ML15132A569
ML15132A569 | |
Person / Time | |
---|---|
Site: | Vogtle |
Issue date: | 06/09/2016 |
From: | Martin R Plant Licensing Branch II |
To: | Pierce C Southern Nuclear Operating Co |
Martin R, NRR/DORL/LPL2-1 | |
References | |
TAC MF4560, TAC MF4561 | |
Download: ML15132A569 (102) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 9, 2016 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company, Inc.
P.O. Box 1295, Bin - 038 Birmingham, AL 35201-1295
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS REGARDING MULTIPLE TECHNICAL SPECIFICATION CHANGES (TAC NOS. MF4560 AND MF4561)
Dear Mr. Pierce:
The U.S. Nuclear Regulatory Commission (NRG, the Commission) has issued the enclosed Amendment No. 180 to Renewed Facility Operating LicensecNo. NPF-68 and Amendment No. 161 to Renewed Facility Operating License No. NPF-81 for the Vogtle Electric Generating Plant (VEGP), Units 1 and 2, in response to your application dated July 18, 2014, as supplemented by letters dated February 27, 2015, and May 2, 2016.
The amendments revise the technical specifications (TSs) by adopting 22 previously NRC-approved Technical Specifications Task Force (TSTF) Travelers. One proposed change is not included in these license amendments and will be addressed by further correspondence.
Southern Nuclear Operating Company, Inc. (SNC) stated that these TSTF Travelers are generic changes chosen to increase the consistency between the VEGP TSs, the Improved Standard Technical Specifications for Westinghouse plants (NUREG-1431), and the TSs of the other plants in the SNC fleet.
C.R. Pierce A copy of the related safety evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Register notice.
Sincerely,
!{:!e( ~ject Plant Licensing Branch 11-1 Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosures:
- 1. Amendment No. 180 to NPF-68
- 2. Amendment No. 161 to NPF-81
- 3. Safety Evaluation cc w/enclosures: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SOUTHERN NUCLEAR OPERATING COMPANY. INC.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MUNICIPAL ELECTRIC AUTHORITY OF GEORGIA CITY OF DALTON. GEORGIA DOCKET NO. 50-424 VOGTLE ELECTRIC GENERATING PLANT. UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 180 Renewed License No. NPF-68
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment to the Vogtle Electric Generating Plant, Unit 1 (the facility), Renewed Facility Operating License No. NPF-68 filed by the Southern Nuclear Operating Company, Inc. (the licensee), acting for itself, Georgia Power Company, Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia (the owners), dated July 18, 2014, as supplemented by letters dated February 27, 2015, and May 2, 2016, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 1
- 2. Accordingly, the license is hereby amended by page changes to the Technical Specifications (TSs) as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-68 is hereby amended to read as follows:
C. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 180, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this license. Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 120 days.
(a) Implementation of the amendment related to TSTF-2-A, Revision 1, shall include relocation of the Surveillance Requirement 3.8.3.7 requirements for sediment cleaning of the fuel oil storage tanks every 10 years from the TSs to a document that is controlled by the licensee pursuant to 10 CFR 50.59.
(b) Implementation of the amendment related to TSTF-110-A, Revision 2 (TSs 3.1.4, 3.1.6, 3.2.3, and 3.2.4), shall include relocation of the surveillance frequencies related to inoperable alarms to a document that is controlled by the licensee pursuant to 10 CFR 50.59.
FOR THE NUCLEAR REGULATORY COMMISSION Michael T. Markley, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to Renewed NPF-68 and Technical Specifications Date of Issuance: June 9, 2016
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SOUTHERN NUCLEAR OPERATING COMPANY. INC.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MUNICIPAL ELECTRIC AUTHORITY OF GEORGIA CITY OF DALTON. GEORGIA DOCKET NO. 50-425 VOGTLE ELECTRIC GENERATING PLANT. UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 161 Renewed License No. NPF-81
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment to the Vogtle Electric Generating Plant, Unit 2 (the facility), Renewed Facility Operating License No. NPF-81 filed by the Southern Nuclear Operating Company, Inc. (the licensee), acting for itself, Georgia Power Company Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia (the owners), dated July 18, 2014, as supplemented by letters dated February 27, 2015, and May 2, 2016, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public: and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 2
- 2. Accordingly, the license is hereby amended by page changes to the Technical Specifications (TSs) as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-81 is hereby amended to read as follows:
C. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 161, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this license. Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 120 days.
(a) Implementation of the amendment related to TSTF-2-A, Revision 1, shall include relocation of the Surveillance Requirement 3.8.3.7 requirements for sediment cleaning of the fuel oil storage tanks every 10 years from the TSs to a document that is controlled by the licensee pursuant to 10 CFR 50.59.
(b) Implementation of the amendment related to TSTF-110-A, Revision 2 (TSs 3.1.4, 3.1.6, 3.2.3, and 3.2.4), shall include relocation of the surveillance frequencies related to inoperable alarms to a document that is controlled by the licensee pursuant to 10 CFR 50.59.
FOR THE NUCLEAR REGULATORY COMMISSION
~-Z:/,u.~
Michael T. Markley, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to Renewed NPF-81 and Technical Specifications Date of Issuance: June 9, 2016
ATTACHMENT TO LICENSE AMENDMENT NO. 180 RENEWED FACILITY OPERATING LICENSE NO. NPF-68 DOCKET NO. 50-424 AND LICENSE AMENDMENT NO. 161 RENEWED FACILITY OPERATING LICENSE NO. NPF-81 DOCKET NO. 50-425 Replace the following pages of the Renewed Facility Operating Licenses and the Appendix A Technical Specifications (TSs) with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Pages Insert Pages License License License No. NPF-68, page 4 License No. NPF-68, page 4 License No. NPF-81, page 3 License No. NPF-81, page 3 1.1-6 1.1-6 1.4-1 1.4-1 1.4-2 1.4-2 1.4-3 1.4-3 1.4-4 1.4-4 1.4-5 1.4-6 1.4-7 1.4-8 3.1.2-1 3.1.2-1 3.1.4-2 3.1.4-2 3.1.4-3 3.1.4-3 3.1.6-3 3.1.6-3 3.1.7-1 3.1.7-1 3.1.7-2 3.1.7-2 3.1.7-3 3.1.7-3 3.2.1-1 3.2.1-1 3.2.2-1 3.2.2-1 3.2.3-1 3.2.3-1 3.2.4-1 3.2.4-1 3.2.4-3 3.2.4-3
3.2.4-4 3.2.4-4 3.3.4-1 3.3.4-1 3.3.4-3 3.4.2-1 3.4.2-1 3.4.5-2 3.4.5-2 3.4.9-1 3.4.9-1 3.4.9-2 3.4.9-2 3.4.11-1 3.4.11-1 3.4.11-2 3.4.11-2 3.4.11-3 3.4.11-3 3.4.12-4 3.4.12-4 3.4.16-1 3.4.16-1 3.6.3-4 3.6.3-4 3.6.3-5 3.6.3-5 3.7.5-1 3.7.5-1 3.7.5-3 3.7.5-3 3.7.5-4 3.7.5-4 3.7.5-5 3.8.3-3 3.8.3-3 3.8.3-4 3.9.1-1 3.9.1-1 3.9.4-2 3.9.4-2 3.9.6-1 3.9.6-1 3.9.6-2 3.9.6-2 5.5-3 5.5-3 5.5-15 5.5-15 5.5-17 5.5-17 5.5-18 5.5-18
( 1) Maximum Power Level Southern Nuclear is authorized to operate the facility at reactor core power levels not in excess of 3625.6 megawatts thermal (100 percent power) in accordance with the conditions specified herein.
(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 180, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this license. Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the environmental Protection Plan.
(3) Southern Nuclear Operating Company shall be capable of establishing containment hydrogen monitoring within 90 minutes of initiating safety injection following a loss of coolant accident.
(4) Deleted (5) Deleted (6) Deleted (7) Deleted (8) Deleted (9) Deleted (10) Mitigation Strategy License Condition The licensee shall develop and maintain strategies for addressing large fires and explosions and that include the following key areas:
(a) Fire fighting response strategy with the following elements:
- 1. Pre-defined coordinated fire response strategy and guidance
- 2. Assessment of mutual aid fire fighting assets
- 3. Designated staging areas for equipment and materials
- 4. Command and control
- 5. Training and response personnel (b) Operations to mitigate fuel damage considering the following:
- 1. Protection and use of personnel assets
- 2. Communications
- 3. Minimizing fire spread
- 4. Procedures for Implementing integrated fire response strategy
- 5. Identification of readily-available pre-staged equipment
- 6. Training on integrated fire response strategy Renewed Operating License NPF-68 Amendment No. 180
(2) Georgia Power Company, Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia, pursuant to the Act and 10 CFR Part 50, to possess but not operate the facility at the designated location in Burke County, Georgia, in accordance with the procedures and limitations set forth in this license; (3) Southern Nuclear, pursuant to the Act and 10 CFR Part 70, to receive, possess, and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (4) Southern Nuclear, pursuant to the Act and 10 CFR Parts 30, 40, and 70 to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5) Southern Nuclear, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6) Southern Nuclear, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as my be produced by the operation of the facility authorized herein.
C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter 1 and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect, and is subject to the additional conditions specified or incorporated below.
(1) Maximum Power Level Southern Nuclear is authorized to operate the facility at reactor core power levels not in excess of 3625.6 megawatts thermal (100 percent power) in accordance with the conditions specified herein.
(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 161 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this license. Southern Nuclear shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
The Surveillance requirements (SRs) contained in the Appendix A Technical Specifications and listed below are not required to be performed immediately upon implementation of Amendment No. 74. The SRs listed below shall be Renewed Operating License NPF-81 Amendment No. 161
Definitions 1.1 1.1 Definitions (continued)
SHUTDOWN MARGIN (SOM) SOM shall be the instantaneous amount of reactivity by which the reactor is subcritical or would be subcritical from its present condition assuming:
- a. All rod cluster control assemblies (RCCAs) are fully inserted except for the single RCCA of highest reactivity worth, which is assumed to be fully withdrawn.
However, with all RCCAs verified fully inserted by two independent means, it is not necessary to account for a stuck rod in the SOM calculation. Wrth any RCCA not capable of being fully inserted, the reactivity worth of the RCCA must be accounted for in the determination of SOM; and
- b. In MODES 1 and 2, the fuel and moderator temperatures are changed to the hot zero power temperatures.
SLAVE RELAY TEST A SLAVE RELAY TEST shall consist of energizing each slave relay and verifying the OPERABILITY of each slave relay.
The SLAVE RELAY TEST shall include, as a minimum, a continuity check of associated testable actuation devices.
STAGGERED TEST BASIS A STAGGERED TEST BASIS shall consist of the testing of one of the systems, subsystems, channels, or other designated components during the interval specified by the Surveillance Frequency, so that all systems, subsystems, channels, or other designated components are tested during n Surveillance Frequency Intervals, where n is the total number of systems, subsystems, channels, or other designated components in the associated function.
THERMAL POWER THERMAL POWER shall be the total reactor core heat transfer rate to the reactor coolant.
TRIP ACTUATING DEVICE A TADOT shall consist of operating the trip actuating device OPERATIONAL TEST and verifying the OPERABILITY of required alarm, (TADOT) interlock, and trip functions. The TADOT shall include adjustment, as necessary, of the trip actuating device so that it actuates at the required setpoint within the required accuracy.
Vogtle Units 1 and 2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.0 USE AND APPLICATION 1.4 Frequency PURPOSE The purpose of this section is to define the proper use and application of Frequency requirements.
DESCRIPTION Each Surveillance Requirement (SR) has a specified Frequency in which the Surveillance must be met in order to meet the associated LCO. An understanding of the correct application of the specified Frequency is necessary for compliance with the SR.
The "specified Frequency" is referred to throughout this section and each of the Specifications of Section 3.0, Surveillance Requirement (SR)
Applicability. The "specified Frequency" consists of the requirements of the Frequency column of each SR as well as certain Notes in the Surveillance column that modify performance requirements.
Sometimes special situations dictate when the requirements of a Surveillance are to be met. They are "otherwise stated" conditions allowed by SR 3.0.1. They may be stated as clarifying Notes in the Surveillance, as part of the Surveillance, or both.
Situations where a Surveillance could be required (i.e , its Frequency could expire), but where it is not possible or not desired that lt be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. To avoid these conflicts. the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.
The use of "met" or "performed" in these instances conveys specific meanings. A Surveillance is "met" only when the acceptance criteria are satisfied. Known failure of the requirements of a Surveillance, even without a Surveillance specifically being "performed," constitutes a Surveillance not "met." "Performance" refers only to the requirement to specifically determine the ability to meet the acceptance criteria.
(continued)
Vogtle Units 1 and 2 1.4-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Frequency DESCRIPTION Some Surveillances contain notes that modify the Frequency of (continued) performance or the conditions during which the acceptance criteria must be satisfied. For these Surveillances, the MODE-entry restrictions of SR 3.0.4 may not apply. Such a Surveillance is not required to be performed prior to entering a MODE or other specified condition in the Applicability of the associated LCO if any of the following three conditions are satisfied:
- a. The Surveillance is not required to be met in the MODE or other specified condition to be entered; or
- b. The Surveillance is required to be met in the MODE or other specified condition to be entered, but has been performed within the specified Frequency (i.e., it is current) and is known not to be failed; or,
- c. The Surveillance is required to be met, but not performed, in the MODE or other specified condition to be entered, and is known not to be failed.
Examples 1.4-3, 1.4-4, 1.4-5, and 1.4-6 discuss these special situations.
EXAMPLES The following examples illustrate the various ways that Frequencies are specified. In these examples, the Applicability of the LCO (LCO not shown) is MODES 1, 2, and 3.
(continued)
Vogtle Units 1 and 2 1.4-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-1 SINGLE FREQUENCY (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY Perform CHANNEL CHECK. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Example 1.4-1 contains the type of SR most often encountered in the Technical Specifications (TS). The Frequency specifies an interval (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />) during which the associated Surveillance must be performed at least one time. Performance of the Surveillance initiates the subsequent interval. Although the Frequency is stated as 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, an extension of the time interval to 1.25 times the stated Frequency is allowed by SR 3.0.2 for operational flexibility. The measurement of this interval continues at all times, even when the SR is not required to be met per SR 3.0.1 (such as when the equipment is inoperable, a variable is outside specified limits, or the unit is outside the Applicability of the LCO). If the other specified condition in the Applicability of the LCO, and the performance of the Surveillance is not other wise modified (refer to Example 1.4-3), then SR 3.0.3 becomes applicable.
If the interval as specified by SR 3.0.2 is exceeded while the unit is not in a MODE or other specified condition in the Applicability of the LCO for which performance of the SR is required, then SR 3.0.4 becomes applicable, The Surveillance must be performed within the Frequency requirements of SR 3.0.2, as modified by SR 3.0.3, prior to entry into the MODE or other specified condition or the LCO is considered not met (in accordance with SR 3.0.1) and LCO 3.0.4 becomes applicable.
(continued)
Vogtle Units 1 and 2 1.4-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-2 MULTIPLE FREQUENCIES (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY Verify flow is within limits. Once within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
<::25% RTP 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter Example 1.4-2 has two Frequencies. The first is a one time performance Frequency, and the second is of the type shown in Example 1.4-1. The logical connector "AND" indicates that both Frequency requirements must be met. Each time reactor power is increased from a power level
< 25% RTP to~ 25% RTP, the Surveillance must be performed within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
The use of "once" indicates a single performance will satisfy the specified Frequency (assuming no other Frequencies are connected by "AND").
This type of Frequency does not qualify for the extension allowed by SR 3.0.2. "Thereafter" indicates future performances must be established per SR 3.0.2, but only after a specified condition is first met (i.e., the "once" performance in this example). If reactor power decreases to
< 25% RTP, the measurement of both intervals stops. New intervals start upon reactor power reaching 25% RTP.
(continued)
Vogtle Units 1 and 2 1.4-4 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-3 FREQUENCY BASED ON A SPECIFIED CONDITION (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY
NOTE Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
~ 25% RTP.
Perform channel adjustment. 7 days The interval continues, whether or not the unit operation is< 25% RTP between performances.
As the Note modifies the required performance of the Surveillance, it is construed to be part of the "specified Frequency." Should the 7 day interval be exceeded while operation is< 25% RTP, this Note allows 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after power reaches ~ 25% RTP to perform the Surveillance.
The Surveillance is still considered to be performed within the "specified Frequency." Therefore, if the Surveillance were not performed within the 7 day (plus the extension allowed by SR 3.0.2) interval, but operation was
< 25% RTP, it would not constitute a failure of the SR or failure to meet the LCO. Also, no violation of SR 3.0.4 occurs when changing MODES, even with the 7 day Frequency not met, provided operation does not exceed 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> with power ~ 25% RTP.
Once the unit reaches 25% RTP, 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> would be allowed for completing the Surveillance. If the Surveillance were not performed within this 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval, there would then be a failure to perform a Surveillance within the specified Frequency and the provisions of SR 3.0.3 would apply.
(continued)
Vogtle Units 1 and 2 1.4-5 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
I
Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-4 (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY
NOTE Only required to be met in MODE 1.
Verify leakage rates are within limits. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Example 1.4-4 specifies that the requirements of this Surveillance do not have to be met until the unit is in MODE 1. The interval measurement for the Frequency of this Surveillance continues at all times, as described in Example 1.4-1. However, the Note constitutes an "otherwise stated" exception to the Applicability of this Surveillance. Therefore, if the Surveillance were not performed within the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> interval (plus the extension allowed by SR 3.0.2), but the unit was not in MODE 1, there would be no failure of the SR nor failure to meet the LCO. Therefore, no violation of SR 3.0.4 occurs when changing MODES, even with the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency exceeded, provided the MODE change was not made into MODE 1. Prior to entering MODE 1 (assuming again that the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency were not met), SR 3.0.4 would require satisfying the SR.
