Letter Sequence Approval |
---|
|
|
MONTHYEARML0202700142002-02-0101 February 2002 Request for Additional Information, Change to Technical Specification 3/4.7.B.1.a.2, Standby Gas Treatment Heater Requirement. Project stage: RAI ML0223501022002-08-20020 August 2002 Technical Specifications for Amendment No. 194, Change to Technical Specification Surveillance Requirement 3/4.7.B.1.a.2 and TS Bases 3/4.7.B.1, for the Standby Gas Treatment System Project stage: Other ML0219803722002-08-20020 August 2002 Issuance of Amendment No. 194, Change to Technical Specification Surveillance Requirement 3/4.7.B.1.a.2 and TS Bases 3/4.7.B.1, for the Standby Gas Treatment System Project stage: Approval 2002-02-01
[Table View] |
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 L-23-008, Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI)2023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 and Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML21251A1732021-10-21021 October 2021 Enclosure 1 - Pilgrim Amendment No. 257 ISFSI Only Emergency Plan ML21203A0482021-08-24024 August 2021 License Amendment No. 256 ML21217A1752021-08-0505 August 2021 Amendment No 255 Pilgrim Independent Spent Fuel Storage Installation (ISFSI) Only Physical Security Plan - Public Version ML21103A0562021-05-12012 May 2021 Amendment Pilgrim Ps -Alternative Measures Rev 20 ML20335A1832020-12-0101 December 2020 Amendment Pilgrim Ps ISFSI to Incorporate ISFSI II ML20328A2972020-12-0101 December 2020 Amendment No. 253 - Non-Safeguards Version ML19274C6742020-01-0202 January 2020 Issuance of Amendment No. 251, Revise Emergency Plan and Emergency Action Level Scheme to Address Permanently Defueled Condition ML19276C4202020-01-0202 January 2020 Issuance of Amendment No. 252, Request to Remove Cyber Security Plan Requirements for the Permanently Defueled Condition ML19275E4252019-10-28028 October 2019 Issuance of Amendment No. 250, Revise Technical Specifications to Permanently Defueled TS and Revise Facility License for Permanently Defueled Condition ML19235A0502019-08-27027 August 2019 Issuance of Amendment No. 249 Order Approving Direct Transfer of Renewed Facility Operating License and ISFSI General License and Conforming Amendment ML19170A1012019-08-22022 August 2019 Letter, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator ML18284A3752018-11-30030 November 2018 Issuance of Amendment No. 248, Revise Site Emergency Plan for On-Shift and Emergency Response Organization Staffing to Address Permanently Defueled Condition ML18295A0252018-11-16016 November 2018 Correction to Remove Technical Specification Pages from Authority File Related to Amendment Nos. 169 and 177 ML17066A1302017-07-10010 July 2017 Pilgrim Nuclear Power Station - Issuance of Amendment No. 246, Revise Administrative Controls Section of Technical Specifications to Change Staffing and Training Requirements for Permanently Defueled Condition (CAC No. MF9304) ML16250A2232016-10-28028 October 2016 Issuance of Amendments Proposed Changes to Emergency Plan to Revise Training for the on - Shift Chemistry Technician ML16082A4602016-06-0606 June 2016 Issuance of Amendment Cyber Security Plan Implementation Schedule ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request ML14272A0702015-03-12012 March 2015 Issuance of Amendment 242 Re Revision to Technical Specification 2.1, Safety Limits to Resolve Pressure Regulator Fail-Open Transient ML14336A6612014-12-11011 December 2014 Issuance of Amendment Regarding Cyber Security Plan Implementation Schedule Milestone 8 (Tac No. MF3482) ML14295A6852014-10-31031 October 2014 Issuance of Amendment Regarding Heavy Loads to Facilitate Dry Storage Handling Operations ML13025A3062013-03-14014 March 2013 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Correction to Amendments Issued on 12/28/12, Revise QA Program Manual and Staff Qualification Technical Specifications ML12261A1302012-11-13013 November 2012 Issuance of Amendments to Renewed Facility Operating License Changes in Cyber Security Plan Implementation Milestone ML1220100482012-08-0707 August 2012 Issuance of Amendment No. 237 Revision to Condensate Storage Tank Low Level Trip Setpoint ML0910404232012-05-29029 May 2012 Issuance of Renewed License for Pilgrim