATA PAGE Task: Respond to a low sample flow rate condition on radiation monitor RIA-1810 Alternate Path: No Facility JPM #: N/A (new)

K/A: 073.A2.02 Importance: RO: 3.2 SRO: 3.2 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the PRM system; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Detector failure.

Task Standard: Restore the adequate sample flow rate to radiation monitor RIA-1810 to clear Control Room alarms for low sample flow rate.

Preferred Evaluation Location: Simulator ____ In Plant __X__

Preferred Evaluation Method: Perform ____ Simulate __X__

References:

SOP-38, Gaseous Process Monitoring System ARP-8, Safeguards Safety Injection and Isolation Scheme Validation Time:10 minutes Time Critical: NO Candidate: ___________________________________________________

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 7 FEBRUARY 2017

JPM SYSTEM I EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • ARP-8, Safeguards Safety Injection and Isolation Scheme
  • SOP-38 Attachment 1, System Malfunctions, Low Sample Flow Rate Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The Plant is at 100% power.
  • Alarm EK-1370, Radiation Monitors Samplers Flow Failure is in for RIA-1810
  • The sample pump for RIA-1810 is OFF.
  • RMC has been notified per ARP-8 INITIATING CUES:

The CRS directs you to respond to alarm EK-1370 in accordance with ARP-8 and clear the low flow condition on RIA-1810.

PALISADES NUCLEAR PLANT Page 3 of 7 FEBRUARY 2017

JPM SYSTEM I Time Start: ______

Evaluator Cue: Provide applicant with a working copy of ARP-8 for EK-1370 and SOP-38 Attachment 1

Proc.

Step TASK ELEMENT 1 STANDARD Grade For Containment Air Rad Monitor RIA- Determines Attachment 1, Step 1.a is not 1.a S U 1817 applicable for RIA-1810 Comment:

Proc.

Step TASK ELEMENT 2 STANDARD Grade Verify sample pump is not operating (given in initial conditions) and identifies hand switch is in OFF.

1.b.1 Ensure sample pump is ON S U Applicant starts sample pump by taking hand switch to Auto.

Comment:

Evaluator Cue: Applicant may notify CRS of abnormal position of sample pump hand switch. If applicant asks, inform applicant to clear the flow condition on the rad monitor.

Evaluator Cue: If applicant asks, question applicant what position they think the hand switch should be in, Hand or Auto (should take to Auto).

CRITICAL STEP Proc.

Step TASK ELEMENT 3 STANDARD Grade Ensure closed cleaner fill valves: Verify closed:

1.b.2

  • MV-VA126
  • MV-VA126 S U
  • MV-VA132
  • MV-VA132 Comment:

Proc.

Step TASK ELEMENT 4 STANDARD Grade Ensure open Sampler Inlet Isolation 1.b.3 Valves: Verify MV-VA120 open S U

  • MV-VA120 Comment:

PALISADES NUCLEAR PLANT Page 4 of 7 FEBRUARY 2017

JPM SYSTEM I Proc.

Step TASK ELEMENT 5 STANDARD Grade

  • Check pressure on PI-2324 to determine initial vacuum pressure.
  • Determine pressure is too high (~8Hg)

Ensure throttled Sampler Outlet and needs to be lowered Isolation Valve MV-VA139 to maintain 1.b.4 S U vacuum less than 5 Hg on pressure

  • Adjusts MV-VA139 clockwise slowly to indicator PI-2324 lower pressure while monitoring PI-2324.
  • Stop adjusting pressure when PI-2324 is <

5Hg vacuum (may be done in multiple steps)

Comment:

Evaluator Cue: If/when applicant checks vacuum pressure on PI-2324, inform applicant that vacuum pressure is too high (~8 Hg).

Evaluator Note: Applicant may make multiple small adjustments to lower vacuum pressure.

CRITICAL STEP Proc.

Step TASK ELEMENT 6 STANDARD Grade Ensure open Pump and Monitor Outlet Verify open:

Valves:

1.b.5

  • MV-VA122 S U
  • MV-VA122
  • MV-VA124
  • MV-VA124 Comment:

Proc.