. (continued)
Vogtle Units 1 and 2 1.4-6 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Frequency EXAMPLES EXAMPLE 1.4-5 (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY NOTE--------
Only required to be performed in MODE 1.
Perform complete cycle of the valve, ?days The interval continues, whether or not the unit operation is in MODE 1,2, or 3 {the assigned Applicability of the associated LCO) between performances.
As the Note modifies the required performance of the Surveillance, the Note is construed to be part of the "specified Frequency." Should the 7 day interval be exceeded while operation is not in MODE 1, this Note allows entry into and operation in MODES 2 and 3 to perform the Surveillance. The Surveillance is still considered to be performed within the "specified Frequency" if completed prior to entering MODE 1.
Therefore, if the Surveillance were not performed within the 7 day (plus the extension allowed by SR 3.0.2) interval, but operation was not in MODE 1, It would not constitute a failure of the SR or failure to meet the LCO. Also, no violation of SR 3.0.4 occurs when changing MODES, even with the 7 day Frequency not met, provided operation does not result in entry into MODE 1.
Once the unit reaches MODE 1, the requirement for the Surveillance to be performed within its specified Frequency applies and would require that the Surveillance had been performed. If the Survelllance were not performed prior to entering MODE 1, there would then be a failure to perform a Surveillance within the specified Frequency, and the provisions of SR 3.0.3 would apply.
(continued)
Vogtle Units 1 and 2 1.4-7 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Frequency 1.4 1.4 Freguency EXAMPLES EXAMPLE 1.4-6 (continued)
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY
NOTE-Not required to be met in MODE 3.
Verify parameter is within limits. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Example 1.4-6 specifies that the requirements of this Surveillance do not have to be met until the unit is in MODE 3 (the assumed Applicability of the associated LCO is MODES 1, 2, and 3). The interval measurement for the Frequency of this Surveillance continues at al! times, as described in Example 1.4-1. However, the Note constitutes an "otherwise stated" exception to the Applicability of this Surveillance. Therefore, if the Surveillance were not performed within the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> interval (plus the extension allowed by SR 3.0.2), and the unit was in MODE 3, there would be no failure of the SR nor failure to meet the LCO. Therefore, no violation of SR 3.0.4 occurs when changing MODES to enter MODE 3, even with the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency exceeded, provided the MODE change does not result in entry into MODE 2. Prior to entering MODE 2 (assuming again that the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency were not met), SR 3.0.4 would require satisfying the SR.
Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 1.4-8 Amendment No. 161 (Unit 2)
Core Reactivity 3.1.2 3.1 REACTIVITY CONTROL SYSTEMS 3.1.2 Core Reactivity LCO 3.1.2 The measured core reactivity shall be within +/- 1% .:.\k/k of predicted values.
APPLICABILITY: MODES 1 and 2.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Measured core reactivity A.1 Reevaluate core design 7days I not within limit. and safety analysis, and determine that the reactor core is acceptable for continued operation.
AND A.2 Establish appropriate 7 days I operating restrictions and I SRs.
B. Required Action and 8.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met.
Vogtle Units 1 and 2 3.1.2-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Rod Group Alignment Limits 3.1.4 ACTtONS CONDITION REQUIRED ACTION COMPLETION TIME Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.1.4-2 Amendment No. 161 (Unit 2)
Rod Group Alignment Limits 3.1.4 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
- c. Required Action and c. 1 Be in MODE 3 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition 8 not met.
D. More than one rod not D.1.1 Verify SOM is ~ the limit 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> within alignment limit. specified in the COLR.
OR D.1.2 Initiate boration to restore 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> required SOM to within limit.
AND D.2 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.4.1 Verify individual rod positions within alignment In accordance with limit. the Surveillance Frequency Control Program (continued)
Vogtle Units 1 and 2 3.1.4-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Control Bank Insertion Limits 3.1.6 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3.1.6.2 Verify each control bank insertion is within the In accordance with limits specified in the COLR. the Surveillance Frequency Control Program SR 3.1.6.3 Verify sequence and overlap limits specified in the Jn accordance with COLR are met for control banks not fully the Surveillance withdrawn from the core. Frequency Control Program Vogtle Units 1 and 2 3.1.6-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Rod Position Indication 3.1.7 3.1 REACTIVITY CONTROL SYSTEMS 3.1.7 Rod Position Indication LCO 3.1. 7 The Digital Rod Position Indication (DRPI) System and the Demand Position Indication System shall be OPERABLE.
APPLICABILITY: MODES 1 and 2.
ACTIONS
NOTE Separate Condition entry is allowed for each inoperable rod position indicator and each inoperable demand position indicator.
CONDITION REQUIRED ACTION COMPLETION Tl ME A. One DRPI per group A.1 Verify the position of the Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> inoperable for one or rods with inoperable more groups. position indicators indirectly by using movable incore detectors.
OR A.2 Reduce THERMAL 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> POWER to .:::; 50% RTP.
(continued)
Vogtle Units 1 and 2 3.1.7-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Rod Position Indication 3.1.7 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME B. More than one DRPI B.1 Place the control rods Immediately group inoperable. under manual control.
AND 8.2 Monitor and Record RCS Once per 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Tavg AND 8.3 Verify the position of the Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> rods with inoperable position indicators indirectly by using the movable incore detectors.
AND B.4 Restore inoperable 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> position indicators to OPERABLE status such that a maximum of one DRPJ per group is inoperable.
- c. One or more rods with C.1 Verify the position of the 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> inoperable DRPls have rods with inoperable been moved in excess DRPls indirectly by using of 24 steps in one movable incore detectors.
direction since the last determination of the OR rod's position.
C.2 Reduce THERMAL 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> POWER to ~ 50% RTP.
(continued)
Vogtle Units 1 and 2 3.1.7-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Rod Position Indication 3.1.7 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. One demand position D.1.1 Verify by administrative Once per B hours indicator per bank means all DRPls for the inoperable for one or affected banks are more banks. OPERABLE.
AND D.1.2 Verify the most withdrawn Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> rod and the least withdrawn rod of the affected banks are s 12 steps apart.
OR D.2 Reduce THERMAL 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> POWER to s 50% RTP.
E. Required Action and E.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.7.1 Verify each DRPI agrees within 12 steps of the In accordance with group demand position for the full indicated range the Surveillance of rod travel. Frequency Control Program Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.1.7-3 Amendment No. 161 (Unit 2)
Fa(Z) 3.2.1 3.2 POWER DISTRIBUTION LIMITS 3.2.1 Heat Flux Hot Channel Factor (Fa(Z)) (Fa Methodology)
LCO 3.2.1 Fa(Z) shall be within the steady state and transient limits specified in the COLR.
APPLICABILITY: MODE 1.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. F0 (Z) not within steady A.1 Reduce THERMAL 15 minutes state limit. POWER ~ 1% RTP for each 1% F0 (Z) exceeds steady state limit.
AND A.2 Reduce Power Range 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Neutron Flux - High trip setpoints ~ 1% for each 1% Fa(Z) exceeds steady state limit.
AND A.3 Reduce Overpower !lT 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> trip setpoints ~ 1% for each 1% F0 (Z) exceeds steady state limit.
ANO A.4 Perform SR 3.2.1.1. Prior to increasing THERMAL POWER above the limit of Required Action A. 1 (continued)
Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.2.1-1 Amendment No. 161 (Unit 2)
F~H 3.2.2 3.2 POWER DISTRIBUTION LIMITS 3.2.2 Nuclear Enthalpy Rise Hot Channel Factor (F~H)
LCO 3.2.2 F~H shall be within the limits specified in the COLR.
APPLICABILITY: MODE 1.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. ----NOTE---- A.1.1 Restore F~H to within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Required Actions A.2 limits.
and A.3 must be completed whenever OR Condition A is entered.
A.1.2.1 Reduce THERMAL 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> POWER to < 50% RTP.
F:H not within limits.
AND A.1.2.2 Reduce Power Range 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Neutron Flux-High trip set points to :s; 55% RTP.
AND A.2 Perform SR 3.2.2.1. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> AND (continued)
Vogtle Units 1 and 2 3.2.2-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
AFD (RAOC Methodology) 3.2.3 3.2 POWER DISTRIBUTION LIMITS 3.2.3 AXIAL FLUX DIFFERENCE (AFD) (Relaxed Axial Offset Control (RAOC) Methodology)
LCO 3.2.3 The AFD shall be maintained within the limits specified in the COLR
- --NOTE The AFD shall be considered outside limits when two or more OPERABLE excore channels indicate AFD to be outside limits.
APPLICABILITY: MODE 1 with THERMAL POWER ~ 50% RTP.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. AFD not within limits. A.1 Reduce THERMAL 30 minutes POWER to < 50% RTP.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.2.3.1 Verify AFD within limits for each OPERABLE In accordance with excore channel. the Surveillance Frequency Control Program Vogtle Units 1 and 2 3.2.3-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
QPTR 3.2.4 3.2 POWER DISTRIBUTION LIMITS 3.2.4 QUADRANT POWER TILT RA TIO (QPTR)
LCO 3.2.4 The QPTR shall be:::;; 1.02.
APPLICABILITY: MODE 1 with THERMAL POWER > 50% RTP.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. NOTE-*-- A.1 Limit THERMAL POWER 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Required Action A.6 to ~ 3% below RTP for must be completed each 1 % of QPTR > 1.00.
whenever Required Action A.5 is AND implemented.
A.2.1 Perform SR 3.2.4.1. Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> QPTR not within limit. AND A.2.2 Limit THERMAL POWER --NOTE---
to ~ 3% below RTP for For performances of each 1% QPTR > 1.00. Required Action A.2.2 the Completion Time is measured from the completion of SR 3.2.4.1.
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> AND A.3 Perform SR 3.2.1.1, SR Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after 3.2.1.2, and SR 3.2.2.1. achieving equilibrium conditions with THERMAL POWER limited by Required Actions A.1 and A.2.2 (continued)
Vogtle Units 1 and 2 3.2.4-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
QPTR 3.2.4 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. (continued) A.6 NOTE----
Perform Required Action A.6 only after Required Action A.5 is completed.
Perform SR 3.2.1.1, SR ---NOTE--
3.2.1.2, and SR 3.2.2.1. Only one of the following Completion Times, whichever becomes applicable first, must be met.
Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after reaching RTP OR Within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after increasing THERMAL POWER above the limit of Required Action A.1 and A.2.2
- 8. Required Action and 8.1 Reduce THERMAL 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> associated Completion POWER to s 50% RTP.
Time not met.
Vogtle Units 1 and 2 3.2.4-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
QPTR 3.2.4 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.2.4.1 ------ NOTE ---
With one power range channel inoperable, the remaining three power range channels can be used for calculating OPTR.
Verify QPTR is within limit by calculation. In accordance with the Surveillance Frequency Control Program SR 3.2.4.2 -NOTE-----
Only required to be performed if input to OPTR from one or more Power Range Neutron Flux channels is inoperable with THERMAL POWER
- 75%RTP.
Confirm that the normalized symmetric power Once within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> distribution is consistent with OPTR.
In accordance with the Surveillance Frequency Control Program Vogtle Units 1 and 2 3.2.4-4 Amendment No. 180 (Unit 1) )
Amendment No. 161 (Unit 2)
Remote Shutdown System 3.3.4 3.3 INSTRUMENTATION 3.3.4 Remote Shutdown System LCO 3.3.4 The Remote Shutdown System Functions shall be OPERABLE.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS
--NOTE-----------*-----
Separate Condition entry is allowed for each Function.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more required A.1 Restore required Function 30 days Functions inoperable to OPERABLE status.
B. Required Action and 8.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND 8.2 Be in MODE4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Vogtle Units 1 and 2 3.3.4-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
RCS Minimum Temperature for Criticality 3.4.2 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.2 RCS Minimum Temperature for Criticality LCO 3.4.2 Each RCS loop average temperature (Tevg) shall be 2: 551°F.
APPLICABILITY: MODE 1, MODE 2 with kart 2: 1.0.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Tavg in one or more RCS A.1 Be in MODE 3. 30 minutes loops not within limit.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.2.1 Verify RCS Tavg in each loop 2: 551<>F. In accordance with the Surveillance Frequency Control Program Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.4.2-1 Amendment No. 161 (Unit 2)
RCS Loops - MODE 3 3.4.5 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME C. One required RCS loop C.1 Restore required RCS 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> not in operation with loop to operation.
Rod Control System capable of rod OR withdrawal.
C.2 Place the Rod Control 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> System in a condition incapable of rod withdrawal.
D. Two required RCS loops D.1 Place the Rod Control Immediately inoperable. System in a condition incapable of rod OR withdrawal.
No RCS loop in AND operation.
0.2 Suspend all operations Immediately involving a reduction of RCS boron concentration.
AND D.3 Initiate action to restore Immediately one RCS loop to OPERABLE status and operation.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.5.1 Verify required RCS loops are in operation. In accordance with the Surveillance Frequency Control Program (continued)
Vogtle Units 1 and 2 3.4.5-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Pressurizer 3.4.9 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.9 Pressurizer LCO 3.4.9 The pressurizer shall be OPERABLE with:
- a. Pressurizer water level ~ 92%; and
- b. Two groups of pressurizer heaters OPERABLE with the capacity of each group ~ 150 kW and capable of being powered from an emergency power supply.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Pressurizer water level A.1 Bein MODE 3 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> not within limit.
AND A.2 Fully insert all rods. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> AND A.3 Place Rod Control 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> System in a condition incapable of rod withdrawal.
AND A.4 Be in MODE4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
- 8. One required group of 8.1 Restore required group of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> pressurizer heaters pressurizer heaters to inoperable. OPERABLE status.
(continued)
Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.4.9-1 Amendment No. 161 (Unit 2)
Pressurizer 3.4.9 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
- c. Required Action and C.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition B not AND met.
C.2 Be in MODE4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.9.1 Verify pressurizer water level is ::; 92%. In accordance with the Surveillance Frequency Control Program SR 3.4.9.2 Verify capacity of each required group of In accordance with pressurizer heaters is t;: 150 kW. the Surveillance Frequency Control Program Vogtle Units 1 and 2 3.4.9-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Pressurizer PORVs 3.4.11 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.11 Pressurizer Power Operated Relief Valves (PORVs)
LCO 3.4.11 Each PORV and associated block valve shall be OPERABLE.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS
-NOTE- ------
Separate Condition entry is allowed for each PORV and each block valve.
CONDITION REQUIRED ACTION COMPLETION TIME A. One or more PORVs A.1 Close and maintain power 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable and capable to associated block valve.
of being manually cycled.
- 8. One PORV inoperable B.1 Close associated block 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and not capable of being valve.
manually cycled.
AND 8.2 Remove power from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> associated block valve.
AND 8.3 Restore PORV to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OPERABLE status.
(continued)
Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.4.11-1 Amendment No. 161 (Unit 2)
Pressurizer PORVs 3.4.11 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
- c. One block valve c. 1 Place associated PORV 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inoperable. in manual control.
ANO C.2 Restore block valve to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OPERABLE status.
- 0. Required Action and D.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition A, B, AND or C not met.
0.2 Be in MODE4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> E. Two PORVs inoperable E.1 Close associated block 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and not capable of being valves.
manually cycled.
AND E.2 Remove power from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> associated block valves.
AND E.3 Bein MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> AND E.4 Bein MODE 4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> F. Two block valves F.1 Restore one block valve 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> inoperable. to OPERABLE status.
(continued) 3.4.11-2 Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 Amendment No. 161 (Unit 2.)
Pressurizer PORVs 3.4.11 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME G. Required Action and G.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition F not AND met.
G.2 Be in MODE4. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.11.1 -- -NOTES----------
- 1. Not required to be performed with block valve closed in accordance with the Required Actions of this LCO.
- 2. Only required to be performed in MODES 1 and 2.
Perform a complete cycle of each block valve In accordance with the Surveillance Frequency Control Program SR 3.4.11.2 -NOTE-*--*---
Only required to be performed in MODES 1 and 2.
Perform a complete cycle of each PORV. In accordance with the Surveillance Frequency Control Program Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.4.11-3 Amendment No. 161 (Unit 2)
COPS 3.4.12 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.12.1 Verify both safety injection pumps are incapable In accordance with the of injecting into the RCS. Surveillance Frequency Control Program SR 3.4.12.2 Verify each accumulator is isolated. In accordance with the Surveillance Frequency Control Program SR 3.4.12.3 Verify RHR suction valves are open for each In accordance with the required RHR suction relief valve. Surveillance Frequency Control Program SR 3.4.12.4 ---*-----*-NOTE ------
Only required to be met when complying with LCO 3.4.12.b.
Verify RCS vent size within specified limits In accordance with the Surveillance Frequency Control Program (continued)
Vogtte Units 1 and 2 3.4.12-4 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
RCS Specific Activity 3.4.16 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.16 RCS Specific Activity LCO 3.4.16 The specific activity of the reactor coolant shall be within limits.
APPLICABILITY: MODES 1 and 2, MODE 3 with RCS average temperature (Tavg) ~ 500°F.
ACTIONS
- --NOTE LCO 3.0.4c is applicable.
CONDITION REQUIRED ACTION COMPLETION TIME A. DOSE EQUIVALENT A.1 Verify DOSE Once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 1-131>1.0µCi/gm. EQUIVALENT 1-131 within the acceptable region of Figure 3.4.16-1.
AND A.2 Restore DOSE 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> EQUIVALENT 1-131 to within limit.
- 8. Gross specific activity of 8.1 Be in MODE 3 with 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> the reactor coolant not Tavg < 500°F.
within limit.
(continued)
Vogtle Units 1 and 2 3.4.16-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Containment Isolation Valves 3.6.3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. Required Action and 0.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND D.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.3.1 Verify each 24 inch purge valve is sealed closed, In accordance with except for one purge valve in a penetration flow the Surveillance path while in Condition C of this LCO. Frequency Control Program SR 3.6.3.2 Verify each 14 inch purge valve is closed, except In accordance with when the associated penetration(s) is (are) the Surveillance permitted to be open for purge or venting Frequency Control operations and purge system surveillance and Program maintenance testing under administrative control.
