ML23095A296
| ML23095A296 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 04/14/2023 |
| From: | Lauren Nist NRC/NRR/VPOB |
| To: | Brown K Southern Nuclear Operating Co |
| Shared Package | |
| ML23095A284 | List: |
| References | |
| EPID L-2022-LLR-0078 | |
| Download: ML23095A296 (1) | |
Text
Mr. Keith R. Brown, Director Regulatory Affairs Southern Nuclear Operating Company, Inc.
3535 Colonnade Parkway, Bin N-274-EC Birmingham, AL 35243
SUBJECT:
ALTERNATIVE INSPECTION REQUIREMENTS FOR STEAM GENERATOR NOZZLE TO REACTOR COOLANT PUMP CASING WELDS (VEGP 3&4-ISI1-ALT-17) (EPID L-2022-LLR-0078)
Dear Mr. Brown:
By letter dated November 4, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22308A156), Southern Nuclear Operating Company, Inc. (SNC or the licensee), submitted a request to the U.S. Nuclear Regulatory Commission (NRC) for the use of an alternative to certain American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (BPV Code),Section XI requirements at Vogtle Electric Generating Plant (VEGP), Units 3 and 4.
Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z)(1), the licensee requested the use of proposed alternative VEGP 3&4-ISI1-ALT-17 on the basis that the alternative provides an acceptable level of quality and safety.
The NRC staff has reviewed the subject request and concludes, as set forth in the enclosed safety evaluation, that SNC has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(1). Therefore, the staff authorizes the use of VEGP 3&4-ISI1-ALT-17 at VEGP Units 3 and 4 for the first ten-year inservice inspection interval. All other ASME BPV Code,Section XI requirements for which an alternative was not specifically requested and approved remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
In accordance with 10 CFR Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
April 14, 2023
K. Brown If you have any questions, please contact Cayetano Santos Jr., Project Manager at (301) 415-7270 or Cayetano.Santos@nrc.gov.
Sincerely, Lauren Nist, Acting Director Vogtle Project Office Office of Nuclear Reactor Regulation Docket Nos.: 52-025 and 52-026
Enclosure:
Safety Evaluation cc: Listserv Signed by Nist, Lauren on 04/14/23
ML23095A284; Ltr ML23095A296 OFFICE NRR/VPO/VPOB NRR/VPO/VPOB NRR/DNRL/NPHP NRR/DRO/IOLB NAME CSantos RButler MMitchell LNist DATE Apr 5, 2023 Apr 12, 2023 Apr 13, 2023 Apr 14, 2023