IR 05000317/2021010
| ML21209A616 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 07/28/2021 |
| From: | Mel Gray Division of Operating Reactors |
| To: | Rhoades D Exelon Generation Co LLC, Exelon Nuclear |
| Gray M | |
| References | |
| IR 2021010 | |
| Download: ML21209A616 (16) | |
Text
July 28, 2021
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000317/2021010 AND 05000318/2021010
Dear Mr. Rhoades:
On June 25, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Calvert Cliffs Nuclear Power Plant, Units 1 and 2 and discussed the results of this inspection with Mr. Thomas P. Haaf, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Calvert Cliffs Nuclear Power Plant, Units 1 and 2.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Calvert Cliffs Nuclear Power Plant, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket Nos. 05000317 and 05000318 License Nos. DPR-53 and DPR-69
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000317 and 05000318
License Numbers:
Report Numbers:
05000317/2021010 and 05000318/2021010
Enterprise Identifier: I-2021-010-0026
Licensee:
Exelon Generation Company, LLC
Facility:
Calvert Cliffs Nuclear Power Plant, Units 1 and 2
Location:
Lusby, MD
Inspection Dates:
June 7, 2021 to June 25, 2021
Inspectors:
J. Brand, Reactor Inspector
P. Cataldo, Senior Reactor Inspector
G. Eatmon, Senior Resident Inspector
M. Patel, Senior Reactor Inspector
B. Pinson, Reactor Inspector
J. Schoppy, Senior Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Calvert Cliffs Nuclear Power Plant, Units 1 and 2, in accordance with the Reactor Oversight Process.
The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Failure to Follow Scaffold Construction Requirements in Close Proximity to Safety-Related Equipment Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000317/2021010-01 Open/Closed
[H.8] -
Procedure Adherence 71111.21M The team identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," because Exelon personnel did not adequately accomplish scaffold construction in the safety-related Unit 1 switchgear room in accordance with approved scaffold control procedures.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)
=
- (1) Unit 1 No. 11 Refueling Water Tank
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents/procedures
- Maintenance effectiveness and records, and corrective action history reflects current system conditions
- Calculations
- Operator Actions
- Surveillance testing and recent test results consistent with design basis calculations and test procedure acceptance criteria
- Equipment protection from fire, flood, and water intrusion or spray
The team used Appendix B guidance during the inspection.
- (2) Unit 1 No. 1A Emergency Diesel Generator
- Energy source verified for accident conditions
- Normal, abnormal, and emergency operating procedures available for decision-making
- Consistency among design and licensing bases and other documents/procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Component controls functional during accident conditions
- Equipment/environmental controls and qualification
- Operation and alignment of component consistent with licensing and design bases
- Operator actions that rely on instrumentation and alarms are available for decision-making
- Design calculations, assumptions and performance capability
- Surveillance testing and validation of recent test results
- Equipment protection (sealing of cable and conduits)
- Installed configuration of component will support design basis functions
- Inputs and outputs of the component acceptable during accident conditions
The team used Appendix B guidance during the inspection.
- (3) Unit 1 No. 12 Steam-Driven Auxiliary Feedwater Pump
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents/procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Design calculations
- Operator Actions
- Surveillance testing and recent test results
- Equipment protection from fire, flood, and water intrusion or spray
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System, during the inspection
- (4) Unit 2 No. 23 High Pressure Safety Injection Pump
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents/procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Equipment/environmental controls and qualification
- Operator Actions
- Design calculations
- Surveillance testing and recent test results
- Equipment protection (sealing of cable and conduits)
- Equipment protection from fire, flood, and water intrusion or spray
The team used Appendix B guidance for Valves, Instrumentation, and Electrical Loads, during the inspection.
