Provides Quarterly Update Re Const Schedule.Fuel Loading & Commercial Operation Projected for Jan & Aug 1984, Respectively
ML20063P355
Person / Time
Site: Clinton Constellation icon.png
Issue date: 10/11/1982
From: Koch L
ILLINOIS POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
U-0561, U-561, NUDOCS 8210130325
Download: ML20063P355 (1)


Text

U-0561 fit /NO/c POWER COMPANY ffy 2-82({0-I 99 HS EET, DECATUR. ILUNOIS 62525 October 11,1982 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Denton:

Reference:

IP Letter 7/8/82 (U-0514), L. J. Koch to H. R.

Denton, NRC Clinton Power Station Unit 1 Docket No. 50-461 The referenced letter provided a quarterly update report on the Clinton Unit 1 construction schedule. This is another quarterly updating and our current schedule for Clinton Unitl remains unchanged from the last report to you, i.e., construction completion and fuel loading in January 1984 and commercial op-eration projected for August 1984.

We will comply with your request to provide your office with quarterly updates. Our next schedule report will be sent in January, 1933.

Sincerely,

/,

f

/

'L J. Koch Vice President GEW/j a cc: Mr. J. H. Williams, NRC Clinton Project Manager Mr. H. H. Livermore, NRC Resident Inspector Illinois Dept. of Nuclear Safety 3oo l fB210130325 B2101'1 05000461 dl PDR ADOCK PDR ._