Step TASK ELEMENT 9 STANDARD Grade Contacts CRS or NCO to validate if low Verify low flow condition and alarm EK-1470 1.b.6 flow condition and alarm EK-1370 has S U clear.

cleared.

Comment:

Evaluator Cue: When applicant has adjusted vacuum pressure to < 5Hg, inform the applicant that alarm EK-1370 for RIA-1810 has cleared Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 7 FEBRUARY 2017

JPM SYSTEM I SIMULATOR OPERATOR INSTRUCTIONS N/A, In plant JPM PALISADES NUCLEAR PLANT Page 6 of 7 FEBRUARY 2017

JPM SYSTEM I CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The Plant is at 100% power.
  • Alarm EK-1370, Radiation Monitors Samplers Flow Failure is in for RIA-1810
  • The sample pump for RIA-1810 is OFF.
  • RMC has been notified per ARP-8 INITIATING CUES:

The CRS directs you to respond to alarm EK-1370 in accordance with ARP-8 and clear the low flow condition on RIA-1810.

PALISADES NUCLEAR PLANT Page 7 of 7 FEBRUARY 2017

JPM SYSTEM J

`

PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYSTEM J TITLE: PURGE THE MAIN GENERATOR TO RAISE HYDROGEN PURITY CANDIDATE: _____________________________________________

EXAMINER: _____________________________________________

PALISADES NUCLEAR PLANT Page 1 of 9 FEBRUARY 2017

JPM SYSTEM J JOB PERFORMANCE MEASURE DATA PAGE Task: Purge the Main Generator to Raise Hydrogen Purity Alternate Path: No Facility JPM #: N/A (new)

K/A: 045.K5.03 Importance: RO: 2.8 SRO: 3.2 K/A Statement: Knowledge of the operational implications of the following concepts as they apply to the MT/G System: Possible presence of explosive mixture in generator if hydrogen purity deteriorates.

Task Standard: Purge the Main Generator with Hydrogen to raise Hydrogen Purity as a result of a low purity alarm.

Preferred Evaluation Location: Simulator ____ In Plant __X___

Preferred Evaluation Method: Perform ____ Simulate __X__

References:

SOP-8, Main Turbine and Generating Systems ARP-2, Generator Scheme ARP-6, Generator Hydrogen System Scheme Validation Time: 20 minutes Time Critical: NO Candidate: ___________________________________________________

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 FEBRUARY 2017

JPM SYSTEM J EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • ARP-2, Generator Scheme
  • ARP-6, Generator Hydrogen System Scheme Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The Plant is at 100% power.
  • Alarm EK-0302, Hydrogen/Seal Oil System Trouble is in.
  • Alarm EK-1001, Hydrogen Purity High or Low is in.

INITIATING CUES:

The CRS directs you to purge the Main Generator to raise Hydrogen purity to 97%

using SOP-8 Attachment 3 via the Feed and Bleed Method. A Hydrogen grab sample is not required.

PALISADES NUCLEAR PLANT Page 3 of 9 FEBRUARY 2017

JPM SYSTEM J Time Start: ______

Evaluator Cue: When applicant has located SOP-8 Attachment 3, Purging Generator to Raise Hydrogen Purity, provide a copy of the procedure attachment.

Evaluator Cue: Applicant may request a copy of ARP-6 to address local alarm EK-1001. A clean working copy can be provided if requested.

Proc.

Step TASK ELEMENT 1 STANDARD Grade Monitor Main Generator Hydrogen pressure:

Monitor Main Generator Hydrogen pressure. May 2.1

  • PI-1419 (Control Room) contact NCO to monitor in the Control Room.

S U

  • PI-1419A (Panel EC-21)

Comment:

Evaluator Cue: If applicant contacts NCO to monitor Hydrogen pressure, acknowledge the request.

Proc.

Step TASK ELEMENT 2 STANDARD Grade Ensure the following Hydrogen pressure alarms are functional and clear:

  • EK-1002, Hydrogen Pressure High Verify alarms EK-1002 and EK-1003 are clear 2.2 S U or Low and performs a functional test of alarms.
  • EK-1003, Hydrogen Supply Pressure Low Comment:

Evaluator Note: Applicant should simulate testing the alarms only.