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)
- (1) Unit 2 Power-Operated Relief Valve (PORV), 2-ERV-402
- Energy source verified for accident conditions
- Normal, abnormal, and emergency operating procedures available for decision-making
- Consistency among design and licensing bases and other documents/procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Control Logic; Component Inputs and outputs
- Equipment/environmental controls and qualification
- Operation and alignment of component consistent with licensing and design bases
- Design calculations, assumptions and performance capability
- Surveillance testing and validation of recent test results
- Equipment protection (sealing of cable and conduits)
The team used Appendix B guidance for Valves, Instrumentation, and As-Built System, during the inspection.
Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)
- (1) ECP-18-285, Update 120V/480V Breaker Coordination Calculations
- (2) ECP-19-391, 2-MOV-4516 Magnesium Motor Replacement
- (3) ECP-19-485, Pump/Motor Assembly Replacements for 1B, 2B, 2A Emergency Diesel Generators
- (4) ECP-19-658, Update Documents for Flooding in Emergency Core Cooling System Rooms
- (5) ECP-20-248, Generic Equipment Qualification Solution for Replacement of Rosemont Transmitter Model 3514N
Review of Operating Experience Issues (IP Section 02.06) (3 Samples)
- (1) IN 88-23, Potential for Gas Binding of High Pressure Safety Injection Pumps During Loss of Coolant Accidents
- (2) IN 2019-01, Inadequate Evaluation of Temporary Alterations
- (3) IN 2019-08, Flow-Accelerated Corrosion Events
INSPECTION RESULTS
Failure to Follow Scaffold Construction Requirements in Close Proximity to Safety-Related Equipment Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems
Green NCV 05000317/2021010-01 Open/Closed
[H.8] -
Procedure Adherence 71111.21M The team identified a Green finding and associated non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," because Exelon personnel did not adequately accomplish scaffold construction in the safety-related Unit 1 switchgear room in accordance with approved scaffold control procedures.
Description:
On June 7, 2021, during a plant barrier impairment walkdown in the Unit 1 45 switchgear room, the team noted that a scaffold (OL-021-033) erected on March 29, 2021, appeared to be in direct contact with conduit B1A4341 in at least two separate locations.
Engineering staff identified that the conduit in question was non-safety-related (NSR);however, since Exelons scaffold procedure clearly states that Scaffolding may NEVER directly contact any plant components, contact with the NSR conduit would still be contrary to the scaffold procedure guidance. During a follow-up scaffold walkdown on June 9, 2021, with the NRC inspector, Exelon engineering staff performed a close-up inspection of the conduit in question and identified that the adjacent scaffold pole was in direct contact in one of the two previously questioned locations. During this follow-up walkdown, the NRC inspector identified an additional location where the scaffold was in direct contact with safety-related equipment. Specifically, the 2 scaffold pole was in direct contact with the smaller 1/2 instrument air tubing associated with 1HVMS-3938A (11 atmospheric dump valve auxiliary shutdown control transfer hand valve) and 1HVMS-3938B (11 atmospheric dump valve quick open solenoid override hand valve). The team discussed the contact of the scaffold with safety-related equipment with the on-duty shift manager. The shift manager promptly directed scaffold builders to inspect and evaluate the scaffold. On June 10, 2021, the scaffold builders repositioned and adjusted the scaffold to establish at least a 1-inch clearance to all plant equipment. Engineering staff initiated corrective action issue report (IR) 4428640, Scaffold in Contact with Safety Related Equipment, for the condition adverse to quality.
Based on additional inspection, Exelon engineering staff determined that there was no observable damage to the instrument tubing. In addition, engineering staff concluded that, although in contact with the tubing, the installed scaffold restraints would have prevented the scaffolding from moving in the direction of the tubing and that the tubing would not have been damaged to the point of leakage during a seismic event. To bound this past operability assessment, engineering staff also evaluated the impact to plant operations given a tubing break at the contact location. Given a seismic event and plant trip, a tubing break at that location would likely result in diversion of air away from the positioner for air-operated valve 1CV3938, the 11 steam generator atmospheric dump valve (ADV), and failure of the ADV to open as designed during the plant transient. Although this would complicate the operators response to the event, the turbine bypass valves would remain available and the operators would still be able to operate the ADV manually. Additionally, a tubing break without a plant trip would result in a control room alarm for lowering air pressure and most likely addressed by operators through procedure AOP-7D, Loss of Instrument Air. The team acknowledged engineerings assessment; however, the inspectors concluded that the placement of the larger scaffold pole in direct contact with the smaller instrument tubing represented an increased probability of tubing failure during a seismic event.
