11/15/2018 Summary of Teleconference with Entergy Operations, Inc. License Amendment Request for Use of Tranflow Code for Determining Pressure Drops Across the Steam Generator Secondary Side Internal Components
ML18323A421
Person / Time
Site: Waterford Entergy icon.png
Issue date: 11/26/2018
From: Pulvirenti A L
Plant Licensing Branch IV
To:
Entergy Operations
Pulvirenti A L, 415-1390
References
EPID L-2018-LLA-0112
Download: ML18323A421 (4)


Text

LICENSEE:

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, 0.C. 20555-0001 November 26, 2018 Entergy Operations, Inc. FACILITY:

Waterford Steam Electric Station, Unit 3

SUBJECT:

SUMMARY

OF NOVEMBER 15, 2018, TELECONFERENCE WITH ENTERGY OPERATIONS, INC. REGARDING LICENSE AMENDMENT REQUEST FOR USE OF THE TRANFLOW CODE FOR DETERMINING PRESSURE DROPS ACROSS THE STEAM GENERATOR SECONDARY SIDE INTERNAL COMPONENTS (EPID L-2018-LLA-0112)

On November 15, 2018, a Category 1 partially closed public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Waterford Steam Electric Station (Waterford), Unit 3; Entergy Operations, Inc.; and Westinghouse (the licensee).

The teleconference notice and agenda, dated November 2, 2018, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 18311A306.

A list of attendees is enclosed with this summary. The NRC staff provided a list of draft requests for additional information (RAI) (ADAMS Accession No. ML 18299A086) for discussion.

The purpose of the teleconference was to discuss details of, and potential responses to, the draft RAls. While the draft RAls were made publicly available, the detailed discussion of the responses was expected to contain proprietary information, such as trade secrets as referenced in Title 10 of the Code of Federal Regulations Section 2.390(a)(4).

Therefore, the teleconference was partially closed to the public. During the public portion of the teleconference, the licensee requested a 60-day time period to provide a response to the final RAI. The licensee stated that extra time would be needed to provide responses because a large amount of research was necessary to provide an adequate response to the questions.

In addition, Waterford, Unit 3, is diverting resources to prepare for a refueling outage scheduled to begin in January 2019; therefore, fewer licensees were available to prepare the response.

The NRC staff tentatively agreed to a 60-day response time. The teleconference was then opened to public comment. No members of the public provided comments.

The teleconference was then closed to the public. During the closed portion of the teleconference, the NRC staff explained the nature of the RAls in more detail. The licensee, including Westinghouse staff, verbally responded with potential answers. The NRC staff and the licensee then discussed technical aspects of the responses and whether the intent of the answers provided appropriately pertained to the intent of the question.

No regulatory decisions were made regarding the technical adequacy of the licensee's responses.

No members of the public called in to listen or provide comments to the staff after the business portion of the teleconeference. Please direct any inquiries to me at 301-415-1390 or April.Pulvirenti@nrc.gov.

Docket No. 50-382

Enclosure:

List of Attendees cc: Listserv April Pulvirenti, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES NOVEMBER 15, 2018, TELECONFERENCE WITH ENTERGY OPERATIONS.

INC. AND WESTINGHOUSE RE: WATERFORD STEAM ELECTRIC STATION. UNIT 3. LICENSE AMENDMENT REQUEST FOR USE OF THE TRANFLOW CODE FOR DETERMINING PRESSURE DROPS ACROSS THE STEAM GENERA TOR SECONDARY SIDE INTERNAL COMPONENTS Name Affiliation James Hoss Enterav Operations, Inc Nicholas Petit Enterav Operations, Inc William Steelman Entergv Operations, Inc Maria Zamber Enterav Operations, Inc Steven Arcaya Westinghouse Michael Bradley Westinghouse David Rubolino Westinghouse Kevin Spencer Westinghouse Creed Taylor Westinghouse Jivan Thakker Westinghouse Nicole Vitale Westinghouse Gary Whiteman Westinghouse April Pulvirenti U.S. Nuclear Regulatory Commission (NRC) Robert Pascarelli NRC Reed Anzalone NRC Michael Breach NRC Stewart Bailey NRC None Public Enclosure

SUBJECT:

SUMMARY

OF NOVEMBER 15, 2018, TELECONFERENCE WITH ENTERGY OPERATIONS, INC. REGARDING LICENSE AMENDMENT REQUEST FOR USE OF THE TRANFLOW CODE FOR DETERMINING PRESSURE DROPS ACROSS THE STEAM GENERATOR SECONDARY SIDE INTERNAL COMPONENTS (EPID L-2018-LLA-0112)

DATED NOVEMBER 26, 2018 DISTRIBUTION:

PUBLIC PM File Copy RidsACRS_MailCTR Resource RidsRgn4MailCenter Resource RidsNrrDorlLpl4 Resource RidsNrrPMWaterford Resource CCook, OEDO ADAMS Accession No.: ML 18323A421 OFFICE DORL/LPL4/PM DORL/LPL4/LA RidsNrrLAPBlechman Resource RAnzalone, NRR MBreach, NRR SBailey, NRR RidsNrrDssSrxb Resource JBowen, OEDO LBurkhart, OEDO DORL/LPL4/BC DORL/LPL4/PM NAME APuvirenti PTalukdar/LRonewicz RPascarelli APulvirenti DATE 11/20/2018 11/20/2018 11/26/2018 11/26/2018 OFFICIAL RECORD COPY