Evaluator Note: EK-1001, Hydrogen Purity Hi or Low will be LIT.

Proc.

Step TASK ELEMENT 3 STANDARD Grade Bypass FI-2245, Hydrogen Flow Indicator:

Bypass Hydrogen Flow Indicator FI-2245 as

  • Close MV-WE103, Main Gen H2 follows:

Flow Meter FI-2245 Inlet 2.3.1-4

  • Close MV-WE103 S U
  • Close MV-WE104, Main Gen H2
  • Close MV-WE104 Flow Meter FI-2245 Out
  • Open MV-WE102
  • Open MV-WE102, Main Gen H2 Flow Meter FI-2245 B/P Comment:

PALISADES NUCLEAR PLANT Page 4 of 9 FEBRUARY 2017

JPM SYSTEM J Proc.

Step TASK ELEMENT 4 STANDARD Grade Ensure the following:

  • NCO is aware of evolution and monitoring Main Gen H2 pressure 2.4
  • NPO involved has walked down Step Verify NCO is monitoring Main Gen H2 pressure S U 2.5 and 2.6 prior to performance since they need to be completed in an expeditious manner Comment:

Evaluator Cue: As NCO, acknowledge NPOs request to monitor Generator H2 pressure.

Evaluator Note: Steps 2.5.1-3 initialize the Feed portion of the Feed and Bleed evolution.

Proc.

Step TASK ELEMENT 5 STANDARD Grade Open MV-WE332, FCV-2201 Bypass 2.5.1 Open MV-WE332 S U (outlet of bulk hydrogen tank)

Comment:

Evaluator Cue: If applicant asks, inform applicant that a full H2 bottle is aligned.

CRITICAL STEP Proc.

Step TASK ELEMENT 6 STANDARD Grade Ensure open:

  • MV-WE052, Main Gen H2 Supply Ensure open:

Manifold Bypass

  • MV-WE052 2.5.2 S U
  • MV-WE053, Main Gen H2 Supply
  • MV-WE008
  • MV-WE008, H2 Supply to Main Gen Comment:

CRITICAL STEP Evaluator Cue: When hydrogen is valved in, H2 header pressure on PI-2245 ~120 psig. When MV-WE050 is opened to initiate the H2 feed to the generator, H2 header pressure should drop on PI-2245 to ~100 psig.

Proc.

Step TASK ELEMENT 7 STANDARD Grade Throttle open MV-WE050, Main Gen H2 Establish H2 flow by throttling open MV-Supply Manifold Outlet as required to 2.5.3 WE050 as necessary and maintain PI-2245 > S U establish H2 flow to Main Gen. and 90 psig maintain PI-2245 > 90 psig Comment:

Evaluator Note: Hydrogen Flow Meter FI-2245 is bypassed at this point. Applicant can verify H2 header pressure > 90 psig, H2 Supply pressures (PI-2262 or PI-2297), and Main Gen H2 Purity rising.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 9 FEBRUARY 2017

JPM SYSTEM J Evaluator Note: Steps 2.6.1-2 initialize the Bleed portion of the Feed and Bleed evolution.

Proc.

Step TASK ELEMENT 8 STANDARD Grade Throttle open 1/2 turn MV-WE006, Main 2.6.1 Throttle open 1/2 turn MV-WE006 S U Gen Bottom Manifold (CO2) Vent Comment:

Proc.

Step TASK ELEMENT 9 STANDARD Grade Barely throttle open MV-WE026, Main Barely throttle open MV-WE026 (crack off the 2.6.2 S U Gen Vent to Atm. closed seat).

Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 10 STANDARD Grade Operate MV-WE006, Main Gen Bottom Manifold (CO2) Vent, as necessary to Operate MV-WE006 as necessary to maintain maintain:

2.7 stable feed and bleed rate as well as stable S U

  • Stable H2 Bleed rate to match the Main Gen H2 pressure (74-76 psig)

Feed rate

  • Gen H2 pressure 74-76 psig Comment:

CRITICAL STEP Proc.