Nuclear Generating Station ML11152A0432011-07-22022 July 2011 License Amendment, Cyber Security Plan ML1106500092011-03-28028 March 2011 Issuance of Amendment No. 235 Revised Technical Specifications for Setpoint and Setpoint Tolerance Increases for Safety Relief Valves and Spring Safety Valves ML0906402242009-03-26026 March 2009 License Amendment, Revised Technical Specifications (TS) Section 2.1.2, Safety Limit Minimum Critical Power Ratio (SLMCPR) for Two-Loop and Single-Loop Operation ML0815703662008-11-20020 November 2008 License Amendment, Issuance of Amendment Adoption of TSTF-448, Revision 3, Control Room Envelope Habitability ML0727503942007-11-0505 November 2007 License Amendment, Issuance of Amendment Control Rod Operability, Scram Insertion Time, and Control Rod Accumulator Requirements ML0723400092007-08-23023 August 2007 Revised License Pages of Facility Operating License DPR-35 B.5.b ML0708711652007-05-14014 May 2007 Issuance of Amendment Adoption of Technical Specification Task Force (TSTF) Change TSTF-372, the Addition of Limiting Condition for Operation (LCO) 3.0.8 on the Inoperability of Snubbers ML0707404192007-04-25025 April 2007 License Amendment, Issuance of Amendment Single Control Rod Withdrawal Allowances ML0705303842007-03-26026 March 2007 License Amendment, Issuance of Amendment Extension of Pressure-Temperature Limits Specified in Technical Specifications ML0705306462007-03-26026 March 2007 Issuance of License Amendment 226 Adoption of Technical Specification Task Force (TSTF) Change TSTF-484 Use of TS 3.10.1 for Scram Time Testing Activities. ML0624303372006-09-20020 September 2006 License Amendment 225 Regarding Revised Reactor Coolant System Leakage Detection Instrumentation Requirements and Actions ML0622803042006-09-14014 September 2006 Issuance of Amendment Relocation of Technical Specifications ML0617200682006-08-0909 August 2006 Issuance of License Amendment 223 Regarding Administrative Changes and Relocation of Certain Technical Specification Responsibilities ML0618400322006-08-0404 August 2006 Issuance of License Amendment 222 Deletion of Requirement Related to NRC Approval of Engineering Evaluation for Elevated Relief Valve Discharge Pipe Temperature ML0606000402006-04-13013 April 2006 Issuance of Amendment Removal of Main Steam Isolation Valve Twice Per Week Testing Surveillance Requirement ML0607402142006-04-13013 April 2006 License Amendment 221 Regarding Revised Rod Worth Minmizer Bypass Allowances ML0601701192006-04-12012 April 2006 Issuance of Amendment Single Recirculation Loop Operation ML0531404332006-04-10010 April 2006 Issuance of Amendment Revised Applicability for Containment Oxygen and Differential Pressure Limits ML0518700032005-08-29029 August 2005 Issuance of License Amendment 217, Surveillance Frequency Improvements ML0518702572005-07-29029 July 2005 License Amendment 216 Revised Action for Scram Discharge Volume Vent and Drain Valves ML0501804932005-03-16016 March 2005 License Amendment No. 211, Revise Reactor Vessel Hydrostatic and Leak Testing Requirements ML0500504862005-02-0202 February 2005 Issuance of Amendment Changes to Technical Specifications Table 3.2.C-1 ML0423001372005-01-0505 January 2005 License Amendment, Revision to the Reactor Pressure Vessel Material Surveillance Program ML0434902432004-12-27027 December 2004 Issuance of Amendment Engineering Evaluation Submitted Pursuant to Technical Specifications Section 3.6.D.3 and 3.6.D.4 ML0419704502004-08-17017 August 2004 License Amendment, Issuance of Amendment Re.: Multiple Control Rod Removal, Limiting Condition for Operation 3/4.10.D ML0411000092004-07-22022 July 2004 License Amendment, Eliminate Requirements for Hydrogen Analyzers 2021-08-05
[Table view] Category:Safety Evaluation