The team identified that Exelon staff constructed and approved the scaffold contrary to the scaffold control procedure guidance. Specifically, MA-CA-796-024-1001, Calvert Rigging and Scaffold Control, Revision 7, Section 5.1 states Scaffold Builders shall maintain station-specific clearances from any plant equipment. See station-specific clearance attachments.
9, Station-Specific Clearance and Bracing Requirements, states that Scaffolding may NEVER directly contact any plant components. Contrary to this requirement, the scaffold builders erected the scaffold, and subsequently, engineering staff approved the scaffold, with direct contact between the scaffold and safety-related instrument tubing in the Unit 1 switchgear room.
Corrective Actions: Exelon personnel relocated the scaffold to ensure no direct contact with plant equipment and to ensure that the scaffold was adequately braced. Exelon personnel performed extent-of-condition walkdowns of accessible scaffolding throughout both units.
On June 23, 2021, engineering issued White Paper Response to the Scaffold Discrepancies Noted by the NRC during 2021 DBAI, in response to the teams question regarding apparent performance gaps in the scaffold building process.
Corrective Action References: IR 04428640
Performance Assessment:
Performance Deficiency: A scaffold was built and approved contrary to the scaffold control procedure guidance. Specifically, the scaffold was in direct contact with safety-related and NSR equipment in the Unit 1 45 switchgear room.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, direct contact between the larger scaffold poles and the smaller safety-related tubing increased the probability of tubing failure following a seismic event.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The team used IMC 0612, Appendix E, Examples of Minor Issues, to inform the screening. The team noted that the performance deficiency was similar to Example 4.a, in that the performance deficiency was associated with the design control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.
Specifically, the subsequent engineering evaluation confirmed that the affected safety-related tubing would be subject to seismic induced pipe loads that had not been considered in the original analysis and increased the probability of pipe failure during accident mitigation.
Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures, and work instructions. The team identified that Exelon personnel did not adequately accomplish scaffold construction in the safety-related Unit 1 switchgear room in accordance with approved scaffold control procedures.
Enforcement:
Violation: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, states that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.
Exelon procedure MA-CA-796-024-1001, Calvert Rigging and Scaffold Control, Revision 7, Section 5.1 states Scaffold Builders shall maintain station-specific clearances from any plant equipment. See station-specific clearance attachments. Attachment 9, Station-Specific Clearance and Bracing Requirements, states that Scaffolding may NEVER directly contact any plant components.