Step TASK ELEMENT 11 STANDARD Grade Determines a Hydrogen grab sample is not 2.8 If a Hydrogen grab sample is desired S U required (Initial Cue).

Comment:

PALISADES NUCLEAR PLANT Page 6 of 9 FEBRUARY 2017

JPM SYSTEM J Proc.

Step TASK ELEMENT 12 STANDARD Grade When Hydrogen Purity is at desired value (97%), stop Feed and Bleed as follows:

  • Close MV-WE026, Main Gen Vent to Atm When H2 Purity reaches 97%, secure Feed
  • Close MV-WE006, Main Gen Bottom and Bleed:

Manifold (CO2) Vent

  • Close MV-WE026
  • Close MV-WE050, Main Gen H2
  • Close MV-WE006 2.9 S U Supply Manifold Outlet
  • Close MV-WE050
  • Close MV-WE052, Main Gen H2
  • Close MV-WE053
  • Close MV-WE053, Main Gen H2
  • Ensure open MV-WE008 Supply Manifold Inlet
  • Ensure open MV-WE008, H2 Supply to Main Gen.

Comment:

Evaluator Cue: After a short time when applicant has balanced the feed and bleed, cue applicant that alarm EK-1001, Hydrogen Purity Hi or Low has cleared.

Evaluator Cue: A short time after the previous cue, inform applicant that Hydrogen purity is ~97%.

CRITICAL STEP Proc.

Step TASK ELEMENT 13 STANDARD Grade Restore FI-2245, Hydrogen Flow Indicator to service

  • Open MV-WE103, Main Gen H2 Restore FI-2245:

Flow Meter FI-2245 Inlet

  • Open MV-WE103 2.10
  • Open MV-WE104, Main Gen H2
  • Open MV-WE104 S U Flow Meter FI-2245 Out
  • Close MV-WE102
  • Close MV-WE102, Main Gen H2
  • Close MV-WE332 Flow Meter FI-2245 B/P
  • Close MV-WE332, FCV-2201 Bypass Comment:

Proc.

Step TASK ELEMENT 14 STANDARD Grade

  • May verify normal Main Gen H2 Contact NCO to verify normal/stable pressure N/A Main Gen parameters and inform CRS of S U
  • May verify stable Main Gen H2 Purity task completion.
  • Inform CRS of task completion.

Comment:

Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 FEBRUARY 2017

JPM SYSTEM J SIMULATOR OPERATOR INSTRUCTIONS N/A, In plant JPM PALISADES NUCLEAR PLANT Page 8 of 9 FEBRUARY 2017

JPM SYSTEM J CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The Plant is at 100% power.
  • Alarm EK-0302, Hydrogen/Seal Oil System Trouble is in.
  • Alarm EK-1001, Hydrogen Purity High or Low is in.

INITIATING CUES:

The CRS directs you to purge the Main Generator to raise Hydrogen purity to 97%

using SOP-8 Attachment 3 via the Feed and Bleed Method. A Hydrogen grab sample is not required.

PALISADES NUCLEAR PLANT Page 9 of 9 FEBRUARY 2017

JPM SYSTEM K PALISADES 2017 INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYSTEM K TITLE: OUTSIDE CONTROL ROOM B ESDE ISOLATION PER EOP SUPPLEMENT 18 CANDIDATE: _____________________________________________

EXAMINER: _____________________________________________

PALISADES NUCLEAR PLANT Page 1 of 10 FEBRUARY 2017

JPM SYSTEM K JOB PERFORMANCE MEASURE DATA PAGE Task: Outside Control Room B S/G ESDE Isolation IAW EOP Supplement 18 Alternate Path: Yes Facility JPM #: PL-OPS-EOP-010J K/A: 040AA1.03 Importance: RO: 4.3 SRO: 4.3 K/A Statement: Isolation of one steam line from the header Task Standard: B S/G isolated per EOP Supplement 18 Section 2.0 Preferred Evaluation Location: Simulator ____ In Plant __X___

Preferred Evaluation Method: Perform ____ Simulate __X__

References:

