Integrated Inspection Report 05000317/2021001 and 05000318/2021001
ML21124A037
Person / Time
Site: Calvert Cliffs  
Issue date: 05/04/2021
From: Matt Young
Division of Operating Reactors
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
Young M
References
IR 2021001
Download: ML21124A037 (15)


See also: IR 05000317/2021001

Text

May 4, 2021

Mr. David P. Rhoades

Senior Vice President

Exelon Generation Company, LLC

President and Chief Nuclear Officer

Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 -

INTEGRATED INSPECTION REPORT 05000317/2021001 AND

05000318/2021001

Dear Mr. Rhoades:

On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at Calvert Cliffs Nuclear Power Plant, Units 1 and 2. On April 9, 2021, the NRC inspectors

discussed the results of this inspection with Mr. Thomas Haaf, Site Vice President and other

members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be Severity Level IV is documented in

this report. We are treating this violation as a non-cited violation (NCV) consistent with Section

2.3.2 of the Enforcement Policy. The NRC will not conduct a follow-up inspection for this

violation because it does not involve any of the initiating criteria in Inspection Procedure 92702,

Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory

Action Letters, and Orders."

If you contest the violation or the significance or severity of the violation documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at

Calvert Cliffs Nuclear Power Plant, Units 1 and 2.

D. Rhoades

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

X /RA/

Signed by: Matthew R. Young

Matt R. Young, Chief

Reactor Projects Branch 5

Division of Operating Reactor Safety

Docket Nos. 05000317 and 05000318

License Nos. DPR-53 and DPR-69

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML21124A037

x

SUNSI Review

x

Non-Sensitive

Sensitive

x

Publicly Available

Non-Publicly Available

OFFICE RI/DORS

RI/DORS

RI/DORS

NAME

DBeacon

LCline

MYoung

DATE

5/4/21

5/4/21

5/4/21

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000317 and 05000318

License Numbers:

DPR-53 and DPR-69

Report Numbers:

05000317/2021001 and 05000318/2021001

Enterprise Identifier: I-2021-001-0101

Licensee:

Exelon Generation Company, LLC

Facility:

Calvert Cliffs Nuclear Power Plant, Units 1 and 2

Location:

Lusby, MD

Inspection Dates:

January 1, 2021 to March 31, 2021

Inspectors:

H. Anagnostopoulos, Senior Health Physicist

D. Beacon, Resident Inspector

R. Clagg, Senior Resident Inspector

L. Cline, Senior Project Engineer

N. Floyd, Senior Reactor Inspector

S. Obadina, Resident Inspector

Approved By:

Matt R. Young, Chief

Reactor Projects Branch 5

Division of Operating Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Calvert Cliffs Nuclear Power Plant,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight

Process is the NRCs program for overseeing the safe operation of commercial nuclear power

reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A

licensee-identified non-cited violation is documented in report section: 71152.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

3

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period.

Unit 2 began the inspection period at rated thermal power and was operated at or near full

power until February 28 when the unit was shut down for a planned refueling outage. Following

refueling, Unit 2 was restarted and began power ascension on March 20. On March 21 during

power ascension, the unit was tripped from 38 percent power due to a steam generator

feedwater regulating valve mechanical failure. Following completion of valve repairs, Unit 2 was

restarted on March 23 and operated at or near full power through the end of the inspection

period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed plant status activities described in

IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem

Identification and Resolution. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

Starting March 20, 2020, in response to the National Emergency declared by the President of

the United States on the public health risks of the coronavirus (COVID-19), resident and

regional inspectors were directed to begin telework and to remotely access licensee information

using available technology. During this time the resident inspectors performed periodic site visits

each week, increasing the amount of time on site as local COVID-19 conditions permitted. As

part of their onsite activities, resident inspectors conducted plant status activities as described in

IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of

IPS. In addition, resident and regional baseline inspections were evaluated to determine if all or

portion of the objectives and requirements stated in the IP could be performed remotely. If the

inspections could be performed remotely, they were conducted per the applicable IP. In some

cases, portion of an IP were completed remotely and on site. The inspections documented

below met the objections and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

Unit 1, 13 auxiliary feedwater pump during 12 auxiliary feedwater pump out of service

for quarterly surveillance testing, January 22, 2021

(2)