SR 3.6.3.3 --~-----~--~-NOTE--~----------
Valves and blind flanges in high radiation areas may be verified by use of administrative controls.
~------*-------
Verify each containment isolation manual valve In accordance with and blind flange that is located outside the Surveillance containment and not locked, sealed, or otherwise Frequency Control secured and required to be closed during accident Program conditions is closed, except for containment isolation valves that are open under administrative controls.
(continued)
Vogtle Units 1 and 2 3.6.3-4 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Containment Isolation Valves 3.6.3 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3.6.3.4 ----*---*---NOTES---------*
- 1. Valves and blind flanges in high radiation areas may be verified by use of administrative means.
- 2. The fuel transfer tube blind flange is only required to be verified closed once after refueling prior to entering MODE 4 from MODES.
Verify each containment isolation manual valve Prior to entering and blind flange that is located inside containment MODE 4 from and not locked, sealed, or otherwise secured and MODE 5 if not required to be closed during accident conditions is performed within the closed, except for containment isolation valves previous 92 days that are open under administrative controls.
SR 3.6.3.5 Verify the isolation time of each automatic power In accordance operated containment isolation valve is within with the lnservice limits. Testing Program SR 3.6.3.6 Perform leakage rate testing for containment In accordance with purge valves with resilient seals. the Surveillance Frequency Control Program SR 3.6.3.7 Verify each automatic containment isolation valve In accordance with that is not Jocked, sealed, or otherwise secured in the Surveillance position, actuates to the isolation position on an Frequency Control actual or simulated actuation signal. Program Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.6.3-5 Amendment No. 161 (Unit 2)
AFWSystem 3.7.5
- 3. 7 PLANT SYSTEMS 3.7.5 Auxiliary Feedwater (AFW) System LCO 3.7.5 Three AFWtrains shall be OPERABLE.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS
NOTE LCO 3.0.4b is not applicable.
CONDITION REQUIRED ACTION COMPLETION TIME A. One steam supply to A.1 Restore affected 7 days turbine driven AFW equipment to OPERABLE pump inoperable. status.
---NOTE----
Only applicable if MODE 2 has not been entered following refueling.
One turbine driven AFW pump inoperable in MODE 3 following refueling.
B. One AFW train 8.1 Restore AFW train to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> inoperable for reasons OPERABLE status.
other than Condition A.
(continued)
Vogtle Units 1 and 2 3.7.5-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
AFWSystem 3.7.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.5.1 NOTE-------
AFW train(s) may be considered OPERABLE during alignment and operation for steam generator level control, if it is capable of being manually realigned to the AFW mode of operation.
Verify each AFW manual, power operated, and In accordance with automatic valve in each water flow path, and in the Surveillance both steam supply flow paths to the steam turbine Frequency Control driven pump, that is not locked, sealed, or Program otherwise secured in position, is in the correct position.
SR 3.7.5.2 --------NOTE------
Not required to be performed for the turbine driven AFW pump until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after~ 900 psig in the steam generator.
Verify the developed head of each AFW pump at In accordance with the flow test point is greater than or equal to the the Surveillance required developed head. Frequency Control Program (continued)
Amendment No. 180 (Unit 1)
Vogtle Units 1 and 2 3.7.5-3 Amendment No. 161 (Unit 2)
AFWSystem 3.7.5 SURVEILLANCE REQUIREMENTS continued SURVEILLANCE FREQUENCY SR 3.7.5.3 -------NOTE AFW train(s) may be considered OPERABLE during alignment and operation for steam generator level control, if it is capable of being manually realigned to the AFW mode of operation.
Verify each AFW automatic valve that is not In accordance with locked, sealed, or otherwlse secured in position the Surveillance actuates to the correct position on an actual or Frequency Control simulated actuation signal. Program SR 3.7.5.4 -NOTES
- 1. Not required to be performed for the turbine driven AFW pump until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after ~ 900 psig in the steam generator.
- 2. AFW train(s) may be considered OPERABLE during alignment and operation for steam generator level control, if it is capable of being manually realigned to the AFW mode of operation.
Verify each AFW pump starts automatically on an In accordance with actual or simulated actuation signal. the Surveillance Frequency Control Program (continued)
Vogtle Units 1 and 2 3.7.5-4 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
AFWSystem 3.7.5 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3.7.5.5 Verify that each AFW pumphouse ESF supply fan In accordance with starts and associated dampers actuate on a the Surveillance simulated or actual actuation signal. Frequency Control Program SR 3.7.5.6 Verify that the ESF outside air intake and exhaust In accordance with dampers for the turbine-driven AFW pump the Surveillance actuate on a simulated or actual actuation signal. Frequency Control Program Vogtle Units 1 and 2 3.7.5-5 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Diesel Fuel Oil, Lube Oil, Starting Air, and Ventilation 3.8.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.3.1 Verify each fuel oil storage tank contains In accordance with 2: 68,000 gal of fuel. the Surveillance Frequency Control Program SR 3.8.3.2 Verify lube oil inventory is 2: 336 gal. In accordance with the Surveillance Frequency Control Program SR 3.8.3.3 Verify fuel oil properties of new and stored fuel oil In accordance with are tested in accordance with, and maintained the Diesel Fuel Oil within the limits of, the Diesel Fuel OH Testing Testing Program Program.
SR 3.8.3.4 Verify each DG has one air start receiver with a In accordance with pressure~ 210 psig. the Surveillance Frequency Control Program SR 3.8.3.5 Check for and remove accumulated water from In accordance with each fuel oil storage tank. the Surveillance Frequency Control Program SR 3.8.3.6 Verify each DG ventilation supply fan starts and In accordance with the necessary dampers actuate on a simulated or the Surveillance actual actuation signal. Frequency Control Program Vogtle Units 1 and 2 3.8.3-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Boron Concentration 3.9.1 3.9 REFUELING OPERATIONS 3.9.1 Boron Concentration LCO 3.9.1 Boron concentrations of the Reactor Coolant System, the refueling canar, and the refueling cavity shall be maintained within the limit specified in the COLR.
APPLICABILITY: MODE 6.
NOTE ---
Only applicable to the refueling canal and refueling cavity when connected to the RCS.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Boron concentration not A.1 Suspend CORE Immediately within limit. ALTERATIONS.
AND A.2 Suspend positive Immediately reactivity additions.
AND A.3 Initiate action to restore Immediately boron concentration to within limit.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.9.1.1 Verify boron concentration is within the limit In accordance with specified in the COLR. the Surveillance Frequency Control Program Vogtle Units 1 and 2 3.9.1-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Containment Penetrations 3.9.4 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.9.4.1 Verify each required containment penetration is Jn accordance with the in the required status. Surveillance Frequency Control Program SR 3.9.4.2 ----~*---~-NOTE~~~~*-
Not required to be met for containment purge and exhaust valve(s) in penetrations closed to comply with LCO 3.9.4.c.1.
Verify at least two containment ventilation valves In accordance with the in each open containment ventilation penetration Surveillance providing direct access from the containment Frequency Control atmosphere to the outside atmosphere are Program capable of being closed from the control room.
SR 3.9.4.3 ------~--~~-NOTE--~--~-----
Only required for an open equipment hatch.
Verify the capability to install the equipment In accordance with the hatch. Surveillance Frequency Control Program Vogtle Units 1 and 2 3.9.4-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
RHR and Coolant Circulation - Low Water Level 3.9.6 3.9 REFUELING OPERATIONS 3.9.6 Residual Heat Removal (RHR) and Coolant Circulation - Low Water Level LCO 3.9.6 Two RHR loops shall be OPERABLE, and one RHR loop shall be in operation.
NOTES---
- 1. One RHR loop may be inoperable for s 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for surveillance testing provided that the other RHR loop is OPERABLE and in operation.
- 2. All RHR pumps may be de-energized for s 15 minutes when switching from one train to another provided:
- a. The core outlet temperature is maintained > 1Odegrees F below saturation temperature.
- b. No operations are permitted that would cause a reduction of the Reactor Coolant System (RCS) boron concentration; and
- c. No draining operations to further reduce RCS water volume are permitted.
APPLICABILITY: MODE 6 with the water level < 23 ft above the top of reactor vessel flange.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Less than the required A.1 Initiate action to restore Immediately number of RHR loops required RHR loops to OPERABLE. OPERABLE status.
OR A.2 Initiate action to Immediately establish>- 23 ft of water above the top of reactor vessel flange.
(continued)
Vogtle Units 1 and 2 3.9.6-1 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
RHR and Coolant Circulation - Low Water Level 3.9.6 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME
- 8. No RHR loop in operation. 8.1 Suspend operations Immediately involving a reduction in reactor coolant boron concentration.
8.2 Initiate action to restore Immediately one RHR loop to operation.
AND 8.3 Close all containment 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> penetrations providing direct access from containment atmosphere to outside atmosphere.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.9.6.1 Verify one RHR loop is in operation and circulating In accordance with reactor coolant at a flow rate of~ 3000 gpm. the Surveillance Frequency Control Program SR 3.9.6.2 ------NOTE -----
An operating RHR loop will meet this requirement for the RHR loop running unless the RHR loop is in a low flow system operation.
Verify RHR loop locations susceptible to gas In accordance with accumulation are sufficiently filled with water. the Surveillance Frequency Control Program Vogtle Units 1 and 2 3.9.6-2 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.4 Radioactive Effluent Controls Program This program conforms to 10 CFR 50 .36a for the control of radioactive effluents and for maintaining the doses to members of the public from radioactive effluents as low as reasonably achievable. The program shall be contained in the ODCM, shall be implemented by procedures, and shall include remedial actions to be taken whenever the program limits are exceeded. The program shall include the following elements:
- a. Limitations on the functional capability of radioactive liquid and gaseous monitoring instrumentation including surveillance tests and setpoint determination in accordance with the methodology in the ODCM;
- b. Limitations on the concentrations of radioactive material released in liquid effluents to unrestricted areas, conforming to ten times the concentrations stated in 10 CFR 20, Appendix B (to paragraphs 20.1001-20.2401),
Table 2, Column 2;
- c. Monitoring, sampling, and analysis of radioactive liquid and gaseous effluents in accordance with 10 CFR 20 .1302 and with the methodology and parameters in the ODCM;
- d. Limitations on the annual and quarterly doses or dose commitment to a member of the public from radioactive materials in liquid effluents released from each unit to unrestricted areas, conforming to 10 CFR 50, Appendix I;
- e. Determination of cumulative dose contributions from radioactive effluents for the current calendar quarter and current calendar year in accordance with the methodology and parameters in the ODCM at least every 31 days.
Determination of projected dose contributions from radioactive effluents in accordance with the methodology in the ODCM at least every 31 days.
t Limitations on the functional capability and use of the liquid and gaseous effluent treatment systems to ensure that (continued)
Vogtle Units 1 and 2 5.5-3 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.15 Safety Function Determination Program CSFDP)
This program ensures loss of safety function is detected and appropriate actions taken. Upon entry into LCO 3.0.6, an evaluation shall be made to determine if loss of safety function exists. Additionally, other appropriate actions may be taken as a result of the support system inoperability and corresponding exception to entering supported system Condition and Required Actions. This program implements the requirements of LCO 3.0.6. The SFDP shall contain the following:
- a. Provisions for cross train checks to ensure a loss of the capability to perform the safety function assumed in the accident analysis does not go undetected;
- b. Provisions for ensuring the plant is maintained in a safe condition if a loss of function condition exists;
- c. Provisions to ensure that an inoperable supported system's Completion Time is not inappropriately extended as a result of multiple support system inoperabilities; and
- d. Other appropriate limitations and remedial or compensatory actions.
A loss of safety function exists when, assuming no concurrent single failure, no concurrent loss of offsite power or no concurrent loss of onsite diesel generator(s), a safety function assumed in the accident analysis cannot be performed. For the purpose of this program, a loss of safety function may exist when a support system is inoperable, and:
- a. A required system redundant to the system(s) supported by the inoperable support system is also inoperable; or
- b. A required system redundant to the system(s) in turn supported by the inoperable supported system is also inoperable; or
- c. A required system redundant to the support system(s) for the supported systems (a) and (b) above is also inoperable.
The SFDP identifies where a loss of safety function exists. If a Joss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered. When a loss of safety function is caused by the inoperability of a single Technical Specification support system, the appropriate Conditions and Required Actions to enter are those of the support system.
(continued)
Vogtle Units 1 and 2 5.5-15 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.17 Containment Leakage Rate Testing Program (continued)
- 4. The visual examination of the steel liner plate inside containment intended to fulfill the requirements of 10 CFR 50, Appendix J, Option B, will be performed in accordance with the requirements of and frequency specified by the ASME Section XI code, Subsection IWE, except where relief has been authorized by the NRC.
- 5. A one time exception to NEI 94-01, Rev. 0, "Industry Guidelines for Implementing Performance-Based Option of 10 CFR 50, Appendix J":
Section 9.2.3: The next Type A test, after the March 2002 test for Unit 1 and the March 1995 test for Unit 2, shall be performed within 15 years.
The peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa. is 37 psig.
The maximum allowable containment leakage rate, La. at Pa. is 0.2% of primary containment air weight per day.
Leakage rate acceptance criteria are:
- a. Containment overall leakage rate acceptance criteria are :s; 1.0 La. During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are*::; 0.60 La for the combined Type 8 and Type C tests, ands; 0.75 La for Type A tests;
- b. Air lock testing acceptance criteria are:
- 1) Overall air lock leakage rate is s 0.05 La when tested at~ Pa.
- 2) For each door, the leakage rate is~ 0.01 La when pressurized to 2:: Pa.
The provisions of SR 3.0.2 do not apply to the test frequencies specified in the Containment Leakage Rate Testing Program.
The provisions of SR 3.0.3 are applicable to the Containment Leakage Rate Testing Program.
(continued)
Vogtle Units 1 and 2 5.5-17 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.18 Configuration Risk Management Program The Configuration Risk Management Program (CRMP) provides a proceduralized risk-informed assessment to manage the risk associated with equipment inoperability. The program applies to technical specification structures, systems. or components for which a risk-informed allowed outage time has been granted. The program shall include the following elements:
- a. Provisions for the control and implementation of a Level 1 at power internal events PRA-informed methodology. The assessment shall be capable of evaluating the applicable plant configuration.
- b. Provisions for performing an assessment prior to entering the LCO Condition for preplanned activities.
- c. Provisions for performing an assessment after entering the LCO Condition for unplanned entry into the LCO Condition.
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues and external events, qualitatively or quantitatively.
5.5.19 Battery Monitoring and Maintenance Program This program provides for restoration and maintenance, based on the recommendations of IEEE Standard 450-1995, "IEEE Recommended Practice for Maintenance, Testing and Replacement of Vented Lead-Acid Batteries for Stationary Applications," of the following:
a Actions to restore battery cells with float voltage < 2.13 V, and
- b. Actions to equalize and test battery cells that had been discovered with electrolyte level below the top of the plates.
(continued)
Vogtle Units 1 and 2 5.5-18 Amendment No. 180 (Unit 1)
Amendment No. 161 (Unit 2)
AMENDMENT NO. 180 TO RENEWED FACILITY OPERATING LICENSE NPF-68 AMENDMENT NO. 161 TO RENEWED FACILITY OPERATING LICENSE NPF-81 VOGTLE ELECTRIC GENERATING PLANT. UNITS 1 AND 2 SOUTHERN NUCLEAR OPERATING COMPANY. INC.
1.0 INTRODUCTION
By letter dated July 18, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14203A124), as supplemented by letters dated February 27, 2015, and May 2, 2016 (ADAMS Accession Nos. ML15058A891 and ML16123A134, respectively), Southern Nuclear Operating Company, Inc., et al (SNC, the licensee),
submitted a license amendment request (LAR) for changes to the Technical Specifications (TSs) for the Vogtle Electric Generating Plant, Units 1 and 2 (VEGP). The LAR proposed to revise the VEGP TSs to incorporate 23 generic changes that have been made to NUREG-1431, "Standard Technical Specifications - Westinghouse Plants" (STS) (WOG),
since VEGP adopted improved TSs based on WOG STS, Revision 1, issued in April 1995.
The changes, which are identified by Technical Specification Task Force (TSTF) Traveler numbers, are:
- 1. TSTF-2-A, Revision 1, "Relocate the 1O year sediment cleaning of the fuel oil storage tank to licensee control"
- 2. TSTF-27-A, Revision 3, "Revise SR [Surveillance Requirement] Frequency for Minimum Temperature for Criticality"
- 3. TSTF-28-A, Revision O, "Delete unnecessary Action to measure gross specific activity"
that are not locked, sealed or otherwise secured"
- 5. TSTF-46-A, Revision 1, "Clarify the CIV surveillance to apply only to automatic isolation valves"
- 6. TSTF-87-A, Revision 2, "Revise 'RTBs [Reactor Trip Breakers] open' and 'CROM
[Control Rod Drive Mechanisms] de-energized' Actions to 'incapable of rod withdrawal"
- 7. TSTF-95-A, Revision 0, "Revise completion time for reducing Power Range High trip setpoint from 8 to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />" Enclosure 3
- 8. TSTF-110-A, Revision 2, "Delete SR frequencies based on inoperable alarms"
- 9. TSTF-142-A, Revision 0, "Increase the Completion Time When the Core Reactivity Balance is Not Within Limit"
- 10. TSTF-234-A, Revision 1, "Add Action for More Than One [D]RPI [Digital Rod Position Indicator] Inoperable"
- 11. TSTF-245-A, Revision 1, "AFW [auxiliary feedwater] train inoperable when in service"
- 12. TSTF-247-A, Revision 0, "Provide separate condition entry for each PORV [Power Operated Relief Valve] and block valve"
- 13. TSTF-248-A, Revision 0, "Revise Shutdown Margin definition for stuck rod exception"
- 14. TSTF-266-A, Revision 3, "Eliminate the Remote Shutdown System Table of Instrumentation and Controls"
- 15. TSTF-272-A, Revision 1, "Refueling Boron Concentration Clarification"
- 16. TSTF-273-A, Revision 2, "Safety Function Determination Program Clarifications"
- 17. TSTF-284-A, Revision 3, "Add 'Met vs. Perform' to Specification 1.4, Frequency"
- 18. TSTF-308-A, Revision 1, "Determination of Cumulative and Projected Dose Contributions in RECP [Radioactive Effluent Controls Program]"
- 19. TSTF-312-A, Revision 1, "Administratively Control Containment Penetrations"
- 20. TSTF-314-A, Revision 0, "Require Static and Transient Fa Measurement"
- 21. TSTF-340-A, Revision 3, "Allow 7-Day Completion Time for a turbine-driven AFW pump inoperable"
- 22. TSTF-343-A, Revision 1, "Containment Structural Integrity"
- 23. TSTF-349-A, Revision 1, "Add Note to LCO 3.9.5 Allowing Shutdown Cooling Loops Removal from Operation" The U.S. Nuclear Regulatory Commission (NRC, Commission) decoupled Item No. 19 above from this review and will complete its review of TSTF-312-A by a separate amendment.