EOP-6.0, Excess Steam Demand Event EOP Supplement 18, B S/G ESDE Isolation Checklist Validation Time: 30 minutes Time Critical: NO Candidate: ___________________________________________________

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 10 FEBRUARY 2017

JPM SYSTEM K EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

  • EOP Supplement 18, B S/G ESDE Isolation Checklist Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • The Plant has been tripped from 100% power.
  • EOP-6.0 has been entered due to a steam leak on the B S/G.
  • The control room has completed EOP Supplement 18 B S/G Isolation Checklist Section 1.0, Isolation from the Control Room.
  • All steps of EOP Supplement 1, Section 1.0 have been completed with the exception of CV-0501, B S/G MSIV which did not close.

INITIATING CUES:

The CRS directs you to perform EOP Supplement 18 B S/G Isolation Checklist Section 2.0, Isolation Outside the Control Room.

PALISADES NUCLEAR PLANT Page 3 of 10 FEBRUARY 2017

JPM SYSTEM K Time Start: ______

Proc.

Step TASK ELEMENT 1 STANDARD Grade Locate EOP Supplement 18. EOP Supplement 18 in hand.

n/a S U Comment:

Evaluator Cue: When applicant has located EOP Supplement 18, provide a working copy of EOP Supplement 18, B S/G ESDE Isolation Checklist, completed with the exception of Step 1.a, CV-0501 is circled as not being complete.

Proc.

Step TASK ELEMENT 2 STANDARD Grade Determines that B S/G MSIV (CV-0501)

Identifies the failure of CV-0501 to close and could not be closed from the Control Room n/a the need to close the valve locally per Section S U and must be closed locally and proceeds 2.0.

to Section 2.0 to locally close the valve.

Comment:

Evaluator Note: Applicant can perform actions to unlatch solenoid valves at panels C-180 and C-181 in any order. The first panel the applicant attempts to unlatch solenoid valves at, will NOT unlatch.

Evaluator Note: Solenoid valves are unlatched by lifting handle upward and sliding locking mechanism to the right, then allowing handle to drop downward.

Proc.

Step TASK ELEMENT 3 STANDARD Grade Close the B MSIV by manually unlatching the indicated solenoids from Attempt to unlatch SV-0505A and SV-0507A 2.1.a ANY of the following locations: S U at C-180 panel

  • C-180 (Turb Bldg East Mezzanine)
  • SV-0505A and SV-0507A Comment:

Evaluator Cue: Use attached picture and have applicant demonstrate how they would unlatch the Solenoid Valve.

Evaluator Cue: IF the applicant has not attempted valve unlatching at panel C-181, then, when applicant attempts to unlatch SV-0505A and SV-0507A, inform the applicant that the SVs remain latched as the locking tab will NOT release.

IF the applicant has previously attempted valve unlatching at panel C-181, then, when the applicant attempts to unlatch SV-0505A and SV-0507A, inform the applicant that the SVs are unlatched.

CRITICAL STEP: Task Element 3 OR Task Element 4 is a critical step. Must unlatch both valves from either cabinet.

PALISADES NUCLEAR PLANT Page 4 of 10 FEBRUARY 2017

JPM SYSTEM K Proc.

Step TASK ELEMENT 4 STANDARD Grade Close the B MSIV by manually unlatching the indicated solenoids from Unlatches SV-0502 and SV-0514 at C-181 2.1.a ANY of the following locations: panel S U

  • C-181 ('D' Bus Cableway)
  • SV-0502 and SV-0514 Comment:

Evaluator Cue: Use attached picture and have applicant demonstrate how they would unlatch the Solenoid Valve.

Evaluator Cue: If the applicant has not attempted valve unlatching at panel C-180, then, when applicant attempts to unlatch SV-0502 and SV-0514, inform the applicant that the SVs remain latched, as the locking tab will NOT release.

IF the applicant has previously attempted valve unlatching at panel C-180, then, when the applicant attempts to unlatch SV-0502 and SV-0514, inform the applicant that the SVs are unlatched.

CRITICAL STEP: Task Element 3 OR Task Element 4 is a critical step. Must unlatch both valves from either cabinet.