Unit 2, 2B emergency diesel generator while 21 saltwater header is out of service for

maintenance, January 26, 2021

4

(3)

Unit 2, 22 saltwater header while the 21 saltwater header is out of service for

maintenance, March 9, 2021

(4)

Unit 2, spent fuel pool cooling during fuel shuffle, March 11, 2021

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Unit 1, cable spreading room and battery rooms, fire areas 16, 16A, and 16B,

January 8, 2021

(2)

Unit 2, cable spreading room and battery rooms, fire areas 17, 17A, and 17B,

January 15, 2021

(3)

Unit 2, turbine building, fire area TB, March 6, 2021

(4)

Unit 2, containment, fire area CNMT, March 10, 2021

(5)

Unit 1, turbine building, fire area TB, March 16, 2021

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated the onsite fire brigade training and performance during an

unannounced drill on March 1, 2021.

71111.08P - Inservice Inspection Activities (PWR)

PWR Inservice Inspection Activities Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors verified that the reactor coolant system boundary, steam generator

tubes, reactor vessel internals, risk-significant piping system boundaries, and

containment boundary are appropriately monitored for degradation and that repairs

and replacements were appropriately fabricated, examined and accepted by

reviewing the following activities from March 1 to March 23, 2021:

03.01.a - Nondestructive Examination and Welding Activities

Manual ultrasonic testing of the pressurizer surge line nozzle, 4-404 (NDE

Report ISI-UT-016).

Manual ultrasonic testing of the pressurizer pipe to safe end weld, 4-PS-2003-

7 (NDE Report ISI-UT-008).

Manual ultrasonic testing of the safety injection pipe to valve weld, 12-SI-

2012-7 (NDE Report ISI-UT-015).

Liquid penetrant testing of the 21 reactor coolant pump support lug, 21A-2

(NDE Report ISI-PT-003).

Visual examinations of the core shroud tie-rods #1 through #8 (NDE Report

ISI-VT-144).

Visual examinations of the containment accessible surfaces, including the

liner, leak chase channels, and moisture barrier (WO C93732456).

Welding activities associated with the repair of the pressurizer heater sleeve

penetration G-1 under engineering change ECP-21-000102

5

(WO C91977390). This repair was in response to leakage identified during

the visual examination of the pressurizer heater sleeves in accordance with

American Society of Mechanical Engineers Code Case N-722-1 (NDE Report

ISI-VT-051).

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination

Activities

Follow-up review of head penetrations 72 and 73 subjected to bare metal

visual examinations as required in response to previous examination results

(NDE Report ISI-VT-134).

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities

Boric acid evaluation for 2CV517 on the core spray system (IR 04405537).

Boric acid evaluation for the reactor vessel head flange (IR 04406312).

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed and evaluated licensed operator performance in the Control

Room during the shutdown of Unit 2 for the refueling outage on March 1, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed operator simulator training involving the loss of a low

pressure safety injection pump, loss of offsite power, and leak on a shutdown cooling

heat exchanger on February 2, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1)

Unit 2, AR04399180, 2CV110Q letdown control valve failure to shut, March 22, 2021

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to

ensure the following SSC remains capable of performing its intended function:

(1)

Unit 2, WO C93721752, 21 saltwater header out of service due to replacement of

2CV5150, 21 A/B service water heat exchanger saltwater inlet, February 24, 2021

6

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1)

Unit 2, elevated risk condition due to preventive maintenance on the 21A service

water heat exchanger, January 13, 2021

(2)

Unit 2, elevated risk condition due to 22 emergency core cooling system pump room

air cooler maintenance, January 21, 2021

(3)

Unit 2, elevated risk condition due to 21 saltwater header out of service for

maintenance, January 27, 2021

(4)

Unit 2, Yellow risk condition due to having four containment air coolers out of service,

March 5, 2021

(5)

Unit 2, Yellow risk condition due to lowered inventory for reactor pressure vessel

head installation, March 14, 2021

(6)

Unit 2, Yellow risk condition due to reduced inventory for reactor coolant system

vacuum fill, March 18, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

Unit 1, AR04393743, 1MOV6200OP, fire protection containment isolation valve,

degraded grease, Grade 3, January 12, 2021

(2)

