MONTHYEARIR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) ML23055A0992023-02-24024 February 2023 Final - Virgil C. Summer - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 ML22075A0482022-03-16016 March 2022 V.C. Summer Nuclear Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000395/2022401 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000395/20200062021-03-0303 March 2021 Annual Assessment Letter for Virgil C. Summer Station, Unit 1 Report 05000395/2020006 ML21050A0012021-02-18018 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21043A1402021-02-11011 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20190062020-03-0303 March 2020 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Report 05000395/2019006 IR 05000395/20190052019-08-28028 August 2019 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1 - (Report 05000395/2019005) ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request ML19066A3792019-03-0707 March 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20180062019-03-0404 March 2019 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 Report 05000395/2018006, Report 05000395/2018402, Report 05000395/2018501 ML18240A2122018-08-27027 August 2018 VC Summer Emailed Information Request EB3 RP 2018004 IR 05000395/20180052018-08-23023 August 2018 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1, (Report 05000395/2018005) IR 05000395/20170062018-02-28028 February 2018 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2017006, Report 05000395/2017402, Report 05000395/2017501 ML17234A2422017-08-21021 August 2017 Updated Inspection Plan ML17150A4552017-05-30030 May 2017 Notification of Virgil C. Summer Design Bases Assurance Inspection - NRC Inspection Report 05000395/2017007 ML17142A1882017-05-19019 May 2017 Virgil C.Summer Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000395/20160062017-03-0101 March 2017 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2016006 IR 05000395/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Inspection Report 05000395/2016005 ML16130A8192016-05-0404 May 2016 Notification of Inspection and Request for Information IR 05000395/20150052015-09-0101 September 2015 Mid-Cycle Letter for Virgil C. Summer Generating Station Unit 1 - NRC Assessment Report 05000395/2015005 IR 05000395/20140012015-03-0404 March 2015 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2014001 ML14245A2002014-09-0202 September 2014 V.C. Summer Mid-Cycle Ltr 2014 ML14175A5762014-06-24024 June 2014 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20130012014-03-0404 March 2014 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2013001 ML13246A1412013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000395/20120012013-03-0404 March 2013 Annual Assessment Letter for Summer Nuclear Station, Unit 1, Report 05000395/2012001 ML12248A1172012-09-0404 September 2012 Mid Cycle Assessment Letter Summer 2012 ML1206505962012-03-0505 March 2012 EOC Report 22 ML1124400632011-09-0101 September 2011 Report 22 - Summer ML1106304142011-03-0404 March 2011 V. C. Summer, Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22 ML1024403162010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006208862010-03-0303 March 2010 Report 22 - 2010001, Inspection/Activity Plan ML0924403682009-09-0101 September 2009 Inspection/Activity Plan, 09/01/2009 - 12/31/2010 ML0906304762009-03-0404 March 2009 Enclosure - Summer Inspection / Activity Plan (03/01/2009 - 06/30/2010) ML0824609582008-09-0202 September 2008 Inspection Activity Plan - 09/02/2008 - 12/31/2009 IR 05000395/20080012008-03-0303 March 2008 Annual Assessment Letter (IR 05000395-08-001) ML0724802462007-08-31031 August 2007 Inspection / Activity Plan 09/01/2007 - 03/31/2009, Report 22 ML0706003462007-03-0101 March 2007 Inspection / Activity Plan for 03/01/2007 - 09/30/2007 RC-07-0021, Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719)2007-01-31031 January 2007 Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719) ML0624303732006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan, 09/01/06 - 03/31/08 ML0606104122006-03-0202 March 2006 Inspection / Activity Plan, 03/01/2006 - 09/30/2007 2024-08-22
[Table view] Category:Letter
MONTHYEARML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application 05000395/LER-2024-001, (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator2024-04-17017 April 2024 (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. ML24087A2262024-03-26026 March 2024 License Amendment Request - Inverter Allowed Outage Time Extension Response to Request for Additional Information ML24088A2062024-03-26026 March 2024 Annual Operating Report 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 2, 2014 Mr. Thomas D. Gatlin Vice President - Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88 Jenkinsville, SC 29065
SUBJECT:
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - NRC ASSESSMENT REPORT 05000395/201006
Dear Mr. Gatlin:
On August 12, 2014, the NRC completed its mid-cycle performance review of V.C. Summer Nuclear Station, Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, V.C. Summer, Unit 1, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined that the performance at V.C. Summer Nuclear Station, Unit 1, during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
T. Gatlin 2 In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4511 with any questions you may have regarding this letter. Sincerely, /Mark Franke RA for/
Michael F. King, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12
Enclosure:
V.C. Summer Inspection/Activity Plan (09/01/2014 - 12/31/2015) cc Distribution via ListServ
________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE BDB /RA/ SON /RA/ MEF /RA for/ NAME BBishop SNinh MKing DATE 8/27/2014 8/27/2014 9/02/2014 E-MAIL COPY? YES NO YES NO YES NO YES NO T. Gatlin 3 Letter to Thomas D. Gatlin from Michael F. King dated September 2, 2014.
SUBJECT:
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - NRC ASSESSMENT REPORT 05000395/201006 DISTRIBUTION: D. Gamberoni, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
Page 1 of 109/02/201409:49:27Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteSummerInspection / Activity Plan09/01/2014-12/31/2015EP-EP PROGRAM INSPECTION31 IPAlert and Notification System Testing711140209/08/201409/12/20141 IPEmergency Preparedness Organization Staffing and Augmentation System711140309/08/201409/12/20141 IPEmergency Action Level and Emergency Plan Changes711140409/08/201409/12/20141 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140509/08/201409/12/20141 IPPerformance Indicator Verification7115109/08/201409/12/2014CDBI-COMPONENT DESIGN BASES INSPECTION71 IPComponent Design Bases Inspection711112109/08/201409/12/20141 IPComponent Design Bases Inspection711112110/06/201410/10/20141 IPComponent Design Bases Inspection711112110/20/201410/24/20141 IPComponent Design Bases Inspection711112111/03/201411/07/2014TFPI-TRIENNIAL FIRE PROTECTION INSP41 IPFire Protection [Triennial]7111105T04/20/201504/24/20151 IPFire Protection [Triennial]7111105T05/04/201505/08/2015RP-RP PUBLIC RAD SAFETY BASELINE31 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0607/27/201507/31/20151 IPRadiological Environmental Monitoring Program71124.0707/27/201507/31/20151 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0807/27/201507/31/20151 IPPerformance Indicator Verification7115107/27/201507/31/2015OL RQ-REQUAL INSP21 IPLicensed Operator Requalification Program7111111B08/10/201508/14/2015RP-RP RAD HAZARDS ASSESSMENT11 IPRadiological Hazard Assessment and Exposure Controls71124.0110/05/201510/09/2015EP-EP EXERCISE51 IPExercise Evaluation711140110/12/201510/16/20151 IPEmergency Action Level and Emergency Plan Changes711140410/12/201510/16/20151 IPPerformance Indicator Verification7115110/12/201510/16/2015ISI-UNIT 1 IN-SERVICE INSPECTION11 IPInservice Inspection Activities - PWR7111108P10/12/201510/16/2015This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.