Therefore, these amendments only address the remaining 22 TSTFs.
The supplement dated February 27, 2015, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staff's original proposed no significant hazards consideration determination as published in the Federal Register on March 3, 2015 (80 FR 11480).
The licensee also included in the LAR its TS Bases changes for the proposed changes to the TSs. These changes were presented for information only because these changes are controlled through TS 5.5.14, "Technical Specification (TS) Bases Change Program." The NRC staff reviewed the changes to ascertain whether they were consistent with the changes in the TSTFs and were technically correct.
2.0 REGULATORY EVALUATION
Title 10 of the Code of Federal Regulations (10 CFR) Section 50.36 requires TSs for nuclear reactors to include items in the following categories: (1) Safety limits, limiting safety system settings, and limiting control settings; (2) Limiting conditions for operation [LCOs];
(3) Surveillance requirements [SRs]; (4) Design features; and (5) Administrative controls. The regulation does not specify the particular requirements to be included in a plant's TSs.
On July 22, 1993, the Commission published the "Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors" (58 FR 39132). This Final Policy Statement discussed criteria for determining which items must be included in the TS as LCOs.
These criteria were subsequently incorporated into 10 CFR 50.36 (60 FR 36953).
Specifically, 10 CFR 50.36(c)(2)(ii) requires that an LCO be established for each item meeting one or more of the following criteria:
Criterion 1: Installed instrumentation that is used to detect, and indicate in the control room, a significant abnormal degradation of the reactor coolant pressure boundary.
Criterion 2: A process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
Criterion 3: A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
Criterion 4: A structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety.
In adopting the Standard Technical Specifications (STS) or a TSTF traveler, licensees propose revisions to their licensed nuclear reactor facility TSs to: (1) incorporate revised NRC policy and guidance regarding the content and format of TSs, (2) clarify a specification's intent by revising ambiguous language and correcting editorial errors, and (3) enhance specifications to correct inadequacies.
In determining the acceptability of TS changes, the NRG staff considers the requirements of 10 CFR 50.36 using the guidance in the WOG STS and the associated Bases for the SLs and LCOs, and the references cited in the Bases. As discussed in the Final Policy Statement, the NRG staff reviews, on a case-by-case basis, whether enforceable regulatory controls (e.g.,
10 CFR 50.59) are needed for material moved to licensee-controlled documents, such as the updated safety analysis report, the Technical Requirements Manual, the TS Bases, the Quality Assurance Plan, etc. The NRG staff determines that plant-specific adoptions of STS format and content provide continued, adequate protection for the public health and safety when (1) the change is editorial, administrative, or provides clarification (i.e., no requirements are materially altered); (2) the change is more restrictive than the licensee's current requirement; or (3) the change is less restrictive than the licensee's current requirement, but nonetheless still affords adequate assurance of safety when judged against current regulatory standards and the facility's licensing basis.
The NRG staff used WOG STS, Revision 4, issued in April 2012, in its review of the TS changes proposed by VEGP. The NRG staff also referred to the TSTF travelers associated with the STS changes proposed for adoption by VEGP.
3.0 TECHNICAL EVALUATION
The NRC staff notes that per the application, the licensee's review of its plant-specific justifications and the approved traveler justifications for the proposed changes discussed below found no significant differences between the licensee's proposed changes and the approved TSTFs. The evaluation below discusses the differences that the licensee identified in its application.
3.1 TSTF-2-A, Revision 1, "Relocate the 10 Year Sediment Cleaning of the Fuel Oil Storage Tank to Licensee Control" The NRC approved this change to STS Revision 1 on July 16, 1998. This traveler modified STS 3.8.3, "Diesel Fuel Oil, Lube Oil, Starting Air, and Ventilation," by relocating SR 3.8.3.6 from the TSs to plant-controlled documents (e.g., documents controlled by 10 CFR 50.59). The SR currently requires sediment cleaning of the fuel oil storage tanks every 10 years as specified in Regulatory Guide (RG) 1.137, "Fuel-Oil Systems for Standby Diesel Generators." RG 1.137 is referenced in the VEGP Updated Final Safety Analysis Report (UFSAR) Sections 1.9 and 9.5.4.2 and in the VEGP TS 3.8.3 Bases.
The equivalent SR in the VEGP TS is numbered SR 3.8.3.7.
TS SR 3.8.3. 7 currently indicates that draining of the fuel oil stored in the supply tanks, removal of accumulated sediment, and tank cleaning will be done at a frequency specified in the licensee's Surveillance Frequency Control Program (SFCP).
The proposed change removes SR 3.8.3.7 from the TSs and relocates it to a document that is controlled by the licensee under 10 CFR 50.59.
The licensee states that administrative methods will be established to control performance of the 10-year diesel fuel oil storage tank cleaning activities that are currently described in SR 3.8.3.7. This has been included in the implementation section of this license amendment.
NRC Staff Evaluation
The NRC staff has determined that the current SR 3.8.3.7 requirements are a maintenance activity and are not a necessary surveillance to demonstrate operability of the emergency diesel generators and the quality of the system, or that a safety limit will not be exceeded as required by 10 CFR 50.36 (See Section 2.0 above) for retention in the TSs. The proper quality of fuel oil related to sediment content is demonstrated by performance of current VEGP SR 3.8.3.3, which determines whether new fuel oil is of the appropriate grade and has not been contaminated with substances that would have an immediate, detrimental impact on diesel engine combustion. As a result, adequate controls exist in the TSs to allow relocation of SR 3.8.3.7 to licensee-controlled documents.
RG 1.137 states that, as a minimum, the fuel oil stored in the supply tanks should be removed, the accumulated sediment removed, and the tanks cleaned at 10-year intervals. As stated above, VEGP Final Safety Analysis Report (FSAR) Section 1.9 incorporates the guidance of RG 1.137, which would continue to be met upon the proposed relocation of subject surveillance to a document that is controlled by the licensee pursuant to the 10 CFR 50.59 regulations.
Since SR 3.8.3.7 does not meet the 10 CFR 50.36 criteria for retention in the TSs as discussed above, there is no change in the licensee's commitment to RG 1.137, and SR 3.8.3.7 is partially duplicative of SR 3.8.3.3, which is not proposed to be relocated, the staff concludes that removal of SR 3.8.3.7 from the TSs is consistent with the requirements of 10 CFR 50.36(c)(3) and is acceptable. In addition, the change is consistent with guidance in NUREG-1431, "Standard Technical Specifications, Westinghouse Plants, Revision 4" because TSTF-2-A changes have been incorporated into the VEGP TSs.
3.2 TSTF-27-A. Revision 3. "Revise SR Frequency for Minimum Temperature for Criticality" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS, issued in April 2001. This traveler revised WOG STS 3.4.2, "RCS [Reactor Coolant System] Minimum Temperature for Criticality,"
to modify the frequency of SR 3.4.2.1.
TS SR 3.4.2.1 currently states:
Verify RCS Tavg in each loop~ 551°F." and specified a FREQUENCY of "Once within 30 minutes and every 30 minutes thereafter when the Tavg - Tret deviation alarm is not reset and any RCS loop Tavg < 561°F.
In a two-step process, the licensee first proposes to revise the frequency from, "once within 30 minutes and every 30 minutes thereafter when the Tavg - Tret deviation alarm is not reset and any RCS loop Tavg < 561°F." to "once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />" in accordance with TSTF-27-A, Revision 3, which the NRC staff accepts, as discussed below. Then, in a second step, the
licensee further proposes to revise the frequency to, "In accordance with the Surveillance Frequency Control Program," in accordance with TSTF-425.
The licensee explained the differences between its proposed changes and the approved TSTFs as follows:
The frequency for ISTS SR 3.4.2.1, and its associated Note, are modified by TSTF-27-A. The changes in TSTF-27-A would modify the Frequency for SR 3.4.2.1 to a periodic frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. As described in TS 5.5.21, Vogtle has adopted a Surveillance Frequency Control Program (SFCP) to control surveillances with periodic frequencies. The Frequency for SR 3.4.2.1, as modified by the changes identified in TSTF-27-A, will become a periodic frequency, and can be controlled under the SFCP. The Frequency for SR 3.4.2.1 is therefore modified to indicate that it is, In accordance with the Surveillance Frequency Control Program. The initial Frequency for this Surveillance will be 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The changes to SR 3.4.2.1 and the Bases for this SR are modified from that in TSTF-27-A to reflect this difference. NRC approval of the license change implementing the SFCP was provided in Amendment Numbers 158/140, dated January 19, 2011 (ACN ML102520083).
NRC Staff Evaluation
(a) Assessment for the licensee's adoption of TSTF-27-A change:
In this LAR, the licensee stated that TS 3.4.2, "RCS Minimum Temperature for Criticality,"
is designed to prevent criticality outside of the normal operating regime. Verification that operation is within the pressure-temperature limits report limits is required when RCS pressure and temperature conditions are undergoing planned changes. The proposed frequency of once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is considered reasonable in view of the control room indication available to monitor RCS status. During the approach to criticality, RCS temperature is closely watched. There are indications in the control room of deviations between actual and reference RCS temperature and on low RCS temperature to alert the operator if temperature is deviating from the program value. In addition, the operators are trained to be sensitive to RCS temperature during approach to criticality and will ensure that the minimum temperature for criticality is met as criticality is approached. Therefore, the NRC staff agrees with the licensee's justification, as stated above, and concludes that the fixed "12-hour" frequency is acceptable.
(b) Assessment for the licensee's adoption of TSTF-425 program for the change:
The licensee's proposed changes to the VEGP TS are different from those contained in TSTF-27-A in that the "12-hours" is replaced with, "In accordance with the Surveillance Frequency Control Program." VEGP has adopted TSTF-425-A, which allows relocation of selected SR frequencies from the TSs to a licensee-controlled document established in accordance with the SFCP described in VEGP TS 5.5.21. The NRC staff approval of the license amendment for adoption of TSTF-425-A was provided in Amendment Nos.
158/140, dated January 19, 2011 (ADAMS Accession No. ML102520083). According to
the approved TSTF-425, all surveillance frequencies can be relocated to the licensee controlled document except:
- Frequencies that reference other approved programs for the specific interval (such as the lnservice Testing Program or the Primary Containment Leakage Rate Testing Program);
- Frequencies that are purely event driven (e.g., "Each time the control rod is withdrawn to the 'full out' position");
- Frequencies that are event-driven but have a time component for performing the surveillance on a one-time basis once the event occurs (e.g., "within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after thermal power reaching;;:: 95% RTP"); and
- Frequencies that are related to specific conditions (e.g., battery degradation, age, and capacity) or conditions for the performance of an SR (e.g., "drywell to suppression chamber differential pressure decrease").
The NRC staff concludes that relocation of the subject surveillance frequency is not considered to be within the scope of the TSTF-425 four exceptions (discussed above) for which the TSTF-425 allowance is not allowed. Furthermore, the staff's approval letter, dated January 19, 2011 (ADAMS Accession No. ML102520083), for the licensee's TSTF-425 program (Amendment Nos. 158/140), states:
The licensee's adoption of TSTF-425 requires application of Nuclear Energy Institute (NEI) 04-10 in the SFCP. NEI 04-10 requires performance monitoring of structures, systems, and components (SSCs) whose surveillance frequency has been revised as part of a feedback process to assure that the change in test frequency has not resulted in degradation of equipment performance and operational safety. The monitoring and feedback includes consideration of maintenance rule monitoring of equipment performance. In the event of degradation of SSC performance, the surveillance frequency will be reassessed in accordance with the methodology, in addition to any corrective actions which may apply as part of the maintenance rule requirements. The performance monitoring and feedback specified in NEI 04-10 is sufficient to reasonably assure acceptable SSC performance and is consistent with Regulatory Position 3.2 of RG 1.177 "An Approach for Plant-Specific, Risk-Informed Decision making:
Technical Specifications."
The NRC staff reviewed the licensee's submittals relative to the TSTF and STS and concludes that relocation of this frequency to the licensee's SFCP meets 10 CFR 50.36 and is, therefore, acceptable.
3.3 TSTF-28-A, Revision 0, "Delete unnecessary Action to measure gross specific activity" The NRC approved this change to STS Revision 1 on September 27, 1996. This traveler revised WOG STS 3.4.16, "RCS Specific Activity," to delete Required Action 8.1, which
requires performance of SR 3.4.16.2 to verify that reactor coolant dose equivalent 1-131 specific activity is within the specified limits.
TS LCO 3.4.16, Required Action B.1, currently states:
CONDITION REQUIRED ACTION COMPLETION TIME B. Gross specific B.1 Perform SR 3.4.16.2 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> activity of the reactor coolant not within limit. AND B.2 Be in MODE 3 with Tav 9 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
< 500°F The licensee's proposed change removes Required Action 8.1 and its associated CT. The change also renumbers Required Action B.2 as B.1 with no change to its CT.
NRC Staff Evaluation
The staff's approval for TSTF-28-A recognized that there is little, if any, safety benefit to having the plant staff implementing Required Action B.1 (i.e., performance of SR 3.4.16.2), within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, while at the same time, per Required Action B.2, bringing the reactor to MODE 3 and
< 500 degrees Fahrenheit (°F) within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
The end result of the current Required Action B.1, which is to perform SR 3.4.16.2, is governed by a Note in SR 3.4.16.2, which says it only has to be performed in MODE 1. However, it is expected that if the reactor is in MODE 1 when the current Required Action B.2 must also be implemented, then the subsequent time in MODE 1 while implementing Required Action B.2 will be short. Thus, the NRC staff concludes that continued implementation of Required Action B.1 is not necessary and that deletion of this Action from the VEGP TS is acceptable. In addition, Required Action B.1 was deleted in NUREG-1431, Revision 2, as a result of the approved TSTF-28-A.
The NRC staff reviewed the licensee's submittals relative to the TSTF and STS and concludes that the proposed changes meet 10 CFR 50.36 and are, therefore, acceptable.
3.4 TSTF-45-A, Revision 2. "Exempt verification of CIVs that are not locked. sealed or otherwise secured" The NRC approved this change to the STS Revision 1 on July 26, 1999. This traveler revised WOG STS 3.6.3, "Containment Isolation Valves (CIVs)," by changing valve position verification SRs.
TS SRs 3.6.3.3 and 3.6.3.4 currently state:
Verify each containment isolation manual valve and blind flange that is located outside (SR 3.6.3.3) I inside (SR 3.6.3.4) containment and required to be closed during accident conditions is closed, except for containment isolation valves that are open under administrative controls.
The proposed change for the SRs would add a provision as shown in bold text below:
Verify each containment isolation manual valve and blind flange that is located outside (SR 3.6.3.3)/inside (SR 3.6.3.4) containment and not locked, sealed, or otherwise secured and required to be closed during accident conditions is closed, except for containment isolation valves that are open under administrative controls.
The licensee provides additional information as follows:
In addition, the proposed change is consistent with other Vogtle Surveillance Requirements to verify the position of valves, such as SR 3.5.2.2 (Emergency Core Cooling System valves), SR 3.7.5.1 (Auxiliary Feedwater System valves),
SR 3.6.6.1 (Containment Spray and Cooling System valves), SR 3.7.7.1 (Component Cooling Water System valves), SR 3.7.8.1 (Nuclear Service Cooling Water System valves), and SR 3.7.14.1 (Engineered Safety Features ESF Room Cooler and Safety-Related Chiller System valves).
NRC Staff Evaluation
TSTF-45-A stated that the proposed change was consistent with the valve position verification requirement for valves that have a function during an accident in other system TSs. The proposed change to the SRs listed above is consistent with current VEGP TS SR 3.5.2.5, which requires that each emergency core cooling system subsystem be demonstrated operable, in part, by performance of a valve alignment of each valve that is in the flow path that is not locked, sealed, or otherwise secured valves. The AFW system and the nuclear service cooling water system are also demonstrated to be operable, in part, by verifying that each valve in the flow path of the system that is not locked, sealed, or otherwise secured in position, is in its correct position (SRs 3.7.5.1, 3.7.8.1, and 3.7.8.2, respectively). Adding these words to the SRs excludes those valves that are locked, sealed, or otherwise secured in the closed position from the verification requirements of these SRs. This is acceptable since these valves were verified to be in the correct position upon locking, sealing, or securing.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(3) continue to be met because the revised SR provides the appropriate surveillance to ensure the necessary quality of components is maintained and the LCO will be met.
Based on the above, the NRC staff concludes that the proposed TS changes are acceptable and they are also consistent with TSTF-45-A.
3.5 TSTF-46-A, Revision 1, "Clarify the CIV surveillance to apply only to automatic isolation valves" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC in Revision 2 of the STS issued in April 2001. The TSTF deletes the WOG STS SR 3.6.3.5 requirement to verify the isolation time of "each power operated"
containment isolation valve and only requires verification of each "automatic power operated isolation valve."
TS SR 3.6.3.5 currently states:
Verify the isolation time of each power operated and each automatic containment isolation valve is within limits.
The proposed change would revise the SR as follows:
Verify the isolation time of each po*::er operated and eaGh automatic power operated containment isolation valve is within limits.