Unit 2, AR04395519, Unit 2 containment outage door penetration 13 leaking

excessively, January 13, 2021

(3)

Units 1 and 2, AR04396365, 0-FP-110, 12 diesel fire pump discharge valve packing

leak, January 21, 2021

(4)

Unit 2, AR04396969, Unit 2 cable spreading room supply damper not functioning

properly, January 21, 2021

(5)

Unit 2, AR04395583, technical evaluation to remove high energy line break barrier

plug for draining of the 21 charging and volume control system letdown filter to

support basket inspection, February 16, 2021

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)

ECP-17-000734, air operated valve/containment isolation valve vulnerability

reduction, March 24, 2021

(2)

ECP-21-000102, Unit 2 pressurizer heater sleeve penetration G-1 plug repair,

March 22, 2021

7

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system

operability and functionality:

(1)

Unit 2, WO C93721752, 21 saltwater header out of service due to replacement of

CV5150, 21 A/B service water heat exchanger inlet valve, January 28, 2021

(2)

Unit 2, WO C93720690, preventative maintenance on 2MOV269OP, safety injection

to charging header motor operated valve, January 29, 2021

(3)

Unit 2, WO C93705327, 23 auxiliary feedwater pump bearing replacement, March 24,

2021

(4)

Unit 2, WO C92676514, 21 high pressure safety injection pump bearing replacement,

March 31, 2021

(5)

Unit 2, WO C93092012, 21 low pressure safety injection pump discharge check valve

maintenance, March 31, 2021

(6)

Unit 2, WO C93704701, 21 auxiliary feedwater governor valve and throttle/stop valve

maintenance, March 31, 2021

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated refueling outage 2R24 activities from February 28, 2021 to

March 26, 2021.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01) (5 Samples)

(1)

Unit 2, I-131-2, "Leak Rate Testing of Containment Outage Door (COD) Seals and

Penetrations," Revision 003, January 12, 2021

(2)

Unit 2, STP-M-698-2, "Functional Test of Halon System for Cable Spreading Room,"

Revision 003, January 21, 2021

(3)

Unit 2, STP-O-8B-2, "Test of 2B Diesel Generator and 4kV Bus 24 Undervoltage,"

Revision 03404, January 21, 2021

(4)

STP-O-8A-1, "Test of 1A Diesel Generator and 11 4kV Bus Undervoltage," Revision

33, February 24, 2021

(5)

Unit 1, STP-O-8B-1, "Test of 1B Diesel Generator and 14 4kV Bus Undervoltage,"

Revision 35, March 31, 2021

Inservice Testing (IP Section 03.01) (2 Samples)

(1)

Unit 1, STP-O-5A12-1, "12 Auxiliary Feedwater Pump Quarterly Surveillance Test,"

Revision 8, January 22, 2021

(2)

Unit 2, STP-O-5A23-2, "23 Auxiliary Feedwater Pump Quarterly Surveillance

Test," Revision 0, February 17, 2021

8

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)

Unit 2, STP-O-108D38-2, "Containment Penetration 38 Local Leak Rate Tests,"

Revision 0, March 15, 2021

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels and the concentrations and quantities of radioactive materials and

how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to

access high radiation areas.

(1)

The inspectors reviewed the following:

Radiation Work Packages

CC-2-21-00401

CC-2-21-00613

CC-2-21-00503

Electronic Alarming Dosimeter Alarms

No alarms occurred during the period of this inspection]

Labeling of Containers

Boxes in the storage yard adjacent to the Unit 2 butler building

Resin drums in the Unit 2 69' truck bay

Storage box for a tri-nuke filtration system in the solid waste processing area

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination

and radioactive material.

(1)

The inspectors verified the following sealed sources are accounted for and are intact:

03C24

(2)

The inspectors verified the following sealed sources are accounted for and are intact:

CZ2578

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and

observation of radiological work activities.

