IR 05000317-09-004, 05000318-09-004 on 07/01/09 - 09/30/09 for Calvert Cliffs Nuclear Power Plant, Units 1 & 2
ML093130685
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 11/09/2009
From: Glenn Dentel
Reactor Projects Branch 1
To: Spina J
Calvert Cliffs, Constellation Energy Nuclear Group
Dentel, G RGN-I/DRP/BR1/610-337-5233
References
IR-09-004
Download: ML093130685 (29)


Text

UNITED STATES NUCLEAR REGULA TORY COMMISSION

REGION I

475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 November 09,2009 James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.

Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657-4702 SUBJECT: CALVERT CLIFFS NUCLEAR POWER PLANT - NRC INTEGRATED INSPECTION REPORT 05000317/2009004 AND 05000318/2009004

Dear Mr. Spina:

On September 30,2009, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Calvert Cliffs Nuclear Power Plant (CCNPP) Units 1 and 2. The enclosed inspection report documents the inspection results, which were discussed on October 14, 2009, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnol.

This report documents one NRC-identified finding of very low safety significance (Green). This finding was determined to involve a violation of NRC requirements. However, because the finding is of very low safety significance and because it is entered into your corrective action program (CAP), the NRC is treating this finding as a non-cited violation (NCV) consistent with Section V I. A. 1 of the NRC Enforcement Policy. If you contest any NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region 1, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC Resident Inspector at Calvert Cliffs. In addition, if you disagree with the characterization of any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region 1, and the NRC Resident Inspector at CCNPP. The information you provide will be considered in accordance with Inspection Manual Chapter (IMC) 0305. In accorclance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).

Sincerely, IRAJ Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-317, 50-318 License Nos.: DPR-53, DPR-69 Enclosure: Inspection Report 05000317/2009004 and 05000318/2009004 w/Attachment: Supplemental Information cc w/enc.l: Distribution via ListServ