Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2018006)
ML19063B496
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/04/2019
From: Julio Lara
Division Reactor Projects III
To: Hamilton D B
FirstEnergy Nuclear Operating Co
References
IR 2018006
Download: ML19063B496 (6)


Text

March 4, 2019

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR PERRY NUCLEAR POWER PLANT April 1, 2018

subject

to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. In April and May 2020, the NRC will conduct a triennial Design Bases Assurance Inspection (Team) and in November 2019 a biennial Problem Identification and Resolution team inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading

-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Please contact Dariusz Szwarc at 630-829-9803 with any questions you have regarding this letter.

Sincerely,

/RA Robert Orlikowski Acting for

/ Julio Lara, DRP Division Director Region III Division of Reactor Projects Docket No. 50

-440 License No. NPF

-58 Enclosure:

Inspection Plan cc: Distribution via LISTSERV