Submits Quarterly Update Re Const Schedule.Critical Path Schedule Analysis Indicates Limiting Sys Schedule for Leak Detection Sys,About 52 Days Behind.Scheduled Fuel Load Date Continues to Be 860103
ML20137F116
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/23/1985
From: Hall D
ILLINOIS POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
U-600234, NUDOCS 8508260150
Download: ML20137F116 (1)


Text

m U-600234 C30-85(08-23)-L 1A.120 ILLINOIS POWER COMPANY y CLINTON POWER STATION. P.O. BOX 678. CLINTON. ILLINOls 61727 August 23, H85 Docket No. 50-461 Mr. Harold R. Denton, Director Office of Nuclear Regulatory Commission U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

Clinton Unit I Construction Schedule Update

Dear Mr. Denton:

The USNRC letter dated May 29, 1981, from H. R. Denton to W. J.

Kelley requested Illinois Power Company provide a quarterly update concerning the Clinton I construction schedule.-

The critical path schedule analysis shows that the limiting system schedule, Leak Detection System, is about fifty-two days behind. Near term corrective actions have already been effected, and evaluation for additional improvement continues. Management attention is being focused on this system consistent with other priority systems which support Fuel Load. The scheduled date for Fuel Load continues to be January 3, 1986.

Reactor Plant Hot Operation commenced on July 3, 1985, within approximately two months of the target date. As of this report, 'all project milestones scheduled through June 1985 have been achieved.

We will continue to submit quarterly updates of the Unit I construction schedule.

S er y ours,

, . Hall Vice President CDS/pkr cc: Mr. B. Siegel, NRC Clinton Project Manager NRC Resident Office Illinois Dept. of Nuclear Safety Regional Administrator, Region III, USNRC 8508260150 850823 PDR ADOCK 05000461 A PDR 0{