MONTHYEARML21217A1752021-08-0505 August 2021 Amendment No 255 Pilgrim Independent Spent Fuel Storage Installation (ISFSI) Only Physical Security Plan - Public Version ML20328A2972020-12-0101 December 2020 Amendment No. 253 - Non-Safeguards Version ML19276C4202020-01-0202 January 2020 Issuance of Amendment No. 252, Request to Remove Cyber Security Plan Requirements for the Permanently Defueled Condition ML19274C6742020-01-0202 January 2020 Issuance of Amendment No. 251, Revise Emergency Plan and Emergency Action Level Scheme to Address Permanently Defueled Condition ML19142A0432019-12-18018 December 2019 Letter and Safety Evaluation, Exemption to Allow Reduced Emergency Planning Requirements; Revise Radiological Emergency Response Plan Consistent with Permanently Defueled Reactor ML19235A0502019-08-27027 August 2019 Issuance of Amendment No. 249 Order Approving Direct Transfer of Renewed Facility Operating License and ISFSI General License and Conforming Amendment ML19170A2502019-08-22022 August 2019 Enclosure 3, Safety Evaluation for Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) ML19122A1992019-06-11011 June 2019 Review of Spent Fuel Management Plan ML18284A3752018-11-30030 November 2018 Issuance of Amendment No. 248, Revise Site Emergency Plan for On-Shift and Emergency Response Organization Staffing to Address Permanently Defueled Condition ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 ML17066A1302017-07-10010 July 2017 Pilgrim Nuclear Power Station - Issuance of Amendment No. 246, Revise Administrative Controls Section of Technical Specifications to Change Staffing and Training Requirements for Permanently Defueled Condition (CAC No. MF9304) ML17093A8942017-05-12012 May 2017 Pilgrim Nuclear Power Station - Relief Requests PNPS-ISI-001 and PNPS-ISI-002, Relief from ASME Code Volumetric Examination Requirements for the Fourth 10-Year Inservice Inspection Interval (CAC Nos. MF8092 and MF8093) ML17058A3252017-04-12012 April 2017 Approval of Certified Fuel Handler Training and Retraining Program ML16250A2232016-10-28028 October 2016 Issuance of Amendments Proposed Changes to Emergency Plan to Revise Training for the on - Shift Chemistry Technician ML16251A6202016-09-13013 September 2016 Entergy Fleet Request for Approval of Change to the Entergy Quality Assurance Program Manual (CAC Nos. MF7086 - MF7097) ML16082A4602016-06-0606 June 2016 Issuance of Amendment Cyber Security Plan Implementation Schedule ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16093A0282016-05-31031 May 2016 Entergy Services, Inc., Proposed Alternative to Utilize ASME Code Case N-789-1, Relief Request RR-EN-15-1, Revision 1 ML16124B0872016-05-0303 May 2016 E-mail Review of Safety Evaluation for Proposed Alternative Relief Request No. PRR-51 ML16042A2912016-03-15015 March 2016 Issuance of Proposed Alternative Relief Request PRR-51, Relief from the Requirements of the ASME Code ML16008B0772016-03-0303 March 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML15338A3092016-01-0505 January 2016 Relief Request PRR-50, Relief from the Requirement of the ASME Code, Implementation of Code Case N-702 ML15166A4012015-06-19019 June 2015 Request for Alternative PRR-26 for the Fifth 10-year Inservice Inspection Interval ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request ML15103A0692015-04-21021 April 2015 Relief Request PRR-24 Regarding Nozzle-to-Vessel Welds and Nozzle Inner Radii Examination ML15084A0252015-03-23023 March 2015 Non-Proprietary - Safety Evaluation - Fourth 10-Year Interval Inservice Inspection - Request for Relief PRR-24 ML14272A0702015-03-12012 March 2015 Issuance of Amendment 242 Re Revision to Technical Specification 2.1, Safety Limits to Resolve Pressure Regulator Fail-Open Transient ML14336A6612014-12-11011 December 2014 Issuance of Amendment Regarding Cyber Security Plan Implementation Schedule Milestone 8 (Tac No. MF3482) ML14295A6852014-10-31031 October 2014 Issuance of Amendment Regarding Heavy Loads to Facilitate Dry Storage Handling Operations ML14210A2662014-08-0808 August 2014 Arkansas, Units 1 & 2, Big Rock Point, James A. Fitzpatrick, Grand Gulf, Unit 1, Indian Point, Units 1, 2 & 3, Palisades, Pilgrim, River Bend, Unit 1, Vermont Yankee, Waterford, Safety Evaluation Quality Assurance Program Manual, Rev. 24 & ML14198A1572014-08-0101 August 2014 Relief Requests PR-03 and PR-05 Regarding the Inservice Testing Program (Tac MF0370) ML14083A6312014-03-27027 March 2014 Relief Request PRR-22 Regarding a Risk-Informed Inservice Inspection Program for Class 1 and 2 Piping Welds ML13149A2152013-05-29029 May 2013 Correction to Staff Assessment Letter to Recommendation 9.3 of the Near-Term Task Force Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident ML13127A1792013-05-21021 May 2013 Staff Assessment in Response to Recommendation 9.3 of the Near-Term Task Force Related to the Fukushima Dai-ichi Nuclear Power Plant Accident ML13025A3062013-03-14014 March 2013 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Correction to Amendments Issued on 12/28/12, Revise QA Program Manual and Staff Qualification Technical Specifications ML12261A1302012-11-13013 November 2012 Issuance of Amendments to Renewed Facility Operating License Changes in Cyber Security Plan Implementation Milestone ML1220100482012-08-0707 August 2012 Issuance of Amendment No. 237 Revision to Condensate Storage Tank Low Level Trip Setpoint ML12174A1472012-07-10010 July 2012 Safety Evaluation for Relief Request PRR-21, Rev 4, to Install a Weld Overlay on RPV-n14-1 Standby Liquid Control Safe-End Nozzle Weld at Pilgrim ML11152A0432011-07-22022 July 2011 License Amendment, Cyber Security Plan ML1106500092011-03-28028 March 2011 Issuance of Amendment No. 235 Revised Technical Specifications for Setpoint and Setpoint Tolerance Increases for Safety Relief Valves and Spring Safety Valves ML1100502982011-01-26026 January 2011 Issuance of Amendment Regarding Revised Pressure and Temperature (P-T) Limit Curves and Relocation of P-T Curves to the PTLR ML1022901632010-08-25025 August 2010 Relief Request PRR-20, Alternative Examination Requirements for Nozzle-To-Shell and Inner Radii Welds Using ASME Code Case N-702 and BWRVIP-108 - Pilgrim Nuclear Power Station ML0936208072010-01-22022 January 2010 Cover Letter, (Non-Proprietary) Order Extending the Effectiveness of the Approval of the Indirect Transfer of Facility Operating Licenses for Big Rock Point, Fitzpatrick, Indian Point, Palisades, Pilgrim, and Vermont Yankee Nuclear Power St ML0936208952010-01-22022 January 2010 Safety Evaluation,(Non-Proprietary) Order Extending the Effectiveness of the Approval of the Indirect Transfer of Facility Operating Licenses for Big Rock Point, Fitzpatrick, Indian Point,Palisades,Pilgrim, and Vermont Yankee Nuclear Power ML0928706472009-10-29029 October 2009 Request for Threshold Determination Under 10 CFR 50.80-Big Rock Point, James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Nos. 1, 2 and 3, Palisades, Pilgrim, Vermont Yankee ML0927301372009-10-0909 October 2009 Safety Evaluation by the Office of Nuclear Reactor Regulation Corporate Restructuring Conversion of Companies and Stock Split-Off by Entergy Nuclear Operations, Inc and Subsidiaries ML0923705492009-09-11011 September 2009 Relief Request (PRR)19, Install a Weld Overlay on Jet Pump Instrumentation Nozzle Weld RPV-N9A-1- Pilgrim Nuclear Power Station ML0911304562009-04-30030 April 2009 Relief Request ISI-2008-1, Use of Later ASME Section XI Code Edition and Addenda for Repair and Replacement, Pressure Testing, and Destructive Testing Activities-Pilgrim Nuclear Power Station ML0906402242009-03-26026 March 2009 License Amendment, Revised Technical Specifications (TS) Section 2.1.2, Safety Limit Minimum Critical Power Ratio (SLMCPR) for Two-Loop and Single-Loop Operation ML0815703662008-11-20020 November 2008 License Amendment, Issuance of Amendment Adoption of TSTF-448, Revision 3, Control Room Envelope Habitability 2021-08-05
[Table view] |
Text
August 20, 2002 Mr. Mike Bellamy Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360
SUBJECT:
PILGRIM NUCLEAR POWER STATION - ISSUANCE OF AMENDMENT RE:
CHANGE TO TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT FOR THE STANDBY GAS TREATMENT SYSTEM (TAC NO. MB2775)
Dear Mr. Bellamy:
The Commission has issued the enclosed Amendment No. 194 to Facility Operating License No. DPR-35 for the Pilgrim Nuclear Power Station (Pilgrim). This amendment is in response to Entergy Nuclear Generation Companys (ENGC) application dated August 22, 2001, as supplemented March 5, 2002. On May 5, 2002, the operating authority for Pilgrim was transferred from ENGC to Entergy Nuclear Operations, Inc. (ENO). By letter dated May 8, 2002, as supplemented May 24, 2002, ENO requested that the U.S. Nuclear Regulatory Commission (NRC) continue to review and act on any pending actions and correspondence which had been submitted by ENGC before the transfer. Accordingly, the NRC staff has acted upon the request.
