Updates Seismic Qualification of Equipment Status,Per Sser 2.Schedule Projections Indicate 85% of Equipment Will Be Qualified & Installed on or Before May 1985
ML20098E967
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/26/1984
From: Spangenberg F, Spangenberg F
ILLINOIS POWER CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
L30-84(09-26)-L, L30-84(9-26)-L, U-0737, U-737, NUDOCS 8410020193
Download: ML20098E967 (2)


Text

_. ,

, U-0737 0982-L L30-84(09-26)-L 1A.120

/LLINDIS POWER 00MPANY IP CLINTON POWER STATION, P.o. box 678, CLINTON, ILLINOIS 61727 Docket No. 50-461 Septcznber 26, 1984 Director of Nuclear Reactor Regulation Attention: Mr. A. Schwencer, Chief Licensing Branch No. 2 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Subj ect: Clinton Power Station Unit 1 i Seismic Qualification of Equipment

Dear Mr. Schwencer:

As referenced in the Clinton SSER 2, attachment 1 is submitted and constitutes a summary update to information previously forwarded with Illinois Power letter #U-0707 dated April 30, 1984. Specific details concerning seismic qualification status for each piece of equipment are available in prelimina , form, and copies can be provided if you need them.

Of the 9.852 pieces of equipment which require seismic qual-ification 5524 are qualified, of which 1767 are installed. Expressed as a percentage, approximately 56% are qualified and 17.9% are qualified and installed. Current schedule projections indicate achievement of the 85% equipment qualified and installed on or before May, 1985.

Substantial improvement in the installation complete status is anticipated in the near term due to improvements in cable pulling and I termination progress which will complete many equipment installations. '

Illinois Power anticipates achievement of 85% qualified and installed criteria commensurate with an NRC SQRT audit by July, 1985.

Please contact us if you have any questions concerning this information.

Sincerely yours, 4.A. a ,

F. A. Sp ngen erg Director-NuclearL[icensing and Configuration Nuclear Station Engineering Attachment HED: lam cc: B. L. Siegel, NRC Clinton Licensing Project Manager NRC Resident Office Illinois Department of Nuclear Safety Regional Administrator Region III, USNRC 0l 8410020193 840926 i PDR ADOCK 05000461 E PDR

p

, U-0737 Jo 0982-L L30-84(09-26)-L LA.120 Attachment 1

-Summary-ELECTRICAL AND MECHANICAL SEISMIC QUALIFICATION TOTAL

  • NUMBER **

ITEMS QUALIFIED-NSSS Mechanical and Electrical 3355 993 BOP Mechanical and Electrical- 6497 4531 TOTAL 9852 5524 PERCENT EQUIPMENT QUALIFIED: 56%

  • Total Items: Of the 9852 items which require seismic qualifications, the seismic reports for 8879 have been received by the architect-engineer and are in various stages of review. Expressed as a percentage, 90% of required seismic reports have been received from suppliers.
    • Number Qualified: Equipment identified in this category has been seismically qualified as attested to by qualification binders which have been assembled, reviewed and approved by the architect-engineer.

u

--