9

(1)

The inspectors also reviewed the following radiological work package for areas with

airborne radioactivity:

CC-2-21-00613

(2)

The inspectors also reviewed the following radiological work package for areas with

airborne radioactivity:

CC-2-21-00503

(3)

The inspectors also reviewed the following radiological work package for areas with

airborne radioactivity:

CC-2-21-00617

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very

High Radiation Areas:

(1)

Unit 2 personnel airlock

(2)

Unit 1 monitored waste retention tank room

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section

03.06) (1 Sample)

(1)

The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (5 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant

walkdowns:

(1)

REM Ball S/N 0024399

(2)

Telepole S/N 0017242

(3)

RO-20 S/N 0021939

(4)

Ludlum 9-4 S/N 0023359

(5)

3030P S/N 0018429

Calibration and Testing Program (IP Section 03.02) (11 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection

instruments:

(1)

FASTSCAN whole body counter in the dosimetry office

(2)

TriCarb 3100TR Liquid Scintillation Counter in the chemistry lab

(3)

Containment High Range Radiation Monitor (1RE5317A)

(4)

Containment High Range Radiation Monitor (2RE5317A)

(5)

Containment High Range Radiation Monitor (1RE5317B)

(6)

Containment High Range Radiation Monitor (2RE5317B)

(7)

REM Ball S/N 0024399

(8)

Telepole S/N 0017242

10

(9)

RO-20 S/N 0021939

(10)

Ludlum 9-4 S/N 0023359

(11)

3030P S/N 0018429

Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive

effluent monitoring and measurement instrumentation:

(1)

Unit 2 Wide Range Gas Monitor (2-RE-5415)

(2)

Gas & liquid waste discharge radiation monitor flow elements (0FT2192 and

0FT2199)

(3)

Waste processing exhaust filter HEPA test and flow verification

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 03.10) (2 Samples)

(1)

Unit 1, January 1, 2020 - December 31, 2020

(2)

Unit 2, January 1, 2020 - December 31, 2020

BI02: RCS Leak Rate Sample (IP Section 03.11) (2 Samples)

(1)

Unit 1, January 1, 2020 - December 31, 2020

(2)

Unit 2, January 1, 2020 - December 31, 2020

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation

71152

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: The Calvert Cliffs Unit 1 and Unit 2 renewed facility operating licenses, DPR-53

and DPR-69, Appendix C, contain a license condition, implemented under License

Amendment 237, that requires, in part, that the established decommissioning trust

agreement must provide that no disbursements or payments from the trust shall be made by

the trustee until the trustee has first given the NRC 30-days prior written notice of payment.

Contrary to the above, on five occasions between 2017 and 2020, Exelon enacted

disbursements from the Calvert Cliffs Units 1 and 2 decommissioning trust funds and the

trustee had not first given the NRC 30-days prior written notice of payment.

Significance/Severity: Severity Level IV. The NRC traditional enforcement process applies to

this violation because the violation represents an impact to the regulatory process (i.e. failure

to notify the NRC of changes in licensed activities). The significance of this violation was

evaluated per the NRC enforcement policy and was determined to be Severity Level IV

because the disbursements made were legitimate decommissioning planning

11

expenses and prior written notice, as required, would not have likely caused the NRC to

reconsider its regulatory position or undertake substantial further inquiry.

Corrective Action References: AR04410080, ML21089A302

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 9, 2021, the inspectors presented the integrated inspection results to

Mr. Thomas Haaf, Site Vice President and other members of the licensee staff.

On January 22, 2021, the inspectors presented the radiation monitoring instrumentation

inspection results to Mr. Thomas Haaf, Site Vice President and other members of the

licensee staff.

On March 5, 2021, the inspectors presented the radiological hazard assessment and

exposure controls inspection results to Mr. Thomas Haaf, Site Vice President and other

members of the licensee staff.

On March 23, 2021, the inspectors presented the inservice inspection activities

inspection results to Mr. Thomas Haaf, Site Vice President and other members of the

licensee staff.

12

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P Corrective Action

Documents

IR 04406378

IR 04407741

IR 04408803

Corrective Action

Documents

Resulting from

Inspection

IR 04411160

Drawings

02-8126886

Calvert Cliffs Unit 2 Pressurizer Penetration G1 Plug

Implementation

Revision 0

and 2

Miscellaneous

ER-CA-330-1001

ISI program Plan Fifth Ten-Year Inspection Interval

Revision 2

Procedures

55-

WP43/43/F43AW1

Welding Procedure Specification for manual GTAW of P-

Number 43 base materials with F-Number 43 filler materials

Revision 11

and 12