This amendment revises the Technical Specification (TS) Surveillance Requirement 3/4.7.B.1.a.2 for the Standby Gas Treatment (SBGT) System and associated TS Bases 3/4.7.B.1, by increasing the SBGT inlet heaters minimum output testing requirement from 14 kilowatts (kW) to 20 kW.
A copy of the related Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commission's biweekly Federal Register Notice.
Sincerely,
/RA/
Travis L. Tate, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosures:
- 1. Amendment No. 194 to License No. DPR-35
- 2. Safety Evaluation cc w/encls: See next page
August 20, 2002 Mr. Mike Bellamy Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360
SUBJECT:
PILGRIM NUCLEAR POWER STATION - ISSUANCE OF AMENDMENT RE:
CHANGE TO TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT FOR THE STANDBY GAS TREATMENT SYSTEM (TAC NO. MB2775)
Dear Mr. Bellamy:
The Commission has issued the enclosed Amendment No. 194 to Facility Operating License No. DPR-35 for the Pilgrim Nuclear Power Station (Pilgrim). This amendment is in response to Entergy Nuclear Generation Companys (ENGC) application dated August 22, 2001, as supplemented March 5, 2002. On May 5, 2002, the operating authority for Pilgrim was transferred from ENGC to Entergy Nuclear Operations, Inc. (ENO). By letter dated May 8, 2002, as supplemented May 24, 2002, ENO requested that the U.S. Nuclear Regulatory Commission (NRC) continue to review and act on any pending actions and correspondence which had been submitted by ENGC before the transfer. Accordingly, the NRC staff has acted upon the request.
This amendment revises the Technical Specification (TS) Surveillance Requirement 3/4.7.B.1.a.2 for the Standby Gas Treatment (SBGT) System and associated TS Bases 3/4.7.B.1, by increasing the SBGT inlet heaters minimum output testing requirement from 14 kilowatts (kW) to 20 kW.
A copy of the related Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commission's biweekly Federal Register Notice.
Sincerely,
/RA/
Travis L. Tate, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosures:
- 1. Amendment No. 194 to License No. DPR-35
- 2. Safety Evaluation cc w/encls: See next page DISTRIBUTION:
J. Zimmerman C. Anderson, RI PUBLIC T. Clark PDI-2 R/F T. Tate OGC G. Hill (2), T-5C3 ACRS R. Dennig S. Richards C. Holden E. Weiss D. Nguyen J. Raval
- See previous concurrence Accession Number: ML021980372 *Safety evaluation dated 3/29/02, no major changes made OFFICE PDI-2/PM PDI-2/LA EEIB/SC* SPLB/SC** RTSB/SC** OGC** PDI-2/SC(A)
NAME TTate TClark CHolden EWeiss RDennig JHeck JZimmerman DATE 8/19/02 8/19/02 3/29/052 7/29/02 7/26/02 8/5/02 8/19/02 OFFICIAL RECORD COPY
Pilgrim Nuclear Power Station cc:
Resident Inspector Mr. C. Stephen Brennion U. S. Nuclear Regulatory Commission Licensing Superintendent Pilgrim Nuclear Power Station Pilgrim Nuclear Power Station Post Office Box 867 600 Rocky Hill Road Plymouth, MA 02360 Plymouth, MA 02360-5599 Chairman, Board of Selectmen Mr. Jack Alexander 11 Lincoln Street Manager, Reg. Relations and Plymouth, MA 02360 Quality Assurance Pilgrim Nuclear Power Station Chairman, Duxbury Board of Selectmen 600 Rocky Hill Road Town Hall Plymouth, MA 02360-5599 878 Tremont Street Duxbury, MA 02332 Mr. David F. Tarantino Nuclear Information Manager Office of the Commissioner Pilgrim Nuclear Power Station Massachusetts Department of 600 Rocky Hill Road Environmental Protection Plymouth, MA 02360-5599 One Winter Street Boston, MA 02108 Ms. Jane Perlov Secretary of Public Safety Office of the Attorney General Executive Office of Public Safety One Ashburton Place One Ashburton Place 20th Floor Boston, MA 02108 Boston, MA 02108 Mr. Stephen J. McGrail, Director Dr. Robert M. Hallisey, Director Attn: James Muckerheide Radiation Control Program Massachusetts Emergency Management Commonwealth of Massachusetts Agency Executive Offices of Health and 400 Worcester Road Human Services Framingham, MA 01702-5399 174 Portland Street Boston, MA 02114 Chairman Nuclear Matters Committee Regional Administrator, Region I Town Hall U. S. Nuclear Regulatory Commission 11 Lincoln Street 475 Allendale Road Plymouth, MA 02360 King of Prussia, PA 19406 Mr. William D. Meinert John M. Fulton Nuclear Engineer Assistant General Counsel Massachusetts Municipal Wholesale Pilgrim Nuclear Power Station Electric Company 600 Rocky Hill Road P.O. Box 426 Plymouth, MA 02360-5599 Ludlow, MA 01056-0426
ENTERGY NUCLEAR GENERATION COMPANY ENTERGY NUCLEAR OPERATIONS, INC.