Contrary to the above, from March 29, 2021, to June 10, 2021, Exelon personnel constructed and maintained a scaffold with direct contact between the scaffold and safety-related instrument tubing in the Unit 1 switchgear room.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On June 25, 2021, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Thomas P. Haaf, Site Vice President and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
CA04581
Evaluation of Maximum HPSI and LPSI Flow for
Containment Response Evaluation
Revision 3
CA05689
Documentation of HPSI Pump Curve Use as an Input to
Design Bases Analysis
Revision 0
CA10120
Gas Accumulation Calculation on the High Points of SI and
CS Suction Piping for CCNPP Units 1 and 2
Revision 0
CA10121
Gas Accumulation Calculation on the High Points of SI and
CS Discharge Piping for CCNPP Units 1 and 2
Revision 0
E-88-015
Diesel Generator Loading Calculation
Revision 6
E-90-088
Protective Relay Setpoint Calculation for 480V Breakers
Revision
E-92-046
Diesel Generator LOCI and Shutdown Sequence Voltage
Profile
Revision 4
IC-88-15
Refueling Water Storage Tank Levels and Capacities
Revision 0
M-90-196
Time Response Calculation for Isolation of a Flooding Event
in the Aux Building and Intake Structure where the Room
Specific Indication for the Control Room
Revision 0
Corrective Action
Documents
2663759
2670533
2713145
03950294
04054643
04054778
04104640
04113592
04115510
04125536
04152920
04156632
04186249
04192991
230952
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
241742
242026
284726
04314005
04319825
04321068
04321267
04321510
04321540
04322504
04327390
04429419
04334605
04377208
04383082
04397735
04415554
04427334
04425600
Corrective Action
Documents
Resulting from
Inspection
04428088
04428181
04428393
04428429
04428436
04428444
04428455
04428609
04428610
04428615
04428632
04428640
04428775
04428795
04428797
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
04428798
04428881
04429394
04429396
04429397
04429398
04429482
04429620
04429723
04429925
04430117
04430166
04430775
04430793
04430847
04430849
04430850
04430874
04431022
04431098
04431361
04431408
04431496
04431527
04432138
Drawings
18002-
0083SH0043
Elementary Diagram Emergency Fast Start Signal
Revision 3
18002-
0083SH0053
Elementary Diagram EDG Breaker Tripping Signal and Cool
Down Cycle
Revision 2
18002-
0083SH0067
Elementary Diagram Normal and Emergency Shutdown
Signal
Revision 2
18002-
0083SH0071
Elementary Diagram Emergency Shutdown and Due to
Electrical Faults
Revision 3
61601SH0002
Turbine Building Barriers for SW Piping Plans, Sections, &
Revision 0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Details
Engineering
Changes
ECP-15-000727-
MU-02
Refueling Water Tank Level(s) and Capacity
Revision 1
ECP-16-000026
Replace Unit 1 and Unit 2 RWT Level Instrumentation
Revision 3
Miscellaneous
CC1R25
Calvert Cliffs Nuclear Power Plant, Flow Accelerated
Corrosion and Erosion Programs, 2020 Post Outage
Summary Report, Unit 1
05/08/2020
CC2R24
Calvert Cliffs Nuclear Power Plant, Flow Accelerated
Corrosion and Erosion Programs, 2021 Post Outage
Summary Report, Unit 2
04/14/2021
STP M-502-1
Calibration Check of #11 4kV Bus LOCI and Shutdown
Sequencer
2/22/21
STP M-651C-1A
SIAS and UV Trip Bypass Test for 1A Diesel Generator
5/28/21
STP O-4A-1
A Train Integrated Engineered Safety Features Test
3/7/20
STP O-5A12-1
Auxiliary Feedwater Pump Quarterly Surveillance Test
3/11/20
STP O-5A12-1
Auxiliary Feedwater Pump Quarterly Surveillance Test
6/25/20
STP O-5A12-1
Auxiliary Feedwater Pump Quarterly Surveillance Test
10/16/20
STP O-5A12-1
Auxiliary Feedwater Pump Quarterly Surveillance Test
4/20/21
STP O-73H-1
AFW Pump Large Flow Test
2/13/20
STP O-73H-1
AFW Pump Large Flow Test
3/11/20
NDE Reports
IHI Project 17-01-
443
Automated Ultrasonic Examination of the Reactor Water
Storage Tank at Calvert Cliffs Unit 1 Nuclear Power Plant
February
2018
Procedures
Plant Barrier Control Program,
Revision 13
OI-32A
Auxiliary Feedwater System
Revision 43
Work Orders
C93612835
C93614275
C93651457
C93686595
C93746932
C93746941
C93307532
C93660721
C93307532
C93201391
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
C93635797
C93602788
C91953304
C92348186
C92758110
C92814953
C93102316
C93449616
C93642803
C93646926
C93646932
C93659256
C93666007
C93700574
C93702793
C93702794
C93708238
C93722103
C93728052
C93728809
C93729482
C93742367
C93771781