Evaluator Cue: While outside on roof area, question applicant as to what the pipes on the top of the roof are.

Proc.

Step TASK ELEMENT 5 STANDARD Grade Isolate S/G E-50B Atmospheric Steam Dump Valves using ANY of the following Isolate B S/G ADVs by performing one of the methods: following:

o Close ADV isolation valves: o Close ADV isolation valves:

  • MV-MS102 closed
  • MV-MS102 closed 2.1.b S U
  • MV-MS104 closed
  • MV-MS104 closed o Fail I/A to ADVs (roof outside CCW
  • Fail I/A to ADVs Upper Level inside Cabinet C-182)
  • MV-CA779 closed
  • MV-CA779 closed
  • MV-CA780 closed
  • MV-CA780 closed Comment:

Evaluator Note: About 150 turns is required to close a Steam Dump Isolation Valve from full open.

Evaluator Cue: After applicant has simulated operating each valve hand wheel in the clockwise direction, CUE operator that valve has turned many times and has stopped moving.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 10 FEBRUARY 2017

JPM SYSTEM K Proc.

Step TASK ELEMENT 5 STANDARD Grade Close B S/G Steam Dump Drain Trap valves Close the following B S/G Steam Dump by turning hand-wheel clockwise:

Drain Trap valves (Middle Level CCW

  • MV-MS529, ST-0790 Bypass (already 2.1.c
  • MV-MS527, ST-0790 Inlet closed) S U
  • Mv-MS525, ST-0789 Bypass Note: Bypass valves are locked closed per system checklists Comment:

Evaluate Note: Applicant is not to close MV-MS527, MV-MS529, MV-MS523, or MV-MS525, simulate only Evaluate Cue: After applicant has simulated operating each valve hand wheel in the clockwise direction, CUE applicant that valve has closed.

CRITICAL STEP Proc.

Step TASK ELEMENT 6 STANDARD Grade Verify B S/G Safety Valves are closed B S/G Safety Valve exhausts verified closed 2.1.d S U (Roof outside CCW Upper Level) (visual inspection of steam)

Comment:

Evaluator Cue: Question applicant as how to determine if steam is issuing from any Safety Valve exhausts.

Once applicant describes correctly, inform applicant of no steam discharging through safety valves.

Proc.

Step TASK ELEMENT 7 STANDARD Grade If CV-0744, B S/G Main Feed Reg Block Determines that this step is not applicable 2.1.e Valve, did NOT close from the Control (given in Supplement 18, Section 1.1.d. as S U Room, then close closed).

Comment:

Proc.

Step TASK ELEMENT 8 STANDARD Grade Competed By: ____________

EOP Supplement 18:

N/A S U Signed Completed by: and Dated/Timed Date/Time _______/________

Comment:

PALISADES NUCLEAR PLANT Page 6 of 10 FEBRUARY 2017

JPM SYSTEM K Proc.

Step TASK ELEMENT 9 STANDARD Grade The CRS notified that EOP Supplement CRS notified Supplement 18 completed N/A S U 18 has been completed. satisfactorily.

Comment:

Time Stop: ______

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 10 FEBRUARY 2017

JPM SYSTEM K SIMULATOR OPERATOR INSTRUCTIONS N/A, In plant JPM PALISADES NUCLEAR PLANT Page 8 of 10 FEBRUARY 2017

JPM SYSTEM K CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • The Plant has been tripped from 100% power.
  • EOP-6.0 has been entered due to a steam leak on the B S/G.
  • The control room has completed EOP Supplement 18 B S/G Isolation Checklist Section 1.0, Isolation from the Control Room.
  • All steps of Section 1.0 have been completed with the exception of CV-0501, B S/G MSIV which did not close.

INITIATING CUES:

The CRS directs you to perform EOP Supplement 18 B S/G Isolation Checklist Section 2.0, Isolation Outside the Control Room.

PALISADES NUCLEAR PLANT Page 9 of 10 FEBRUARY 2017

JPM SYSTEM K PALISADES NUCLEAR PLANT Page 10 of 10 FEBRUARY 2017