NRC Staff Evaluation
The original wording states that the surveillance applied to power operated and automatic isolation valves, which could result in an interpretation that power operated valves that do not receive an automatic closure signal for design basis events are also required to have a closure time associated with them. These changes removed the unintended requirement to verify isolation times of non-automatic power operated CIVs. Appropriate changes to the Bases for Surveillance and LCO 3.6.3 were also made.
The changes proposed for the corresponding CIV SRs in VEGP TS 3.6.3 are identical to those contained in the traveler. These changes only clarify the original intended scope of containment isolation valves covered by the existing Surveillance, and hence, are administrative. The current scope of these Surveillances has not changed and there is no impact on safety.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(3) continue to be met because the revised SR provides the appropriate surveillance to ensure the necessary quality of components is maintained and the LCO will be met.
Based on the above, the NRC staff concludes that these changes are acceptable.
3.6 TSTF-87-A, Revision 2. "Revise 'RTBs open' and 'CRDM de-energized' Actions to
'incapable of rod withdrawal' "
The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler modifies certain Required Actions in WOG STSs 3.4.5, "RCS Loops - Mode 3, and STS 3.4.9, "Pressurizer," as explained in the licensee's proposed changes.
The following specifies changes to LCOs 3.4.5 and 3.4.9:
- TS LCO 3.4.5 currently specifies the following Conditions and Required Actions:
Condition C currently states:
One required RCS loop not in operation, and reactor trip breakers closed and Rod Control System capable of rod withdrawal.
Revised Condition C would state:
One required RCS loop not in operation, and reactor trip breakers closed aoo with Rod Control System capable of rod withdrawal.
Required Action C.2 currently states:
De-energize all control rod drive mechanisms (CRDMs).
Revised Required Action C.2 would state:
Ge-energize all control rod drive mechanisms (CRDMs). Place the Rod Control System in a condition incapable of rod withdrawal.
Required Action D.1 currently states:
De-energize all CRDMs.
Revised Required Action D.1 would state:
Ge-energize all CRDMs. Place the Rod Control System in a condition incapable of rod withdrawal.
- TS 3.4.9 currently specifies the following Required Actions:
Required Actions A.1 and A.2 currently state:
A.1 Be in Mode 3 with reactor trip breakers open, AND A.2 Be in MODE 4.
Revised Required Actions:
Required Action A.1 is revised, new Required Actions A.2 and A.3 and their CTs are added, and the current Required Action A.2 is renumbered to A.4 as follows:
A.1 Be in Mode 3.
A.2 Fully insert all rods," with a Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
AND
A.3 Place Rod Control System in a condition incapable of rod withdrawal with a Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, AND A.4 Be in MODE 4.
NRC Staff Evaluation
The licensee's proposed changes to VEGP TSs 3.4.5 and 3.4.9 are identical to those contained in the traveler. The licensee states that the intent of these Required Actions is to prevent introduction of positive reactivity by inadvertent rod withdrawal. While the proposed changes replace the specific methods of precluding rod withdrawal, rod withdrawal remains assured of being prohibited by plant/system configuration. The specific methods are still provided in the Bases as examples to guide plant operators, if needed. In addition, the TSTF states for Westinghouse plants, that these changes are necessary to eliminate undesirable secondary effects of opening the RTBs. In particular, by opening the RTBs, plant interlock P-4 is tripped, which results in a trip of the main turbine and will close the main and bypass feedwater lines if RCS Tavg is below the low setpoint in Mode 3. Forcing reliance on AFW in this condition is not the intent, nor is it desirable, over continued use of normal feedwater.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the NRC staff concludes that this change is acceptable.
In addition, the change is consistent with guidance in NUREG-1431, "Standard Technical Specifications, Westinghouse Plants, Revision 4," because the TSTF-87-A, Revision 2, changes have been incorporated into the VEGP TSs.
- 3. 7 TSTF-95-A, Revision 0, "Revise completion time for reducing Power Range High trip setpoint from 8 to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />" The NRC approved this change to STS Revision 1 on September 27, 1996. This traveler revised WOG STS 3.2.1 and STS 3.2.2. The proposed change revised the CTs for TS 3.2.1, "Heat Flux Hot Channel Factor (Fa(Z)) (Fa Methodology)," Required Action A.2, and TS 3.2.2, "Nuclear Enthalpy Rise Hot Channel Factor (Fe.HN)," Required Action A.1.2.2, to provide a 72-hour CT instead of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to reset the Power Range Neutron Flux - High Trip setpoints to a lower value.
For TS 3.2.1, "Heat Flux Hot Channel Factor (Fa(Z)) (Fa Methodology)," when Condition A, "Fa(Z) not within steady state limit," is not met, Required Action A.2 currently states "Reduce Power Range Neutron Flux - High trip setpoints ~ 1% for each 1% Fa(Z) exceeds steady state limit." The CT for the Action is 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
For TS 3.2.2, "Nuclear Enthalpy Rise Hot Channel Factor (Ft1HN)," when Condition A, "Ft1HN not within limits" is not met, Required Action A.1.2.2 currently states, "Reduce Power Range Neutron Flux - High trip setpoints to 55% RTP." The CT for the Action is 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
The proposed change would revise the CT to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> for both Required Actions.
NRC Staff Evaluation
The licensee's proposed change to the VEGP TSs is identical to that contained in TSTF-95 in that the 8-hour CT is changed to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. A CT of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> will allow time to perform a second flux map to confirm the results of the first one, or determine that the condition was temporary, without implementing an unnecessary trip setpoint change, during which there is increased potential for human error and a plant transient. Following a significant power reduction, at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is required to re-establish steady state xenon prior to taking a flux map and approximately 8 to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to obtain a flux map and analyze the data. A significant potential for human error can be created by requiring the trip setpoints to be reduced within the same timeframe that a unit power reduction is taking place and within the current 8-hour period.
Setpoint adjustment of the four channels is estimated to take approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. Further, setpoint changes should only be required for extended operation in this condition. The licensee states that the TSTF justification is also applicable to the VEGP TS requirements.
The VEGP also has a Power Range Neutron Flux, High Positive Rate Trip to provide protection against a large positive reactivity addition event during the proposed extended time to reduce the power range neutron flux-high trip setpoints. Therefore, the NRC staff has reasonable assurance that the extended time will not adversely affect safety margin.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the staff concludes that the Required Actions, as modified above, are acceptable. In addition, the changes are consistent with TSTF-95, Revision 0.
3.8 TSTF-110-A, Revision 2. "Delete SR frequencies based on inoperable alarms" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. The proposed change would eliminate surveillance frequencies related to certain inoperable alarms by removal from the TS of the bolded text noted below.
TS 3.1.4, "Rod Group Alignment Limits," SR 3.1.4.1 currently states:
Verify individual rod positions within alignment limit in accordance with the Surveillance Frequency Control Program AND Once within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter when the rod position deviation monitor is inoperable
TS 3.1.6, "Control Bank Insertion Limits," SR 3.1.6.2 currently states:
Verify each control bank insertion is within the limits specified in the COLR, in accordance with the Surveillance Frequency Control Program AND Once within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter when the rod insertion limit monitor is inoperable TS 3.2.3, "AXIAL FLUX DIFFERENCE (AFD) (Relaxed Axial Offset Control (RAOC)
Methodology)," SR 3.2.3.1 currently states:
Verify AFD within limits for each OPERABLE excore channel in accordance with the Surveillance Frequency Control Program AND Once within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and every 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> thereafter with the AFD monitor alarm inoperable TS 3.2.4, "QUADRANT POWER TILT RATIO (QPTR)," SR 3.2.4.1 currently states:
Verify QPTR is within limit by calculation in accordance with the Surveillance Frequency Control Program AND Once within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter with the QPTR alarm inoperable Consistent with TSTF-110 and the licensee's application, the requirement to perform the surveillances more frequently when the associated alarms are inoperable is removed from the TSs and relocated to plant administrative documents that are controlled pursuant to 10 CFR 50.59.
The licensee amplifies its proposed change with the following information:
The Vogtle Section 3.1 specification numbers are different from the ISTS Section 3.1 specification numbers. Vogtle Specification 3.1.4, "Rod Group Alignment Limits" is equivalent to Specification 3.1.5 in the ISTS, and Vogtle Specification 3.1.6, "Control Bank Insertion Limits" is equivalent to Specification 3.1.7 in the ISTS. This has no effect on the requested change.
The ISTS contains two alternative specifications for Axial Flux Difference to reflect different methodologies. TSTF-110-A revised Specification 3.2.3A, "AFD (CAOC Methodology)," and Specification 3.2.38, "AFD (RAOC Methodology)."
Vogtle Specification 3.2.3 is equivalent to ISTS Specification 3.2.3B.
NRC Staff Evaluation
- Assessment for the Deletion of TS Rod Position Deviation Monitor in SR 3.1.4.1:
The OPERABILITY, including position indication (i.e., trippable), of the shutdown and control rods is an initial assumption in the safety analyses that assumes rod insertion upon reactor trip.
Maximum rod misalignment is an initial assumption in the safety analysis that directly affects core power distributions and assumptions of available shutdown margin (SDM). Rod position indication is required to assess operability and misalignment.
Mechanical or electrical failures may cause a control rod to become inoperable or to become misaligned from its group. Control rod inoperability or misalignment may cause increased power peaking due to the asymmetric reactivity distribution and a reduction in the total available rod worth for reactor shutdown. Therefore, control rod alignment and OPERABILITY are related to core operation in design power peaking limits and the core design requirement of a minimum SOM. Limits on control rod alignment have been established, and all rod positions are monitored and controlled during power operation to ensure that the power distribution and reactivity limits defined by the design power peaking and SOM limits are preserved.
The licensee's proposed change to the TS SR 3.1.4.1 (i.e., to remove requirements for surveillances when the rod position deviation monitor is inoperable), is identical to that contained in the traveler. The rod position monitor/alarm is provided as an aid to alert the operator if any rod deviates from the bank position by more than +/- 12 steps. This SR verifies that each control bank insertion is within the limits specified in the Core Operating Limits Report (COLR).
One of the requirements of the COLR specified in the licensee's TS Section 5.6.5 requires that:
The core operating limits shall be determined such that all applicable* limits (e.g.,
fuel thermal mechanical limits, core thermal hydraulic limits, Emergency Core Cooling Systems (ECCS) limits, nuclear limits such as SOM, transient analysis limits, and accident analysis limits) of the safety analysis are met.
The NRC staff concludes that since performance of the SR per the licensee's COLR program assures that the plant is operating within the limits established in its accident analysis, as a result, actions based on the availability of the rod position monitor are not required to be retained in the TSs; therefore, the proposed change is acceptable.
- Assessment for Deletion of TS Rod Insertion Limit (RIL) Monitor in SR 3.1.6.2:
The insertion limits of the shutdown and control rods are initial assumptions in all safety analyses that assume rod insertion upon reactor trip. The insertion limits directly affect core power and fuel burnup distributions and assumptions of available SOM, and initial reactivity insertion rate. TS limits on control rod insertion have been established, and all rod positions are monitored and controlled during power operation to ensure that the power distribution and reactivity limits defined by the design power peaking and SOM limits are preserved. VEGP SRs 3.1.4.1 through 3.1.4.3 associated with these TSs rely solely upon the Bank Demand Position Indication system and Digital Rod Position Indication (DRPI) system. The RIL monitor is not used in satisfying these SRs.
The RI L monitor/alarm is provided as an aid to alert the operator if the control banks are outside of the insertion limits. It performs no protective functions assumed in a safety analysis.
Considering that rod motion is limited and infrequent during steady-state power operations, verification that banks are within the limits once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> allows the operator to detect a bank that is approaching the insertion limits. This specified frequency takes into account other rod position information that is continuously available to the operator in the control room so that during actual rod motion, deviations can be immediately detected.
Therefore, since the rod position indication systems provide accurate information on rod positions, the operators routinely verify rod position are within limits and the RIL monitor serves no protective function, the NRC staff has concluded that removal of the modified SR when the RIL is inoperable is acceptable. In addition, this change is consistent with NUREG-1431, Revision 1, dated April 1995, as modified by the NRC staff-approved TSTF-110, Revision 2.
- Assessment for Deletion of TS Axial Flux Difference (AFD) Monitor Alarm for SR 3.2.3.1:
The AFD is a measure of the axial power distribution skewing to either the top or bottom half of the core. The AFD is sensitive to many core-related parameters such as control bank positions, core power level, axial burnup, axial xenon distribution, and to a lesser extent, reactor coolant temperature and boron concentration.
The allowed range of the AFD is used in the nuclear design process to confirm that operation within these limits produces core peaking factors and axial power distributions that meet safety analysis requirements.
TS limits on AFD were established in order to ensure core peaking factors are consistent with the assumptions used in the safety analysis. VEGP TSs address these requirements, which require that the indicated AFD be maintained within the target band specified in the COLR), and that the AFD is verified to be within limits on a routine basis using the operable excore channels.
Additionally, there is an AFD monitor/alarm, which does not perform any protective functions, to aid the operator in maintaining AFD within limits. This monitor/alarm is not relied upon for these surveillances. However, there are TS requirements to perform the AFD verifications more frequently during periods when this monitor is not operable.
The licensee has proposed revision of SR 3.2.3.1 to remove SR frequency changes related to the operability of the AFD monitor alarm, and revision of the associated bases to remove discussion of the alarm operation.
The NRC staff agrees with the licensee's position that the AFD monitor alarm is provided as an operator aid for maintaining AFD within established limits and that it performs no protective functions assumed in a safety analysis. Although AFD indication ensures that core peaking factors do not exceed assumptions in the accident analysis, the NRC staff concludes that removal of the modified SR when the AFD monitor alarm is inoperable is acceptable, since the ex-core detectors (for which no change is proposed) are capable of verifying the AFD.
Therefore, the NRC staff has concluded that removal of the AFD monitor alarm requirements in SR 3.2.3.1 is acceptable. In addition, this change is consistent with NUREG-1431, "Standard Technical Specifications - Westinghouse Plants," Revision 1, dated April 1995, as modified by the NRC staff-approved TSTF-110, Revision 2, because the TSTF changes have been incorporated into the VEGP TS.
- NRC Staff Evaluation for Deletion of TS Quadrant Power Tilt Ratio (QPTR) Monitor requirements for SR 3.2.4.1.
The licensee states that the QPTR is a measure of the radial power distribution within the core.
The QPTR limit ensures that the gross radial power distribution remains consistent with the design values used in the safety analysis. The power density at any point in the core must be limited so that the fuel design criteria are maintained. Together, VEGP LCO 3.2.3, "Axial Flux Difference"; LCO 3.2.4, "Quadrant Power Tilt Ratio"; and LCO 3.1.6, "Control Bank Insertion Limits," provide limits on process variables that characterize and control the three dimensional power distribution of the reactor core. Control of these variables ensures that the core operates within the fuel design criteria and that power distribution remains within the bounds used in the safety analysis.
Precise radial power distribution measurements are made during startup testing, after refueling, and periodically during power operation. The TS limit on QPTR is addressed by an LCO and SRs, which require that the QPTR be maintained within its limit, and that this is verified on a routine basis using the excore detectors. Additionally, there is a QPTR monitor/alarm, which does not perform any protective functions, to aid the operator in maintaining QPTR within the TS limit. Although this monitor/alarm is not relied upon for the TS-required QPTR surveillances, there are TS requirements to perform the QPTR verification more frequently during periods when this monitor is not operable.
The licensee has proposed revision of SR 3.2.4.1 to remove requirements associated with the QPTR monitor alarm, and revision of the associated bases to remove discussion of alarm operability. Specifically, the SR is modified to remove the requirement to calculate QPTR and verify that it is within limits in accordance with the licensee's SFCP when the QPTR alarm is inoperable. The TS requirements to maintain QPTR less than or equal to 1.02 when reactor power is greater than 50 percent rated thermal power (RTP) and the associated action statements are unchanged.
The NRC staff agrees with the licensee's position that the QPTR monitor alarm is provided as an operator aid for maintaining QPTR within established limits and that it performs no protective functions assumed in a safety analysis. When the QPTR exceeds its limit, it does not necessarily mean a safety concern exists. This change removes requirements associated with the QPTR monitor alarm, but leaves the TS QPTR limit and QPTR SRs unchanged. Per 10 CFR 50.36, SRs assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the LCOs will be met.
SR 3.2.4.1 verifies that the QPTR, as indicated by the Nuclear Instrumentation System excore channels, is within its limits. The surveillance frequency for SR 3.2.4.1 is controlled under the SFCP. Valid inputs to the detector current comparator from the upper and lower sections from three or four power range channels are required for the QPTR alarm to be OPERABLE. This requirement is not being changed in the licensee's proposed change for the SR 3.2.4.1 frequency. For those causes of QPTR that occur quickly (e.g., a dropped rod), there typically are other indications of abnormality that prompt a verification of core power tilt.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(3) continue to be met because the revised SR provides the appropriate surveillance to ensure the necessary quality of components is maintained and the LCO will be met.
Based on the above, the NRC staff concludes that the changes are acceptable.
The changes are also consistent with guidance in the STS and TSTF-110-A, Revision 2, because the TSTF changes have been incorporated into the VEGP TS.
3.9 TSTF-142-A, Revision 0. "Increase the Completion Time When the Core Reactivity Balance is Not Within Limit" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler extended WOG STS LCO 3.1.3 (equivalent to VEGP TS 3.1.2), "Core Reactivity," the CT from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days for specific Required Actions.
Currently, when TS 3.1.2, "Core Reactivity, Condition A," "Measured core reactivity not within limit," is not met, Required Actions A.1 and A.2 must be completed within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
The revised CT would be exfended from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days.
