U-0561 fit /NO/c POWER COMPANY ffy 2-82({0-I 99 HS EET, DECATUR. ILUNOIS 62525 October 11,1982 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Denton:
Reference:
IP Letter 7/8/82 (U-0514), L. J. Koch to H. R.
Denton, NRC Clinton Power Station Unit 1 Docket No. 50-461 The referenced letter provided a quarterly update report on the Clinton Unit 1 construction schedule.
This is another quarterly updating and our current schedule for Clinton Unitl remains unchanged from the last report to you, i.e.,
construction completion and fuel loading in January 1984 and commercial op-eration projected for August 1984.
We will comply with your request to provide your office with quarterly updates.
Our next schedule report will be sent in January, 1933.