MONTHYEARDCL-20-063, Pacific Gas & Electric Co - License Amendment Request 20-02, Non-Voluntary License Amendment Request to Revise Technical Specifications2020-08-31031 August 2020 Pacific Gas & Electric Co - License Amendment Request 20-02, Non-Voluntary License Amendment Request to Revise Technical Specifications Project stage: Request RS-20-114, License Amendment Request - Proposed Changes to Technical Specifications Sections 1.1, Definitions, and 5.0, Administrative Controls, for Permanently Defueled Condition2020-09-24024 September 2020 License Amendment Request - Proposed Changes to Technical Specifications Sections 1.1, Definitions, and 5.0, Administrative Controls, for Permanently Defueled Condition Project stage: Request RS-20-129, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 5 of 52020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 5 of 5 Project stage: Request ML20303A3252020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 2 of 5 Project stage: Request ML20303A3232020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 1 of 5 Project stage: Request ML20303A3272020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 4 of 5 Project stage: Request ML20303A3262020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition, Part 3 of 5 Project stage: Request DCL-20-092, License Amendment Request 20-03, Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition2020-12-0303 December 2020 License Amendment Request 20-03, Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition Project stage: Request ML21012A4432021-01-12012 January 2021 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request to Revise Technical Specification to Reflect the Permanent Cessation of Reactor Operation Project stage: Acceptance Review DCL-21-019, Supplement to License Amendment Request 20-03 Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition2021-04-0101 April 2021 Supplement to License Amendment Request 20-03 Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition Project stage: Supplement ML21104A3642021-04-14014 April 2021 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition Project stage: RAI ML21264A6722021-09-21021 September 2021 NRR E-mail Capture - Revised Schedule: Diablo Canyon Request to Revise Technical Specification to Reflect the Permanent Cessation of Reactor Operation Project stage: Other DCL-22-001, Supplement to License Amendment Request 20-03, Editorial Corrections to Diablo Canyon Power Plant Units 1 and 2 Operating Licenses2022-01-13013 January 2022 Supplement to License Amendment Request 20-03, Editorial Corrections to Diablo Canyon Power Plant Units 1 and 2 Operating Licenses Project stage: Supplement ML22152A1502022-06-21021 June 2022 Request for Additional Information Regarding License Amendment Request for Technical Specifications and Revised License Conditions for the Permanently Defueled Condition Project stage: RAI DCL-22-058, Responses to NRC Requests for Additional Information on LAR 20-03, Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition2022-07-20020 July 2022 Responses to NRC Requests for Additional Information on LAR 20-03, Proposed Technical Specifications and Revised License Conditions for the Permanently Defueled Condition Project stage: Response to RAI ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 Project stage: Approval ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 Project stage: Other 2021-04-14
[Table View] |
Text
July 13, 2023 Mr. David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 -
CORRECTION TO THE RENEWED FACILITY OPERATING LICENSE PAGES IN AMENDMENT NOS. 336 AND 314 (EPID L-2020-LLA-0261)
Dear Mr. Rhoades:
The U.S. Nuclear Regulatory Commission (NRC) staff has identified a typographical error in Renewed Facility Operating License (RFOL) No. DPR-53, Calvert Cliffs Nuclear Power Plant (Calvert Cliffs), Unit 1, and RFOL DPR-69 for Calvert Cliffs, Unit 2. The NRC staff is issuing this letter to correct an error per the guidance in the NRC memorandum dated January 16, 1997 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML103260096), which is derived from the Staff Requirements Memorandum (ML003754054) for SECY-96-238 (ML20134M324, non-public).
By letter dated August 13, 2020 (ML20182A194), the NRC staff issued Amendment Nos. 336 to RFOL DPR-53 for Calvert Cliffs, Unit 1, and Amendment 314 for RFOL DPR-69 for Calvert Cliffs, Unit 2, in response to license amendment request dated November 21, 2019, as supplemented by letter dated April 16, 2020 (ML19325C128 and ML20107F765, respectively) from Exelon Generation Company, LLC which has been subsequently renamed Constellation Energy Generation, LLC.
The typographical error inadvertently listed the approved technical specification (TS) amendment number for Calvert Cliffs, Unit 1, in the bottom right-hand corner of TS page 5.5-10 as 316 instead of 336.
To correct this error, NRC staff replaced 316 with 336 on the bottom right corner.
The enclosure to this letter has a copy of the revised and corrected RFOL DPR-53 and DPR -69 page 5.5-10.
If you have any questions, please contact me at 301-415-0489 or by email to Sujata.Goetz@nrc.gov.
Sincerely,
/RA/
Sujata Goetz, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318
Enclosure:
Corrected RFOL No. DPR-53 and DPR-69 Page 5.5-10 cc: Listserv
Programs and Manuals 5.5 5.5 Programs and Manuals CALVERT CLIFFS - UNIT 1 5.5-10 Amendment No. 336 CALVERT CLIFFS - UNIT 2 Amendment No. 314 This constitutes the fourth and subsequent inspection periods.
- 3.
If crack indications are found in any SG tube, then the next inspection for each affected and potentially affected SG for the degradation mechanism that caused the crack indication shall not exceed 24 effective full power months or one refueling outage (whichever results in more frequent inspection). If definitive information, such as from examination of a pulled tube, diagnostic non-destructive testing, or engineering evaluation indicates that a crack-like indication is not associated with a crack(s), then the indication need not be treated as a crack.
- e.
Provisions for monitoring operational primary to secondary LEAKAGE.
5.5.10 Secondary Water Chemistry Program This program provides controls for monitoring secondary water chemistry to inhibit steam generator tube degradation and low pressure turbine disc stress corrosion cracking. The program shall include:
- a.
Identification of a sampling schedule for the critical variables and control points for these variables;
- b.
Identification of the procedures used to measure the values of the critical variables;
- c.
Identification of process sampling points which shall include monitoring the discharge of the condensate pumps for evidence of condenser in leakage;
- d.
Procedures for the recording and management of data;
- e.
Procedures defining corrective actions for all off control point chemistry conditions; and
ML23188A051 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA OGC - NLO NAME SGoetz KEntz MCarpentier DATE 06/7/2023 07/13/2023 07/13/2023 OFFICE NRR/DORL/LPL1/BC NRR/DORL/LPL1/PM NAME HGonzalez SGoetz DATE 07/13/2023 07/13/2023