August 15, 2023 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 0001 Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Patrick 0. Navin Site Vice President Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MO 20657 410-495-5200 Office 717-817-6827 Mobile www.constellation.com Pat.Navin@constellation.com Renewed Facility Operating License Nos. DPR-53 and DPR-69
Subject:
Notification of Readiness for NRC 95001 Inspection
References:
- 1. Letter from David C. Lew (NRC) to David P. Rhoades (Constellation Energy Generation, LLC), Calvert Cliffs Nuclear Power Plant, Unit 1 - Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2022090, dated December 5, 2022 (ADAMS Accession No. ML22314A100)
- 2. Letter from Patrick D. Navin (Constellation Energy Generation, LLC) to NRC Document Control Desk, Notification of Readiness for NRC 95001 Inspection, dated March 30, 2023 (ADAMS Accession No. ML23089A104)
- 3. Letter from Patrick D. Navin (Constellation Energy Generation, LLC) to NRC Document Control Desk, Notification of Readiness Postponement for NRC 95001 Inspection, dated May 18, 2023 (ADAMS Accession No. ML23139A084)
In the Reference 1 letter, Constellation Energy Generation, LLC (CEG) was informed of an escalated enforcement action, EA-22-089, associated with a preliminary White finding and apparent violation 05000317/2022090, a failure to implement foreign material exclusion (FME) practices in accordance with site procedures. In the Reference 1 letter, the NRC provided a final significance determination of a White finding and notice of violation.
In the Reference 2 letter, CEG informed the NRC on the readiness for the supplemental inspection. In the Reference 3 letter, due to the need to complete an additional causal analysis, CEG informed the NRC of the need to postpone the supplemental inspection and would inform the NRC in writing of readiness to perform the supplemental inspection.
This letter notifies the NRC that Calvert Cliffs is ready for the supplemental inspection.
Document Control Desk August 15, 2023 Page 2 There are no new regulatory commitments contained in this letter. If you should have any questions, please contact Mr. Larry Smith, Regulatory Assurance Manager, at 410-495-5219.
Patrick D. Navin Site Vice President PDN/LDS/aj f
cc:
USNRC Regional Administrator, Region I USNRC Senior Resident Inspector, CCNPP USNRC Project Manager, CCNPP S. Seaman, State of Maryland