DOCKET NO. 50-293 PILGRIM NUCLEAR POWER STATION AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 194 License No. DPR-35
- 1. The Nuclear Regulatory Commission (the Commission or the NRC) has found that:
A. The application for amendment filed by the Entergy Nuclear Generation Company (the licensee) dated August 22, 2001, as supplemented March 5, 2002, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B of Facility Operating License No. DPR-35 is hereby amended to read as follows:
B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 194, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of the date of issuance and shall be implemented within 30 days.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Jacob I. Zimmerman, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: August 20, 2002
ATTACHMENT TO LICENSE AMENDMENT NO. 194 FACILITY OPERATING LICENSE NO. DPR-35 DOCKET NO. 50-293 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert 3/4.7-11 3/4.7-11 B3/4.7.9 B3/4.7.9
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 194 TO FACILITY OPERATING LICENSE NO. DPR-35 ENTERGY NUCLEAR GENERATION COMPANY ENTERGY NUCLEAR OPERATIONS, INC.
PILGRIM NUCLEAR POWER STATION DOCKET NO. 50-293
1.0 INTRODUCTION
By application dated August 22, 2001, as supplemented on March 5, 2002, Entergy Nuclear Generation Company (ENGC) requested changes to the Technical Specifications (TSs) for the Pilgrim Nuclear Power Station (Pilgrim or the licensee). The supplement dated March 5, 2002, provided additional information that clarified the application, and did not expand the scope of the application or change the staffs proposed no significant hazards consideration determination as published in the Federal Register on November 14, 2001 (66 FR 57121). On May 5, 2002, the operating authority for Pilgrim was transferred from ENGC to Entergy Nuclear Operations, Inc. (ENO). By letter dated May 8, 2002, as supplemented May 24, 2002, ENO requested that the U.S. Nuclear Regulatory Commission (NRC) continue to review and act on any pending actions and correspondence which had been submitted by ENGC before the transfer. Accordingly, the NRC staff has acted upon the request.
The proposed changes would revise the TS surveillance requirement (SR) and the associated Bases for the Standby Gas Treatment (SBGT) System based upon revised design basis calculations performed for the SBGT inlet heaters and the replacement of the existing heaters with heaters of higher output capability. Specifically the proposed change would revise:
(1) SR 3/4.7.B.1.a.2, and (2) Bases 3/4.7.B.1, to reflect an increase in the SBGT inlet heaters minimum output capability required to be demonstrated once per operating cycle for each train from at least 14 kilowatts (kW) to 20 kW.
2.0 REGULATORY EVALUATION
As discussed in Section 7.18 of the Pilgrim Updated Final Safety Analysis Report (UFSAR), the purpose of the SBGT system is to mitigate the release of radioactive materials to the environment such that the offsite doses resulting from a postulated loss-of-coolant-accident (LOCA) or postulated fuel handling accident in the reactor building are below the limits in Title 10 of the Code of Federal Regulations (10 CFR), Part 100. The SBGT system is designed to filter reactor building exhaust air and discharge through a ventilation exhaust stack. During accident conditions, charcoal filters used in the SBGT system must remove 99% of the
radioactive methyl iodide from the air to ensure the 10 CFR Part100 limits are not exceeded. A limiting maximum value of 70% relative humidity (RH) for the inlet airstream ensures that the charcoal filters will remove 99% of the radioactive methyl iodide. The rate of elemental iodine removal is relatively insensitive to humidity. The SBGT system uses a bank of electric heaters designed to raise the temperature of the inlet airstream sufficiently to decrease the humidity of the airstream to 70% RH at assumed inlet air conditions of 120 °F and 100% RH.