NRC Staff Evaluation
The licensee states that upon determination that the reactivity balance is not within its limits, the proposed TS change would allow VEGP TSs 7 days to reevaluate core design and safety analyses to determine if the core is acceptable for continued operation, and to establish appropriate operating restrictions and perform appropriate SRs. Under the current TSs, had the reactivity balance been outside its limits, VEGP would have to be in MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
VEGP justifies this extension by stating that the actions to perform an evaluation would ensure appropriate corrective actions are taken to resolve all of the issues associated with the reactivity anomaly. In TSTF-142-A, the NRC approved the 7-day period for incorporation into the STS based on the conservatisms used in designing the reactor core and performing the safety analyses, and because of the low probability of a design basis accident approaching the core design limits occurring during the proposed 7-day period.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, and since the 7-day period allows for appropriate actions to resolve the reactivity anomaly issues, the NRC staff concludes that the proposed change is acceptable.
3.10 TSTF-234-A. Revision 1. "Add Action for More than One [Digital) Rod Position Indicator (RPI) Inoperable" The NRC approved this change to STS Revision 1 on January 13, 1999. This traveler revised WOG STS 3.1.8 by adding a new TS Action B to allow 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to restore inoperability of more than one [D]RPI in a group. VEGP TS 3.1.7, "Rod Position Indication," is equivalent to Specification 3.1.8 in the STS.
The following changes are proposed for TS 3.1.7:
- The NOTE under ACTIONS in the LCO currently states:
Separate Condition entry is allowed for each group with no more than one inoperable rod position indicator in the group and for each bank with no more than one inoperable demand position indicator in the bank.
The NOTE is revised to read as follows:
Separate Condition entry is allowed for each inoperable rod position indicator and each inoperable demand position indicator.
- Required Action A.1 currently states:
Verify the position of the rods with inoperable position indicators by using movable incore detectors.
Revised Required Action A.1 would state:
Verify the position of the rods with inoperable position indicators indirectly by using movable incore detectors.
- Required Action 8.1 currently states:
Verify the position of the rods with inoperable DRPls by using movable incore detectors.
Revised Required Action 8.1, which is renumbered C.1, would state:
Verify the position of the rods with inoperable DRPls indirectly by using movable incore detectors.
- A new Condition 8, "More than one DRPI per group inoperable." with its associated Required Actions 8.1, 8.2, 8.3, 8.4 and associated Completion Times is added, as shown below.
CONDITION REQUIRED ACTION COMPLETION TIME B. More than one DRPI B.1 Place the control rods Immediately per Group inoperable. under manual control.
AND B.2 Monitor and Record RCS Once per 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Tavg.
AND B.3 Verify the position of the Once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> rods with inoperable position indicators indirectly by using the movable incore detectors.
AND B.4 Restore inoperable 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> position indicators to OPERABLE status such that a maximum of one DRPI per group is inoperable.
Due to the insertion of the new Condition B, the current Conditions B, C, and D, with associated Required Actions and CTs are renumbered as Conditions C, D, and E, with associated Required Actions and CTs. The CTs for renumbered Conditions C, D, and E are unchanged.
The licensee explains the differences between the proposed changes and the approved traveler as follows:
The Vogtle Section 3.1 specification numbers are different from the ISTS Section 3.1 specification numbers. Vogtle Specification 3.1. 7, "Rod Position Indication," is analogous to Specification 3.1.8 in the ISTS.
The existing Vogtle Actions Note is worded differently than the ISTS Actions Note that is modified by TSTF-234-A due to a plant specific clarification. The proposed Actions Note is identical to the wording approved in TSTF-234-A. This has no effect on the proposed change or the justification.
TSTF-234-A contains the bracketed text"[, or 8.1, as applicable]" in the Bases discussion for Condition C. This change was not adopted because it is not necessary to provide direction in the Bases that all applicable Conditions must be entered.
NRC Staff Evaluation
TSTF-234 allows for more than one DRPI to be inoperable for a maximum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, given that other indirect means of monitoring changes in rod position are available. This provides sufficient time to restore operability while minimizing shutdown transients during the time that the position indication is degraded.
The proposed change is consistent with TSTF-234, which allows verification of core peaking factors and shutdown margin to satisfy the action requirements, providing the non-indicating rods have not been moved. The additional time to restore an inoperable DRPI is appropriate because the proposed action would require that the control rods be under manual control, that reactor coolant system average temperature (RCS Tavg) be monitored and recorded hourly, and that rod position be verified indirectly every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, thereby assuring that the rod alignment and rod insertion LCOs are met. Therefore, the required shutdown margin will be maintained. Given the alternate position monitoring requirement, and other indirect means of monitoring changes in rod position (e.g., alarms on average versus reference temperature deviation), a 24-hour CT to restore all but one DRPI per group provides sufficient time to restore operability while minimizing shutdown transients during the time that the position indication system is degraded.
The licensee clarified that rod position verification will be performed every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, which is consistent with TSTF-234, which also allows verification of core peaking factors and shutdown margin to satisfy the action requirements, provided the non-indicating rods have not been moved. Additionally, consistent with TSTF-234, the TSs will require that the control rods be placed under manual control, the RCS Tavg be monitored and recorded hourly, and the rod position to be verified indirectly every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The proposed change requires the use of the movable incore detectors as an indirect means of monitoring changes in rod position in order to assure that the rod alignment and rod insertion LCOs are met, consistent with TSTF-234.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the proposed changes are acceptable to the staff.
3.11 TSTF-245-A. Revision 1. "AFW train operable when in service" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler revised WOG STS 3.7.5. The proposed change modifies TS SRs 3.7.5.1, 3.7.5.3, and 3.7.5.4 by adding a Note stating that, "AFW train(s) may be considered OPERABLE during alignment and operation for steam generator level control, if it is capable of being manually realigned to the AFW mode of operation."
TS SR 3.7.5.1 currently states:
Verify each AFW manual, power operated, and automatic valve in each water flow path, and in both steam supply flow paths to the steam turbine driven pump, that is not locked, sealed, or otherwise secured in position, is in the correct position.
TS SR 3.7.5.3 currently states:
Verify each AFW automatic valve that is not locked, sealed, or otherwise secured in position actuates to the correct position on an actual or simulated actuation signal.
TS SR 3.7.5.4 currently specifies the following NOTE:
N 0 TE------------------------------------------------
Not required to be performed for the turbine driven AFW pump until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after ~ 900 psig in the steam generator.
The proposed change to SRs 3.7.5.1, 3.7.5.3, and 3.7.5.4 would add the following NOTE:
AFW train(s) may be considered OPERABLE during alignment and operation for steam generator level control, if it is capable of being manually realigned to the AFW mode of operation.
The licensee explains the differences between the proposed changes and the approved traveler as follows:
ISTS SR 3.7.5.3 contains a note stating that the SR is "Not applicable in MODE 4 when steam generator is relied upon for heat removal." The approved Traveler deletes and replaces this note. Vogtle SR 3.7.5.3 does not currently include this note, and will add the note identified in the approved Traveler under this change.
Additionally, the Bases for SR 3. 7.5.1 includes clarifying text that is supplemental to that provided in the ISTS. As a result of this change, the supplemental text is no longer necessary and is deleted. These differences do not affect the applicability of the traveler justification.
NRC Staff Evaluation
The licensee proposed changes to the SRs stated in TS SR 3.7.5.1, SR 3.7.5.3, and SR 3.7.5.4 in order to conform to the provisions in TSTF-245, Revision 1. The proposed changes would add a note to the SRs that would allow an AFW train to be considered operable at low-power operation when its components are being operated manually for steam generator (SG) level control in MODES 1, 2, and 3, and the components can be realigned for AFW mode of operation. SNC states that there are no differences between its plant-specific justification and the approved TSTF justification.
The NRC staff-approved TSTF-245, Revision 1, dated July 3, 2003 (ADAMS Accession No. ML040611028). The TSTF evaluation includes a letter from the NRC staff to the licensee for the Indian Point Nuclear Generating plant, dated May 23, 1997, which outlines the NRC staff's position on taking credit for manual actions. The letter states in part, "In general, it is not appropriate to take credit for manual action in place of automatic action for protection of safety limits to consider equipment operable." Thus, credit for any manual actions should be part of the plant's licensing basis. In order to credit manual actions, the licensee must evaluate
physical differences between automatic and manual actions and the ability to perform the manual actions. The May 23, 1997, letter states that the NRC staff has made a determination that for the AFW system on a typical pressurized-water reactor (PWR), manual actions versus automatic operation are permissible in certain circumstances. VEGP is a PWR type plant.
Accordingly, the NRC staff concludes that an AFW train may be considered operable when an operator is controlling AFW manually to maintain SG levels in the normal control band during startup, normal shutdown, and hot standby conditions.
TS SR 3.7.5.1 verifies the correct alignment for manual, power operated, and automatic valves in the AFW system water and steam supply flow paths and provides assurance that the proper flow paths will exist for AFW operation. While the licensee is utilizing AFW in manual during low-power operations (i.e., startups and shutdowns), the plant operators must take manual control of the AFW pump(s) and control valves to maintain proper SG level. In doing so, the valves may no longer be in the position assumed in the accident analyses. Since the licensee's application states that the VEGP Operating Procedures and Emergency Operating Procedures contain steps to support realignment of the AFW system from manual steam generator level control mode to the emergency operation mode, when required, the NRC staff concludes that the licensee's proposed changes are consistent with TSTF-245, Revision 1, for VEGP.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(3) continue to be met because the revised SR provides the appropriate surveillance to ensure the necessary quality of components is maintained and the LCO will be met.
Based on the above, the NRC staff concludes that the changes are acceptable.
3.12 TSTF-24 7-A, Revision 0, "Provide separate condition entry for each PORV and block valve" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler modified WOG STS 3.4.11, "Pressurizer PORVs," to extend the Actions Note, which allows separate Condition entry for each PORV to apply also for each block valve.
TS LCO, 3.4.11, ACTIONS NOTE currently states:
Separate Condition entry is allowed for each PORV Revised ACTIONS NOTE would state:
Separate Condition entry is allowed for each PORV and each block valve TS 3.4.11, Condition F currently states:
More than one block valve inoperable.
TS 3.4.11, Revised Condition F would state:
Two block valves inoperable.
TS LCO 3.4.11, Condition F, Required Actions, and associated CTs currently state:
F.1 Place associated PORVs in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, AND F.2 Restore one block valve to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, AND F.3 Restore remaining block valve to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> The proposed change deletes Required Actions F.1 and F.3 and associated CTs, and renumbers Required Action F.2 as Required Action F.1 as stated below:
F.1 Restore one block valve to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> The licensee states that there are no differences between the proposed changes and the approved TSTF; however, TSTF-247-A provides options depending on the number of PORV and block valves that are included in the plant design. The design of VEGP includes two PORVs and associated block valves. The options from TSTF-247-A for plants with three PORVs and associated block valves are not adopted.
The pressurizer of the RCS includes two PO RVs that can be manually controlled from the control room. The block valves are used to isolate the PORVs. This is done to stop excessive leakage through a PORV seat or stuck-open PORV to stop RCS depressurization and coolant loss.
Per the licensee's TSs, when a PORV block valve is declared inoperable per LCO 3.4.11, Condition C, Required Action C.1 requires placing the associated PORV in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> AND Required Action C.2 requires restoring the block valve to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The licensee states that these Required Actions and CTs are not being changed in this amendment.
NRC Staff Evaluation
Currently, the Note in LCO 3.4.11 allows a separate condition entry for each PORV where the LCO requires each PORV to be operable. This allows each PORV to be treated separately with a separate CT for each inoperable PORV.
The proposed change adds the PORV block valves to the Note, which, along with PORVs, would also allow the PORV block valves to be treated as separate entities with a separate CT for each inoperable PORV block valve. The change simply extends the separate condition entry for the PORVs in the current TSs to the PORV block valves. This is treating the PORV block valves in the same manner as the PORVs. Since the block valves back-up the PORVs in performing the same function in the event of PORV problems, the NRC staff concludes that this proposed change is acceptable.
The proposed Condition F is modified to apply when two block valves are inoperable. The licensee also proposes to delete Required Actions F.1 and F.3 in TS 3.4.11. These Required
Actions are for the condition of more than one (revised to two) block valves inoperable and require that the associated PO RVs for the inoperable block valves are placed in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> (required Action F .1) and restore the remaining block valve to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (Required Action F.3). The licensee's current Conditions and Required Actions provide compensatory actions for separate condition entry for each block valve, such as when a PORV block valve is declared inoperable per LCO 3.4.11, Condition C, Required Action C.1, requires placing the associated PORV in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> AND Required Action C.2 requires restoring the block valve to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. These Required Actions and CTs are not affected by the proposed changes.
When a PORV block valve is declared inoperable, there is entry into Condition C, one block valve inoperable. The Required Actions are (1) to place the associated PORV in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and (2) restore the block valve to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. These Required Actions and CTs are not being changed in this amendment. Therefore, there would be a separate entry into Condition C for each inoperable block valve requiring the associated PORV to be in manual control within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. Accordingly, the NRC staff concludes that allowing separate condition entry for PORV block valves makes Required Action F.1 and F.3 redundant to Required Actions C.1 and C.2, and is, therefore, no longer necessary. Therefore, the NRC staff concludes that a separate condition entry for the PORV block valves is acceptable. The staff further concludes that the proposed deletion of Required Actions F.1 and F.3 is acceptable.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the NRC staff concludes that the changes are acceptable.
3.13 TSTF-248-A. Revision 0, "Revise Shutdown Margin definition for stuck rod exception" The NRC approved this change to STS Revision 1 on October 31, 2000. This traveler revised WOG STS 1.1. This change revises the definition of shutdown margin to eliminate the requirement that shutdown margin calculations must assume the single rod cluster control assembly (RCCA) of highest worth is fully withdrawn if all RCCAs can be verified to be fully inserted by two independent means.
TS 1.1, "Shutdown Margin" (SOM) definition currently has the following paragraph:
All rod cluster control assemblies (RCCAs) are fully inserted except for the single RCCA of highest reactivity worth, which is assumed to be fully withdrawn. With any RCCA not capable of being fully inserted, the reactivity worth of the RCCA must be accounted for in the determination of SOM; and Proposed changes (shown in bold text below) modify the paragraph as follows:
All rod cluster control assemblies (RCCAs) are fully inserted except for the single RCCA of highest reactivity worth, which is assumed to be fully
withdrawn. However, with all RCCAs verified fully inserted by two independent means, it is not necessary to account for a stuck rod in the SOM calculation. With any RCCA not capable of being fully inserted, the reactivity worth of the RCCA must be accounted for in the determination of SOM; and
NRC Staff Evaluation
The proposed change modifies the TSs by changing the definition of SOM to reflect the definition in the latest revision to Westinghouse STSs NUREG-1431. The revised definition includes a provision allowing an exception to the highest reactivity RCCAs penalty if there are two independent means of confirming that all RCCAs or control rods are fully inserted in the core.
SOM is the instantaneous amount of reactivity by which the reactor is subcritical or would be subcritical from its present condition if all RCCAs are fully inserted except for the single RCCA of highest reactivity worth, which is assumed to be fully withdrawn. The VEGP COLR is the unit-specific document that provides cycle-specific parameter limits for the current fuel cycle.
These cycle-specific parameter limits are determined for each fuel cycle. The analytical methods used to determine the core operating limits shall be those previously reviewed and approved by the NRC, specifically those described in the documents listed in VEGP TS Section 5.6.5. The COLR, in conjunction with the TSs, ensures for each specific fuel cycle that all parameters, including SOM, meet the licensing basis requirements. While the control rods are withdrawn from the reactor core, the required amount of SOM includes the penalty for the single control rod of highest reactivity worth, which is assumed to be fully withdrawn. Once all control rods are fully inserted into the reactor and verified by two independent means, the SOM limit in the COLR assures that adequate SOM, as assumed in the UFSAR for accidents and transients that initiate from a shutdown condition are met. Once all control rods have been verified to be fully inserted into the core, requiring the SOM calculation to include the penalty for the single control rod of highest reactivity worth fully withdrawn would be overly conservative.
Per the VEGP FSAR, Revision 19, the axial position of shutdown rods and control rods is indicated by two separate and independent systems, which are the Bank Demand Position Indication System (commonly called group step counters) and the Digital Rod Position Indication (DRPI) System.
The Bank Demand Position Indication System counts the pulses from the rod control system that moves the rods. There is one step counter for each group of rods. Individual rods in a group all receive the same signal to move and should, therefore, all be at the same position indicated by the group step counter for that group. The Bank Demand Position Indication System is considered highly precise (+/- 1 step or+/-% inch). If a rod does not move one step for each demand pulse, the step counter will still count the pulse and incorrectly reflect the position of the rod.
The DRPI System provides a highly accurate indication of actual control rod position but at a lower precision than the step counters. This system is based on inductive analog signals from a series of coils spaced along a hollow tube with a center to center distance of 3. 75 inches, which
is six steps. However, the magnetic drive rod concentrates the magnetic lines of flux developed in the coil resulting in a change in coil output voltage when the shaft is close to it. This provides a+/- 4 step accuracy with all coils operable. To increase the reliability of the system, the inductive coils are connected alternately to data systems A or B. Thus, if one system fails, the
=
DRPI will go on half accuracy (System A failure +10, -4 steps and System B failure =- 10, +4 steps) with an effective coil spacing of 7.5 inches, which is 12 steps. The resolution of the rod position indicator channel is+/- 5 percent of span (+/- 7.5 in. or+/- 12 steps). Deviation of any RCCA from its group by 10 percent of span (15 inches or 24 steps) will not cause power distributions worse than the design limits. The deviation alarm alerts the operator to rod deviation with respect to the group position in excess of 5 percent of span (12 steps).
Therefore, since indication from one system is sufficient to maintain alignment within 24 steps, operation with one system (in the event of failure of the other) is acceptable.
The NRC staff has reviewed the independence of the control rod indication and concludes that VEGP has two independent systems that verify all rods are fully inserted.
The change in the SOM definition does not change continued compliance with all applicable regulatory requirements and design criteria (e.g., train separation, redundancy, and single failure). The change simply allows the elimination of a calculational assumption when it can be demonstrated by the two sources to not be applicable. All plant systems will continue to function as designed and all plant parameters will remain within their design limits.
