IR 05000324/2014001

From kanterella
Revision as of 12:59, 14 June 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2014001 and 05000324/2014001
ML15063A241
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 03/04/2015
From: Hopper G T
NRC/RGN-II/DRP/RPB4
To: Gideon W R
Progress Energy Carolinas
References
IR 2014001
Download: ML15063A241 (6)


Text

March 4, 2015

Mr. William Vice President Brunswick Steam Electric Plant P.O. Box 10429 Southport, NC 28461

SUBJECT: ANNUAL ASSESSMENT LETTER FOR BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - NRC INSPECTION REPORT 05000325/2014001 AND 05000324/2014001

Dear Mr. Gideon:

On February 11, 2015, the NRC completed its end-of-cycle performance review of the Brunswick Steam Electric Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. The NRC determined that overall, Brunswick Steam Electric Plant, Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Brunswick Steam Electric Plant, Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. We also plan on conducting the following infrequently performed inspections and temporary instructions: Operator Licensing Exams; TI 2515/190: Inspection of the Licensee's Proposed Interim Actions as a Result of the Near-Term Task Force Recommendation 2.1 Flooding Evaluation; and TI 2515/191: Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me 404-997-4645 with any questions you may have regarding this letter.

Sincerely,/RA/ George T. Hopper, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62

Enclosure:

Brunswick Inspection/Activity Plan (03/01/2015 - 06/30/2016) cc Distribution via ListServ

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE DRP:RII DRP:RII DRP:RII SIGNATURE DXW4 JSD GTH NAME D. Jackson J. Dodson G. Hopper DATE 02/ 13 /2015 03/04/2015 02/20/2015 E-MAIL COPY? YES NO YES NO YES NO Letter to William from George T. Hopper dated March 4, 2015.

SUBJECT: ANNUAL ASSESSMENT LETTER FOR BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - NRC INSPECTION REPORT 05000325/2014001 AND 05000324/2014001 DISTRIBUTION: D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMBrunswick Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 203/04/201509:39:23Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteBrunswickInspection / Activity Plan03/01/2015-06/30/2016ISI-UNIT 2 IN-SERVICE INSPECTION12 IPInservice Inspection Activities - BWR7111108G03/02/201503/06/2015RP-RP OCCUPATIONAL BASELINE WEEK 131,2 IPRadiological Hazard Assessment and Exposure Controls71124.0103/02/201503/06/20151,2 IPOccupational ALARA Planning and Controls71124.0203/02/201503/06/20151,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0303/02/201503/06/20151,2 IPOccupational Dose Assessment71124.0403/02/201503/06/20151,2 IPRadiation Monitoring Instrumentation71124.0503/02/201503/06/20151,2 IPPerformance Indicator Verification7115103/02/201503/06/2015RP-RP OCCUPATIONAL BASELINE WEEK 221,2 IPRadiological Hazard Assessment and Exposure Controls71124.0103/16/201503/20/20151,2 IPOccupational ALARA Planning and Controls71124.0203/16/201503/20/20151,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0303/16/201503/20/20151,2 IPOccupational Dose Assessment71124.0403/16/201503/20/20151,2 IPRadiation Monitoring Instrumentation71124.0503/16/201503/20/20151,2 IPPerformance Indicator Verification7115103/16/201503/20/2015PI&R-PROBLEM IDENTIFICATION AND RESOLUTION61,2 IPProblem Identification and Resolution71152B05/04/201505/08/20151,2 IPProblem Identification and Resolution71152B05/18/201505/22/2015HS-TRIENNIAL HEAT SINK PERFORMANCE11,2 IPHeat Sink Performance7111107T07/20/201507/24/2015EP-EP PROGRAM INSPECTION41,2 IPAlert and Notification System Testing711140208/17/201508/21/20151,2 IPEmergency Preparedness Organization Staffing and Augmentation System711140308/17/201508/21/20151,2 IPEmergency Action Level and Emergency Plan Changes711140408/17/201508/21/20151,2 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140508/17/201508/21/20151,2 IPPerformance Indicator Verification7115108/17/201508/21/2015OL EXAM-INITIAL LICENSE EXAM PREP31 BRUNSWICK/NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIESV2343111/02/201511/06/2015OL EXAM-INITIAL LICENSE EXAM31 BRUNSWICK/NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIESV2343111/30/201512/11/2015ISI-UNIT 1 IN-SERVICE INSPECTION11 IPInservice Inspection Activities - BWR7111108G02/22/201602/26/2016This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 203/04/201509:39:23Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteBrunswickInspection / Activity Plan03/01/2015-06/30/2016RP-RAD HAZARDS AND TRANSPORTATION21,2 IPRadiological Hazard Assessment and Exposure Controls71124.0102/22/201602/26/20161,2 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0802/22/201602/26/2016OL EXAM-INITIAL LICENSE EXAM PREP31 BRUNSWICK MAY 2016 INITIAL EXAM AT POWER FACILITIESV2346404/04/201604/08/2016OL EXAM-INITIAL LICENSE EXAM31 BRUNSWICK MAY 2016 INITIAL EXAM AT POWER FACILITIESV2346405/02/201605/13/2016RP-RP PUBLIC RAD SAFETY BASELINE21,2 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0605/23/201605/27/20161,2 IPRadiological Environmental Monitoring Program71124.0705/23/201605/27/20161,2 IPPerformance Indicator Verification7115105/23/201605/27/2016This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.