During a review of the adequacy of the SBGT system, the licensee discovered that the inlet heaters could not assure the desired 70% RH under all conditions. The licensee determined that the electric heaters have a total capacity of 21.9 kW at 480 Vac, but degraded ac voltage conditions can significantly decrease the heaters effective capacity. The licensee reviewed this condition in accordance with the guidance of Generic Letter 91-18, Information to Licensees Regarding Two NRC Inspection Manual Sections on Resolution of Degraded and Nonconforming Conditions and on Operability, and determined the SBGT system to be operable but in need of modification.
To ensure the RH of the SBGT airstream will be no greater than 70% under the assumed inlet airstream conditions of 120 °F and 100% RH and other conservative assumptions, the minimum capacity of the heaters must be increased to 20 kW under all conditions. The licensee implemented a plant design change (PDC 00-26) and installed heaters to increase the capacity to a total rated capacity of 30.2 kW with a degraded voltage capacity of approximately 23.4 kW.
The heaters were installed in accordance with the provisions of 10 CFR 50.59. The higher heater output may impact the environmental qualification (EQ) of other electrical equipment. In accordance with the requirements of 10 CFR 50.49, electrical equipment important to safety must be environmentally qualified for its intended safety function. The licensees 10 CFR 50.59 evaluation considered the impact of updated temperature conditions to ensure that the increased heater capacity does not adversely impact other equipment.
3.0 TECHNICAL EVALUATION
The NRC staff reviewed the licensees application dated August 22, 2001, as supplemented on dated March 5, 2002.
The proposed change involves requesting approval of a more restrictive TS SR and does not involve changes in the frequency, method, or scope of testing of the operability and capacity of the inlet heaters. The inlet heaters will be tested to higher acceptance criteria. The licensee evaluated the effects of the higher capacity heaters (e.g., increased electrical load and heat load on components and charcoal) and found no adverse impacts on other equipment. The licensee also determined the increased electrical load of the higher capacity heaters will not adversely impact other equipment during a design-basis accident. The licensee increased the heaters capacity to meet the 70% RH design requirement for the charcoal beds in the SBGT system in accordance with the provisions of 10 CFR 50.59. The impact of the increased heater capacity and component replacements on supply breakers, cable sizing, 480 Vac motor control center (MCC) loading, and emergency diesel generators (EDGs) loading was considered in the 10 CFR 50.59 evaluation.
In addition to the heaters, the licensee also replaced electrical support components to accommodate the higher capacity of the heaters and/or to obtain appropriate EQ documentation for the higher temperature conditions. The existing 30-ampere, three-pole
circuit breakers were replaced with 50-ampere breakers for each SBGT system unit. The four contactors for the four banks of heaters and the 480/120 Vac control transformer for each SBGT system unit were also replaced. In addition, some of the wiring in contactor panels was replaced and new cables were installed from these panels to the banks of heaters. The licensee evaluated the total effects of the modification and concluded that the modification did not adversely impact other equipment. Condolences 3.1 Analysis of Minimum Heater Capacity The staff performed an independent calculation that verified the licensees determination of at least 20 kW heater capacity is acceptable to maintain the SBGT system flow (downstream of the heaters) at 70% RH based on the bounding accident condition assumptions at the inlet of the heaters while taking into account the possibility of a degraded voltage supply. Therefore, the staff finds that the licensees proposed inlet heater output surveillance requirement of at least 20 kW is acceptable because the heater output values are consistent with the system design, and are more conservative than the current values of the heater ratings.
3.2 System EQ Evaluation 3.2.1 Temperature Conditions The assumed maximum SBGT system unit surface and room temperatures include the maximum electric heater output and a conservatively derived estimate of the effect from radioactive decay heat loading on the charcoal. The SBGT system unit surface and room temperatures are highest when only one SBGT system train is operating, after the other train has absorbed the maximum post-LOCA halogen loading and then becomes inactive (the fan is shut down).
Maximum temperature conditions can occur if the SBGT system A train is operated for the first 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> (8.3 days) after a LOCA to adsorb the maximum halogen loading and then the system is swapped over to the B train. In this configuration, the A train charcoal is cooled only by the 500 cubic-feet-per-minute (CFM) flow of air from the active B train. The total heat radiated to the SBGT system room is maximized because the surface temperature of the SBGT system in the inactive A train is maximized due to the charcoal decay heat load and the low bypass-airflow rate.