Revising the TS definition of SOM would not require core designers to revise any SOM boron calculations. Rather, it would afford the analytical flexibility for determining SOM for a particular circumstance. The proposed change does not involve any change in the design, configuration, or operation of the nuclear plant. The current plant safety analyses remain complete and accurate in addressing the design basis events and in analyzing plant response and consequences. The LCOs, limiting safety system settings, and safety limits specified in the TSs are not affected by the proposed change. As such, the plant conditions for which the design basis accident analyses were performed are not changed.
Furthermore, margin of safety is related to confidence in the ability of the fission product barriers to perform their accident mitigation functions. These barriers include the fuel and fuel cladding, the RCS, and the containment and containment-related systems. The proposed changes will not impact the reliability of these barriers to function. Radiological doses to plant operators or to the public will not be impacted as a result of the proposed change. The change in the TS definition of SOM will have no impact to these barriers.
The NRC staff reviewed the licensee's submittals relative to the TSTF and STS and concludes that the proposed change meets 10 CFR 50.36 and is, therefore, acceptable.
Based on the above evaluation, the NRC staff concludes the licensee's proposed change to the TSs definition of SOM is acceptable.
3.14 TSTF-266-A, Revision 3, "Eliminate the Remote Shutdown System Table of Instrumentation and Controls" The NRC approved this change to STS Revision 1 on September 10, 1999. This traveler revised WOG STS 3.3.4 by removing a list of Remote Shutdown System instrumentation and controls from the TSs and placing them in the TS Bases.
TS LCO 3.3.4 currently states:
The Remote Shutdown System Functions in Table 3.3.4-1 shall be OPERABLE.
Revised TS LCO 3.3.4 would state:
The Remote Shutdown System Functions shall be OPERABLE.
The proposed change removes the LCO Table 3.3.4-1, "Remote Shutdown System Instrumentation and Controls," from the TSs, and places the table and its contents in the TS Bases.
NRC Staff Evaluation
The VEGP Remote Shutdown System provides the operator with sufficient instrumentation and controls to place and maintain the unit in a safe shutdown condition from a location other than the control room. This capability is necessary to protect against the possibility that the control room becomes inaccessible.
If the control room becomes inaccessible, the operators can establish control at the remote shutdown panel and place and maintain the unit in MODE 3. Not all controls and necessary transfer switches are located at the remote shutdown panel. Some controls and transfer switches will have to be operated locally at the switchgear, motor control panels, or other local stations. Table 3.3.4-1 lists the readout location, transfer switch location, and controls location for remote shutdown instrumentation. The proposed change would relocate these requirements to the TS licensee-controlled documents.
GDC-19 requires that remote shutdown capability be provided. The VEGP FSAR, Revision 19, Chapter 3, discusses the licensee's position on GDC 19 and states:
In the event that the operators are forced to abandon the control room, panel-mounted instrumentation and controls are provided on the train-related shutdown panels to achieve and maintain the plant in the safe shutdown condition.
Therefore, the NRC staff concludes that the relocation of instrumentation listed in TS Table 3.3.4-1 to the TS Bases will continue the licensee's compliance with its statement regarding operations of its remote shutdown functions, as the licensee has not proposed any change to its plans in this regard. The definition of "operable" in the VEGP specifications states that a system shall be operable or have operability when it is capable of performing its specified safety function(s) and when all necessary attendant instrumentation, controls, electrical power,
cooling and seal water, lubrication, and other auxiliary equipment that are required for the system to perform its specified safety function(s) are also capable of performing their related support function. This definition requires that all instrumentation and controls necessary for the remote shutdown function be operable in order for the Remote Shutdown System LCO to be met. The ability to transfer control of a function from the main control room to the remote shutdown panel is a required support function by the TS definition of operability. Therefore, LCO 3.3.4 is sufficient to ensure that the instruments and control circuits will be OPERABLE if unit conditions require that the Remote Shutdown System be placed in operation. SR 3.3.4.2 still requires the local panel transfer function to be tested, which is sufficient to assure that the system will be operable.
The relocation of the Remote Shutdown System table of instrumentation and controls from the TSs to the Bases is acceptable because it will be adequately controlled by NRC requirements in the TS 5.5.14 Bases control program. This approach provides an effective level of regulatory control and provides for a more appropriate change control process.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the NRC staff concludes that the changes are acceptable.
3.15 TSTF-272-A. Revision 1, "Refueling Boron Concentration Clarification" The NRC approved this change to STS Revision 1 on December 21, 1999. This traveler revised WOG STS 3.9.1, "Boron Concentration," to add an Applicability Note to clarify that boron concentration limits do not apply to the refueling canal and the refueling cavity when those volumes are not connected to the RCS.
TS LCO 3.9.1 currently states:
Boron concentrations of the Reactor Coolant System, the refueling canal, and the refueling cavity shall be maintained within the limit specified in the COLR.
The applicability of LCO 3.9.1 is revised by the addition of a note as follows:
N0 TE--------------------------------------------
0 n Iy applicable to the refueling canal and refueling cavity when connected to the RCS.
NRC Staff Evaluation
The licensee states that TS 3.9.1 limits the boron concentrations of the RCS, the refueling canal, and the refueling cavity during refueling to ensure that the reactor remains subcritical during MODE 6. The staff concludes that the proposed change is acceptable because boron concentration limits do not apply to the refueling canal and refueling cavity when these areas are not connected to the RCS, because any water in the refueling canal and refueling cavity
would not be in communication with the reactor fuel. For MODE 6, current VEGP TS SR 3.9.1.1 ensures that the coolant boron concentration in all filled portions of the RCS, the refueling canal, and the refueling cavity is within the COLR limits. The boron concentration of the coolant in each volume is determined periodically by chemical analysis. The licensee's revised SR 3.9.1.1 TS Bases state that if any dilution has occurred while the cavity or canal were disconnected from the RCS, this SR would ensure the correct boron concentration prior to communication with the RCS.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above evaluation, the NRC staff concludes the licensee's proposed change to the TSs is acceptable. In addition, the proposed change is consistent with guidance in the STS and approved TSTF-272.
3.16 TSTF-273-A. Revision 2. "Safety Function Determination Program Clarifications" The NRC approved TSTF-273-A, Revision 2, to STS Revision 1, as documented in a letter from William Beckner (NRC) to James Davis (NEI), dated August 16, 1999. This traveler modified STS 5.5.15, "Safety Function Determination Program (SFDP)," which implements the requirements of LCO 3.0.6.
TS 5.5.15, "Safety Function Determination Program (SFDP)," contains the following two separate paragraphs:
A loss of safety function exists when, assuming no concurrent single failure, a safety function assumed in the accident analysis cannot be performed. For the purpose of this program, a loss of safety function may exist when a support system is inoperable.
The SFDP identifies where a loss of safety function exists. If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.
The proposed change adds the following statements (shown in bold) in those paragraphs:
A loss of safety function exists when, assuming no concurrent single failure, no concurrent loss of offsite power or no concurrent loss of onsite diesel generator(s), a safety function assumed in the accident analysis cannot be performed. For the purpose of this program, a loss of safety function may exist when a support system is inoperable.
The SFDP identifies where a loss of safety function exists. If a loss of safety function is determined to exist by this program, the appropriate Conditions and
Required Actions of the LCO in which the loss of safety function exists are required to be entered. When a loss of safety function is caused by the inoperability of a single Technical Specification support system, the appropriate Conditions and Required Actions to enter are those of the support system.
The licensee explains the proposed changes as follows:
The proposed TS changes adds explanatory text to the LCO 3.0.6 Bases clarifying the appropriate LCO for loss of function, and that consideration does not have to be made for a loss of power in determining loss of function.
Explanatory text is also added to the programmatic description of the Safety Function Determination Program (SFDP) in Specification 5.5.15 to provide clarification of these same issues.
NRC Staff Evaluation
SNC proposed to revise TS 5.5.15 by incorporating TSTF-273-A, Revision 2, changes without deviations. The changes to TS 5.5.15, and the Bases for LCO 3.0.6, are intended to clarify the intent of LCO 3.0.6 in the event a single inoperable TS support system makes both redundant subsystems of a supported system inoperable (a loss of safety function condition). The STSs were developed such that the LCO Actions for a single support system inoperability would be addressed by that support system's Actions, without cascading to the supported system's LCO Actions. LCO 3.0.6 establishes this exception to LCO 3.0.2 for support systems that have an LCO specified in the TSs. However, LCO 3.0.6 also requires an evaluation under the SFDP to ensure that a loss of function does not exist.
The staff concludes that these changes do not affect the design, operation, or maintenance of VEGP, but only add clarification for determining when a loss of safety function condition exists and what LCO Actions are required to be taken when a safety function is lost. By clarifying the intent of the existing requirements of the SFDP and LCO 3.0.6, these changes remove an ambiguity that could lead to a misinterpretation of those requirements.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above, the NRC staff concludes the licensee's proposed change to the TSs is acceptable.
3.17 TSTF-284-A, Revision 3, "Add 'Met vs. Perform' to Technical Specification 1.4, Frequency" TSTF-284-A, Revision 3, was approved by the NRC as documented in a letter from William Beckner (NRC) to James Davis (NEI), dated February 16, 2000 (ADAMS Accession No. ML003684596). The change inserts a discussion paragraph into Specification 1.4, and several new examples are added to facilitate the use and application of SR Notes that utilize the
terms "met" and "perform." The changes also modify certain SRs to appropriately use the "met" and "perform" exceptions.
(a) TS 1.4 "Frequency," third paragraph, currently states:
Situations where a Surveillance could be required (i.e., its Frequency could expire), but where it is not possible or not desired that it be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. To avoid these conflicts, the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.
Revised TS 1.4 replaces the paragraph in its entirety with the following:
Sometimes special situations dictate when the requirements of a Surveillance are to be met. They are "otherwise stated" conditions allowed by SR 3.0.1.
They may be stated as clarifying Notes in the Surveillance, as part of the Surveillance, or both.
Situations where a Surveillance could be required (i.e., its Frequency could expire), but where it is not possible or not desired that it be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. To avoid these conflicts, the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.
The use of "met" or "performed" in these instances conveys specific meanings.
A Surveillance is "met" only when the acceptance criteria are satisfied. Known failure of the requirements of a Surveillance, even without a Surveillance specifically being "performed," constitutes a Surveillance not "met." The word "Performance" refers only to the requirement to specifically determine the ability to meet the acceptance criteria. Some Surveillances contain notes that modify the Frequency of performance or the conditions during which the acceptance criteria must be satisfied. For these Surveillances, the MODE-entry restrictions of SR 3.0.4 may not apply. Such a Surveillance is not required to be performed prior to entering a MODE or other specified condition in the Applicability of the associated LCO if any of the following three conditions are satisfied:
- a. The Surveillance is not required to be met in the MODE or other specified condition to be entered; or
- b. The Surveillance is required to be met in the MODE or other specified condition to be entered, but has been performed within the specified Frequency (i.e., it is current) and is known not to be failed; or
- c. The Surveillance is required to be met, but not performed, in the MODE or other specified condition to be entered, and is known not to be failed.
Examples 1.4-3, 1.4-4, 1.4-5, and 1.4-6 discuss these special situations.
(b) TS 1.4, "Frequency," currently includes examples up through Example 1.4-3 regarding the Frequency Based on a Specified Condition.
The change would add Examples 1.4-4, 1.4-5, and 1.4-6 on SRs, as shown in revised TS pages 1.4-6, 1.4-7, and 1.4-8 in the preceding attachment to this license amendment.
(c) TS SR 3.4.11.1 currently specifies the following requirement:
SURVEILLANCE FREQUENCY SR 3.4.11.1---------------------NOTE-------------------------- In accordance Not required to be performed with block valve closed in with the accordance with the Required Action of Conditions A, B, or Surveillance E. Frequency
Control Program Perform a complete cycle of each block valve.
In accordance SR 3.4.11.2 Perform a complete cycle of each PORV. with the Surveillance Frequency Control Program The change would add a NOTE (shown in bold) in SRs 3.4.11.1 and 3.4.11.2 as below:
SURVEILLANCE FREQUENCY SR 3.4.11.1---------------------NOTES-------------------------- In accordance with
- 1. Not required to be performed with block valve the Surveillance closed in accordance with the Required Actions Frequency Control of this LCO. Program
- 2. Only required to be performed in MODES 1 and 2.
Perform a complete cycle of each block valve.
SR 3.4.11.2---------------------NOTE-------------------------- In accordance with Only required to be performed in MODES 1 the Surveillance and 2. Frequency Control
-------------------------- Program Perform a complete cycle of each PORV.
(c) TS SR 3.4.12.4 NOTE currently states:
Only required to be performed when complying with LCO 3.4.12.b.
Revised TS SR 3.4.12.4 NOTE would state:
Only required to be met when complying with LCO 3.4.12.b.
(d) TS SR 3.9.4.2 NOTE currently states:
Only required for unisolated penetrations Revised TS SR 3.9.4.2 NOTE would state:
Not required to be met for containment purge and exhaust valve(s) in penetrations closed to comply with LCO 3.9.4.c.1.
The licensee explains the proposed changes as follows:
The change inserts a discussion paragraph into Specification 1.4, and several new examples are added to facilitate the use and application of SR Notes that utilize the terms "met" and "perform." The changes also modify SR 3.4.11.1, SR 3.4.11.2, SR 3.4.12.4, and SR 3.4.9.2 to appropriately use "met" and "perform" exceptions.
The licensee explains the differences between the proposed changes and the approved traveler as follows:
TSTF-284-A, Revision 3 includes changes to SR 3.1.11.1 and SR 3.1.11.2 of ISTS Specification 3.1.11, "SOM Test Exceptions." This LCO allows suspension of SOM requirements in MODE 2 provided specific conditions are met in order facilitate measurement control rod worth and SOM. The Vogtle Technical Specifications do not include a Specification that is analogous to ISTS TS 3.1.11, "SOM Test Exceptions," or SRs that are analogous to ISTS SRs 3.1.11.1 and 3.1.11.2. Therefore, the TS and Bases changes identified in TSTF-284-A for ISTS 3.1.11 are not adopted.
Changes to the Actions Bases for Specification 3.4.11, "Pressurizer PORVs,"
are not adopted. The changes described in the TSTF are related to a Note in the ISTS that provides an exception to LCO 3.0.4 that allows entry into MODES 1, 2, and 3 to perform cycling of the PORVs or block valves in order to demonstrate their operability. Consistent with NUREG-1431, Vogtle Technical Specification 3.4.11, and its associated Bases, do not include the Note providing this exception to LCO 3.0.4.
The Bases changes identified in TSTF-284-A for SR 3.4.12.8 is not adopted.
The Bases descriptions for corresponding Vogtle SR 3.4.12.4 is substantially different from the Bases text in TSTF-284-A, which is based on NUREG-1431, Revision 1. These differences result from the adoption of a Surveillance Frequency Control Program (SFCP), as described in TS 5.5.21, to control
periodic surveillance frequencies. Adoption of the SFCP included deletion of Bases text that provided the basis for surveillance frequency if control of the frequency had been moved to the SFCP. NRC approval of the license change implementing the SFCP was provided in Amendment Numbers 158/140, dated January 19, 2011 (ACN ML102520083).
NRC Staff Evaluation
The change in TSTF-284, Revision 3, is to modify Improved Technical Specifications, Section 1.4, "Frequency," to clarify the usage of the terms "met" and "performed" to facilitate the application of SR Notes. Three new SR Examples, 1.4-4, 1.4-5 and 1.4-6, are added to illustrate the application of the terms.
STS Section 1.4, "Frequency," defines the proper use and application of SR frequency requirements in the STS format. It states that, "An understanding of the correct application of the specified frequency is necessary for compliance with the SR." It also establishes that, "The specified frequency consists of the requirements of the frequency column of each SR as well as certain Notes in the Surveillance column that modify performance requirements." The purpose of TSTF-284, Revision 3, was to clarify, and make consistent, the use of Notes in the Surveillance column that modify frequency requirements as discussed below.
Specifically, this TSTF added the following language already contained in the two Boiling Water Reactor (BWR/4 and BWR/6) NU REGS, to STS Section 1.4 of the three PWR NU REGS (Babcock & Wilcox, Westinghouse and Combustion Engineering Pressurized Water Reactors, VEGP is a Westinghouse PWR facility):
Sometimes special situations dictate when the requirements of a Surveillance are to be met. They are "otherwise stated" conditions allowed by SR 3.0.1.
[SR 3.0.1 states "SRs shall be met during Modes or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR."] They may be stated as clarifying Notes in the Surveillance, as part of the Surveillance, or both.
Situations where a Surveillance could be required (i.e., its Frequency could expire), but where it is not possible or not desired that it be performed until sometime after the associated LCO is within its Applicability, represent potential SR 3.0.4 conflicts. [SR 3.0.4 states "Entry into a MODE or other specified condition in the Applicability of an LCO shall not be made unless the LCO's Surveillances have been met within their specified Frequency."] To avoid these conflicts, the SR (i.e., the Surveillance or the Frequency) is stated such that it is only "required" when it can be and should be performed. With an SR satisfied, SR 3.0.4 imposes no restriction.
The use of "met" or "performed" in these instances conveys specific meanings. A Surveillance is "met" only when the acceptance criteria are satisfied. Known failure of the requirements of a Surveillance, even without a Surveillance specifically being "performed," constitutes a Surveillance not "met."
"Performance" refers only to the requirement to specifically determine the ability to meet the acceptance criteria.
In addition, this change replaced existing language in all five NUREGS with the following clarification:
Some Surveillances contain Notes that modify the Frequency of performance or the conditions during which acceptance criteria must be satisfied. For these Surveillances, the Mode-entry restrictions of SR 3.0.4 may not apply. Such a Surveillance is not required to be performed prior to entering a Mode or other specified condition in the Applicability of the associated LCO if any of the following are satisfied:
- The Surveillance is not required to be met in the Mode or other specified condition to be entered; or
- The Surveillance is required to be met in the Mode or other specified condition to be entered, but has been performed within the specified Frequency (i.e., it is current) and is known not to be failed; or
- The Surveillance is required to be met, but not performed, in the Mode or other specified condition to be entered, and is known not to be failed.
