Amendment Pilgrim Ps -Alternative Measures Rev 20
ML21103A056
Person / Time
Site: Pilgrim
Issue date: 05/12/2021
From: Bruce Watson
Reactor Decommissioning Branch
To:
Holtec Decommissioning International
Snyder A
Shared Package
ML21103A046 List:
References
Download: ML21103A056 (2)


Text

HOLTEC DECOMMISSIONING INTERNATIONAL, LLC.

DOCKET NO. 50-293 PILGRIM NUCLEAR POWER STATION AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 254 License No. DPR-35

1. The Nuclear Regulatory Commission (the Commission or the NRC) has found that:

A. The application for license amendment filed by the Holtec Decommissioning International LLC, Inc. (HDI or the licensee), dated April 2, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20141L057 Pkg.), as supplemented by letters dated April 22, 2020, (ADAMS Accession No. ML20122A055), June 25, 2020 (ML20188A061), July 21, 2020 (ML20213C031, nonpublic), July 22, 2020 (ML20213B743, nonpublic), and July 30, 2020 (ML20220A351 and ML20220A352, nonpublic), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and applicable portions of the Commissions regulations set forth in Title 10 of the Code of Federal Regulations (10 CFR) Chapter I, and all required notifications to other agencies or bodies have been duly made; B. The facility will operate in conformity with the application, as supplemented, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security, or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, of the Commissions regulations and all applicable requirements have been satisfied.

2. The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to 10 CFR 72.212(b)(9) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, is titled: Pilgrim Nuclear Power Station Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Pilgrim ISFSI II Physical Security Plan, Revision 20," dated October 5, 2020 (Agencywide Documents Access and Management System [ADAMS] Accession No.

Main Library [ML] ML20283A292), as supplemented by letters December 10, 2020

2 (ADAMS Accession No. ML20346A047), February 25, 2021 (ADAMS Accession No.ML21063A104), and March 17, 2021 (ADAMS Accession No. ML21077A103, non-public OUO-Security Related Information).

3. This license amendment is effective immediately. The Physical Security Plan, Rev. 20 shall be implemented when the required physical security training to address changes from Rev. 19A to Rev. 20 is complete. Appendix D of the Physical Security Plan, Revision 20, shall not be implemented until after the required security training to address changes from Appendix D Rev. 19A to Appendix D Rev. 20 is complete and the licensee receives written verification from the NRC that the licensee has adequately demonstrated compliance with the additional security measure requirements (as applicable to ISFSI II) per Order EA-13-132.

FOR THE NUCLEAR REGULATORY COMMISSION Signed by Watson, Bruce on 05/12/21 Bruce A. Watson, CHP, Chief Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards

Attachment:

Change to Facility Operating License No. DPR-35 Date of Issuance: May 12, 2020