The highest temperatures on the surface of SBGT system units and in the SBGT system room occur when the total SBGT system airflow rate is minimized at 3,600 CFM, the electric heater output is maximized at 30.2 kW total, and 13.4 kW of energy is generated by the radioactive decay of halogen on the charcoal in the inactive train. At these conditions, the airstream temperatures of the SBGT system units are highest for each of the calculated locations downstream of the electric heaters and downstream of the inactive charcoal beds (bypass air only) and for the total mixed exhaust airstream. At the peak charcoal decay heat loading 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> after the LOCA, the airstream temperature of the SBGT system unit downstream of the electric heaters entering the charcoal beds is 148 EF; downstream of the inactive charcoal bed is 199 EF (bypass air only); the mixed exhaust is 155 EF (air flow of active train plus bypass airflow); and the SBGT system room temperature is 140 EF.
3.2.1.a Electrical Equipment The SBGT system room was previously defined as a mild-temperature environment (not exceeding 130 EF). Accordingly, new electrical support components were installed and the EQ profile was updated to 140 EF to meet the design-basis requirement to evaluate all components affected by the new conditions. The existing control transformers and contactors for the inlet heaters were replaced with transformers and contactors having appropriate EQ profiles. EQ data was also updated for the new wiring installed and EQ evaluations for existing components requiring EQ design record files were updated to reflect the new temperature conditions. The NRC staff verified that the licensees action to upgrade equipment and verify the EQ profile meets the requirements of 10 CFR 50.49.
3.2.1.b Charcoal Beds The maximum airstream temperature from the SBGT system units entering the charcoal beds downstream of the electric heaters operating at 30.2 kW capacity is 148 EF with a total flow of 3,600 CFM (4,000 CFM -10%). The over-temperature cutoff switch has a setpoint of 200 EF.
The highest temperature exiting the inactive charcoal bed is bounded by a maximum potential value of 244 °F so that the airstream through the high energy particulate filters remain below the design-basis value of 260 EF.
Using a conservative heat transfer calculation for the decay heat load on the charcoal, it was determined that the charcoal temperature is bounded by a maximum potential value of 253 EF.
Therefore, the charcoal will be below the design-basis value of 330 EF under all conditions and iodine desorption is prevented.
3.2.2 Outlet Damper Operations Special consideration was given to the qualification status of the motor-operated standby gas fan outlet dampers. For the emergency mode of operation, the outlet dampers are in the full-open position and remain in that position; that is, the damper is a static component and the motor-operator has no required active function in the emergency mode. Therefore, the EQ design record file for this component does not require an evaluation of the active operation of the motor-operator during the worst-case design-basis-accident temperatures. The staff reviewed the outlet dampers and concluded that the licensees treatment of these dampers is consistent with 10 CFR 50.49.
3.3 Electrical Load Analysis The licensee evaluated the increased EDG loads due to the increased heater capacity and determined that the increased load was within the EDG ratings. The increased EDG loads were included in the EDG loading profile. In addition, the licensee updated: (1) certain electrical calculations for ampacity and degraded voltage to include the higher kW heaters; (2) the undercurrent relay trip setpoint for detecting SBGT system inlet heater failures; and (3) the SBGT system airflow, temperature, humidity, charcoal temperature, and SBGT system room temperature in the design-basis analysis. The updated design-basis calculation uses a maximum SBGT system flow rate of 4,400 CFM (4,000 CFM +10%), which is the highest potential flow rate for the SBGT system in actual operation. The continuous rating of the EDG is 2,600 kW. The 2,000-hour rating is 2,750 kW and the 2-hour rating is 2,860 kW.
Tables 8.5-1 and 8.5-2 of the UFSAR list the total kW of continuous and short-term emergency loads for a Loss of Offsite Power (LOOP) or LOOP/LOCA events. The staff verified that the increased load was within these EDG ratings and the EDGs are periodically tested at these ratings.
The licensee also evaluated the impact of increased heater capacity on the 480 Vac MCCs and replaced the 480/120 Vac control transformer for each SBGT system unit to accommodate the additional electrical loading.
3.4 Conclusion Based upon the preceding discussion, the NRC staff concludes that the licensee has evaluated the effects of the larger heaters (e.g., increased electrical load and heat load on components and charcoal) and has provided sufficient data to support the conclusion that the increased electrical load of the larger heaters will not adversely impact other equipment during a design-basis accident. The staff concludes that this change is acceptable since the affected electrical equipment remains qualified per 10 CFR Part 50.49, the additional load is within the EDG rating, and this change will ensure 10 CFR Part 100 limits will be met for all conditions.
4.0 STATE CONSULTATION
In accordance with the Commissions regulations, the Massachusetts State Official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes surveillance requirements. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (66 FR 57121). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributors: D. Nguyen J. Raval Date: August 20, 2002