Examples 1.4-3, 1.4-4, 1.4-5, and 1.4-6 discuss these special situations.
VEGP's proposed changes stated under the "licensee's proposed changes," above, refer to the NUREG guidance as mentioned above.
In adopting TSTF-284, Revision 3, a licensee must verify that Notes such as illustrated by these four examples are used properly and only as necessary. This includes ensuring the associated Bases are also correct. Proper application of these Notes in the individual SRs in the NUREGs was verified. The staff concludes that the proposed changes VEG P's adoption of the TSTF changes conforms to the guidance provided in the NUREGs described above. These changes are administrative in nature because they only serve to clarify the meanings of the terms "met" and "performed" as used in SR Notes throughout the VEGP TSs. This change serves to improve TS usefulness by clarifying terminology usage and providing additional examples of the application of SR Notes. Therefore, these changes are acceptable.
In addition to the changes discussed above, the licensee also proposed a change to the NOTE in SR 3.4.11.1, which currently states that the SR is not required to be performed with block valve closed in accordance with the Required Action of Conditions A, B, or E. The proposed change concerns deletion of Conditions A, B, or E from the NOTE in the SR. These conditions provide actions for the inoperability of one or more PORVs.
NRC Staff Assessment:
The staff reviewed the licensee's proposed change, the approved TSTF-284, and the STS. The staff considers the testing of the PORV block valve to be unnecessary, if the block valve has
been closed due to an inoperable PORV. The additional assurance of block valve operability gained from the surveillance test is outweighed by the risk associated with the development of an unisolable leak in the RCS. Accordingly, the provision of TSTF-284, Revision 3, which allows the extension of the range of circumstances under which the surveillance testing of the PORV block valve is not required for any of the Actions of TS 3.4.11, instead of limiting to Conditions A, B or E as currently specified in the SR, is acceptable as a change to VEGP TSs.
Therefore, the change to remove the surveillance testing under the specific conditions of the revised PORV block valve SR 3.4.11.1 of TS 3.4.11 is acceptable for VEGP.
Lastly, the staff review of the licensee's proposed addition of a new NOTE that SRs 3.4.11.1 and 3.4.11.2 are only required to be performed in MODES 1 and 2 is acceptable, since it allows the test to be performed in MODE 3 under operating temperature and pressure conditions prior to entering MODES 1 or 2.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO, and the appropriate remedial measures are specified if the LCO is not met.
Based on the above evaluation, the NRC staff concludes the licensee's proposed change to the TSs is acceptable. These changes are also consistent with the approved TSTF-284 changes as discussed in paragraph (c) above.
3.18 TSTF-308-A. Revision 1. "Determination of Cumulative and Projected Dose Contributions in RECP" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler modified WOG STS 5.5.4, "Radioactive Effluent Controls Program," to describe the original intent of the dose projections.
TS 5.5.4, paragraph 'e' currently states:
Determination of cumulative and projected dose contributions from radioactive effluents for the current calendar quarter and current calendar year in accordance'with the methodology and parameters in the ODCM at least every 31 days; Proposed change revises paragraph 'e' in its entirety as follows:
Determination of cumulative dose contributions from radioactive effluents for the current calendar quarter and current calendar year in accordance with the methodology and parameters in the ODCM at least every 31 days.
Determination of projected dose contributions from radioactive effluents in accordance with the methodology in the ODCM at least every 31 days;
NRC Staff Evaluation
Section 50.36(a) of 10 CFR, "Technical specifications on effluents from nuclear power reactors,"
requires each licensee to submit a report to the NRC that will allow an estimation of the maximum potential annual radiation doses to the public resulting from effluent releases.
Generic Letter (GL) 89-01, "Implementation of Programmatic and Procedural Controls for Radiological Effluent Technical Specifications," provides guidance in support of implementing programmatic controls in TSs for radioactive effluents and for radiological environmental monitoring that conforms to the applicable regulatory requirements. The regulation in 10 CFR 20.1302, "Compliance with dose limits for individual members of the public," paragraph (b), requires that a licensee show compliance with the annual dose limit in 10 CFR 20.1301, "Dose limits for individual members of the public," demonstrating by measurement or calculation that the total effective dose equivalent to the individual likely to receive the highest dose from the licensed operation does not exceed the annual dose limit.
GL 89-01 combined two SRs, the cumulative and projected dose determinations, into one program element. In combining these requirements, the new program element can be interpreted to require determining projected dose contributions for the calendar quarter and current calendar year every 31 days. This wording was misleading and resulted in misinterpretation of the intent of the original STS and was not consistent with the original surveillance. Therefore, TSTF-308-A was developed and subsequently approved by the NRC to not require dose projections for a calendar quarter and a calendar year every 31 days (i.e., to describe the actual intent of the dose projections).
VEGP TS 5.5.4, "Radioactive Effluent Controls Program," states that:
The program conforms to 10 CFR 50.36a for the control of radioactive effluents and for maintaining the doses to members of the public from radioactive effluents as low as reasonably achievable. The program shall be contained in the ODCM, shall be implemented by procedures, and shall include remedial actions to be taken whenever the program limits are exceeded.
TS 5.5.4.e is one of the elements in the program, which states:
Determination of cumulative and projected dose contributions from radioactive effluents for the current calendar quarter and current calendar year in accordance with the methodology and parameters in the ODCM at least every 31 days; The NRC staff reviewed the clarifications proposed by the licensee that were prepared using the guidance in TSTF-308 and concludes that the revised wording for the VEGP TSs clarifies the reporting requirements for projected doses, thus ensuring consistency with the requirements of 10 CFR 50.36a and 10 CFR 20.1302, and are, therefore, acceptable.
3.19 TSTF-312-A, Revision 1. "Administratively Control Containment Penetrations" The NRC staff decoupled TSTF-312 from its review under the current request to be processed by a separate amendment.
3.20 TSTF-314-A, Revision 0. "Require Static and Transient Fa Measurement" The NRC approved this change to STS Revision 1 on January 13, 1999. This traveler revised WOG STS LCO 3.1.5, "Rod Group Alignment Limits," and LCO 3.2.4, "Quadrant Power Tilt Ratio (QPTR)," to require measurement of both the steady state and transient portions of the Heat Flux Hot Channel Factor, Fa(Z). VEGP TS LCO 3.1.4, "Rod Group Alignment Limits," is equivalent to STS 3.1.5.
- Currently, when TS LCO 3.1.4, Condition B, for one rod not being within alignment limits, is not met, Required Action B.4 requires performing SR 3.2.1.1 to verify the steady state value of Fq(Z).
Revised Required Action B.4 by adding a requirement to perform SR 3.2.1.2 to verify the transient value of Fq(Z)
- Similarly for TS LCO 3.2.4, when Condition A of QPTR is not within its limit, Required Actions A.3 and A.6 currently require only the performance of SR 3.2.1.1 to verify the steady state value of Fq(Z).
Revised Required Actions A.3 and A.6 by adding a requirement to perform SR 3.2.1.2 to verify the transient value of Fq(Z).
NRC Staff Evaluation
The licensee proposes to add Required Actions to perform SR 3.2.1.2, which requires confirming that the transient component of the heat flux hot channel factor, Fq(z), is within its limits, to Condition B associated with TS LCO 3.1.4, "Rod Group Alignment Limits," and to Condition A associated with LCO 3.2.4, "Quadrant Power Tilt Ratio." The NRC staff review considers the acceptability of the proposed additions.
As the licensee notes, Fq(z) is approximated by both a steady-state and a transient component of Fq. The proposed Required Actions will modify the TS to include, along with the present requirement to verify the steady-state Fq is within limits, a new requirement to verify that the transient Fq. In conditions in which other LCOs may not be met (i.e., the LCOs for Rod Group Alignment Limits and QPTR), this added Required Action, in addition to other Required Actions in the specified condition, would ensure that the power distribution remains appropriately limited within the bounds of the safety analyses.
Since Fq(z) is approximated by both a transient and a steady-state component, the additional SR to confirm that the transient component is within its limits is consistent with 10 CFR 50.36 requirements. Specifically, the requirement to perform the proposed SRs will provide an additional remedial action to follow until the LCO can be met, consistent with
10 CFR 50.36(c)(2)(i). Since the proposed change will add a new remedial action, it is more restrictive than the existing TS requirements.
Based on the considerations that (1) the proposed Required Actions will be more restrictive than the existing TS, and (2) the proposed Required Actions are consistent with 10 CFR 50.36 requirements, the NRC staff determined that the addition of SR 3.2.1.2 to the Required Actions associated with Condition B for TS LCO 3.1.4, and Condition A for TS LCO 3.2.4, is acceptable.
3.21 TSTF-340-A. Revision 3. "Allow 7 Day Completion Time for a turbine-driven AFW pump inoperable" The NRC approved this change to STS NUREG-1431, Revision 1, on March 16, 2000. This traveler revised WOG STS 3.7.5, "Auxiliary Feedwater System, to extend Condition A CT to 7 days to restore an inoperable turbine-driven AFW steam supply, and to expand Condition A by adding an OR statement and a NOTE in the Condition. The added statement states, "One turbine driven AFW pump inoperable in MODE 3 following refueling, and the NOTE states, "Only applicable if MODE 2 has not been entered following refueling."
(As shown below, VEGP TS LCO 3.7.5 currently allows a CT of 7 days; therefore, this part of the TSTF change is not adopted by the licensee.)
VEGP TS 3.7.5, "Auxiliary Feedwater System, Condition A currently requires:
CONDITION REQUIRED ACTION COMPLETION TIME A. One steam supply to A.1 Restore steam supply 7 days turbine driven AFW pump to OPERABLE status.
The proposed change would add a statement and a NOTE in Condition A as shown in bold below:
CONDITION REQUIRED ACTION COMPLETION TIME A. One steam supply to A.1 Restore affected 7 days turbine driven AFW equipment to OPERABLE pump inoperable. status.
l'llOT'E: -------
Only applicable if MODE:
2 has not been entered following refueling.
One turbine driven AFW pump inoperable in MODE: 3 following refueling.
NRC Staff Evaluation
As stated above, the current VEGP TS already include the 7-day CT for one steam supply to a turbine driven AFW pump inoperable; therefore, that part of TSTF-340 is not the subject of this review.
However, the licensee proposed to modify TS 3.7.5, Condition A, so as to allow a 7-day CT for the turbine-driven AFW pump being inoperable in Mode 3, immediately following a refueling outage, if Mode 2 has not been entered. The purpose of the AFW system is to provide cooling water to the SGs for removal of decay heat when main feedwater flow is not available. This change was proposed on the basis that it could reduce the number of unnecessary mode changes by providing added flexibility in Mode 3 to repair and test the turbine-driven AFW pump, if the pump were to be declared inoperable following a refueling outage. In the proposed condition, there is minimal decay heat for the AFW system to have to remove through the SGs due to the time that irradiated fuel has decayed during the refueling outage and the replacement of irradiated fuel with un-irradiated fuel. The NRC staff agrees with that basis and concludes that the change is reasonable, given the redundant capabilities afforded by the AFW system, the time needed to perform repairs and testing of the turbine-driven pump, and the low probability of an accident occurring during this time period that would require the operation of the turbine-driven pump. In addition, there are alternate methods, such as feed and bleed, available to remove decay heat if necessary.
The NRC staff concludes that the requirements of 10 CFR 50.36(c)(2) continue to be met, because the minimum performance level of equipment needed for safe operation of the facility is contained in the LCO and the appropriate remedial measures are specified if the LCO is not met.
Based on the above evaluation, the staff concludes that this change is acceptable. It is also consistent with guidance in the STS and TSTF-340-A, Revision 3, because the applicable TSTF-340 changes have been incorporated into the VEGP TSs.
3.22 TSTF-343-A, Revision 1. "Containment Structural Integrity" The NRC approved this change to STS, Revision 1, on December 6, 2005. This traveler revised WOG STS 5.5.6, "Pre-Stressed Concrete Containment Tendon Surveillance Program,"
and STS 5.5.16, "Containment Leakage Rate Testing Program," for consistency with the requirements of 10 CFR 50.55a(g)(4). Per the application, (a) no change to VEGP TS 5.5.6 is proposed, and (b) VEGP TS 5.5.17 is equivalent to STS 5.5.16.
TS 5.5.17 currently specifies a program for the implementation of leakage rate testing of the containment with three exemptions.
The proposed change would add a fourth exception to the program as follows:
The visual examination of the steel liner plate inside containment intended to fulfill the requirements of 10 CFR 50, Appendix J, Option B, will be performed in accordance with the requirements of and frequency specified by the ASME
Section XI code, Subsection IWE, except where relief has been authorized by the NRC.
NRC Staff Evaluation
The licensee's proposed changes to the VEGP TS 5.5.17 are different from those contained in the traveler in that only a portion of these changes related to the visual inspection of the steel liner plate inside Containment will be adopted by this LAR. This was the subject of a request for additional information, and the licensee responded in its letter dated February 27, 2015. VEGP has previously adopted the other proposed changes by TSTF-343-A related to inspections of the containment tendons and the outside containment concrete surfaces. The NRC staff approval of the license amendment for adoption of the changes related to containment tendons was provided in Amendment Nos. 147/127, dated December 12, 2006 (ADAMS Accession No. ML062970484), and the license amendment for adoption of changes related to containment concrete surfaces was provided in Amendment Nos. 122/100, dated June 6, 2001 (ADAMS Accession No. ML011570674).
Specifically, the licensee proposed to change TS 5.5.17 by adding the following to the RG 1.163 exception list:
The visual examination of the steel liner plate inside containment intended to fulfill the requirements of 10 CFR 50, Appendix J, Option 8, will be performed in accordance with the requirements of and frequency specified by the ASME Section XI code, Subsection IWE, except where relief has been authorized by the NRC.
The proposed change would require the steel liner plate visual examination be performed pursuant to ASME Code,Section XI, Subsection IWE, rather than the visual inspection guidelines in RG 1.163. Subsection IWE requires the licensee to perform the general visual examinations of the containment liner three times in a 10-year interval, which is consistent with the current requirement specified in RG 1.163. The requirements for inspection in Subsection IWE of the ASME Code,Section XI, are more rigorous than those currently provided in RG 1.163. For the inspection of Class MC and metallic liners of Class CC components, the ASME Code requires that the examiner be knowledgeable in the requirements for design, inservice inspection, and testing of the components, and that examinations be performed by an examiner with visual acuity sufficient to detect evidence of degradation. In addition, Subsection IWE requires that the visual examinations be reviewed by an inspector employed by a State or municipality of the United States or an inspector regularly employed by an insurance company authorized to write boiler and pressure vessel insurance. The NRC staff concludes that the licensee is adopting more rigorous inspection requirements for the steel liner plate.
The NRC staff reviewed the licensee's submittals relative to the TSTF and STS and concludes that the proposed change meets 10 CFR 50.36.
Based on the above, the NRC staff concludes that the proposed TS change is acceptable.
3.23 TSTF-349-A. Revision 1. "Add Note to LCO 3.9.6 Allowing Shutdown Cooling (SOC)
Loops Removal from Operation" The NRC did not issue a letter approving this change to STS Revision 1; however, this change was incorporated by the NRC into Revision 2 of the STS issued in April 2001. This traveler revised WOG STS 3.9.6, "RHR and Coolant Circulation - Low Water Level," to add a Note to the LCO statement allowing securing the operating train of residual heat removal (RHR) for up to 15 minutes to support switching operating trains.
The proposed change adds a NOTE in TS LCO 3.9.6 as follows:
All RHR pumps may be de-energized for::;; 15 minutes when switching from one train to another provided:
- a. The core outlet temperature is maintained > 10 degrees F below saturation temperature;
- b. No operations are permitted that would cause a reduction of the Reactor Coolant System (RCS) boron concentration; and
- c. No draining operations to further reduce RCS water volume are permitted.
NRC Staff Evaluation
The RHR system is used to remove core decay heat and reactor coolant sensible heat during unit cooldown and cold shutdown and to provide adequate mixing of borated coolant. Currently, VEGP TS 3.9.6 requires two RHR loops to be operable and one in operation when a unit is in Mode 6 with < 23 feet of water above the top of the reactor vessel flange. The existing LCO 3.9.6 also contains a Note that allows operational status changes in the RHR system to support surveillance testing.
With the adoption of TSTF-349-A, the licensee proposed to add a second Note to allow all RHR pumps to be de-energized for up to 15 minutes when switching from one train to another. This is a short period of time to be in without coolant flow through the reactor core. The new Note includes three restrictions, as stated above, when entering this condition. These restrictions will minimize the risk while switching trains and will improve the likelihood that RHR will be safely restored.
Based on the above evaluation, which notes the short duration and the three limitations, the NRC staff concludes that the proposed changes meet the requirements of 10 CFR 50.36 and are acceptable. The proposed changes are consistent with the guidance in the STS, and TSTF-349-A, Revision 1, since the two notes in the TSTF have been incorporated into the VEGP TSs.
5.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Georgia State official was notified of the proposed issuance of the amendments. The State official had no comments.
6.0 ENVIRONMENTAL CONSIDERATION
The amendments change requirements with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes surveillance requirements. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such finding (80 FR 11480). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b),
no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
7.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributors: T. Tjader, NRO H. Le, NRO D. Scully, NRO R. Grover, NRR B. Martin, NRR Date: June 9, 2016
ML15132A569 OGC (NLO OFFICE DORLLPL2-1 /PM DORL/LPL2-1 /LA DSS/STSB/BC DORL/LPL2-1 /BC w/comments)
SFigueroa; NAME BMartin LRonewicz (06/09/16 RElliott MRing MMarkley overview)
DATE 06/02/16 07/08/15 02/24/16 03/15/16 06/09/16 OFFICE DSS/SRXB/BC DSS/SCVB/BC NRR/DORL/LPL2-1 /PM NAME CJackson, #20, 23 RDennia #4, 5, 22 BMartin DATE 10/19/15 11/02/15 06/09/16